the nineteenth annual international maritime law ...€¦ · smith hogg & co ltd v black sea...
TRANSCRIPT
THE NINETEENTH ANNUAL INTERNATIONAL MARITIME LAW ARBITRATION MOOT
Memorandum for the Claimant
On Behalf of:
Cerulean Beans and Aromas Ltd
(CLAIMANT)
Against:
Dynamic Shipping LLC
(RESPONDENT)
A. NAMIRA IMANI – CINDY RAHMADAVITA – JEVON HOLLY – RAISYA MAJORY – VINKA DAMIANDRA
TEAM NO. 17
MEMORANDUM FOR THE CLAIMANT
TEAM NO. 17
iii
TABLE OF CONTENTS
TABLE OF CONTENTS iii
LIST OF AUTHORITIES v
LIST OF ABBREVIATIONS viii
SUMMARY OF FACTS 1
ARGUMENTS PRESENTED 2
I. THIS TRIBUNAL HAS THE CAPACITY TO RULE ON ITS OWN JURISDICTION 2
II. THIS TRIBUNAL HAS THE JURISDICTION TO RULE ON CLAIMANT’S CLAIMS
FOR DAMAGES 2
III. THE RESPONDENT IS LIABLE FOR THE LOSS CAUSED BY THE DELAY 3
A. The Delay was Caused by the Respondent’s Breach of Warranty to Provide Seaworthy
Ship 4
i. The Respondent has breached its warranty to provide seaworthy ship 4
ii. Respondent’s breach was the cause of the delay 6
B. In the Alternative, the Delay was Caused by the Respondent’s Unlawful Deviation to the
Port of Spectre 7
i. The deviation was beyond what is reasonably necessary 8
ii. The deviation was not due to a Force Majeure Event 8
iii. The Respondent’s unlawful deviation caused the delay 9
C. In any event, the Respondent Cannot be Exempted by Clause 17 of the Charterparty 10
D. The Delay Caused Claimant’s Loss 11
IV. THE RESPONDENT IS LIABLE FOR THE LOSS RESULTING FROM ITS FAILURE
TO TAKE REASONABLE CARE OF THE CARGO UNDER BAILMENT 11
A. The Respondent is under a Duty to Take Reasonable Care of the Cargo as a Bailee 12
B. The Cargo was Damaged under the Respondent's Custody as a Bailee 12
C. The Damage to The Cargo was Caused by The Respondent’s Failure to Take Reasonable
Care of The Cargo 14
D. The Claimant is entitled to recover for the damaged Cargo and the replacement cargo 16
E. The Respondent Cannot Limit Its Liability Pursuant to Article IV rule 5 of the HVR 16
V. THE CLAIMANT IS ENTITLED TO AN EQUITABLE MARITIME LIEN OVER THE
VESSEL 17
A. There is a Maritime Lien Over the Vessel for the Crews’ Wages 18
B. The Claimant Is Entitled to The Equitable Maritime Lien for The Crews’ Wages By Way
Of Subrogation 18
iv
i. The circumstances give rise to equitable subrogation to the crew’s maritime lien 19
ii. Further, there are no circumstances precluding such equitable subrogation 19
VI. THE CLAIMANT IS NOT LIABLE TO PAY FOR AMOUNTS CLAIMED UNDER
THE CHARTERPARTY IN FULL 21
A. The Claimant is not responsible for demurrage, the use of electronic access at the Port of
Dillamond, the agency fee at the Port of Spectre, and the repair to the Vessel’s hull 21
i. No demurrage is recoverable under the present circumstances 21
ii. The Respondent's non-compliance with Clause 15 of the Charterparty bars from it
claiming demurrage, the use of electronic access at the Port of Dillamond, the
agency fee at the Port of Spectre, and the repair to the Vessel's hull 22
B. The Respondent is not entitled to freight in full upon damages to the Cargo 23
C. The Claimant is not liable for the payment of agency fee at the Port of Dillamond in a
separate amount with the freight 24
PRAYER FOR RELIEF 25
v
LIST OF AUTHORITIES
CASES
Adamastos Shipping Co Ltd v Anglo Saxon Petroleum Co Ltd [1959] A.C. 133
Asfar v. Blundell [1896] 1 Q.B. 123
Australasian United Steam Navigation Co. Ltd. v. Hiskens (1914) 18 CLR 646
Automatic Totalisators Ltd v Oceanic Steamship Co [1965] NSWR 702
Automatic Tube Co and Email Ltd v Adelaide Steamship Co (The Beltana) [1966] WAR 103
B.P. Refinery (Westernport) Pty. Ltd v Hastings Shire Council (1977) 180 CLR 266
Baldwin’s Ltd v Halifax Corporation (1916) 85 LJ KB
Bankers Trust International v Todd Shipyards Corp (The Halcyon Isle) [1981] A.C. 221 (1980)
Banque Financiere de la Cite SA v Parc (Battersea) Ltd [1999] 1 A.C. 226
Benedetti v Sawiris [2014] AC 938
Berard Trading Inc. v. Empire Stevedoring Co. Ltd. (1976) Carswell BC 1033
Boodle Hatfield & Co v British Film Ltd (1986) 2 B.C.C. 99221
Boscawen v. Bajwa [1996] 1 W.L.R. 32
Brazzill v Willoughby [2009] EWHC 1633 (Ch)
Burston Finance Ltd v Speirway Ltd, [1974] 1 W.L.R. 1648
Butler v Rice [1910] 2 Ch. 277
C V Sheepvaartonderneming Ankergracht v Stemcor (Asia) Pty Ltd [2007] FCAFC 77
Chartered Bank v. British India S.N. Co. [1909] A.C. 369, 375
Cheltenham & Gloucester Plc v Appleyard & Another [2004] EWCA Civ 291
Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337
Commissioner of Railways (WA) v Stewart, 56 CLR 520 (1936)
Dallah Real Estate v. Gov’t of Pakistan [2010] UKSC 46
Danae v. T.P.A.O. [1983] 1 Lloyd’s Rep. 498
David Duncan v Daniel Augustus (The Teutonia) (1873) LR 4 PC 179
Davis v Garrett (1830) 6 Bing 716 Duthie v. Hilton (1868) L.R. 4 C.P. 138
East & West Steamship Co v Hossain Bros [1968] 2 Lloyd's Rep 145
Elder Dempster & Co Ltd v Paterson, Zochonis & Co Ltd [1924] AC 522
Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523
Eridania SpA & Ors v. Oetker & Ors (The Fjord Wind) [2000] C.L.C. 1376
Fairline Shipping Corporation v Adamson [1975] QB 180
FC Bradley & Sons Ltd v Federal Steam Navigation Co [1926] 24 Ll L Rep 446, 454
Federal Commerce v. Tradax Export (The Maratha Envoy) [1978] A.C. 1
Felthouse v Bindley (1862) 11 CB (NS) 869142 ER 1037
Ghana Commercial Bank v. Chandiram [1960] 3 W.L.R. 328
Gilchrist Watt & Sanderson Pty Ltd v York Products Pty Ltd [1970] 1 WLR 1262
Glencore International AG v. MSC Mediterranean Shipping Co SA & Anor [2015] EWHC 1989
(Comm)
Global Dress Company Ltd. v. Boase & Co. Ltd. [1966] 2 Ll.L.R. 72
Goldman v Thai Airways International Ltd [1983] 1 WLR 1186, 1194
Great Eastern Shipping Co Ltd v Far East Chartering Ltd (2012) WL 608696
Hadley v Baxendale (1854) 2 CLR 517
vi
Hobbs v Petersham Transport Co Pty Ltd (1971) 124 CLR 220 Houghland v. R. R. Low (Luxury Coaches) Ltd. [1962] 1 QB 694
Hyundai Merchant Marine Co Ltd v Dartbrook Coal (Sales) Pty Ltd [2006] FCA 1324
Investment Trust Companies v Revenue and Customs Comrs [2012] STC 1150
Kopitoff v Wilson (1876) 1 QBD 377
Koufos v C Czarnikow Ltd (The Heron II), [1969] 1 A.C. 350 (1967)
Kyokuyo Co Ltd v. AP Moller-Maersk A/A (t/a Maersk Line [2017] EWHC 654 (Comm)
McFadden v Blue Star Line, [1905] 1 K.B. 697 (UK)
Mediterranean Shipping Co SA v Delumar BVBA (The MSC Rosa M) [2000] 2 Lloyd’s Rep 399,
401
Menelaou v Bank of Cyprus Plc [2015] UKSC 66
Mercury Communication Ltd v The Director General of Telecommunications [1994] C.L.C. 1125
Mogilyuk v Australian Maritime Safety Authority [2014] AATA 409
Monarch Steamship v Karlshamns Oljefabriker [1949] A.C. 196
Montedison S.p.A. v. Icroma S.p.A. (The Caspian Sea) [1980] 1 Lloyd’s Rep. 91
Morris v C W Martin & Sons Ltd [1966] 1 QB 716
Nea Agrex SA v Baltic Shipping Co Ltd (The Agios Lazarus), [1976] Q.B. 933
Nikolay Malakhov Shipping Co Ltd v SEAS Sapfor Ltd (1998) 44 NSWLR 371
Nugent v Smith, (1876) 1 CPD 423
Ontario Bus Industries Inc v Federal Calumet (The) [1991] FCJ 535
Orakpo v Manson Investments Ltd. [1978] AC 95
Paterson Steamships, Limited Appellants v. Canadian Co-Operative Wheat Producers, Limited
Respondents [1934] A.C. 538
Paul v. Speirway Ltd. [1976] Ch. 220
Phelps, James & Co v Hill [1891] 1 QB 605 CA
Reardon Smith Line v. Ministry of Agriculture, Fisheries and Food [1963] A.C. 691
Riverstone Meat Co Pty Ltd v Lancashire Shipping Co Ltd (The Muncaster Castle) [1961] AC
807
Roger v Whitaker (1992) 175 CLR 479.
