stormwater pollution prevention plan for - illinois …€¦ · · 2010-01-043.6 spill prevention...
TRANSCRIPT
Stormwater Pollution Prevention Plan
for:
Waubonsee Community College – Aurora Campus 18 S. River Street Aurora, IL 60506
SWPPP Preparation Date: 10 / 16 /2008
Estimated Project Dates:
Project Start Date: 10 / 01 / 2008
Project Completion Date: 09 / 30 / 2010
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
ii
Contents SECTION 1: SITE EVALUATION, ASSESSMENT, AND PLANNING ......................................... 1 1.1 Project/Site Information .................................................................................................... 1 1.2 Contact Information/Responsible Parties........................................................................ 2 1.3 Nature and Sequence of Construction Activity.............................................................. 3 1.4 Soils, Slopes, Vegetation, and Current Drainage Patterns ............................................ 3 1.5 Construction Site Estimates .............................................................................................. 4 1.6 Receiving Waters............................................................................................................... 4 1.7 Site Features and Sensitive Areas to be Protected ......................................................... 5 1.8 Potential Sources of Pollution.......................................................................................... 5 1.9 Endangered Species Certification .................................................................................... 5 1.10 Historic Preservation......................................................................................................... 6 1.11 Applicable Federal, Tribal, State or Local Programs ..................................................... 6 1.12 Maps ................................................................................................................................... 6 SECTION 2: EROSION AND SEDIMENT CONTROL BMPS 2.1 Minimize Disturbed Area and Protect Natural Features and Soil................................ 7 2.2 Phase Construction Activity ............................................................................................. 7 2.3 Control Stormwater Flowing onto and through the Project.......................................... 8 2.4 Stabilize Soils..................................................................................................................... 8 2.5 Protect Slopes .................................................................................................................... 9 2.6 Protect Storm Drain Inlets .............................................................................................. 10 2.7 Establish Perimeter Controls and Sediment Barriers.................................................... 11 2.8 Establish Stabilized Construction Exits.......................................................................... 12 2.9 Additional BMPs.............................................................................................................. 12 SECTION 3: GOOD HOUSEKEEPING BMPS ............................................................................ 13 3.1 Material Handling and Waste Management ................................................................ 13 3.2 Establish Proper Building Material Staging Areas ........................................................ 14 3.3 Designate Washout Areas .............................................................................................. 16 3.4 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices ................ 16 3.5 Control Equipment/Vehicle Washing............................................................................ 16 3.6 Spill Prevention and Control Plan ................................................................................. 17 3.7 Allowable Non-Stormwater Discharge Management ................................................. 18 SECTION 4: SELECTING POST-CONSTRUCTION BMPs ........................................................ 19 SECTION 5: INSPECTIONS .......................................................................................................... 20 5.1 Inspections ....................................................................................................................... 20 5.2 Delegation of Authority .................................................................................................. 21 5.3 Corrective Action Log ..................................................................................................... 22
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
iii
SECTION 6: RECORDKEEPING AND TRAINING..................................................................... 23 6.1 Recordkeeping................................................................................................................. 23 6.2 Log of Changes to the SWPPP ....................................................................................... 23 6.2 Training ............................................................................................................................ 23 SECTION 7: FINAL STABILIZATION .......................................................................................... 24 SECTION 8: CERTIFICATION AND NOTIFICATION .............................................................. 25 SWPPP APPENDICES .................................................................................................................... 27
Appendix A – General Location Map Appendix B – Site Maps Appendix C – Construction General Permit Appendix D – NOI and Acknowledgement Letter from EPA/State Appendix E – Inspection Reports Appendix F – Corrective Action Log (or in Part 5.3) Appendix G – SWPPP Amendment Log (or in Part 6.2) Appendix H – Subcontractor Certifications/Agreements Appendix I – Grading and Stabilization Activities Log (or in Part 6.1) Appendix J – Training Log Appendix K – Delegation of Authority Appendix L – Additional Information (i.e., Endangered Species and Historic Preservation Documentation)
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
1
SECTION 1: SITE EVALUATION, ASSESSMENT, AND PLANNING
1.1 Project/Site Information
Project/Site Name: Waubonsee Community College – Aurora Campus Project Street/Location: 18 South River Street City: Aurora State: IL ZIP Code: 60506 County or Similar Subdivision: Kane
Latitude/Longitude Latitude: Longitude: 41.75893 º N (decimal) -88.31750º W (decimal)
Method for determining latitude/longitude:
USGS topographic map (specify scale: )
EPA Web site
Other (please specify): www.terraserver-usa.com
Is the project located in Indian country? Yes No If yes, name of Reservation, or if not part of a Reservation, indicate "not applicable." Not Applicable
Is this project considered a federal facility? Yes No
NPDES project or permit tracking number*: ILR10K766 *(This is the unique identifying number assigned to your project by your permitting authority after you have applied for coverage under the appropriate National Pollutant Discharge Elimination System (NPDES) construction general permit.)
