technical specification - engineering...

29
TENDER DOCUMENT NIT No.: DLI/C&E/WI-665/286 FOR Tender for „Design, Engineering, Supply, installation, testing and commissioning of MVWS & IG-541 TYPE FIRE PROTECTION WITH FDA PACKAGE AND ASSOCIATED WORKS‟ for the project of “Augmentation of Raw Material Handling Receipt and Handling facilities with new OHP PartB (Package- 061) of Bhilai Steel Plant, (SAIL)”. VOLUME 2B TECHNICAL SPECIFICATION ENGINEERING PROJECTS (INDIA) LIMITED (A GOVT. OF INDIA ENTERPRISE) Core-3, Scope Complex, 7, Institutional Area, Lodhi Road, New Delhi-110003 TEL NO: 011-24361666 FAX NO. 011- 24363426

Upload: buituong

Post on 08-Feb-2018

222 views

Category:

Documents


2 download

TRANSCRIPT

TENDER DOCUMENT

NIT No.: DLI/C&E/WI-665/286 FOR

Tender for „Design, Engineering, Supply, installation, testing and commissioning of MVWS & IG-541 TYPE FIRE PROTECTION WITH FDA PACKAGE AND ASSOCIATED WORKS‟ for the project of “Augmentation of Raw Material Handling Receipt and Handling facilities with new OHP Part– B (Package- 061) of Bhilai Steel Plant, (SAIL)”.

VOLUME – 2B

TECHNICAL SPECIFICATION

ENGINEERING PROJECTS (INDIA) LIMITED (A GOVT. OF INDIA ENTERPRISE)

Core-3, Scope Complex, 7, Institutional Area, Lodhi Road, New Delhi-110003

TEL NO: 011-24361666 FAX NO. 011- 24363426

EPI – New Delhi Volume-2B, Rev.0 Page 1 of 28

VOLUME - 2B

CONTENTS

Sl. No.

DESCRIPTION

1.

Documents/information to be furnished alongwith offer

2.

Scope of Supply

3. Brief System Description

4.

Technical Specifications –MVWS & IG-541 type Fire

Protection with FDA Package

5.

Spares

6.

Technical data sheet (to be filled by the vendor)

EPI – New Delhi Volume-2B, Rev.0 Page 2 of 28

GENERAL

The following Technical Specification shall be read in conjunction with General

Technical Specification (GTS) of Bhilai Steel Plant, SAIL and General

Specification. If there are any provisions in this Technical Specification, which

are at variance with the provisions of General Technical Specification (GTS) of

Bhilai Steel Plant, SAIL and General Specification, the provisions in this

Technical Specification shall take precedence.

1.0 DOCUMENTS/ INFORMATION TO BE FURNISHED

ALONGWITH OFFER.

(i) Clear Scope of supply.

(ii) Type and quantity of oil, lubricants & consumables for initial fill till

successful commissioning of equipment.

(iii) List of Commissioning spares and start-up spares with unit rates.

(iv) List with unit rates of special tools and tackles, if any required.

(v) Price Schedule for supply & erection work as per the format enclosed.

(vi) List of recommended spare parts for 3 years trouble free operation and

maintenance alongwith unit rates as per the format enclosed in price

schedule.

(vii) Technical Data sheets duly filled by the vendor (blank data sheets

enclosed).

(viii) Weight of the equipment in Kgs.

(ix) Catalogues/ Leaflets and O&M Manuals.

(x) Reference list of your Customers for the similar supply of items.

(xi) Unpriced Copy

EPI – New Delhi Volume-2B, Rev.0 Page 3 of 28

2.0 SCOPE OF SUPPLY

The scope of the supply includes Design, engineering, manufacture, shop

fabrication. assembly, testing and inspection at manufacturer’s works,

packing , dispatch, transportation, delivery to site, receipt, required

fabrication at site, installation, testing & commissioning completion of

facilities, performance guarantee testing, final painting at site and handing

over to Bhilai Steel Plant, SAIL / EPI of COMPLETE MVWS & IG-541

TYPE FIRE PROTECTION WITH FDA PACKAGE AND ASSOCIATED

WORKS as per specifications and scope defined in tender documents

complete with all accessories and drive, which are not mentioned specifically

but are required for the efficient and trouble free operation of the

equipment/system.

2.1 Following items are also included in bidder’s scope.

(i) Complete items as per the details given in the specifications.

(ii) Consumables like first fill of lubricating oils etc. for the initial

operation of the equipment till handing over.

(iii) Commissioning spares and start-up spare parts.

(iv) Special tools & tackles, if any required.

(v) Recommended spare parts for (3) three years trouble free operation

and maintenance.

(vi) Painting of complete equipment (including final painting before

handing over to the Employer).

(vii) Installation, testing & commissioning at site.

(viii) All drawings/documents along with operation and maintenance

manuals as per requirement mentioned elsewhere in the tender

document.

(ix) Getting approval of design/drawings and any other design calculation

related to the equipment from BSP/MECON/EPI.

(x) 3 Ph, 415V +10% & -15%, 50Hz +4% & -6% power supply shall be

provided at Power cum Control Panel of Ventilation at one point only

through power cables. Other voltage levels, if required shall be

arranged by the bidder itself. Installation, testing & commissioning of

panel shall be in Bidder’s scope.

(xi) Carrying out any modifications/deletions/additions/alteration in

design/drawings/documents as required by client & Client’s

consultant and EPI for proper execution of works at site till

completion and handing over of the project to the client.

(xii) Drinking Water & Construction Power shall be provided free of cost to

the bidder at one point. However, further distribution shall be in the

bidder’s scope. Bidder has to ensure the optimum and effective

utilization of Construction Water & Construction Power.

(xiii) Construction Water shall be arranged by the bidder themselves.

EPI – New Delhi Volume-2B, Rev.0 Page 4 of 28

2.2 Bidder to note the following:

1) BSP approved preferred make list shall be followed for Hydraulics &

Pneumatics.

2) All HT and LT AC/DC motors, actuators, brakes etc. as per technological

and process requirement.

3) Generally Squirrel Cage Induction Motor with DOL starter / Soft Starter

will be provided. Use of Slip ring motor in general will be avoided. Suitable

Rotor contactor panels and SS-grid Resistance Boxes will be provided for

slip ring motors if inevitable.

4) Soft starter will be provided for LT motors of rating more than 75kW.

5) All LT motors for conveyors will be S6 duty and will have class F insulation

with temperature rise limited to class B.

6) Equipment selection and dating will generally be based on ambient

temperature of+50 Deg.C. For specific areas and shops, the ambient

temperature conditions indicated above will be taken into consideration

and equipment suitably derated wherever necessary.

7) The equipment should be suitable for smooth, efficient and trouble free

service in the tropical humid climate prevailing at plant site and under the

ambient temperature conditions indicated above for the different shops

and areas. In hot areas of higher temperature conditions, the equipment

will be adequately protected against damage from radiant heat and hot

air.

8) Roller bearings will be provided at DE end for motor of rating 30KW and

above.

EPI – New Delhi Volume-2B, Rev.0 Page 5 of 28

3.0 BRIEF SYSTEM DESCRIPTION

The turnkey package of this Contract Document comprises of the following sub-

systems:

1) New Ore Handling Plant (OHP-II) including receiving, unloading,

Stacking & Reclaiming and finally transporting of Raw Material required for

Blast Furnace #8, Sinter Plant-III.