Sailing Ship Garston Co v. Hickie (1885) 15 QBD 580
Scanlan's New Neon Ltd v Tooheys Ltd (1943) 67 C.L.R. 169
Scaramanga & Co v Stamp (1880) 5 CPD 295 (CA)
Secured Income Real Estate (Australia) Ltd v St Martins Investments Pty Ltd [1979] HCA 51
Smith Hogg & Co Ltd v Black Sea and Baltic General Insurance Co Ltd [1940] 3 All ER 405.
Société Telus Communications v Peracomo Inc [2011] FC 494, 521
SS Pharmaceutical Co Ltd v Qantas Airways Ltd (1988) 92 FLR 231
Stag Line v. Foscolo, Mango [1932] A.C. 328
Stemcor (A/sia) Pty Ltd v CV Scheepvaartonderneming Ankergracht [2005] FCA 1808
Swynson Ltd v Lowick Rose LLP (formerly Hurst Morrison Thomson LLP) (in liquidation)
[2017] UKSC 32
The Arawa [1977] 2 Lloyd's Rep 416
The “British Trade” [1924] P. 104
The “Ruby” (No. 2) [1898] P. 59
The “Tacoma City” [1991] 1 Lloyd’s Rep. 330
The Bold Buccleugh (1851) 7 Moo P.C. 284
The British Shipowners’ Company (Limited) v. J. and A. D. Grimond No. 152. (1876) 3 R. 968
The Colorado [1923] P. 102
The Commonwealth of Australia v Amann Aviation Pty. Limited [1991] HCA 54
The Eurasian Dream [2002] 1 Lloyd’s Rep 719
The Express (1872) L.R. 3 A. & E. 597
vii
The Johanna Oldendorff (E.L. Oldendorff & Co. v. Tradax Export) [1974] A.C. 479 (H.L.)
The Maria G [1985] 1 Lloyd's Rep 616
The Patria (1871) L.R. 3 A. & E. 436
The Pioneer Container [1994] C.L.C. 332
The San Roman (1872) L.R. 5 P.C. 301
The Tolten [1946] P. 135.
The Two Ellens (1872) L.R. 4 P.C. 161
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB
Westrac Equipment Pty Ltd v Owners of Ship (Assets Venture) [2002] FCA 440 (2002)
Wylie v. Carlyon [1922] 1 Ch. 51; Paul v. Speirway Ltd. [1976] Ch. 220
Yemgas FZCO v Superior Pescadores SA Panama [2016] EWCA Civ 101
STATUTES AND REGULATIONS
Australia Navigation Act 2012
Australia’s National Standard for Commercial Vessel
Australian Marine Order 27
English Arbitration Act 1996
CONVENTIONS
International Convention for Safety of Life at Sea 1974 (SOLAS)
International Convention for the Unification of Certain Rules of Law relating to Bills of
Lading 1968 (Hague-Visby Rules)
BOOKS
Ewan McKendrick. Force Majeure and Frustration of Contract, 2nd edn, LLP, London, 1995
Gary B Born. International Commercial Arbitration Vol 1. Kluwer Law International 2009.
Graham Virgo. The Principles of the Law of Restitution. Oxford University Press, 2016.
International Chamber of Shipping. "Safe TransPort of Containers by Sea: Guidelines on Best
Practices". London: Marisec Publications, 2008.
International Trade Centre. "The Coffee Exporter's Guide". Genevam 2011.
Julian Cooke. Voyage Charters. 4th Edn, 2014.
Nigel Blackaby et al, Redfern and Hunter on International Arbitration. Oxford University Press,
5th ed, 2009.
Nigel Meeson. Admiralty Jurisdiciton and Practice. Third Edition, Lloyd’s Shipping Law
Library, 2003.
JOURNAL & OTHERS
Australian Maritime Safety Authority. “Navigation System.” AMSA.
https://www.amsa.gov.au/safety-navigation/navigation-systems (accessed on 15 April 2018)
viii
LIST OF ABBREVIATIONS
AATA
A.C.
All ER
ALJR
ALMD
Bing.
Cargo
C.P.D.
Claimant
C.L.C.
Charterparty
Delivery Deadline
FCA
HCA
HVR
K.B.
Lloyd’s Rep
L.R.
Moo. P.C.
Administrative Appeals Tribunal
UK Law Reports, Appeal Cases
All England Law Reports (United Kingdom)
Australian Law Journal Reports
Australia Legal Monthly Digest
Bingham's Common Pleas Reports (England)
1,000 bags of 70,000 kilograms of high-grade coffee
beans contained inside four containers, carried by the
Vessel
Common Pleas Division - Law Reports
Cerulean Beans and Aromas Ltd
Commercial Law Cases
Voyage charterparty between the Parties
7:00 PM 28 July 2017
Federal Court of Australia
High Court of Australia
Hague-Visby Rules
King’s Bench
Lloyd’s Law Report
Law Reports (England)
Moore's Privy Council Cases
ix
LIST OF ABBREVIATIONS
NSWLR
p.
¶
Parties
Respondent
QBD
SOLAS
Storm
UKSC
Vessel
Voyage
WAR
WLR
New South Wales Law Report
page
paragraph
the Claimant and the Respondent
Dynamic Shipping LLC
Queen’s Bench Division
International Convention for Safety of Life at Sea 1974
The storm occurred at 5:13 PM on 28 July 2017
United Kingdom Supreme Court
Madam Dragonfly
The voyage concerning the carriage of the Cargo from
Cerulean to Dillamond on 24 July 2017
Western Australia Reports
Weekly Law Reports
1
SUMMARY OF FACTS
1. On 22 July 2017, Cerulean Beans and Aromas (the “Claimant”) and Dynamic Shipping (the
“Respondent”) (together, the “Parties”) entered into a contract of carriage (the
“Charterparty”) to deliver 70,000 kilograms of high-grade coffee beans (the “Cargo”) from
Cerulean to Dillamond on 24 July 2017 (the “Voyage”) on board the Respondent’s vessel, the
Madam Dragonfly (the “Vessel”). The Cargo was to be delivered at 7:00 PM on 28 July 2017
(the “Delivery Deadline”) to the Claimant’s client, Coffees of the World, for an impending
coffee festival in Dillamond. The Claimant also agreed to loan the Respondent USD100,000 to
pay for the Vessel’s crew wages prior to the Voyage.
2. Due to solar flares from 24 July 2017 until 25 July 2017, the Vessel’s communication and
navigation failed at approximately 9:32 PM on 25 July 2017 for 17 hours. Shortly after the
Vessel’s communication and navigation systems failed, it deviated to the Port of Spectre. The
Vessel did not proceed with the Voyage until 27 July 2017.
3. A heavy storm occurred near the Vessel’s location at 5:13 PM on 28 July 2017 (the “Storm”),
causing the Respondent to fail to meet the Delivery Deadline.
4. At 8:42 PM on 29 July 2017, the Vessel docked at the Port of Dillamond and the Cargo was
available for collection. The Respondent has sent an electronic authority access barcode to allow
the collection of the Cargo past 12:02 AM, on 30 July 2017.
5. The Claimant collected the Cargo at 1:17 PM, on 31 July 2017. Three containers of the Cargo
were found to be completely water damaged. The Claimant suffered loss, was forced to find
replacement coffee, and has to make settlement payment to prevent legal action by its client.
6. The Claimant issued a notice of breach to the Respondent on 1 August 2017, demanding
damages in respect of damage towards the Cargo, replacement coffee, and a settlement payment
with the Claimant’s client. The Claimant commenced arbitration proceedings on 11 August 2017.
2
ARGUMENTS PRESENTED
I. THIS TRIBUNAL HAS THE CAPACITY TO RULE ON ITS OWN JURISDICTION
7. Under Section 30 (1) of Arbitration Act 1996,1 an arbitral tribunal may rule on its own
jurisdiction pursuant to an arbitration agreement. Accordingly, this Tribunal may adjudicate
matters submitted to arbitration in accordance with an arbitration agreement. This reflects a well-
established principle of international arbitration, known as the ‘competence-competence’
principle.2 Therefore this Tribunal has the capacity to rule on its own jurisdiction.
