subsea system design: same dog new tricks · subsea system design: same dog new tricks by k.milne...

31
woodplc.com Subsea System Design: Same Dog New Tricks By K.Milne

Upload: others

Post on 27-Jun-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

woodplc.com

Subsea System Design:Same Dog New Tricks

By K.Milne

Page 2: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• OGA analysed 58 oil and gas projects

– Input from 11 Operators

• Less than 25% delivered on time

• Average overspend = 35%

Same Dog…

2 A presentation by Wood.

Page 3: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Case Study: Subsea Production Tree Leak

3 A presentation by Wood.

The Issue

The Traditional Response

What We Did

Key Point Comparison

Example Key Item Design Philosophy

Page 4: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• 2 well subsea tie-back

• Sour 3-phase production

– Well A ~30,000ppm H2S

– Well B ~ 3,000ppm H2S

• Water depth is ~60m

– Designed for routine ROV intervention

– Installed by sat divers

Case Overview

4 A presentation by Wood.

Page 5: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Bypass Requirements

5 A presentation by Wood.

• Leak Identified in 2014

Page 6: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• Horizontal production tree

• Leak point identified at Tree / Flowbase interface

• No leak during stable flow, only during shutdown

– Estimated 42 pressure cycles observed in 2015

– Leak observed to continue even when pipeline was blown down

• PFIV failed ~60% /Open

Case Overview

6 A presentation by Wood.

Tree / Flowbase Clamp

Page 7: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• The tried and tested method is:

– Change out the Tree and Flowbase

How to Repair a Leaking Tree?

7 A presentation by Wood.

DSV – Preparation & deconstruction

Drill Rig – Tree & flowbase change Out

DSV – Re-connection & commissioning

Horizontal production tree

Production flowbase

Upper completion inc. valves & sensors

Equipment & Services Required

Page 8: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Tree Change Out Scenario

8 A presentation by Wood.

Cam

paig

n O

ne: D

SV • Isolate tree

• Flood pipeline

• Remove tie-in spool

• Disconnect subsea control system

Cam

paig

n T

wo

: M

OD

U • Set downhole isolation plugs

• Pull upper completion

• Recover tree & flowbase

• Install new tree & flowbase

• Recomplete well

Cam

paig

n T

hre

e: D

SV • Install tie-in

spool

• Leak test pipeline

• De-water pipeline

• Re-connect subsea control system

• Commission well

Page 9: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• Campaign One: Est. 6 Days (inc. Mob)

• Campaign Two: Est. 30 Days

• Campaign Three: Est. 7 Days (inc. Mob)

• Total Repair Cost £53.5M not economically viable for this Asset

Tree Change Out Scenario

A presentation by Wood.9

Task Duration Cost

Engineering 18 months £4.5M

Equipment 12 months £7M

Offshore Execution 44 days £35M

Lost Production 42 days* £7M

Total 19 months £53.5M

*Does not allow for delays between campaigns

Page 10: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

…New Tricks: Bypass Solution

A presentation by Wood.10

AMV

SCSSV

MIV

WOV

PCV

Tree

Flowbase

PWV

PFIV

PMV

XOV

D

Flo

wb

ase

Flo

wli

ne

Key: Normally Open

Normally Closed

Failed (Open)

Future Tie-in

AWV

Production

Leak Point

Page 11: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

…New Tricks: Bypass Solution

A presentation by Wood.11

AMV

SCSSV

MIV

WOV

PCV

Tree

Flowbase

PWV

PFIV

PMV

XOV

D

Flo

wb

ase

Flo

wli

ne

Key: Normally Open

Normally Closed

Failed (Open)

Future Tie-in

AWV

Production

Leak Point

PCV

MIVS

Bypass

Unit

Tree Iso. Valve

Future Tie-in Valve

Choke Skid

Tree

Flowbase

PWV

PFIV

D

Production

Bypass Unit

Spool

Tie-in

Spool

Leak Point

(Bypassed)

Production

Leak Point

Page 12: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

…New Tricks: Bypass Solution

A presentation by Wood.12

AMV

SCSSV

MIV

WOV

PCV

Tree

Flowbase

PWV

PFIV

PMV

XOV

D

Flo

wb

ase

Flo

wli

ne

Key: Normally Open

Normally Closed

Failed (Open)

Future Tie-in

AWV

Production

Leak Point

PCV

MIVS

Bypass

Unit

Tree Iso. Valve

Future Tie-in Valve

Choke Skid

Tree

Flowbase

PWV

PFIV

D

Production

Bypass Unit

Spool

Tie-in

Spool

Leak Point

(Bypassed)

Production

Leak Point

Production

Seal

Leak Point

Page 13: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

…New Tricks: Bypass Solution

A presentation by Wood.13

AMV

SCSSV

MIV

WOV

PCV

Tree

Flowbase

PWV

PFIV

PMV

XOV

D

Flo

wb

ase

Flo

wli

ne

Key: Normally Open

Normally Closed

Failed (Open)

Future Tie-in

AWV

Production

Leak Point

PCV

MIVS

Bypass

Unit

Tree Iso. Valve

Future Tie-in Valve

Choke Skid

Tree

Flowbase

PWV

PFIV

D

Production

Bypass Unit

Spool

Tie-in

Spool

Leak Point

(Bypassed)

• Production choke valve

• Flowbase Isolation

Valve (PFIV)

• D/S choke pressure

sensor

• D/S choke temperature

sensor

Bypassed Functionality

Page 14: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

…New Tricks: Bypass Solution

A presentation by Wood.14

AMV

SCSSV

MIV

WOV

PCV

Tree

Flowbase

PWV

PFIV

PMV

XOV

D

Flo

wb

ase

Flo

wli

ne

Key: Normally Open

Normally Closed

Failed (Open)