2) New conveyor line for New Lime Dolomite plant RMP3 and for proposed

SMS-III.

3) Modifications/ up-gradations of existing equipment, including:

An additional series of conveyor from OHP I to JH-20 and JH-

42(Exst’g) parallel to existing route.

Up gradation of capacity of existing shuttle conveyors J9BRSC1.

3.1 New Ore Handling Plant (OHP-II)

The raw material to be handled by the proposed system is mainly, Iron Ore

Lump, Iron Ore Fines, Lime Stone (BF grade), Lime Stone (SMS grade),

Dolomite (BF grade), Dolomite (SMS grade), Quartzite, Manganese ore. These

raw materials are mainly required for Blast Furnace, Sinter Plant, Lime-

Dolomite Plant, SMS. All the raw materials will be received at the plant

boundary by rail. The type of Wagon will be BOXN, BOXNHA, BOY, BOBRN,

BOST, BOBS, BOXNEL, BOYL,BOXN HS etc which will transport the raw

materials depending upon the location of loading and type of raw materials.

(i) Design Considerations

The Ore Handling Plant (OHP-II) has been planned based on the following

assumption:

A. Size of Raw Material

1. Lump Iron Ore : -40 mm

2. Iron ore fines : - 8 mm

3. Lime Stone (BF/SP grade) : -60 mm

4. Dolomite (BF/SP grade) : -60 mm

5. Quartzite : -50 mm

6. Lime Stone (SMS grade) : -25 mm

7. Dolomite (SMS grade) : -25 mm

8. Pellets : -18 mm

9. Manganese Ore : -25 mm

10. Coke Breeze : -25 mm

B. No of Days of Working per year: 330 days

EPI – New Delhi Volume-2B, Rev.0 Page 6 of 28

C. Maximum material carrying capacity of each wagon shall be as per IS:

10095-1982 reaffirmed 2001. Iron-ore-lump will be received in Track-

Hopper & all other material in Wagon Tipplers. Two Track Hoppers have

been considered for materials received in BOBS/ BOBRN wagons (mainly

iron-ore), whereas wagon tippler with side arm charger has been considered

for unloading the materials received in BOXN/BOST/ BOXNHA/BOY/BOBS,

BOXNEL, BOYL wagons.

(ii) UNLOADING, STORAGE, BLENDING AND RECLAIMING IN OHP-II

One number Wagon tippler WT no.B1 along with a Track Hopper TH-B1 with

two parallel tracks on it have been envisaged for unloading Iron ore (lump and

fines), Limestone & Dolomite (both BF grade and Sinter Plant grade), Mn-ore,

Quartzite etc.

The Wagon Tippler shall be of Rota-side type capable of unloading BOXN and

proposed BOXNHA ,BOXNHS, BOBS, BOY wagons as per IS:10095-1982,

reaffirmed 2001. The rated unloading capacity shall be rated 20 Tips/hour.

Adequate system of handling sticky rakes such as vibrator/ air blaster shall be

provided.

25t wagon axle load and 110t gross weight of wagons (BOX, BOXN, BOXN HA,

BOXN HS, BOXN EL, BOYEL) to be considered for design of Wagon Tippler and

track hopper. 2 nos. Weighbridges included in contractor's scope. The location

of Weigh Bridge shall presently be considered at entry of pre hopper yard.

However as the total railway track is being engineered by RITES, the location of

Weigh Bridge may undergo change in detailed engineering stage. The drawings

of wagon tippler/track hopper shall be subjected to approval by RITES

/SECR/RDSO as applicable.

The placement of rakes shall be done by Side arm chargers capable of handling

a full rake BOXN, BOXNHA, BOBS, BOY, BOXN EL, BOYEL wagons.

Two nos. of track hopper each of length 210 m excluding maintenance bay and

holding capacity of 6000 t each considering material of bulk density of 1.6 t/

cu.m. shall be included in contractor's scope. The side angle of hopper with

vertical shall be minimum 60 deg. Each hopper shall have four compartments.

Track hopper envisaged to accommodate minimum 18 BOBS wagons.

Contractor to maintain sufficient height of the track hopper superstructure to

take care of OHE.

Total 4 nos. Electric hoist of 5 t capacity shall be provided for maintenance of

Paddle Feeder at both ends of Track Hopper building. Two nos. double door

pressurized cabin shall be provided for paddle feeder inside the track hopper

tunnel. Anti-derailment device/ check rail shall be provided in the track hopper

subject to approval of RITES. Supply / Laying of 60 kg/ m rail with continuous

MS insert plate within track hopper building only are in scope of contractor.

In addition to the above, one dedicated compressor station at track hopper TH-

B1for unloading of BOBRN wagons is to be provided. Compressed air connection

to BOBRN wagons to be provided at 15 mts interval. The details of requirement

of compressed air, the pressure and type shall be obtained from RDSO. Other

points as applicable for compressed air station shall be considered as per CS for

compressed air facilities indicated elsewhere.

EPI – New Delhi Volume-2B, Rev.0 Page 7 of 28

Provision of adequate illumination should be there on both pre & post tippler as

well as on Merry Go Round circuit.

Two belt feeders below Wagon Tippler shall discharge the raw material on

either of two conveyors i.e. Z1-C1 or Z1-C2 which, in turn will discharge the

material at Jn House JH-Z1. From Jn House JH-Z1, conveyors Z3-C1 & Z3-C2

will carry the material and discharge at JH-Z3. There will be three incoming

conveyors in Junction House JH-Z3. The tail end of two conveyors Z3-C1 & Z3-

C2 will start from JH-Z1 and Belt conveyor Z3-C3 from JH-Z2. Junction house

JH-Z2 shall be located in between the JH-Z1 & JH-Z3.

The track hopper with four nos. paddle feeders of 1500 tph each, two on

conveyors Z2-C1 and two on conv Z2-C2 has been envisaged. From Jn. House

JH- Z2, either of three conveyors Z3-C1, Z3-C2 (coming from JH-Z1) & Z3-C3

(begin from JH-Z2) shall carry the material upto Jn house JH -Z3. Reversible

shuttle conveyors Z2RSC1/2 at JH-Z2 will facilitate to discharge the material on

either of any three conveyors. Therefore, JH-Z2 shall be designed suitably so as

to receive material from any of the conveyors coming from Track Hoppers. Non

sticky liners/ polymer liners are to be fixed in the track hoppers to improve

flowability.

Suitable interchangeability shall be provided below Wagon Tipplers and Track

Hoppers for the conveyors by providing Diverter gates.

In Jn House Z3, three nos. Reversible Shuttle conveyors no. Z3-RSC1,2&3 can

feed any one of conveyor no. Z6C1, Z6C2 and Z6C3. Contractor to provide

jumbo gallery suitable for three nos. mobile trippers up to JH-Z5 from JH Z4

over conveyors Z6C1, Z6C2 and Z6C3. Out of three trippers, two nos. (Over

conv. Z6C2 and Z6C3) shall extend upto JH-Z6 and one no. shall have provision

of extension up to junction house coming in future. Maintenance hoist of

minimum 5t cap shall be provided for the trippers. Each of the three conveyors

Z6C1, Z6C2 and Z6C3 shall be capable of feeding the stacking conv. Z4BC1 as

well as itself in JH Z4 and stacking conv. Z5BC1 as well as itself in JH Z5. Each

of the two conveyors Z6C2 and Z6C3 shall be capable of feeding the stacking

conv. Z6BC1 as well as future conveyor in Junction House –JH-Z6.