II. THIS TRIBUNAL HAS THE JURISDICTION TO RULE ON CLAIMANT’S CLAIMS
FOR DAMAGES
8. In its Points of Defense, the Respondent objects to the jurisdiction of this Tribunal to adjudicate
the claims made by the Claimant because its claims for damages are matters which should be
determined in accordance with Clause 27 (d) to (g) of the Charterparty (the “Expert
Determination Provisions”).3
9. Clause 27 (d) provides that, “...any dispute as to technical matters arising out of or in connection
with this contract shall be referred to expert determination by an independent Master Mariner.”4
The scope of ‘technical matters’ defined under Clause 27 (g) is limited to only cover matters
“which could reasonably be considered to be within the expert technical knowledge of a Master
Mariner.”5 In deciding such matter, the expert may only decide matters, which fall within the
scope of the Expert Determination Provisions that have been agreed by both Parties.6 As such, an
expert may not decide on matters which fall outside the scope of the Expert Determination
Provisions have been agreed by both Parties.
1 Moot Scenario, p. 12. 2 Dallah Real Estate v. Gov't of Pakistan [2010] UKSC 46; Gary B Born, International Commercial Arbitration (Kluwer
Law International 2009) vol 1, p, 853; Nigel Blackaby et al, Redfern and Hunter on International Arbitration (Oxford
University) Press, 5th ed, 2009), p. 346-7. 3 Moot Scenario, p. 40. 4 Ibid, p. 12. 5 Ibid. 6 Mercury Communication Ltd v The Director General of Telecommunications [1994] C.L.C. 1125.
3
10. In the present case, there are no disputes as to technical matters in respect of the Claimant’s
claims for damages. The cruxes of these claims for damages are matters regarding the
interpretation of contract, determination of liability, and the quantum of damages. The
determination of these issues could not in any way be deemed to fall within the definition of
technical matters as envisioned by Clause 27 (g).
11. The Respondent might argue that there is a dispute regarding technical matters with regards
whether the Respondent had exercised satisfactory due diligence to ensure the Vessel’s
seaworthiness and whether the Respondent has fulfilled the standard of duty of care for the cargo.
However, in the case of Roger v Whitaker (1992),7 it was affirmed that on a question on whether
a defendant’s action conforms to the standard of reasonable care, which is a question of law, is a
question exclusively for the court and cannot be delegated to any profession or group in the
community. Therefore, the Claimant’s claims for damages are questions of law that must be
determined by this Tribunal, not a Master Mariner.8 Consequentially, this Tribunal has
jurisdiction to adjudicate the Claimant’s claims for damages.
III. THE RESPONDENT IS LIABLE FOR THE LOSS CAUSED BY THE DELAY
12. The Claimant submits that the Respondent is liable for the losses incurred as a result of the
Respondent’s delay in delivering the Cargo to Dillamond, because (A) the delay was caused by
the Respondent’s breach of warranty to provide seaworthy ship, and (B) in the alternative, the
delay was caused by the Respondent’s unlawful deviation to the Port of Spectre. In any event,
(C) the Respondent cannot be exempted by Clause 17 of the Charterparty, and (D) the delay
caused the Claimant’s loss.
7 Roger v Whitaker (1992) 175 CLR 479. 8 Ibid.
4
A. The Delay was Caused by the Respondent’s Breach of Warranty to Provide Seaworthy
Ship
13. It is implied under a Charterparty that a shipowner has a duty to provide seaworthy ship.9 This
duty is further stipulated under Clause 1, where both parties have agreed that, “…the said ship,
warranted tight, staunch and strong and in every way fitted for the voyage”.10 The Respondent is
liable for the delay, because (i) the Respondent has breached its warranty to provide a seaworthy
ship, and (ii) such breach is the dominant cause of the delay.
i. The Respondent has breached its warranty to provide seaworthy ship
14. For a ship to be deemed as seaworthy, a ship must have that degree of fitness which an ordinary
careful and prudent owner would require his ship to have at the commencement of her voyage,
having regard to all the probable circumstances of it.11 In the present case, the Respondent has
breached its warranty to provide seaworthy ship, as it has failed to make the Vessel has that
“degree of fitness” at the commencement of the Voyage, having regard to all the probable
circumstances that might occur during the Voyage.
15. On 18 July 2017, a week prior to the Voyage, it was reported in Cerulean that solar flares were
expected to occur.12 As solar flares were known to have been strong enough to disrupt radio and
satellite communications systems, anyone who relied on radio and satellite communication
systems were warned to have back-up arrangements to anticipate the effect of such solar flares.13
16. Considering the possibility of the solar flares and its effect to radio and satellite communication
systems, an ordinary careful and prudent owner would not have allowed the Vessel to undertake
its Voyage without adequate back-up arrangements and equipment capable to anticipate the
adverse effect of such solar flares.
9 Kopitoff v Wilson (1876) 1 QBD 377; Paterson Steamships, Limited Appellants; v. Canadian Co-Operative Wheat
Producers, Limited Respondents [1934] A.C. 538. 10 Moot Scenario, p. 4; Elder Dempster & Co Ltd v Paterson, Zochonis & Co Ltd [1924] AC 522. 11 McFadden v Blue Star Line, [1905] 1 K.B. 697 (UK); FC Bradley & Sons Ltd v Federal Steam Navigation Co [1926]
24 Ll L Rep 446, 454; Eridania SpA & Ors v. Oetker & Ors (The Fjord Wind) [2000] C.L.C. 1376. 12 Moot Scenario, p. 35. 13 Ibid.
5
17. Under Section 224 of Australia Navigation Act 2012, an owner of a regulated Australian must
ensure that his vessel is supplied with nautical charts (including charts in electronic form)
necessary for use on the particular voyage.14 Further, under Section 23 of Australian Marine
Order No. 27, where a shipowner relies on electronic nautical charts, it is obliged to ensure the
vessel is equipped with back-up arrangements in the event its electronic nautical charts is not
available,15 by installing a back-up electronic nautical charts or procurement of hardcopy nautical
charts.16 In cases where a shipowner is aware of the likelihood of events that may hamper their
reliance on electronic nautical charts, the maintenance of hardcopy nautical charts as back-up
arrangement becomes obligatory,17 and the hardcopy nautical charts for such purposes must be
up-to-date and relevant for the intended voyage.18 Failure to provide appropriate nautical charts
will render the ship unprepared to encounter any unexpected events that may occur during the
voyage, and expose the crew to potentially threatening danger.19
18. In the present case, the Respondent failed to equip the Vessel with the necessary hardcopy
nautical charts before the commencement of the Voyage. It did not replace the hardcopy nautical
charts from the Vessel’s previous journey, leaving the Spectre nautical charts the only hardcopy
nautical charts available onboard.20 As such, at the commencement of the Voyage, the Vessel
was not equipped with adequate back-up arrangements in the event solar flares occurred and
affected its electronic navigation system.
19. Further, under Australia’s National Standard for Commercial Vessel, a shipowner has the
obligation to arrange communications equipment that reduces navigation risks associated with
operating the vessel, and significantly enhances the probability of survival in the event of an
14 Australia Navigation Act 2012 No. 128, 2012; SOLAS Chapter V regulation 27. 15 International Maritime Organization, ECDIS – Guidance for Good Practice, MSC.1/Circ.1503, Section 14. 16 Australian Marine Order No. 27, Section 23. 17 Primar Stavanger, IC-ENC Working Group on information (PSIWG), Facts about Charts and Carriage Requirements,
1st Edition, (Kort & Matrikelstyrelsen: 2004), p. 7. 18 Australian Marine Order No. 27, Section 23. 19 Mogilyuk v Australian Maritime Safety Authority [2014] AATA 409. 20 Moot Scenario, p. 18.
6
incident.21 Under Australian Marine Order 27, a shipowner is responsible to ensure a receiver of
global navigation satellite system or a terrestrial radio navigation system suitable for use at all
times throughout the intended voyage.22 Being aware of the possibility of the solar flares a week
before the commencement of the Voyage, an ordinary careful and prudent owner would have
provided communications equipment that is fit to encounter the effect of such solar flares.
20. According to the report provided by Cerulean National Communications Agency, any navigation
or satellite communication systems which comply with applicable regulations for utilisation in
commercial ventures should have reconnected straight away after the solar flares attack.23
Meanwhile, on 25 July 2017, the Vessel’s systems went down for 17 hours due to the effect of
the solar flares.24 Such prolonged delay shows that the Vessel was not equipped with
communication equipment capable of significantly enhance the probability of survival in the
event of solar flares attack. Therefore, by failing to arrange proper communication and
navigation equipment at the time of the commencement of the Voyage, the Respondent has
breached its warranty to provide seaworthy ship.
ii. Respondent’s breach was the cause of the delay.
21. The Vessel’s unseaworthiness is the cause of the delay in delivering the Cargo, as the delay
would not have happened had the Vessel was seaworthy when it sails on the Voyage.
22. The Respondent admitted that the reason of its deviation to the Port of Spectre on 25 July 2017
was because the only hardcopy nautical charts on board the Vessel were for Spectre.25 Had the
Vessel been equipped with the necessary navigation and communications system to counter the
effect of the solar flares, deviation to the Port of Spectre would be avoidable.