Future Tie-in

AWV

Production

Leak Point

PCV

MIVS

Bypass

Unit

Tree Iso. Valve

Future Tie-in Valve

Choke Skid

Tree

Flowbase

PWV

PFIV

D

Production

Bypass Unit

Spool

Tie-in

Spool

Leak Point

(Bypassed)

Page 15: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• Bypass is a DSV based approach

• Opportunity to improve existing field architecture

Bypass Requirements

A presentation by Wood.15

DSV – isolation, repair & commissioning

• Proprietary choke bypass tool

(modified)

• Remote choke skid (inc. valves and

sensors)

• Choke control jumper extensions

• Tie-in spools

Equipment & Services Required

• Increase LP hydraulic

supply

• Local subsea control

system isolations

• Include isolation points

at future tie-in point

Improvements

Page 16: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Bypass Scenario

A presentation by Wood.16

Page 17: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• DSV Repair campaign: est. 21 days (inc. Mob)

– Assumed metrology spools delivered to worksite

• Actual repair time: 20 Days (inc. Mob)

Bypass Scenario

A presentation by Wood.17

Task Duration Cost

Engineering 18 months £6M

Equipment 20 months £3M

Offshore Execution 21 days £5M

Lost Production 21 days £3.5M

Total 21 months £17.5M

Page 18: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• Bypass Option was ~1/3 of the estimated cost

– Repaired tree has been in operation since Q2 2018

• This was achieved by applying the same strategy to all elements of the system

Approach Comparison

A presentation by Wood.18

Engineering &

Equipment

Offshore

Campaign

Costs

Deferred

Production

Costs

Total

Tree Change £11.5M £35M £7M £53.5M

Bypass £9M £5M £3.5M £17.5M

Saving £2.5M £30M £3.5M £36M

Page 19: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Leak Bypass: Manifold Design

19

Page 20: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Comparison

Case Study: Manifold Design

20 A presentation by Wood.

Traditional Design

Modified Design

Page 21: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Manifold Requirements

A presentation by Wood.21

• Production choke valve

• Flowbase Isolation

Valve (PFIV)

• D/S choke pressure

sensor

• D/S choke temperature

sensor

Bypassed Functionality

• Well B tie-in

• Future tie-in point

Tie-in Functionality

• Sour service materials

• Chemical injection

• Diverless choke insert

change out

• Local hydraulic/

chemical isolations

• Fishing friendly

• Gravity base

Design Requirements

Page 22: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Traditional Manifold Design

A presentation by Wood.22

• Sloped side gravity based design

• Removable roof & hinged side panels allow access for interventions

Page 23: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Traditional Manifold Design – Valves

A presentation by Wood.23

• 4 x 6” Manual gate valves

• 1 x 1” Hydraulic gate valve inc. check valve

• 2 x ½ Double block and bleeds

• 1 x Production choke ValveValve

Valve

Valve

Choke

Valve

Future Tie-in

From Tree

To Main 10” Pipeline

Page 24: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• Valves arrangement dictates size and weight of this structure

– Valves arrangements were identified as key area for optimisation

Traditional Manifold Design

A presentation by Wood.24

Item Qty Cost

6” Manual, Slab Gate Valve (5ksi) 4 £320k

½” Needle Valve Double Block and Bleed Assembly 2 £140k

1” Actuated Gate Valve with Check Valve 1 £26.5k

Structural Fabrication, Pipework and Assembly - £840k

Total £1.3M

Page 25: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Double Expanding Split Gate Valves

A presentation by Wood.25

• First used subsea by Shell on the Pelican Expansion Manifold

• Seals are mechanically energised not pressure energised and spring loaded

• Mechanical rather than spring return prevents split gate not retracting on closure

• Allow for a double isolation to be achieved using a single valve

– IMCA recognised

Equipment Overview

Page 26: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Modified Design – Valves

A presentation by Wood.26

• 2 x 6” Manual double expanding gate valves

• 1 x 1” Hydraulic gate valve inc. check valve

• 1 x Production choke

Valve

Valve

Choke

Valve

Future Tie-in

From Tree

To Main 10” Pipeline

Page 27: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

Modified Design – Footprint Comparison

A presentation by Wood.27

Page 28: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• Split Gate valves are more expensive on a 1-to-1 basis

– ~£80k for manual gate valve

– ~£95k for double expanding split gate valve

• Halves the number of valves required

• Removes the need for double block and bleed assemblies

Modified Design

A presentation by Wood.28

Item Qty Cost

6” Manual Expanding Split Gate Valve (5ksi) 2 £185k

1” Actuated Gate Valve with Check Valve 1 £26.5k

Structural Fabrication, Pipework and Assembly - £650k

Total £861.5k

Page 29: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

• One of a number of non-traditional approaches taken

• All technologies used were field proven

Manifold Design Comparison

A presentation by Wood.29

Item Traditional Expanding Gate Saving \ Reduction

Skid Length 10.6m 8.8m 1.8m

Skid Width 10.6m 8.8m 1.8m

Skid Weight (air) 75 Te 59.3 Te 15.7 Te

Valve Costs £486.5k £211.5k £275k

Fabrication Costs £840k £650k £190k

Skid Cost £1.3M £861.5k £438.5k

Page 30: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

30

If you always do what you’ve always done, you’ll always get what you’ve always got.

- Source Unkown

Page 31: Subsea System Design: Same Dog New Tricks · Subsea System Design: Same Dog New Tricks By K.Milne • OGA analysed 58 oil and gas projects ... 3 A presentation by Wood. The Issue

woodplc.com