The raw material can be either transported via. Jn House Z4, Z5 or Z6 to the

respective stacking conveyors Z4B-C1, Z5B-C1 & Z6B-C1 for stockpiling or can

be fed directly to the reclaiming conveyors Z7-C1/ Z7-C2 which means convey

material directly from the WT/ Track Hopper to:

(a) To the Blast Furnace#8 Stock House

(b) To the Fuel & Flux crushing circuit of Sinter Plant-III.

Suitable interchangeability shall be provided at Junction house JH-Z4, 5 & 6

for the conveyors by providing 2-way chutes in mobile tripper. 5T Electric hoist

each shall be provided at JH-Z5 & JH-Z6. Whereas, JH-Z4 shall be designed

only as a transfer point.

The Stacking conveyors Z4B-C1, Z5B-C1 & Z6B-C1 can form a stockpile 30m

wide, 350m long and 10.5 m (maximum) high with the help of Twin boom

stackers.

Suitable number of electrically operated Under-Slung Cranes, Hoists etc. shall

be provided in all floors of Junction Houses and building for maintenance of

equipment. Electro-Magnetic Separators, In-Line Magnetic Separators, Metal

EPI – New Delhi Volume-2B, Rev.0 Page 8 of 28

Detectors, Belt- Weigh-Scales, Air-Blasters/ Bin Vibrators shall be provided to

make the system complete and the operation/ maintenance smooth.

(i) STORAGE AND RECLAMATION OF ORE

From the Wagon Tipplers WT-B1 and the Track Hopper TH-B1, the raw material

may sometimes be fed directly to the consuming plant in case of emergency.

However, this shall not happen under normal circumstances, when the three

Twin-boom stackers over conveyors Z4B-C1, Z5B-C1 & Z6B-C1 store the raw

material in the designated place of the yard in bed nos. 1 to 6. Flexibility shall

be in built in the Jn Houses Z4, Z5, & Z6 to ensure stacking is trouble free.

Bed blending system shall be possible with the stacker running to and fro on

the length of the pile -or- on a length between two defined position in case

more than one material is stored in a bed marked by travel limit switches,

which through a relay sequencing circuit, with time control-reverses the

traveling gear after the travel in each direction covering the desired length of

the pile. After a layer of some pre -determined amount is deposited in one

traveling direction of the stacker, probes fitted on the stacker boom gives it a

“raise” signal as soon as a net height of material is formed. The next layer is

then formed.

Iron ore may require stockpile formation as described above for blending and

uniformity. However, the emphasis on blending shall be for iron ore fines which

shall be blended while stacking.

Four nos Bucket-wheel reclaimers have been envisaged for bed no. 1 to 6.

All stacking line conveyors feeders and stackers etc. shall have a rated capacity

of 1500 tph & a designed capacity of 1800 tph.

All reclaim line equipment shall have a rated capacity of 1500 tph and a

designed capacity of 1800 tph in the ore handling area.

Reclamation takes place by the conveyors Z7-C3 (Bed no. 1), Z4A-C1 (Bed 2or

3), Z5A-C1 (Bed no.4 or 5) and Z6A-C1 (Bed no. 6) and the reclaimed material

via Jn House Z4A, B, Z5A, B, Z6A and Z6B shall reach Jn House Z7. Two

reclaim conveyors Z7-C1 and Z7-C2 between Z6A to Z7 will receive all the

materials from yard for further transportation.

Reclamation from OHP takes place for the following circumstances:-

Feeding of iron ore lump, dolomite, limestone, manganese, quartzite,

pellet etc. to BF#8 stock house.

Transporting Limestone/ Dolomite (SP grade) and iron-ore fines to fuel &

flux crushing area for Sinter Plant-III.

Two streams of belt conveyors shall reclaim the material from new OHP-B yard

to above places. Belt conveyor Z7-C1 & C2 shall carry the material and

transport thru Z8-C1, C2, Z9-C1, C2, Z10-C1, C2 to Z11-C1& C2 to Junction

house JH-Z11. Junction House-Z11 can discharge the material either to existing

conveyors R103/ R104 of Sinter Plant-III or proposed conveyor Z12-C1/ C2 of

BF#8, with the help of reversible conveyors. To receive the material from Z11-

C1 & C2, suitable modification in existing gallery of R103 & R104 is required.

Also a junction house JH-Z11 with two reversible conveyors & tail end of belt

EPI – New Delhi Volume-2B, Rev.0 Page 9 of 28

conveyors Z12-C1 & C2 shall be erected above these conveyors. Further,

conveyor Z12-C1 & C2 and then Z13-C1 & C2 shall move towards stock house

of BF#8 and discharge at JH-Z15 onto reversible shuttle conveyors J15RSC1/2.

The gallery from JH-Z14 to JH-Z15 shall have provision for installation of three

identical conveyors i.e. Z15-C1, Z15-C2 and future conveyor Z15-C3. Suitable

insert plate/ foundation bolts shall be provided for future conveyor Z15-C3.

However, future conveyor Z15-C3 is not in scope of contractor.

Specification of future conveyor:

Length - ~ 35 m: Lift 0.0 m: Capacity 1200 tph: Belt width – 1400mm

Centre to centre distance from Z15C2 – 3010 mm

A junction house JH-Z14 shall be provided in between the junction houses JH-

Z13 & JH-Z15. Two series of belt conveyors shall discharge the Sinter at the

Junction House Z14 over belt conveyor Z15-C1 & C2. Junction House JH-Z14

and conveyors Z14-C1/C2 shall be in the scope of Employer i.e. BSP.

Suitable Junction houses with RCC floors, diverter gates & galleries shall be

provided to transfer the material from one conveyor to another. The scope of

contractor shall finish at JH-Z15 with complete drive and discharge (including

reversible shuttle conveyor) facilities. The receiving belt conveyor below Z15-

C1 & C2 shall be in the scope of Employer i.e. BSP. However, JH-Z15 shall have

a provision (inserts/ foundation bolts) to erect outgoing conveyors to Stock

House.

3.2 OTHER ADDITIONS/ MODIFICATIONS AND UPGRADATION IN

EXISTING OHP (REF. DRG. NO. MEC/S/9101/11/17/0/00/00/061.B01)

(i) An Additional series of conveyor from OHP to J-20 and JH-42(Exst’g)

Another proposed conveyor No J9-C1 parallel to J9-C3/J9-C4, besides

conveyors R-102, shall start from Jn. House JH-9B and shall discharge the

material in a proposed conveyor J9H-C1 in existing JH-9, which in turn feeds to

conveyor J10-C2 in new Junction house JH-9H . Conv J10-C2 can feed proposed

conveyor J11-C3, J11-RC2, J14-C2/J12-C2 (Exst’g) , J15-C2. Conv J15-C2 shall

feed new reversible conv. J15-RC1 in junction house JH-15, which in turn can

feed either existing SMS-II feeding conv. J15A-C1 or new conv. J15B-C1.