23. After deviating to Spectre, the Vessel attempted to proceed to Dillamond, but was halted at 4:58
PM on 28 July due to the Storm.26 Meanwhile, at the beginning of the Voyage, the Respondent
21 Australia’s National Standard for Commercial Vessel, Part C, Section 7, Subsection 7B, Section 2.3. 22 Marine Order 27 (Safety of navigation and radio equipment) 2016 s. 20; SOLAS, Regulation 19, Section 2.1.6. 23 Moot Scenario, p. 35. 24 Ibid, p. 17. 25 Ibid, p. 19. 26 Ibid.
7
had expected delivery to be completed by 5:00 PM on 28 July 2017.27 Had the Vessel been
seaworthy, the Storm would not have prevented the Respondent to deliver the Cargo on time, as
delivery would have been completed before the Storm even occurred.
24. The Respondent may further argue that the Storm, exempted the Respondent from its liability for
the delay by virtue of Clause 17 of the Charterparty. However, unseaworthiness as a cause,
operates immediately whenever it comes into effect.28 According to Lord Wright in Smith Hogg v
Baltic General Insurance (1940),29 if a shipowner’s breach of duty to provide a seaworthy ship is
‘a’ cause of the loss, then the shipowner is liable for such damage though there were other co-
operating causes of such damage.30 The House of Lords in Monarch Steamship v Karlshamns
Oljefabriker (1949),31 had affirmed the general rule of causation in the event of unseaworthiness:
“The shipowner, of course, under the familiar general rule, is debarred by his breach of duty [to
provide seaworthy ship] from relying on the specific exception. Though he would not be liable for
the consequences caused by the specific excepted peril or the accident alone if he were not in
default … yet the breach of the warranty operates directly as a cause and, indeed, a dominant
cause.” Therefore, the Vessel’s unseaworthiness was the cause of the delay, and the Respondent
is liable despite the existence of the Storm as co-operating cause.
B. In the Alternative, the Delay was Caused by the Respondent’s Unlawful Deviation to the
Port of Spectre
25. Under the Charterparty, the Respondent is under the obligation to carry the Cargo from Cerulean
to Dillamond without deviation, unless for cause justifying such deviation.32 The Claimant
submits that the Respondent’s deviation to the Port of Spectre was unlawful, since (i) the
deviation was beyond what is reasonably necessary, and (ii) it was not due to a Force Majeure
Event. Further, (iii) such deviation caused the delay in delivering the Cargo.
27 Ibid, p. 15. 28 Monarch Steamship v Karlshamns Oljefabriker [1949] A.C. 196. 29 Smith Hogg & Co Ltd v Black Sea and Baltic General Insurance Co Ltd [1940] 3 All ER 405. 30 Ibid. 31 Monarch Steamship v Karlshamns Oljefabriker [1949] A.C. 196. 32 Scaramanga & Co v Stamp (1880) 5 CPD 295 (CA).
8
i. The deviation was beyond what is reasonably necessary
26. Under Clause 17 of the Charterparty, the Vessel has liberty to deviate for the purpose of saving
life or property at the sea.33 Under common law, deviation is only allowed when it is done to save
lives on board.34 In The Teutonia (1873),35 it was held that a Master is justified to deviate where
he "... receives credible information that if he continues in the direct course of his voyage his
ship will be exposed to some imminent peril."36 However, when a ship deviates on the grounds of
necessity, the deviation must not exceed what is reasonable for the purpose of achieving its
justifiable object.37 Where the deviation consists of delay, the delay must not exceed what is
reasonable in the light of the danger that it is sought to avoid.38
27. Here, the Vessel’s communication and navigation systems had successfully recovered from the
effect of the solar flares on 26 July 2017 at 2:32 PM.39 If the deviation was needed to avoid risks
imposed to the crew and the Vessel due to the effect of the solar flares, the Vessel should have
been able to proceed back to its course immediately after such material time. However, the
Vessel chose to stay at the Port of Spectre until 27 July 2017,40 making its deviation beyond what
is reasonably necessary. Hence, the Respondent’s deviation is unlawful.
ii. The deviation was not due to a Force Majeure Event
28. Clause 17 of the Charterparty releases a party from any liability when the party is being delayed
or prevented from performing its obligations by reasons of the relevant Force Majeure Event in
which defined as, among others, “unforeseen weather events, acts of God, accidents, fire,
explosions, flood, landslips, ice, frost or snow.”41 However, the Solar flares do not qualify as a
Force Majeure Event stipulated under such clause.
33 Moot Scenario, p. 9. 34 Scaramanga And Co v. Stamp (1880) 5 C.P.D. 295. 35 David Duncan v Daniel Augustus (The Teutonia) (1873) LR 4 PC 179. 36 Ibid. 37 Phelps, James & Co v Hill [1891] 1 Q.B. 605; Stag Line v. Foscolo, Mango [1932] A.C. 328; Danae v. T.P.A.O.
[1983] 1 Lloyd’s Rep. 498. 39 Ibid, p. 17. 39 Ibid, p. 17. 40 Ibid, p. 18. 41 Moot Scenario, p. 9.
9
29. The solar flares could not be classified as “unforeseen weather events” as it was foreseeable by
the Respondent before and at the time of the commencement of the Voyage. To be considered as
a force majeure event, an event must have been unforeseeable by a reasonable person at the time
of the conclusion of the contract.42 In the present case, it was predicted in The Cerulean Mail on
18 July 2017 that solar flares were to occur for the next two weeks.43 As a company based in
Cerulean,44 the Respondent should have foreseen the occurrence of the solar flares at the time of
the conclusion of the Charterparty.
30. Further, the solar flares could not be classified as an act of God. An Act of God is defined as
accident caused by nature without any human intervention that could not have been anticipated
and prevented by a reasonably prudent person.45 In the present case, the accident caused by the
solar flares was the Vessel’s inability to proceed to Dillamond. As solar flares were known to
have been strong enough to disrupt radio and satellite communications,46 NASA has warned
vessels to have back up plans to anticipate the effect of such solar flares.47 The Vessel's inability
to proceed could have been prevented by having hardcopy nautical charts as a form of back-up
arrangement for the Vessel to continue the Voyage when it lost its electronic navigation system.48
Therefore, the solar flares could be anticipated by a reasonable prudent person, and cannot be
classified as a Force Majeure Event.
iii. The Respondent’s unlawful deviation caused the delay
31. When a loss is caused by a shipowner’s unlawful deviation, he is liable for the loss.49 He is only
exempted if he can show that the delay would have occurred even if the vessel did not deviate.50
42 Ewan McKendrick, Force Majeure and Frustration of Contract 2nd edn, LLP, London, 1995 at p. 24; Hyundai
Merchant Marine Co Ltd v Dartbrook Coal (Sales) Pty Ltd [2006] FCA 1324. 43 Moot Scenario, p. 35. 44 Procedural Order No. 2, ¶1. 45 Nugent v Smith, (1876) 1 CPD 423; Baldwin’s Ltd v Halifax Corporation (1916) 85 LJ KB; Commissioner of Railways
(WA) v Stewart, 56 CLR 520 (1936). 46 Moot Scenario, p. 35. 47 Ibid. 48 Team 17 Memorandum for Claimant, ¶17. 49 Davis v Garrett (1830) 6 Bing 716. 50 Ibid.
10
32. In this case, the delay in delivering the Cargo is caused by the Respondent’s unlawful deviation.
The Storm does not exempt the Respondent from any liability pursuant to Clause 17, as the delay
would not have happened if the Vessel had not deviated to the Port of Spectre. As argued in
paragraph 23-24, had the Voyage proceeded as planned, the Storm would not have prevented the
Respondent to deliver the Cargo on time, as delivery would have been completed before the
Storm even occurred. Therefore, the delay was caused by the Respondent’s unlawful deviation,
and the Respondent is liable for the delay.
C. In any event, the Respondent Cannot be Exempted by Clause 17 of the Charterparty
33. In any event, the Respondent cannot rely on any exemptions under Clause 17 of the Charterparty,
as it has failed to fulfill the condition to rely on Clause 17. To rely on Clause 17, the Respondent
has to exercise due diligence to ensure that the Vessel is seaworthy,51 i.e. to exercise a reasonable
care and skill to make the vessel fit for foreseeable perils of the sea.52
34. In the present case, the Claimant maintains its position that the Vessel was unseaworthy when it
sails on the Voyage. The Respondent, despite knowing the possibility of the solar flares since a
week before the Voyage, failed to equip the Vessel with hardcopy nautical charts to Dillamond as
well as communication equipment capable to significantly enhance the probability of survival in
the event of such solar flares.53 A reasonable prudent owner, exercising reasonable care, would
not have allowed the Vessel to undertake its Voyage without such hardcopy nautical charts and
adequate communication equipment on board. Therefore, the Respondent has failed to exercise
its due diligence to ensure the Vessel was seaworthy when it sails on the Voyage, and the
Respondent cannot be exempted under Clause 17.
51 Moot Scenario, p. 9. 52 Riverstone Meat Co Pty Ltd v Lancashire Shipping Co Ltd (The Muncaster Castle) [1961] AC 807; The Eurasian
Dream [2002] 1 Lloyd’s Rep 719; McFadden v Blue Star Line, [1905] 1 K.B. 697 (UK); FC Bradley & Sons Ltd v
Federal Steam Navigation Co [1926] 24 Ll L Rep 446, 454; Eridania SpA & Ors v. Oetker & Ors (‘The Fjord Wind’)
[2000] C.L.C. 1376. 53 Team 17 Memorandum for Claimant, ¶¶14-20.
