2
TNA Plan Of Lady Bird. Sl.No Task Start Day 1 Design Receipt. 1 2 Proto Sample. 5 3 Base Fabric Approval. 5 4 Lab Dip Approval. 5 5 Print & Embroidary Approval. 5 6 Trims Approval. 5 7 Fabric & Trims Order. 15 8 Photoshoot Sample. 25 9 Fit Sample. 25 10 Preproduction Sample 40 11 Fabric & Trims Inhouse. 40 12 Lab Testing. 40 13 Per production Meet. 14 Pilot Run. 45 15 Cutting. 51 16 Print & Embroidary. 53 17 Sewing. 55 18 Inline Inspection. 19 Production Sample. 75 20 Final Inspection. 83 21 Ex-Factory. 22 Hand Over to Logistics. 23 Vessel Date. 24 Payment Receipt.

Upload: riyasen

Post on 18-Nov-2015

18 views

Category:

Documents


1 download

DESCRIPTION

time n action

TRANSCRIPT

Sheet1

TNA Plan Of Lady Bird.

Sl.NoTaskStart DayEnd Day1Design Receipt.12Proto Sample.5123Base Fabric Approval.5124Lab Dip Approval.5125Print & Embroidary Approval.5126Trims Approval.5127Fabric & Trims Order.158Photoshoot Sample.259Fit Sample.253210Preproduction Sample404711Fabric & Trims Inhouse.4012Lab Testing.404413Per production Meet.4514Pilot Run.455015Cutting.5116Print & Embroidary.5317Sewing.557518Inline Inspection.6519Production Sample.758220Final Inspection.838521Ex-Factory.8522Hand Over to Logistics.8823Vessel Date.9024Payment Receipt.130

Sheet2

Sheet3