Conv. J15B-C1 or another new conv. J15B-C2 which shall receive sinter from

existing conv. SS-10 shall feed new conveyor J16-C3 in new junction house JH-

15B which in turn shall discharge onto new conv. J16-C3A in new junction

house JH-16A. Conv. J16-C3A shall discharge onto new conv. J17-C3 in JH-16A

which shall convey material to conveyor J17A-C1 in JH-17(exst’g). Conveyor

J17A C1 (Capacity 1500tph) shall discharge to either of the two conveyors

J20C3 or J17B-C1 through a adjustable flap gate in junction house J17A.

further J17B-C1 shall discharge the material over J42-C2 in JH-17B. The

capacity of the outgoing conveyors J20C3 and J17B-C1/J42C2 shall be 500tph

and 1000tph respectively. Conveyor J20-C3 shall be provided with one no. belt

weigh scale and have provision of discharging onto existing sinter carrying

conveyor J27-C5 (Exst’g) in junction house JH-20 (Exst’g). Conveyor J42-C2

shall have provision of discharging onto existing conveyor J44-C5 in junction

house J42 (Exst’g). Necessary modification/strengthening shall be carried out in

junction house J42 to take care of additional loads by new conveyor. Suitable

EPI – New Delhi Volume-2B, Rev.0 Page 10 of 28

electrical interlock shall be provided between the conveyors J27-C5 & J20-C3 in

junction house JH-20 to trip all the incoming conveyors in case feed rate

exceeds capacity (500tph) of the corresponding downstream conveyor J27-C5.

Similar interlock shall also be provided between J44-C5 & J44-C2 in junction

house JH-42 to avoid any spillage/chute blockage.

These additional conveyors with gate will facilitate a new additional route for

BF # 7.

All above conveyor shall run adjacent to the existing conveyor/ galleries at

same elevation. Junction houses JH-9H, JH-10A, JH-15B, JH-16A ,JH 17A and

JH- 17B shall be new Junction houses. For conveyor no. J11-C3, J11-RC2,J14-

C2, J15-C2, J15-RC1, J15B-C1, J15B-C2 , J17-C3, J17A-C1, J20-C3 & J42-C2,

the existing junction houses (JH-10, JH-11, JH-14, JH-15, JH- 17, JH-20 and

JH-42) shall be suitably modified to suit proposed conveyor transfer

points/crossing over.

(ii) Up gradation of Reclaiming conveyors

The capacity up-gradation and utilization of reclaim conveyors are of utmost

importance to ensure smooth operation in the OHP.

The list of conveyors in the reclaiming circuit that shall be upgraded to

1500 tph are given in table 03.01.

Table 03.01

SL

No

CONVEYOR

NO

EXISTING PROPOSED

BELT WIDTH

mm CAP

BELT WIDTH

mm CAP tph

1 J9B-RSC1

1400

500

m3/hr

1400

1500

The capacity of all Belt conveyors shall be 1500tph for all raw materials viz. iron

ore, limestone, dolomite with 1400mm belt width and belt speed shall be 2.0

m/s with a troughing angle of 35o. (Bulk density of raw material shall be

considered as 2.2 t/m3 for power calculation/load data of structures and 1.6

t/m3 for volumetric capacity calculation of conveyor)

3.3 NEW LIME DOLO PLANT (RMP III) AND SMS III CIRCUIT

Existing conveyor R-101/R-102 shall be utilized to convey raw material required

for Lime/Dolo Calcination plant RMP III and of SMS-III by tapping the conveyor

from Jn house JH-N102 (With suitable modification in the Jn House) and taking

a new route to the proposed Lime/Dolo calcination plant/SMSIII. Any civil work

related to installation of new conveyors in existing junction house JN#102 shall

be contractor’s scope.

The SMS grade limestone, dolomite and iron ore in existing OHP-I shall be

reclaimed via. Jn House N101, N102. Existing Belt Conveyors R101/102 coming

from OHP-I shall now mostly carry Lime stone and dolomite. In JH-N102, two

existing reversible conveyor R103A & R104A are having a provision for taking

material to Sinter plant III as well as proposed Lime Plant. A discharge chute

below R103A & R104A to feed at the tail end of proposed belt conveyor L1C1

shall be provided at Junction house J-N102. Belt conveyor L1C1 shall discharge

EPI – New Delhi Volume-2B, Rev.0 Page 11 of 28

the material on L2C1 in junction house JH-L2. Conv L2C1 discharges onto

conveyor L3C1 which discharges onto L4C1 in JH L3.Conv L3C1 in turn

discharge material at Junction House JH-L4 to any of the two conveyors i.e.

L5C1 & L7C1 with the help of diverter Gate.

Thereafter, conveyor L7C1 will carry the material and transfer onto conveyor

L9C1. Conveyor L9C1 will carry the material up to Surge Bin building JHL9

through reversible shuttle conv. JL9RSC1. Surge bin building JHL9 shall have 3

nos. bunkers of minimum geometric capacity 190 cub m each for storing iron

ore lump/limestone /bauxite. Suitable rod gate and motorized rack and pinion

gates shall be fitted at the bottom of bunkers. Three (3) nos. VVF controlled

vibro feeders of 420 tph capacity each shall withdraw material from bunker and

discharge it onto conveyor L10C1 which shall convey up to Junction house JH

L10 for onward transportation to Surge Bin Building for SMS-III (Surge bins

with Vibro-feeder as shown in flow diagram at JH-L9 are in contractor’s scope.)

through SMS feeding conveyor. Conveyor L10C1 complete with discharge

facilities and junction house JH L10 shall be in the scope of contractor and SMS

feeding conveyor shall be in the scope of employer.

The other conveyor L5C1 shall receive material from conveyor L4C1 and

discharge at JH-L5 on to conv. L6C1 which shall convey up to junction house

JH-L6 and discharge onto lime plant feeding conveyor for onward transport to

Lime & Dolomite calcination plant RMP III. Conveyor L6C1 complete with

discharge facilities and junction house JH L6 shall be in the scope of contractor

.However lime plant feeding conveyor shall be in the scope of employer i.e.

BSP.

Calcined lime/dolomite is received from the day bins of lime/dolo product

storage building of RMP III onto conveyor L8C1.Conv. L8C1 discharges onto

conv. L9C2 in JH L8 which in turn discharges onto conveyor L10C1 in Surge Bin

building JH L9. This finished product of RMP III is transported to the junction

house JH L10 by conveyors L10C1 which shall also carry limestone, bauxite,

iron ore received directly from OHP I yard to SMS III. The scope of contractor

starts from tail end on conveyor L8C1 including skirt boards.

A fixed hopper of 8 cub m capacity on conveyor L10C1 near JH L9 with VVF

controlled vibro feeder of 420 tph capacity shall also be used to transport coke

fines as and when required in the storage bins of the bulk material charging

system of SMS III. Any other material e.g limestone/ DRI can also be

transported under emergency conditions through fixed hopper. Suitable ramp

shall be provided to unload the material over hopper.

EPI – New Delhi Volume-2B, Rev.0 Page 12 of 28

4.0 Technical Specifications of MVWS & IG-541 TYPE FIRE

PROTECTION WITH FDA PACKAGE

The scope of work of Fire Protection, Fire Detection & Alarm package includes;

4.1 Medium Velocity Water Spray (MVWS) & Automatic Clean

Agent (only IG-541-Inergen) System 4.2 Fire Detection & Alarm (FDA) System

4.1.0 Fire Protection System

Contract specification for complete fire protection system to be provided for the

OHP-Part B package is given below.

4.1.1 INTRODUCTION

In order to combat any occurrence of fire in various areas/units of the proposed

OHP-B package, an elaborate system of fire protection will be provided. The

system will be planned in conformity with Tariff Advisory Committee’ guidelines,

BIS and other relevant standard/codes.