11
D. The Delay Caused Claimant’s Loss
35. The settlement payment arising out of the delay is recoverable. Damages resulting from breach of
contract are claimed upon what may be reasonably be supposed to be in the contemplation of
both parties at the time they made the contract as the probable result of the breach.54 In the
present case, the Respondent was informed at the time the Charterparty was signed that the Cargo
was to be urgently shipped to meet the demands of the Claimant’s client.55 A settlement payment
would be a loss which would have been reasonably contemplated by the Respondent, having
been informed of the urgent nature of the shipment demanded by a third party. Hence, the loss
caused by the delay is recoverable, and the Claimant is entitled to claim the settlement payment.
IV. THE RESPONDENT IS LIABLE FOR THE LOSS RESULTING FROM ITS FAILURE
TO TAKE REASONABLE CARE OF THE CARGO UNDER BAILMENT
36. On 31 July 2017, approximately at 1:17 PM, the Claimant took the Cargo.56 It was later found
that the Cargo inside three containers was damaged.57 As a result, the Claimant suffered loss for
the damaged Cargo and had to purchase a replacement cargo for Coffees of The World. The
Claimant submits that the Respondent is liable for the damages.
37. As set out in Hobbs v Petersham Transport Co Pty Ltd (1971),58 "the obligation of a carrier as
bailee is to exercise due care, skill and diligence for the safety of chattels entrusted to him."59
The duty only ceases when the goods have been delivered.60 A failure to deliver them safely at
the end of the bailment constitutes a prima facie evidence of a failure to perform his duty to
54 Hadley v Baxendale (1854) 2 CLR 517; Automatic Totalisators Ltd v Oceanic Steamship Co [1965] NSWR 702;
Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB; Koufos v C Czarnikow Ltd (The Heron II),
[1969] 1 A.C. 350 (1967); The Commonwealth of Australia v. Amann Aviation Pty. Limited [1991] HCA 54. 55 Moot Scenario, p. 2. 56 Ibid, p. 24. 57 Ibid, p. 43. 58 Hobbs v Petersham Transport Co Pty Ltd (1971) 124 CLR 220; Westrac Equipment Pty Ltd v Owners of Ship “Assets
Venture” [2002] FCA 440 (2002). 59 Hobbs v Petersham Transport Co Pty Ltd (1971) 124 CLR 220; 45 ALJR 356; Gilchrist Watt & Sanderson Pty Ltd v
York Products Pty Ltd [1970] 1 WLR 1262; Morris v C W Martin & Sons Ltd [1966] 1 QB 716; The Pioneer Container
[1994] C.L.C. 332. 60 Gilchrist Watt & Sanderson Pty Ltd v York Products Pty Ltd [1970] 2 NSWR 156.
12
exercise due care, rendering him liable for the damages.61 He can only be exempted by showing
that their loss or damage was not the result of any default on his part. 62
38. In the present case, (A) the Respondent is under duty to take reasonable care of the Cargo as
bailee; (B) the Cargo was damaged under the Respondent's custody as a Bailee; further (C.) the
damage was caused by the Respondent's failure to take reasonable care of the Cargo. Further, (D)
the Claimant is entitled to recover for the damaged Cargo and the replacement cargo, and (E) the
Respondent cannot limit its liability pursuant to Article IV rule 5 of the HVR.
A. The Respondent is under a Duty to Take Reasonable Care of the Cargo as a Bailee
39. Bailment exists upon "a delivery of goods of one person, the bailor, into the possession of
another person, the bailee, upon a promise ... that they will be re-delivered to the bailor or dealt
with in a stipulated way."63 Here, on 24 July 2017 the Claimant delivered, and the Respondent
accepted the possession of the Cargo, evidenced by the dock receipt.64 Further, under the
Charterparty the Respondent undertook to deliver the Cargo back to the Claimant at the Port of
Dillamond.65 This shows that the relationship between the Claimant and the Respondent
constitutes a bailment. Therefore, the Respondent owes a duty of care for the Cargo.
B. The Cargo was Damaged under the Respondent's Custody as a Bailee
40. The Respondent’s duty as a bailee to take reasonable care of the Cargo only ceases after it has
delivered the Cargo.66 Here, the Cargo was damaged sometime between 4:30 AM on 30 July
2017 and 4:30 AM on 31 July, before it was delivered to the Claimant.67
41. In Australian United Steam Navigation Co. Ltd v. Hiskens (1914), the court held that delivery as
a transfer of possession is a matter of agreement, and thus delivery occurred when the carrier had
61 Morris v C W Martin & Sons Ltd [1966] 1 QB 716. 62 Ibid. 63 Hobbs v Petersham Transport Co Pty Ltd 1971) 124 CLR 220; Westrac Equipment Pty Ltd v Owners of Ship (Assets
Venture) [2002] FCA 440 (2002). 64 Moot Scenario, p. 16. 65 Ibid, p. 3, 4. 66 Gilchrist Watt & Sanderson Pty Ltd v York Products Pty Ltd [1970] 2 NSWR 156. 67 Moot Scenario, p. 43.
13
performed the agreed mode of transfer of possession.68 However, in the present case, there was
no agreement as the method of Cargo delivery. Clause 14 of the Charterparty only provides that
delivery must be made "always afloat as customary to the nominated discharge port or ports,
bearing in mind the individual port / berth restrictions to which the vessel must comply."69 This
does not govern the method as to how the Cargo has to be transferred.
42. The Respondent might argue that the Parties have agreed to use the electronic access sent by the
Respondent at 4:28 PM on 29 July 2017 as the method of delivery since the Claimant did not
reply to its email. However, it is established that silence or failure to reject an offer will not
constitute an acceptance.70 Hence, the Claimant’s silence after the Respondent sent the electronic
access attached to the Respondent’s email on 29 July 2017 does not constitute as an agreement as
to the mode of the delivery. Since there has been no agreement as to the method of delivery, the
Respondent’s dispatch of electronic access does not constitute as delivery of the Cargo.
43. In the absence of any agreement as to the method of delivery, delivery only occurs when the
goods are “placed under the absolute dominion and control of the consignees.”71 That is when
“they are so completely in the custody of the consignee that he may do as he pleases with
them.”72 The carrier has to surrender the possession of the goods to the consignee, which is done
when the carrier has divested himself of all powers to control any physical dealing in the goods
to the person entitled to receive the goods.73 Delivery only occurs when the Cargo is placed
68 Australasian United Steam Navigation Co. Ltd. v. Hiskens (1914) 18 CLR 646. 69 Moot Scenario, p. 8. 70 Empirnall Holdings Pty Ltd v Machon Paull Partners Pty Ltd (1988) 14 NSWLR 523 ; Felthouse v Bindley (1862) 11
CB (NS) ; 869142 ER 1037; Fairline Shipping Corporation v Adamson [1975] QB 180; M Powell, “Acceptance by
Silence in the Law of Contract” (1977) 5 Aust Bus L Rev 260; W J Grosse, “Silence as Acceptance” (1982) 9 Sthn Uni L
Rev 81; J Beatson, “Abandoning the Contract of Abandonment?” (1986) 102 LQR 19 at 21; M J Lawson “Silence May
Not be Golden” (1987) Lloyd's Maritime and Com LQ 155; M J Lawson, “Abandonment of Arbitration by Silence or
Inactivity” (1987) Lloyd's Maritime and Com LQ 263. 71 Australasian United Steam Navigation Co Ltd v Hiskens (1914) 18 CLR 646; Chartered Bank v. British India S.N. Co.
[1909] A.C. 369, 375. 72 The British Shipowners’ Company (Limited) v. J. and A. D. Grimond No. 152. (1876) 3 R. 968. 73 Glencore International AG v. MSC Mediterranean Shipping Co SA & Anor. [2015] EWHC 1989 (Comm); Cooke on
Voyage Charters (4th Edn, 2014) at ¶10.4; Australasian United Steam Navigation Co. Ltd. v. Hiskens (1914) 18 CLR
646.; Automatic Tube Co and Email Ltd v Adelaide Steamship Co (The Beltana), The "Beltana" [1966] WAR 103.
14
under the Claimant’s absolute dominion, free from the Respondent’s power to control the
physical dealing of the goods.74
44. The Cargo was also not under the dominion of the Claimant when the Cargo was offloaded and
stored in the electronic system maintained by the port authority. In Great Eastern Shipping Co
Ltd v Far East Chartering Ltd (2012),75 it was held that delivery occurred because the shipowner
had surrendered possession to the consignee. In contrast, the Respondent in the present case had
not surrendered possession when it offloaded the Cargo into the electronic system. Anyone with
the barcode, including the Respondent, can always take the Cargo.
45. The Cargo was only under the Claimant’s absolute dominion at 1:17 PM on 31 July 2017, i.e.
when the Claimant had the possession of the Cargo.76 That was the time when the Cargo was
placed under the absolute dominion and control of the Claimant, so as the Claimant could do
anything with the Cargo.