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
2
1.2 Contact Information/Responsible Parties
Prime Contractor: To Be Determined – Refer to Multiple Contractor Signature Sheet Bradley R. Booker Route 47 at Waubonsee Drive Sugar Grove, IL 60554 Tel: (630) 466-2451 Fax/Email: (630) 466-2460
Construction Manager:
Turner Construction Company Bradley R. Booker Route 47 at Waubonsee Drive Sugar Grove, IL 60554 Tel: (630) 466-2451 Fax/Email: (630) 466-2460
This SWPPP was Prepared by:
JJR, LLC Robert W. Marshall, P.E. 35 East Wacker Drive Chicago, IL 60601 Tel: ( 312) 641-6774 Fax/Email: [email protected]
Emergency 24-Hour Contact:
Waubonsee Community College Public Safety Tel: (630) 801-7900 x4142 Insert Telephone Number: TBD
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
3
1.3 Nature and Sequence of Construction Activity
Describe the general scope of the work for the project, major phases of construction, etc: The 2.9 acre project includes, but is not limited to: A new 4-story higher education facility, vehicular drive with permeable paving, loading area, drop off, parking lot, pedestrian walks as well as general site grading, drainage, and storm water management of these facilities plus landscape and irrigation as specified in the bidding documents. What is the function of the construction activity?
Residential Commercial Industrial Road Construction Linear Utility
Other (please specify): Education Facility Estimated Project Start Date: 10 / 01/ 2008 Estimated Project Completion Date: 09 / 30 / 2010
1.4 Soils, Slopes, Vegetation, and Current Drainage Patterns
Soil type(s): Fill soils at the site generally consisted of sand and gravel with trace amounts of clay, silt, wood, brick, and crushed stone. Beneath the rubble of the old building basement level fill soils were found to extend to depths of about 1 ½ to 3 feet below existing grades. Fill amounts found in the borings completed within the parking lot or near the grade of the previous buildings first floor slab level were generally greater with depths of about 8 ½ to 13 ½ feet. On the east corner of the site fill materials were encountered, which extended to about 20 feet below grade. Native soils below the fill soils predominately consisted of fine to coarse sand with gravel or sandy gravel and extended to the boring termination depths of about 25 feet or to bedrock refusal materials. Elevations of the borings ranged from about 634 feet to 642 feet in reference to the benchmark at 647. About 3 to 4 inches of asphalt pavement was encountered at the surface of the existing parking lot and 4 inches of concrete slab was also encountered near Hoyt Place. Slopes (describe current slopes and note any changes due to grading or fill activities): The slopes range from 5.20% - 8.90%. Drainage Patterns (describe current drainage patterns and note any changes dues to grading or fill activities): The existing drainage pattern drains from northwest of the site to southeast of the site towards Fox River.
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
4
Vegetation: Grass exists on the northwest half of the site. Other: Asphalt paving parking exists on the southeast half of the site.
1.5 Construction Site Estimates
The following are estimates of the construction site.
Total project area: 2.90 acresConstruction site area to be disturbed : 2.90 acresPercentage impervious area before construction: 59.79 %Runoff coefficient before construction: 0.78Percentage impervious area after construction: 60.05 %Runoff coefficient after construction 0.79
1.6 Receiving Waters
Description of receiving waters: Fox River
Description of storm sewer systems: Strom drains in area drain to Fox River.
Description of impaired waters or waters subject to TMDLs: N/A
Other: N/A
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
5
1.7 Site Features and Sensitive Areas to be Protected
1.8 Potential Sources of Pollution
Potential sources of sediment to stormwater runoff: - During demolition there could be potential for asphalt and concrete dust to get into the stormwater runoff. Silt fences are built to prevent such pieces from entering the river or stormwater system. Also wet down materials or use other suitable methods to limit the amount of airborne dust and dirt from the site to the lowest practical level. Potential pollutants and sources, other than sediment, to stormwater runoff: N/A
1.9 Endangered Species Certification
Are endangered or threatened species and critical habitats on or near the project area? Yes No
Describe how this determination was made: Per IDNR EcoCAT Consultation - #0810891 If yes, describe the species and/or critical habitat: Black-Crowned Night Heron (Nycticorax nycticorax) EcoCAT reports that this species may be in the area. However, its habitat is wetland type areas, and their typical nests are found within cattail vegetation. It is an urban site with a parking lot and turf area, and it is assumed this species will not be impacted by construction.