Major Facilities envisaged are as following:

i/ Fire detection and alarm system (For details, Refer 4.2.0)

ii/ Water spray system comprising of MVWS & HVWS.

HVWS (High velocity water spray system) is not in the

scope of Bidder as there are no transformers greater or

equal to 10 MVA or having oil capacity 2000 liter. Hence

not in the scope of Bidder.

iii/ Automatic clean agent system (only IG 541- Inergen)

v/ Passive fire protection

4.1.2 SCOPE OF WORK AND SERVICES

The scope of work covers on turnkey basis design & engineering, supply, erection,

painting, testing, commissioning, and handing over of complete Fire Protection

System envisaged for the OHP-B of Bhilai Steel Plant 7.0 MT expansion. Two

years operation and maintenance spares, necessary tools, spanners etc. required

for regular operation / maintenance of systems will be supplied along with the

equipment.

Major work comprises of following:

a/ Fire fighting water at three points for MVWS system within the battery

limit of the contractor will be provided .However Contractor has to tap

water from this point and further design and supply of the entire fire

fighting facilities under their scope of work.

b/ Medium velocity water spray system (MVWS) for cable tunnels /

galleries in the OHP-B complex & HVWS (High velocity water spray

EPI – New Delhi Volume-2B, Rev.0 Page 13 of 28

system) for transformers will be provided if transformers are greater or

equal to 10 MVA or having oil capacity 2000 liter.

c/ Automatic Clean agent (only IG 541- Inergen) total flooding system for

computer rooms/ PLC room/control rooms.

d/ Microprocessor based Fire detection and Alarm system for electrical

premises and premises with automatic fire extinguishing system.

e/ Detector will be multi criteria combination of rate of rise heat detectors

and photo electric smoke detector. Ionization smoke detectors are not to

be accepted.

f/ Piping, valves, sluice gates etc.

g/ All civil & structural works

h/ All electrics.

i/ Controls and instrumentation.

j/ Shop and site painting for all equipments, pipes etc.

k/ Erection, testing, commissioning, PG test and Warranty for the complete

fire protection system.

l/ All the requirements of TAC for complete FPS will be incorporated by the

contractor in their scope irrespective of whether the details are

described in specification and/or shown in the drawings or not.

m/ Passive Fire Protection measures

The scope of work and services to be rendered by the Contractor for

installation of fire protection systems will include but will not be limited to

the following activities.

i/ Design & engineering, handling at site, preparation of erection drawings,

fabrication and erection as per approved drawings, site testing, painting,

commissioning and fulfillment of guarantee of all fire protection systems,

sub-systems and integrated systems as described above and also

covered in general technical specification.

ii/ Miscellaneous materials and services will include but not limited to the

following :

a/ All piping integral to and/or between any equipment furnished under this

specification, except as otherwise specified.

b/ Coupling guards for all exposed shafts and couplings.

c/ Foundation bolts, base plates, thrust blocks, duck-foot bends, matching

flanges, supporting materials and shims.

d/ All necessary instruments, power and control wiring integral to any

EPI – New Delhi Volume-2B, Rev.0 Page 14 of 28

equipment furnished under this specification. These will include terminal

blocks and integral wiring to the terminal blocks for equipment requiring

external connection.

e/ Earthing strips of all panels, & other fire fighting equipments supplied by

the contractor will be connected to the nearest earthing ring available at

site.

f/ Digging of underground trenches, laying of cables, laying of protection

slab/bricks over the cable routes, back filling of trench and levelling of

earth if required.

g/ GI pipes/ conduits and other accessories wherever required for laying of

cables.

h/ Other erection materials like cable supporting structures, channels,

brackets, clamps and other hardware materials, as required, for laying

of cables.

i/ All erection accessories, consumables and miscellaneous materials,

though not specifically indicated in this specification, but actually

required for completing the job in all respects.

j/ All necessary connections for hook-up with other system, if required as

per instruction of the employer.

k/ Erection, testing and commissioning materials.

l/ Initial fill of gas and other fire extinguishing media (including quantity

required for PG test) and demonstration.

m/ Valve chambers for all isolation valves.

n/ Housing for deluge valves.

o/ Cylinder battery racks.

4.1.3 DRAWINGS AND DOCUMENTS

Drawings/documents to be furnished

a/ Scope of work with general description of system and equipment offered

specifying the important features supplemented with scheme drawings.

The contractor has to give a confirmation with respect to the scope of

work as detailed in this specification. The description to be accompanied

by single line diagrams, and equipment layout to enable the

Employer to have a proper appreciation of the equipment and its

operation.

b/ Specification of equipment/material along with their makes/catalogues.

Approval certificate from authorizing bodies for various components of

the systems.

EPI – New Delhi Volume-2B, Rev.0 Page 15 of 28

c/ List of mandatory spares.

d/ List of special tools and tackles

e/ Certificate of approval from TAC and similar other authorizing body for

various component of the system.

4.1.4 TECHNICAL SPECIFICATION

Please refer General Technical Specification (GTS) for various fire protection

systems/facilities for detailed specification. However a brief description is

provided herewith.

Fire Detection & Alarm system (For details, Refer 4.2.0)

Water spray system comprising of MVWS & HVWS.

Medium velocity water spray system (MVWS) for cable tunnels / galleries in the

OHP-B complex & HVWS (High velocity water spray system) for transformers if

transformers are greater or equal to 10 MVA or having oil capacity 2000 litre.

Automatic Clean agent fire extinguishing system

For protection of Computer rooms/ PLC rooms/ important Control rooms

Automatic Clean agent fire extinguishing system (IG-541) will be provided.

These systems will function in automatic mode by actuation from Fire detection

& alarm system in the respective premises. There will be provision for manual

operation also with a selector toggle. When detectors detect fire, the signal will

be communicated to the main control panel, which shows the address (along

with location) of the actuated detector. On confirmation of fire by next detector

falling in different software zone in the same premises, the respective Air-

conditioning & Ventilation system will first trip and evacuation alarm signal will

appear in the premises provided with these system followed by actual discharge

of the gas(after time lag). The system will be designed according NFPA 2001.

100% reserve cylinders will be provided for all systems.

4.1.5 Passive Fire Protection System

Passive fire protection is an integral part of a complete fire protection system

and are essential for prevention of spread of fire through openings in walls or

floors. Following measures will be provided:

Fire Retardant Coating/Painting of cables

For vertical run of cables -Whole length of cable will have fire retardant

water based in-tumescent / ablative compound non toxic resistance to

hydrocarbon, acid, Alkali attack, water & oil resistance.

For horizontal run of cables –1 m length of fire retardant coating will be

provided at every 20 m interval. Wherever cables cross any partition

EPI – New Delhi Volume-2B, Rev.0 Page 16 of 28

wall, floor or pass through any opening, coating will be provided for at

least 1 m length on either side.

Fire rating of coating materials for cables will be 2.5 hrs.

Sealing of Cable Openings

Partitions in Cable Channels/tunnels/galleries

Fire door

Fire rating of fire door will be 3 hrs as per GS.

4.1.6 ERECTION, TESTING, COMMISSIONING & PERFORMANCE GUARANTEE

The erection of all plant and equipment will be carried out according to the

latest engineering practices and according to the working drawings, erection

specification, instructions etc. duly approved by the Employer. The Contractor

will carry out the work in the presence and/or as per the instructions of site

engineer/supervisory personnel deputed by the Employer. The erection will be

carried out by highly skilled workmen.