46. In the event that this Tribunal deems the Claimant’s use of the electronic access as an acceptance
to the Respondent's offer, this only occurred at 1:17 PM, after the Cargo was damaged. Hence,
the damage still occurred before the delivery, and the Respondent remains liable.
C. The Damage to The Cargo was Caused by The Respondent’s Failure to Take
Reasonable Care of The Cargo
47. A bailee is only exempted by the liability arising from the damages to the Cargo if he can prove
that the loss or damage was not the result of any default on his part.77 It is the Respondent's
burden to show that the Cargo was not damaged by any default on his part. However, the
Respondent is not exempted under this present circumstance. The standard of care and diligence
is that which a careful and vigilant man would exercise in respect of goods of his own of the
74 Glencore International AG v. MSC Mediterranean Shipping Co SA & Anor [2015] EWHC 1989 (Comm); Australasian
United Steam Navigation Co. Ltd. v. Hiskens (1914) 18 CLR 646; Automatic Tube Co and Email Ltd v Adelaide
Steamship Co (The Beltana) [1966] WAR 103. 75 Great Eastern Shipping Co Ltd v Far East Chartering Ltd (2012) WL 608696. 76 Moot Scenario, p. 24, 25. 77 Hobbs v Petersham Transport Co Pty Ltd (1971) 124 CLR 220; Westrac Equipment Pty Ltd v Owners of Ship “Assets
Venture” [2002] FCA 440 (2002); Houghland v. R. R. Low (Luxury Coaches) Ltd. [1962] 1 QB 694; Global Dress
Company Ltd. v. Boase & Co. Ltd. [1966] 2 Ll.L.R. 72.
15
same kind in similar circumstances.78 In this present case, In the present case, as evidenced in the
statement of expert opinion, the Cargo was damaged due to an unprecedented rainfall and
prolonged use of the sealant.79 The Respondent failed to fulfill its duty of care to the Cargo, by
using waterproof containers that only lasted for five days and subsequently discharging the Cargo
during a heavy rainfall.80
48. It is a general practice that containers used to ship coffee beans had to be watertight.81 In Stemcor
v CV Scheepvaartonderneming Ankergracht (2005),82 when it is known to the carrier that the
Cargo was sensitive to moisture, it was reasonable for the carrier to take steps to prevent the
Cargo to be water-damaged, even though the steps are beyond what is required in general
practice.83 Further, heavy weather and ordinary perils which might delay the voyage are usually
expected.84 In the present case, the Claimant emphasised prior to the Voyage that since the risk of
moisture damage to the Cargo is too great, it is imperative that the containers used are entirely
waterproof.85
49. A vigilant man would not provide waterproof sealants that only last for five days knowing that it
ordinarily takes more than four days to complete the voyage, as risk of delay is well-known in the
shipping industry. A vigilant man would fear that the voyage might be delayed, and the Cargo
might be exposed to water. Therefore, the Respondent should have taken reasonable care and
provide waterproof sealants that last longer than the Voyage to provide for unexpected peril.
50. Further, when it is known to the carrier that the goods are perishable by water, he is considered to
be negligence when he discharges the during a heavy rain.86 In the present case, the Cargo was
78 Hobbs v Petersham Transport Co Pty Ltd (1971) 124 CLR 220. 79 Moot Scenario, p. 43. 80 Ibid, p. 14, 43. 81 Procedural Order No. 2, ¶12; International Chamber of Shipping, "Safe TransPort of Containers by Sea: Guidelines on
Best Practices" (London: Marisec Publications, 2008), p. 38; International Trade Centre, "The Coffee Exporter's Guide",
(Genevam, 2011) p. 94. 82 Stemcor v CV Scheepvaartonderneming Ankergracht [2005] FCA 1808. 83 Stemcor (A/sia) Pty Ltd v CV Scheepvaartonderneming Ankergracht [2005] FCA 1808; C V Sheepvaartonderneming
Ankergracht v Stemcor (A/sia) Pty Ltd [2007] FCAFC 77. 84 Gamlen Chemical Co (A/asia) Pty Ltd v Shipping Corporation of India Ltd 34 FLR 305. 85 Moot Scenario, p. 2. 86 Nikolay Malakhov Shipping Co Ltd v SEAS Sapfor Ltd (1998) 44 NSWLR 371; East & West Steamship Co v Hossain
Bros [1968] 2 Lloyd's Rep 145; The Arawa [1977] 2 Lloyd's Rep 416.
16
offloaded at 12:02 AM on 30 July 2017. It was reported that 350 mL of rain fell 24 hours since
1:00 AM 29 July 2017 and haven’t eased up since then. Hence, on 29 July, when the Cargo was
discharged, it should be known by the Respondent that the containers were no longer waterproof
and the Cargo might be damaged by the rain. Yet, the Respondent discharged the Cargo and
exposing the Cargo to the rain. Therefore, the Respondent has failed its duty to take care of the
Cargo and hence liable for the loss resulting from the damage to the Cargo.
D. The Claimant is entitled to recover for the damaged Cargo and the replacement cargo
51. A party can recover from a loss that is within the reasonable contemplation of the parties.87 That
is, when the loss ‘does not unlikely to result from a breach’.88 When there are special
circumstances resulting to a loss that does not naturally arise from a breach, the Claimant is
entitled to damages when such circumstances were made known to the Respondent prior to the
conclusion of the contract.
52. In the present case, the Claimant has informed the Respondent that it has promised to deliver the
Cargo to its client for a coffee festival in Dillamond on 29-31 July.89 It is again reiterated on the
Dock Receipt that the Cargo was meant for immediate sale.90 It is not unlikely that as a result of a
damaged Cargo, the Claimant had to buy a replacement cargo to fulfill its promise to a third
party. Hence, the Claimant is entitled to recover for such loss.
E. The Respondent Cannot Limit Its Liability Pursuant to Article IV rule 5 of the HVR
53. The Respondent is not entitled to limit its liability pursuant to Article IV rule 5 of the HVR by
virtue of the Paramount Clause contained in the Charterparty, because the damage to Cargo
resulted from its own personal act, which was committed recklessly, with the knowledge that the
loss would probably result.
87 Hadley v. Baxendale (1854) 9 Exch. 341; Victoria Laundry (Windsor) Ltd v Newman Industries Ltd [1949] 2 KB;
Koufos v C Czarnikow Ltd (The Heron II), [1969] 1 A.C. 350 (1967); The Commonwealth of Australia V. Amann
Aviation Pty. Limited [1991] HCA 54. 88 Ibid. 89 Moot Scenario, p. 1, 38, 41; Procedural Order ¶6. 90 Ibid, p. 16.
17
54. Article IV rule 5 (e) of HVR stipulates that a carrier will not be entitled to limit its liability if it is
proved that the damage is results an act or omission of the carrier which is committed with
“intent to cause damage”, or “recklessly” and “with knowledge that damage would probably
result”. On a proper construction, it is to be interpreted that commission of the act or omission is
not only qualified by the alternative adverbs “with intent to cause damage” or “recklessly”, but
also by the adverbial phrase “with knowledge that damage would probably result.”91 However,
when an act or omission is alleged to be done “recklessly”, it is sufficient to prove the word
“recklessly”,92 since a conduct is stigmatised as reckless when a conduct is done with omission
of the knowledge that damage would probably result.93
55. In the present case, the Respondent provided the Cargo with waterproof sealants that only last for
five days despite knowing the risk of delay in the shipping industry. Further, despite knowing
that the containers were no longer waterproof, the Respondent decided to discharge the Cargo at
the Port of Dillamond, causing it to be exposed to heavy rain. Knowing that the Cargo was water-
sensitive and the risk of moisture damage was too great, the Respondent neglected the risk that
such conduct may cause damage to the Cargo. As a result, the Cargo was damaged, as
corroborated by the statement of expert opinion.94 As such, the damage to the Cargo was a result
from the Respondent’s reckless act, and as a consequence, it is not entitled to limit its liability
under Article IV Rule 5 of Hague Visby Rules.
V. THE CLAIMANT IS ENTITLED TO AN EQUITABLE MARITIME LIEN OVER THE
VESSEL
56. The Claimant advanced USD100,000 to cover the Vessel's crew wages at the Respondent’s
request.95 Until the present time, the Respondent has not paid its crew nor has it repaid the
91 Ontario Bus Industries Inc v Federal Calumet (The) (TD) [1991] FCJ 535; Goldman v Thai Airways International Ltd
[1983] 1 WLR 1186, 1194. 92 Goldman v Thai Airways International Ltd [1983] 1 WLR 1186, 1194. 93 Goldman v Thai Airways International Ltd [1983] 1 WLR 1186, 1194; Mediterranean Shipping Co SA v Delumar
BVBA (The “MSC Rosa M”) [2000] 2 Lloyd’s Rep 399, 401; Société Telus Communications v Peracomo Inc [2011] FC
494, 521; SS Pharmaceutical Co Ltd v Qantas Airways Ltd (1988) 92 FLR 231. 94 Moot Scenario, p. 43. 95 Ibid, p. 1, 38, 41.
18
Claimant.96 Although the outstanding amount does not give rise to a maritime lien, nonetheless,
(A) there is a maritime lien over the Vessel for the crew’s wages, and (B) the Claimant is entitled
to the equitable maritime lien for the crews’ wages by way of equitable subrogation.