Description of unique features that are to be preserved: N/A Describe measures to protect these features: N/A
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
6
1.10 Historic Preservation
Are there any historic sites on or near the construction site? Yes No
Describe how this determination was made: Illinois Historic Preservation Agency - Historic Architectural/ Archaeological Resources Geographic Information System If yes, describe or refer to documentation that determines the likelihood of an impact on this historic site and the steps taken to address that impact. N/A
1.11 Applicable Federal, Tribal, State or Local Programs
1. Kane/DuPage Soil and Water Conservation District – Soil Erosion and Sediment Control Plan.
2. City of Aurora Engineering Permit.
1.12 Maps
See Appendix A and B for site maps.
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
7
SECTION 2: EROSION AND SEDIMENT CONTROL BMPS
2.1 Minimize Disturbed Area and Protect Natural Features and Soil
Silt fences will be installed near the south perimeter of the project limits where it all drains towards the Fox River prior to construction according to the Illinois Urban Manual Code 920. Two Stabilized Construction Entrances will be installed at the existing driveway entrances and another one at the proposed northeast entrance according to Illinois Urban Manual Code 930. Siltsack is used for curb inlets along the perimeter of the project limits. Siltsack is a temporary sediment inlet filter that is inserted along the rim of the inlet, covered and secured by the inlet lid.
2.2 Phase Construction Activity
• Phase I Phase I includes the following tasks: Preliminary utility relocations, new utility
construction, mass grading, building construction, and Hoyt Place base material placement.
October 2008 – April 2010 Silt fences will be installed near the south perimeter of the project limits where it
all drains towards the Fox River prior to construction according to the Illinois Urban Manual Code 920. Two Stabilized Construction Entrances will be installed at the existing driveway entrances and another one at the proposed northeast entrance according to Illinois Urban Manual Code 930. Siltsack is used for curb inlets along the perimeter of the project limits. Siltsack is a temporary sediment inlet filter that is inserted along the rim of the inlet, covered and secured by the inlet lid.
• Phase II Phase II includes: Final grading, pavement installation, and final plantings. April 2010 – September 2010 Silt fences will be installed near the south perimeter of the project limits where it
all drains towards the Fox River prior to construction according to the Illinois Urban Manual Code 920. Siltsack is used for curb inlets along the perimeter of the project limits. Siltsack is a temporary sediment inlet filter that is inserted along the rim of the inlet, covered and secured by the inlet lid.
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
8
2.3 Control Stormwater Flowing onto and through the Project
BMP Description: Silt Fence – IL 920 Installation Schedule: October 2008 – September 2010 Maintenance and Inspection:
Silt fences shall be removed when they have served their
usefulness, but not before the upslope areas have been
permanently stabilized.
Silt fences shall be inspected immediately after each rainfall
and at least daily during prolonged rainfall.
Should the fabric decompose or become ineffective prior to
the end of the expected usable life and the fence still is
necessary, the fabric or the entire system shall be replaced
promptly.
Sediment deposits should be removed after each rainfall.
They must be removed when the level of deposition reaches
approximately one-half the height of the silt fence.
Any sediment deposits remaining in place after the silt fence
is no longer required shall be dressed to conform to the
existing grade, a seedbed prepared and the site vegetated.
Responsible Staff: Prime Contractor
2.4 Stabilize Soils
BMP Description: Temporary Erosion Control Seeding Permanent Temporary
Installation Schedule: October 2008 – April 2010 Maintenance and Inspection:
The seed shall be applied by hand broadcasting to achieve a reasonable uniform coverage at the rate of 100 lb/acre. Seed shall be applied all bare areas every seven days, regardless of weather conditions or progress of the work.