The Contractor will be responsible for paying strict attention to statutory

regulations for prevention of accidents and to other safety rules. The

regulations for prevention of accidents will be deployed at appropriate places

and should be distinctly visible to all personnel working in the area.

The Contractor will supply all required consumables, construction and erection

materials, petrol, diesel oil, kerosene, solvents, sealing compound, tapes,

brazing and soldering materials, welding and brazing gases, erection bolts, nuts

and packing sheets/compounds, temporary supports, wooden blocks, spacers,

templates, jute and cotton wastes, sand and emery paper etc. as required for

the satisfactory completion of work.

The Contractor will make his own arrangement for storing, handling the

equipment and pipelines at the stores and transporting it to the site for

installation. In addition to the above, the contractor will follow all the relevant

erection clauses/conditions stated under various chapters in the contract

document.

Contractor has taken note that training to fire engineers for maintenance/

checking of FDA and fire fighting system at OEM training centre. Training on fire

risk analysis and its mitigation in the new OHP technology will be provided at

site.

The contractor will provide all tools, labour including necessary subsistence,

erection supervision, equipment, materials, accessories, to erect/install and

make ready for operation & functionally complete the total fire protection

system as described and specified in this document.

EPI – New Delhi Volume-2B, Rev.0 Page 17 of 28

4.1.7 Testing, Commissioning & Performance Guarantee of the complete

system.

Testing

Contractor has taken note that all fire protection system will be tested and

commissioned in presence of CFO / Fire Brigade representative or MECON

before the commissioning of main units.

All tests and inspection of the installation will be done in conformity with the

functional and statutory requirement of the system. The contractor will furnish

a detailed testing and commissioning procedure for all the systems for approval

by the employer. As soon as a given facility or a portion thereof is completed

and ready to energize and start-up, the employer may test run and operate it

without relieving the contractor of his responsibility or guarantee.

4.1.8 Start-up and commissioning

i/ Contractor will provide the services of all technicians, erection and

start-up engineers necessary to bring the complete installation of fire

protection system into operation.

The contractor will be responsible for the integrated commissioning of

the plant & equipment supplied by him including trials, commissioning

and demonstration of performance guarantee test.

ii/ The Contractor will render the following services:

a) Prepare equipment for trial runs and start-up

b) Start-up and commissioning of equipment.

c) Preliminary operation, initial operation, trial operation and Final

acceptance test.

The Contractor will be required to clean up the equipment and

surrounding area and prepare it for trial runs and operation.

Priming connections, cooling water supply to bearings, lubrication piping to

bearings, stuffing box jackets and sealing glands of all rotating equipment

will be checked by the contractor.

Sequence checking of all control systems, pneumatic and cable connections,

checking operation of all interlocks and protective devices will be done by the

contractor.

Blow down of all piping systems, installations and removing strainers in piping

and equipment, as required will be done by the contractor.

Calibration and adjustment of relay settings, instruments etc., disconnecting

and reconnecting the driven and driving parts of any equipment and drives,

as required, during the trial runs and rectification, if any will be done by the

contractor.

EPI – New Delhi Volume-2B, Rev.0 Page 18 of 28

The Contractor will provide personnel as required for assisting starting up

and commissioning of equipment as well as adjustments, repairs and

rectifications of defects in erection of the equipment during commissioning of

the equipment and upto final acceptance.

4.1.9 Commissioning

On completion of the trial operation, all the systems will be under observation

in operative condition. The Contractor will provide skilled personnel including

necessary tools and consumables wherever necessary to rectify the deficiencies

observed.

4.1.10 Performance guarantee

The performance guarantee tests will be completed within a time schedule to be

mutually agreed upon between the Employer and the Contractor. Details of

the performance tests, test procedures and test schedules for the

demonstration of the performance guarantee on NFPA Codes/TAC Regulations

will be submitted to the Employer and will be mutually agreed upon.

The Contractor will conduct the operation during the performance tests and

will take full responsibility of the operations.

If the Contractor is unable to achieve the performance values as a whole or in

part during the performance tests, the Contractor will repeat the tests for

demonstrating the performance values. Before repeating the tests the

Contractor will take any and all measures as may be needed, at his own cost in

order that the performance values can be achieved.

If even with two repetitive tests and if necessary, by using additional operating

personnel from the Contractor's crew and at his own expenses, the

performance values are not reached the Contractor will undertake at his own

cost such modification or replacement as are considered necessary to obtain

the performance guarantee values and the responsibility to demonstrate

performance guarantee will continue to remain with the Contractor till so

established.

4.2.0 Fire Detection & Alarm (FDA) System

This section covers major features of Fire Detection & Alarm system to be

supplied by Contractor for Augmentation of Raw material receipt & handling

facilities – Part – B.

The Contractor shall refer to General Technical Specification for Fire Detection &

Alarm system for detailed specification of equipment / components. This

Technical Specification (TS), General technical Specification (GTS) including

Preferred Makes for Equipment and supplies and other attached documents

considered, as a whole shall comprise the complete Contract Specification.

These are complementary and anything laid down in one and not in other will

be deemed as binding, as though laid down in the Contract specification as a

EPI – New Delhi Volume-2B, Rev.0 Page 19 of 28

whole. In case of conflict between the Technical specification and GTS, the

Technical specification (TS) shall prevail.

4.2.1 Scope of Work

The scope of work of Contractor shall cover design, basic and detailed

engineering, supply, submission of drawings for approval, manufacture, testing,

inspection by Purchaser/Consultant, packing, loading, forwarding, delivery at

Plant site, loading/unloading, storage, handling of material / equipment for

erection testing, commissioning, PG test, PAT/FAT and liquidating the all defects

related to FDA (Fire detection & Alarm) equipment for complete & satisfactory

operation of the system on Turnkey basis.

Any item or equipment not specifically mentioned but essential for proper

installation, operation, maintenance and safety of plant, equipment and

personnel shall be included by the Contractor in his scope of work

The scope of work for this package shall include but not limited to the following:

Intelligent, microprocessor based, addressable type automatic fire detection

and alarm (FDA) system for the following premises shall be provided.

i) All HT/LTSS, cable basement/cellar, cable tunnel and concrete cable channels,

conveyors, MCC Rooms, Hydraulic rooms, Control rooms, Electrical premises

etc including their associated utility areas like offices, Pantry, AHU rooms,

Stairs etc. shall be covered under this system.

ii)Details of Microprocessor Based Analogue Addressable Type Fire

Detection And Alarm System (FDAS).

The scope shall broadly cover the following and also shall include such of those

items and accessories not mentioned here but required for satisfactory

operation of the system.

Intelligent, microprocessor based, addressable type automatic fire

detection and alarm system for all MCC rooms, HT/LT substation

rooms, Cable cellar, Transformer rooms, Control rooms using smoke

detectors, heat detectors with cross zoning.

Fire Alarm system shall be supplied along with HMI and required

software loaded.

The Fire Alarm panel shall have auto Dialer facility to inform to central

fire station of BSP through plant telephone network. However the FDA

panel shall have Ethernet connectivity port with TCP/IP protocol to

connect to plant LAN in future. The supplier of this package shall keep

necessary software and hardware in his scope of supply.

EPI – New Delhi Volume-2B, Rev.0 Page 20 of 28

Provision for interlocking of FDA system with Fire Fighting System

shall be kept in Fire Alarm control panel. Details shall be provided

during detail engineering stage.