A. There is a Maritime Lien Over the Vessel for the Crews’ Wages
57. A maritime lien is a right of one creditor of a particular claim to receive the proceeds of sale of a
vessel in priority over other creditors through an in rem proceeding against the vessel.97 A claim
that gives rise to a maritime lien under common law is crew wages,98 which exists in this present
case. A maritime lien for crew wages arises for the sums due to the crew for work done to the
ship,99 and is only extinguished at the moment the wages are paid to the crew.100 In the present
case, payment of crew wages provided by the Claimant in the amount of USD100,000 was
payable to the crew following the Voyage.101 However, the crew has not received such
payment.102 Therefore, the outstanding and unpaid wages to the Vessel's crew, allows for a
maritime lien over to the Vessel to be made, which survives until the present time.
B. The Claimant Is Entitled to The Equitable Maritime Lien for The Crews’ Wages By
Way Of Subrogation
58. The Claimant is entitled to receive the crews’ maritime lien for the sums advanced on account of
the crews’ wages under doctrine of equitable subrogation. This is because (i) the circumstances
give rise to equitable subrogation of the crew’s maritime lien; and (ii) nothing precludes this
equitable subrogation.
96 Ibid, p. 38, 41. 97 Bankers Trust International v Todd Shipyards Corp (The halcyon Isle) [1981] A.C. 221 (1980); The Bold Buccleugh
(1851) 7 Moo. P.C. 267. 98 Bankers Trust International v Todd Shipyards Corp (The Halcyon Isle) [1981] A.C. 221 (1980); The Bold Buccleugh
(1851) 7 Moo. P.C. 267; Nigel Meeson, Admiralty Jurisdiciton and Practice (Third Edition, Lloyd’s Shipping Law
Library, 2003), p. 62. 99 The “Tacoma City” [1991] 1 Lloyd’s Rep. 330; The “Chieftan” (1863) Br. & L. 104; The “Ruby” (No. 2) [1898] P.
59; The Tagus [1903] P. 44. 100 The Bold Buccleugh (1851) 7 Moo. P.C. 267. 101 Moot Scenario, p. 38, 41. 102 Ibid, 36; Procedural Order No.2, ¶11.
19
i. The circumstances give rise to equitable subrogation to the crew’s maritime lien.
59. Equitable subrogation allows a party that has made payments for another party to lay a claim to
the recovery of damages from a third-party, to prevent unjust enrichment.103 For example, where
a loan arrangement provides that a loan by a lender to a borrower is made to repay another third-
party secured loan,104 the lender is entitled to a subrogation of such third-party security.105
Mutual consent is not required for a party to claim for equitable subrogation.106
60. Before entering into the Charterparty, the Respondent requested the Claimant to loan
USD100,000 to the Respondent, to subsequently pay the Vessel's crew at the Voyage's
conclusion.107 The Claimant understood that once this payment has been disbursed to the
Respondent, the Respondent would then proceed to pay the wages of the Vessel's crew.108 In this
vein, a maritime lien may be asserted over the Vessel crew’s wages in respect of the
Respondent’s obligation to pay its crew.109
ii. Further, there are no circumstances precluding such equitable subrogation.
61. The Respondent may argue that the Claimant is precluded to be subrogated to the crew’s
maritime lien. Under these circumstances, equitable subrogation is not possible when the terms
of an agreement bar it,110 or if its application would produce an unjust result,111 for example,
when a party already receives what they bargained for.112 Thus, if the true nature of the
103 Menelaou v Bank of Cyprus Plc [2015] UKSC 66; Benedetti v Sawiris [2014] AC 938; Cheltenham & Gloucester Plc
v Appleyard & Another [2004] EWCA Civ 291; Orakpo v Manson Investments Ltd. [1978] AC 95; Graham Virgo, The
Principles of the Law of Restitution (Oxford University Press, 2016), p. 9. 104 Burston Finance Ltd v Speirway Ltd, [1974] 1 W.L.R. 1648 (1974); Swynson Ltd v Lowick Rose LLP (formerly Hurst
Morrison Thomson LLP) (in liquidation) [2017] UKSC 32.; Orakpo v Manson Investments Ltd. [1978] AC 95; Boodle
Hatfield & Co v British Film Ltd, (1986) 2 B.C.C. 99221 (1985); Brazzill v Willoughby [2009] EWHC 1633 (Ch); Ghana
Commercial Bank Appellants; v D. T. Chandiram and Another Respondents [1960] 3 W.L.R. 328; Wylie v. Carlyon
[1922] 1 Ch. 51; Paul v. Speirway Ltd. [1976] Ch. 220; Butler v Rice [1910] 2 Ch. 277. 105 Orakpo v Manson Investments Ltd. [1978] AC 95; Boodle Hatfield & Co v British Film Ltd, (1986) 2 B.C.C. 99221
(1985); Wylie v. Carlyon [1922] 1 Ch. 51; Paul v. Speirway Ltd. [1976] Ch. 220. 106 Banque Financiere de la Cite SA v Parc (Battersea) Ltd [1999] 1 A.C. 226. 107 Moot Scenario, p. 38, 41. 108 Ibid. 109 Ibid, p. 38, 41. 110 Boodle Hatfield & Co v British Film Ltd. (1986) 2 B.C.C. 99221 (1985); Orakpo v Manson Investments Ltd. [1978]
AC 95. 111 Boodle Hatfield & Co v British Film Ltd, (1986) 2 B.C.C. 99221 (1985); Paul v Speirway (In Liquidation), (1976) 31
P. & C.R. 353 (1976). 112 Paul v Speirway (In Liquidation), (1976) 31 P. & C.R. 353 (1976).
20
transaction is shown to be no more than a creation of an unsecured loan, there will be no
subrogation to any security.113
62. However, no such circumstances appear in this case. First, no terms have been agreed between
the Parties to bar subrogation of the maritime lien. Second, the true nature of the transaction at
hand is a secured one, and does not displace subrogation. Although it may seem that there has
been no agreement or discussion on security for the loan, this does not affect the right of
subrogation. In Boodle Hatfield & Co. v. British Films Ltd (1986)114 it was held that, the failure
of the lender to ask for security prior to entering into the loan agreement does not preclude
subrogation.115 If time constraints made it commercially unreasonable to hold further discussions
on security, the lender was deemed to not waive its right and interest for security.
63. Before the Voyage's commencement, its crew would not have sailed, without the sums advanced
by the Claimant. 116 The urgency of the Voyage made it imprudent to hold further negotiations on
security for the loan arrangement which may prove to be lengthy.117 Because of the approaching
deadline and the legal action threatened by the coffees of the world,118 it was only commercially
sensible not to not impend the Voyage further.119 However, this does not mean the Claimant has
forfeited any right as to security. The Claimant made it clear that it insisted on repayment and
take steps “to ensure our interest are adequately protected”.120 Thus, the absence of an agreement
or negotiation on security does not affect the Claimant's right to security.
64. Consequentially, as there are no circumstances preventing subrogation, the Claimant remains
entitled for the subrogation to the Crew’s maritime lien.
113 Paul v Speirway (In Liquidation), (1976) 31 P. & C.R. 353 (1976); Orakpo v Manson Investments Ltd. [1978] AC
95;Boodle Hatfield & Co. v. British Films Ltd. [1986] P.C.C. 176; Menelaou v Bank of Cyprus Plc [2016] A.C. 188;
Banque Financiere de la Cite SA v Parc (Battersea) Ltd [1999] 1 A.C. 226. 114 Boodle Hatfield & Co. v. British Films Ltd. [1986] P.C.C. 176. 115 Boodle Hatfield & Co. v. British Films Ltd. [1986] P.C.C. 176; Banque Financiere de la Cite SA v Parc (Battersea)
Ltd [1999] 1 A.C. 221 (1998). 116 Moot Scenario, p. 1. 117 Ibid. 118 Ibid, p. 1, 2. 119 Ibid, p. 1. 120 Ibid.
21
VI. THE CLAIMANT IS NOT LIABLE TO PAY FOR AMOUNTS CLAIMED UNDER THE
CHARTERPARTY IN FULL
65. In its Point of Defence, the Respondent submitted that the Claimant is liable for certain
outstanding amounts under the Charterparty.121 The Claimant denies its liability in full because
(A) the Claimant is not responsible for demurrage, the use of electronic access at the Port of
Dillamond, agency fee at the Port of Spectre, and the repair to the Vessel’s hull. Further, (B) the
Claimant is not liable for freight in full due to damages to the Cargo and (C) the Claimant is not
liable for the payment of the agency fee at the Port of Dillamond.
A. The Claimant is not responsible for demurrage, the use of electronic access at the Port
of Dillamond, the agency fee at the Port of Spectre, and the repair to the Vessel’s hull.
66. The Claimant is not obligated to make payment for the demurrage, use of electronic access at the
Port of Dillamond, agency fee at the Port of Spectre, and the repair to the Vessel’s hull from
Claimant. This is because (i) no demurrage is recoverable under the present circumstances.
Further, (ii) the Respondent's non-compliance with Clause 15 of the Charterparty bars from it
claiming demurrage, the use of electronic access at the Port of Dillamond, the agency fee at the
Port of Spectre, and the repair to the Vessel's hull.
i. No demurrage is recoverable under the present circumstances.
67. Under Clause 9 of the Charterparty, demurrage accrues when the discharge of the Cargo exceeds
laytime.122 Clause 8 (c) (ii) provides that the time allowed for discharge is 0.5 Weather Working
Days (“WWD”).123 Laytime only starts to count when the Vessel arrives at the discharge port,124
i.e. when the Vessel arrives at certain space of water where port can have its authority.125
121 Ibid, p. 41, 42. 122 Ibid, p. 7. 123 Ibid. 124 Ibid. 125 E.L. Oldendorff & Co. v. Tradax Export (The Johanna Oldendorff) [1974] A.C. 479 (H.L.); Federal Commerce v.
Tradax Export (The Maratha Envoy) [1978] A.C. 1; Sailing Ship Garston Co v. Hickie (1885) 15 QBD 580.
22
68. As decided in the case of Reardon Smith Line v. Ministry of Agriculture, Fisheries and, Food
(1963),126 ‘Weather Working Days’ means the time where weather allows discharging to
commence.127 Whether weather allows discharging to commence shall be determined by the
relevant circumstances and the Cargo.128
69. On 29 July 2017 at 7:00 AM, the Vessel had been instructed by the port authority to wait for
berth in the Port of Dillamond’s usual waiting area, and thus could be deemed to mark the start of
the laytime. Nonetheless, although laytime began on 29 July 2017 at 7:00 AM, 350 mL of rain
fell in Dillamond for 24 hours starting from 1:00 AM on 29 July 2017.129 This period could not
be deemed as a time where weather allows discharging to commence, since the Cargo was not fit
to be discharged during the rain. Although the Cargo was carried inside 4 containers sealed with
waterproof sealants,130 the Cargo was no longer protected by the waterproof sealants at the time
the Vessel arrived at the Port of Dillamond. These sealants were intended to be used for 5 days
only,131 starting from 24 July 2017 at 5:00 AM132 and ended on 29 July 2017 at 5:00 AM.
70. As discharging the Cargo from 5:00 AM on 29 July 2017 to 1:00 AM on 30 July 2017 was not
possible, this period does not qualify as a Weather Working Day, and laytime did not count
during such period. Thus, laytime has not ended when the Respondent decided to discharge the
Cargo on 30 July 2017 at 00:02 AM. Therefore, no demurrage accrued in the present case.
ii. The Respondent's non-compliance with Clause 15 of the Charterparty bars from it
claiming demurrage, the use of electronic access at the Port of Dillamond, the agency fee
at the Port of Spectre, and the repair to the Vessel's hull
71. Under Clause 15 (a) (i) of the Charterparty, the Respondent must ensure that the Vessel complies
with the applicable provisions under the Commonwealth of Australia Navigation Act 2012 and
126 Reardon Smith Line v. Ministry of Agriculture, Fisheries and Food [1963] A.C. 691, esp. p. 739; The Maria G [1985]
1 Lloyd's Rep 616. 127 Ibid. 128 Ibid. 129 Moot Scenario, p. 36. 130 Ibid, p. 14, 43. 131 Ibid, p. 42. 132 Procedural Order No. 2, ¶13.
23
the Regulations thereunder.133 For any delay caused by the Vessel’s failure to comply with such
requirements, Clause 15 (b) provides that, “… time shall not count nor demurrage accrue during
the period of such delay and any extra expenses incurred, including cost of stevedoring/receival
labour, equipment and truck demurrage, ordered and not used, to be for Owners’ account.”
72. In the present case, the Respondent’s failure to comply with the Commonwealth of Australia
Navigation Act 2012 and the Regulations caused its failure to deliver the Cargo on time.134
Demurrage, if any, would accrue during the period of the delay. Here, the period of delay is
accounted from the time between the Delivery Deadline and the actual time of the Cargo's
discharge, namely on 1:17 PM on 31 July 2017. Consequentially, demurrage could only be
claimed by the Respondent if it was not during the period of such delay. Therefore, there is no
demurrage payable to the Respondent.
73. Consequentially, the use of electronic access at Dillamond, the agency fee at the Port of Spectre,
and the repair to the Vessel’s hull are also not claimable by the Respondent. These costs are extra
expenses that have not been agreed by the Parties under the Charterparty, all of which were
incurred after the Respondent’s own failure to comply with the applicable regulations. Therefore,
pursuant to Clause 15 (b), none of these extra expenses are recoverable to the Respondent.
B. The Respondent is not entitled to freight in full upon damages to the Cargo
74. When there is damage to cargo to such a degree that it destroys the commercial identity of the
cargo, the cargo is regarded as totally lost. Consequentially, where the earning of freight is
dependent upon delivery, freight is not earned, irrespective of whether the shipowner is liable for
the loss.135 The test for whether there is a total loss of the goods was provided in Asfar & Co. v
Blundell (1896),136 where Lord Esher MR held that, “If it is so changed in its nature by the perils
of the sea as to become an unmerchantable thing, which no buyer would buy and no honest seller
133 Moot Scenario, p. 8. 134 Team 17 Memorandum for Claimant, ¶¶14-24. 135 Duthie v. Hilton (1868) L.R. 4 C.P. 138; Asfar v. Blundell [1896] 1 Q.B. 123; Montedison S.p.A. v. Icroma S.p.A.
(The Caspian Sea) [1980] 1 Lloyd’s Rep. 91. 136 Asfar & Co. v Blundell [1896] 1 Q.B. 123
24
would sell, then there is a total loss.” Kay LJ further affirmed that a mere destruction of the
merchantable character of the goods is sufficient to create total loss.137
75. In the present case, 75% of the Cargo became unmerchantable when it was delivered to the
Claimant, verified by the analysis of an independent surveyor to be completely water damaged,138
depriving the Claimant with any willful buyers.139 Thus, the Respondent is not entitled to freight
in its full amount. At best, the Respondent it is only entitled to 25% of the freight in the amount
of USD125,000.
C. The Claimant is not liable for the payment of agency fee at the Port of Dillamond in a
separate amount with the freight
76. Under Clause 12 of the Charterparty, customary fees at the discharge port shall be paid by the
Vessel.140 The Parties have further agreed under Clause 22 that the calculation of the freight is
based on bill of lading weight on completion of load, “…in full of all port charges, pilotages,
light dues and all other dues usually paid by vessels.”141 This means that the Parties have
intended that all dues usually paid by the Vessel is included as part of the freight.
77. However, the current freight was not calculated on the bill of lading weight on completion of
load as stipulated under Clause 22, but based on the numbers of containers loaded upon the
conclusion of the Charterparty.142 This has caused a void on who should bear the fees paid by the
Vessel, when the freight was not calculated based on the method stipulated under Clause 22.
78. When there is a deficiency in the express term of an agreement, to foster business efficacy, a
tribunal is open to imply a term to foster business efficacy.143 The ground for implication of a
term lies on five conditions to be, i.e. it must be: “(1) reasonable and equitable; (2) necessary to
give business efficacy to the contract; (3) so obvious that ‘it goes without saying’; (4) capable of
137 Asfar & Co. v Blundell [1896] 1 Q.B. 123. 138 Moot Scenario, p. 44. 139 Ibid, p. 27. 140 Ibid, p. 7. 141 Ibid, p. 11. 142 Ibid, p. 3. 143 Codelfa Construction Pty Ltd v State Rail Authority (NSW) (1982) 149 CLR 337; Secured Income Real Estate
(Australia) Ltd v St Martins Investments Pty Ltd [1979] HCA 51.
25
clear expression; (5) not contrary with any express term of the contract.”144 In assessing such
condition, this Tribunal shall objectively ascertain and reinforce the presumed intention of the
Parties by seeing the factual matrices.145
79. In the present case, seeing the absence of contradictory express terms under the Charterparty, it
would only be reasonable to imply that under Clause 22, the Parties have intended that the fees
charged at the discharge port to be included as part of the calculation of freight. Consequently,
the Respondent is not entitled to claim such fees in a separate amount with the freight.
PRAYER FOR RELIEF
For the reasons submitted above, the Claimant respectfully requests this Tribunal to:
DECLARE that it does have jurisdiction to hear the merits of the Claimant’s claims;
Further,
ADJUDGE that the Respondent is liable to the Claimant for:
1. USD15,750,000 on account of the damaged Cargo;
2. USD9,450,000 for the replacement cargo; and
3. USD5,000,000 on account of the settlement payment;
Further,
ADJUDGE that the Respondent is not entitled to limit its liability in respect of the Claimant’s
claims;
Further,
ADJUDGE that the Claimant holds a maritime equitable lien over the Vessel; and
ADJUDGE that the Claimant is not liable for the sums claimed by the Respondent in full.
144 B.P. Refinery (Westernport) Pty. Ltd v Hastings Shire Council. (1977) 180 CLR 266. 145B.P. Refinery (Westernport) Pty. Ltd v Hastings Shire Council. (1977) 180 CLR 266; Scanlan's New Neon Ltd v
Tooheys Ltd (1943) 67 C.L.R. 169.