INTERLOCKING OF FDA SYSTEM WITH FIRE FIGHTING SYSTEM

Medium Velocity Water Spray (MVWS) envisaged for cable galleries &

tunnels. In the event of fire in these premises, the detection system

shall give signal to Main Fire Alarm Control Panel which in turn will

actuate the solenoid of the deluge valve concerned. Apart from this,

HVWS system which has been envisaged for out-door transformer of

capacity more than 10 MVA OR having oil more than 2000 Litre will

have provision for annunciation in the FACP. The scope of work of

Contractor shall also include power supply & cabling to Solenoid

valves & taking feedback of pressure switches through cabling. The

Contractor shall be fully responsible for testing & commissioning of

water spraying system with Deluge valves as per specification for

providing Fire Hydrant system & water spraying with Deluge valves.

All annunciation of the Deluge valves & accessories will come in the

Fire Alarm panel along with automatic control.

Automatic Carbon dioxide system & Clean agent system – CO2

system has been envisaged for oil cellars of shops & mills whereas

Clean agent system has been considered for Computer rooms / PLC

Rooms / main control rooms (in various technological units). These

areas are covered by network of smoke & heat detectors. When

detectors detect fires, the signal is communicated to the main control

panel, which shows the address (along with location) of the actuated

detector. On detection of fire the respective hooters of the area will

be actuated. On confirmation if fire by next detector falling in

different software zone in the same premises, AC/Ventilation system

will trip & evacuation alarm signal will appear in the premises

provided with the system. Gas will be discharged automatically in the

affected premises after a time lag of 30 seconds. There will also be

selector switch for manual and automatic actuation of the system.

Break glass type manual call points with chain & hammer (with or

without hand set) / Pull down type manual call point.

Manual call points will also be provided at every 50 m interval in the

bays, rooms & Jn. House. Minimum one number of manual call point

shall be provided for each entrance / exit.

EPI – New Delhi Volume-2B, Rev.0 Page 21 of 28

Central control panel. The CPU of the panel shall co-ordinate function

of various loops. Failure of CPU shall not stop detection of fire by

various loops and annunciation in display unit and communicating to

Graphics station and remote LAN workstation. The software of the

panel shall be upgradeable through easy software downloads required

from time to time.

Power supply equipment.

Power supply for the FDA system shall be obtained from the

Automation UPS system

Power supply from UPS system for Local Graphics computer and

printer.

Siren and Accessories.

The Contractor shall work out Bill of quantities to cover plant and

equipment in various zones as per layout drawings.

For other details of FDA system equipment, cables & other

components, accessories etc, refer GTS.

4.3 Tentative Details of Areas (Computer rooms/ PLC rooms/ important

Control rooms) where Automatic clean agent system (only IG 541-

Inergen) is to be provided for Package- 061

Sr. no. Area Description Approx. Size (LxWxH) in Mtrs.

1 In Despatcher D 2 near JH-10 10x8x3.5

2 In Despatcher D 4 above LTSS-2 Bldg. 13.5x8.5x3.5

3 In Despatcher D 5 above LTSS-3 Bldg. 10.5x6.2x3.5

4 In Wagon Tippler Control Room 9x9x3.5

Note : The Bidder has to provide the approx. Room sizes where Cylinder

Banks alongwith accessories shall be installed / provided for the above

premises.

EPI – New Delhi Volume-2B, Rev.0 Page 22 of 28

4.5 LEVEL OF VARIOUS BUILDINGS AND JUNCTION HOUSES

(A) Z-LINE

Sr.

No.

Name of Building

/ Junction House

Ground

Level

(Mtr.)

No. of

Floors

Floor Levels (Mtr.)

I II III IV V

1

Wagon Tippler

Building 307.250 5 307.250 304.982 298.500 295.000 291.100

2 Pump House-2 307.250 --- --- --- --- --- ---

3 LTSS-1 307.250 --- --- --- --- --- ---

4 JH-Z1 306.000 3 303.750 300.050 296.050 --- ---

5 JH-Z2 307.000 3 309.000 313.000 316.900 --- ---

6

Track Hopper

Building 308.358 2 308.358 299.158 --- --- ---

7 JH-Z3 306.000 3 306.000 310.100 314.100 --- ---

8 JH-Z4A 303.000 4 303.000 307.100 310.600 315.800

9 JH-Z5A 303.000 3 303.000 307.100 310.600 --- ---

10 JH-Z6A 303.000 3 303.000 307.100 310.600 --- ---

11 JH-Z7A 303.000 3 303.000 307.100 310.600 --- ---

12 JH-Z4 303.000 2 309.000 312.600 --- --- ---

13 JH-Z4B 303.000 2 303.000 309.000 --- --- ---

14 JH-Z5B 303.000 2 303.000 309.000 --- --- ---

15 JH-Z6B 303.000 2 303.000 308.700 --- --- ---

16 JH-Z7 303.000 2 303.000 308.300 --- --- ---

17 Main Pump House-1 303.000 --- --- --- --- --- ---

18 Compressor House 303.000 --- --- --- --- --- ---

19 LTSS-2 303.000 --- --- --- --- --- ---

20 JH-Z8 303.000 2 316.600 321.600 --- --- ---

21 FTH-1 311.000 2 318.000 322.500 --- --- ---

22 JH-Z9 308.000 2 313.900 317.500 --- --- ---

23 JH-Z10 310.500 3 317.000 320.600 324.100 --- ---

24 JH-Z11 310.000 3 320.000 323.700 327.300 --- ---

25 Pump House-3 310.000 --- --- --- --- --- ---

26 LTSS-3 310.000 --- --- --- --- --- ---

27 JH-Z12 310.000 2 316.500 320.000 --- --- ---

28 JH-Z13 310.000 2 322.900 328.000 --- --- ---

29 JH-Z15 308.500 3 343.800 347.400 350.400 --- ---

EPI – New Delhi Volume-2B, Rev.0 Page 23 of 28

(B) L-LINE

Sr.

No.

Name of

Building /

Junction House

Ground

Level

(Mtr.)

No. of

Floors

Floor Levels (Mtr.)

I II III IV V

1 JH-J102 310.000 1 317.100 --- --- --- ---

2 JH-L1 310.900 2 314.525 318.525 --- --- ---

3 JH-L2 310.100 2 325.625 328.225 --- --- ---

4 JH-L3 310.500 2 317.800 324.325 --- --- ---

5 JH-L4 310.000 3 316.800 320.400 324.000 --- ---

6 LTSS-4 310.000 --- --- --- --- --- ---

7 JH-L5 310.000 2 315.332 320.150 --- --- ---

8 JH-L6 308.500 2 322.670 327.670 --- --- ---

9 JH-L7 306.000 2 312.900 316.500 --- --- ---

10 Pump House-4 306.000 --- --- --- --- --- ---

11 JH-L8 304.000 2 304.000 309.300 --- --- ---

12 JH-L9 312.000 3 312.000 328.000 332.000 --- ---

13 JH-L10 307.000 1 352.600 --- --- --- ---

(C) J -LINE

Sr.

No.

Name of

Building /

Junction House

Ground

Level

(Mtr.)

No. of

Floors

Floor Levels (Mtr.)

I II III IV V

1 JH-J9B 308.500 1 308.500 --- --- --- ---

2 JH-J9H 309.200 3 312.120 316.000 320.000 --- ---

3 JH-J10A 310.000 2 324.000 327.800 --- --- ---

4 JH-11 310.000 3 312.400 319.600 323.800 --- ---

5 Pump House-5 310.000 --- --- --- --- --- ---

6 JH-J14A 310.000 2 317.578 321.100 --- --- ---

7 JH-J15B 309.500 4 314.650 318.650 322.150 325.650 ---

8 LTSS-5 309.500 --- --- --- --- --- ---

9 JH-J17A 307.300 2 313.700 317.700 --- --- ---

10 JH-J17B 307.300 3 323.300 327.100 330.800 --- ---

11 JH-J20 307.300 1 330.850 --- --- --- ---

EPI – New Delhi Volume-2B, Rev.0 Page 24 of 28

5.0 SPARES (A) Commissioning Spares and Insurance Spares

Supply of commissioning spares and insurance spares as required shall be

in scope of supply of the Bidder alongwith the equipment. The list of

commissioning spares and the insurance spares as per the format as given

in SBD shall be furnished alongwith the tender. It shall cover requirements

of erection, cold tests, startup and initial operation of the plant till

integrated testing & successful commissioning and commencement of

commercial production up to a period of six months. Any leftover

commissioning spares shall be the property of the Purchaser. Any

commissioning spares required over and above the list given by the Bidder

shall have to be provided by the Bidder free of cost up to the successful

commissioning & commencement of commercial production of the plant and

equipment. The Bidder shall supply adequate insurance spares to ensure

smooth operation and maintenance of the plant.

(B) Consumables

The Bidder shall supply all consumables such as initial fill of lubricants, oils,

grease, chemicals, refractories, resins etc. as required to complete the plant

till commissioning and shall have a shelf life of minimum one year. The

scope of consumables shall include electrodes, shims, packings, bolts, nuts,

gaskets, rivets, washers etc. The Bidder shall fulfill the requirement given

in SBD.

The Bidder shall also furnish Indian equivalent of oils, lubricants,

refractories and other consumables along with necessary specifications,

drawings, catalogues etc. to enable the Purchaser to procure them from

indigenous sources.

The Bidder shall indicate the annual requirement of all such consumables.

(C) Operating, Maintenance and Two Years’ Spares:

(1) The Bidder shall ensure the interchangeability of the parts wherever

possible. The Bidder shall furnish an itemized list of interchangeable

spares as given in SBD.

(2) The list of spares as necessary and recommended by the respective

manufacturer for two years’ of reliable and trouble free operation and

maintenance of all equipment under this package shall be in the scope of

the Bidder. The same shall be quoted separately. In the event of order

the successful Bidder shall furnish complete specification of the same.

(3) Spares list giving complete list of the replaceable parts, fully illustrated,

shall be supplied. The list shall include the following information.

Item designation

Reference drawings

EPI – New Delhi Volume-2B, Rev.0 Page 25 of 28

Quantity installed

Quantity recommended for two years’ normal operation including the

insurance spares

Weight of each spare part

Supplier or sub-supplier’s catalogue number

Recommended minimum stock

Expected replacement time

Installation instruction in detail shall be supplied both for original

installation and future, for replacement of major electrical

equipment, circuit wiring diagram shall be provided.

(D) Special Erection / Maintenance Tools and Tackles:

(1) The Bidder shall supply a complete and unused wet of all the special tools

and tackles including required number of tool boxes as required for

erection, maintenance, overhaul or complete replacement of the

equipment and components required for the plant. The Bidder shall

submit a list of such special erection and maintenance tools and tackles.

(2) All the tools shall be supplied in separate containers clearly marked with

the name of the equipment for which they are intended.

(3) The Successful Bidder shall indicate list of construction machineries,

handling equipment and other facilities including tower crane or equivalent

for erection at high elevation required for the execution of work based on

their previous experience, considering site conditions and other

considerations of work and furnish resource deployment plan. The

successful Bidder shall mobilize these equipment at site for the execution

of work and this is an important requirement of the project. The

availability of required facilities shall be ensured for completeness of the

project in time.

(4) For any fabrication / control assembly (necessary for erection) work to be

done in the plant premises the plan shall be indicated by the Bidder. The

necessary equipment such as plate bending machines, special purpose

welding machines, fixtures, tools & tackles and other equipment required

for fabrication shall be arranged by the successful Bidder.

(5) The successful Bidder shall carry out the testing of welded joints by

radiographic and ultrasonic methods. They must have only qualified /

certified welders with them for completing all the welding jobs.

(6) All the measuring instruments shall be calibrated having reference to NPL

(National Physics Laboratory).

EPI – New Delhi Volume-2B, Rev.0 Page 26 of 28

(7) All tools and tackles, apparatus, special instruments required for erection,

testing, commissioning and establishment of the Performance Guarantee

Test, measurements required for establishing the pollution control norms

and such other instruments, as required, shall be arranged by the

successful Bidder. After commissioning, the successful Bidder shall

handover all the special tools & tackles to the Purchaser as per the

requirement given in SBD.

(8) The successful Bidder shall supply all required consumables, initial fill, oil,

lubricants, construction and erection materials including but not limited to

shims, packing plates, joining compounds, kerosene, solvents, sealing

compounds, tapes, connectors, brazing and soldering materials, welding

and brazing gases and rods, electrodes and wires, erection bolts, nuts,

rivets, piano wire, packing sheet and packing compounds, temporary

supports, spacer templates, jute and cotton waste cloth, sand and emery

paper etc. for the commissioning of the plant.

(9) For load testing of handling equipment, loads shall have to be arranged by

the successful Bidder. Electrical/ operation tests, as per standard practice,

shall also be arranged and completed by them.

(10) All materials, equipment, tools, tackles etc. brought at site by the

successful Bidder within the plant area shall not be removed without the

written permission of the Purchaser. Similarly, all enabling works

built/erected and/or acquired by them within the plant premises shall not

be dismantled and removed without the written permission of the

Purchaser.

(E) Information/ Data on Spares and Consumables

The list of Spares & consumables shall be furnished by the successful Bidder

as required in SBD. However, the successful Bidder shall furnish various

information regarding spares, consumables, tools & tackles etc. as per the

schedules indicated in chapter 12 of this Technical Specification.

EPI – New Delhi Volume-2B, Rev.0 Page 27 of 28

DATA SHEETS

EPI – New Delhi Volume-2B, Rev.0 Page 28 of 28

6.0 TECHNICAL DATA SHEET (To be filled by the vendor)

6.1 MEDIUM VELOCITY WATER SPRAY (MVWS) SYSTEM

1. Material of Pipe :

2. Pipe Standard :

3. Class of Pipe :

4. Thickness of pipe material :

5. Make of Pipe :

6. Maximum recommended 0C : operating temperature : 7. Maximum recommended : operating pressure : 8. Type of protective coating on Pipe : 9. Make of Deluge Valve : 10. Make of Spray Nozzles / Projectors : 11. Make of Solenoid Valve : 12. Make of rate of rise Heat Detector and Photoelectric Smoke Detector : 13. Make of FDA Panel : 14. Technical Details of Microprocessor based Fire Detection and Alarm System (FADS) :

6.3 AUTOMATIC CLEAN AGENT SYSTEM (ONLY IG 541- INERGEN) (To be

furnished separately for all systems envisaged by the bidder for

complete package)

1. Manufacturer’s name :

2. Capacity :

3. Quantity :

4. Location :

5. Other Technical Details of Auotmatic : Clean Agent (only IG-541 Inergen)