Responsible Staff: Prime Contractor
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
9
2.5 Protect Slopes
BMP Description: N/A Installation Schedule: N/A Maintenance and Inspection:
N/A
Responsible Staff: N/A
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
10
2.6 Protect Storm Drain Inlets
BMP Description: Siltsack Installation Schedule: October 2008 – September 2010 Maintenance and Inspection:
Tasks Schedule Inspect for accumulated sediment
Weekly and after each 1/2" rain event
Removal of accumulated sediment > 1' deep
As required
Inspect for floatables and debris
Weekly and after each 1/2" rain event
Remove floatables and debris
As required
Certified stormwater management inspections
Weekly and after each 1/2" rain event
Professional engineer, reporting to developer construction observations
As required
Modifications per engineering recommendation
Monthly
Street sweeping As needed
Responsible Staff: Prime Contractor
BMP Description: Inlet Protection – Fabric Drop Plan – IL 860 Installation Schedule: October 2008 – September 2010 Maintenance and Inspection:
Inspect the fabric barrier after each rain and make repairs as
needed.
Sediment deposits should be removed after each rainfall to
provide adequate storage volume for the next rain. The
sediment must be removed when the level of deposition
reaches approximately one-half the height of the barrier. Be
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
11
2.7 Establish Perimeter Controls and Sediment Barriers
BMP Description: Silt Fence – IL 920 Installation Schedule: October 2008 – September 2010 Maintenance and Inspection:
Silt fences shall be removed when they have served their
usefulness, but not before the upslope areas have been
permanently stabilized.
Silt fences shall be inspected immediately after each rainfall
and at least daily during prolonged rainfall.
Should the fabric decompose or become ineffective prior to
the end of the expected usable life and the fence still is
necessary, the fabric or the entire system shall be replaced
promptly.
Sediment deposits should be removed after each rainfall.
They must be removed when the level of deposition reaches
approximately one-half the height of the silt fence.
Any sediment deposits remaining in place after the silt fence
is no longer required shall be dressed to conform to the
existing grade, a seedbed prepared and the site vegetated.
Responsible Staff: Prime Contractor
careful not to damage or undercut the fabric during sediment
removal.
When the contributing drainage area has been adequately
stabilized, remove all materials and any unstable sediment
and dispose of them properly. Bring the disturbed area to the
grade of the drop inlet and smooth and compact it.
Appropriately stabilize all bare areas around the inlet. Responsible Staff: Prime Contractor
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
12
2.8 Establish Stabilized Construction Exits
BMP Description: Stabilized Construction Entrance – IL 630 Installation Schedule: October 2008 – April 2010 Maintenance and Inspection:
The entrance shall be maintained in a condition that will
prevent tracking of sediment onto public right-of-ways or
streets. This may require periodic top dressing with additional
aggregate. All sediment spilled, dropped, or washed onto
public right-of-ways must be removed immediately. Periodic
inspection and needed maintenance shall be provided after
each rain. Responsible Staff: Prime Contractor
2.9 Additional BMPs
BMP Description: Additional BMP’s per KDSWCD Requirements Installation Schedule: N/A Maintenance and Inspection:
Install BMP’s at the request of KDSWCD as required for additional protection
Responsible Staff: Prime Contractor
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
13
SECTION 3: GOOD HOUSEKEEPING BMPS
3.1 Material Handling and Waste Management
- An effort will be made to store only enough products required to do the job - All materials stored onsite will be stored in a neat, orderly manner in their
appropriate containers an if possible, under a roof or other enclosure - Products will be kept in their original containers with the original
manufacturer’s label - Substances will not be mixed with one another unless recommended by the
manufacturer - Whenever possible, all of a product will be used up before disposing of the
container - Manufacturers’ recommendations for proper use and disposal will be
followed. - The foreman of each prime contractor will inspect daily to ensure proper
use and disposal of materials onsite BMP Description: Waste Materials
Installation Schedule: Maintenance and Inspection:
All waste materials will be collected and stored in a 30 yard metal open-top dumpster provided by Waubonsee Community College. The dumpster will meet all local municipal and any State solid waster management regulations. All trash and construction debris from the site will be deposited in the dumpster. The dumpster will be emptied as required, and the trash will be disposed in approved manor. No construction waster materials will be buried onsite. All personnel will be instructed regarding the correct procedure for waster disposal. Notices stating these practices will be posted in the contractor superintendent office, the individual from each Prime Contractor who manages the day-today operations, will be responsible for seeing these procedures are followed.
Responsible Staff: Prime Contractor
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
14
BMP Description: Hazardous Waste
Installation Schedule: Maintenance and Inspection:
All hazardous waster materials will be disposed of in the manner specified by local or State regulation or by the manufacturer. Site personnel will be instructed in these practices, the individual from each Prime Contractor who manages day-to-day site operations, will be responsible for seeing that these practices are followed.
Responsible Staff: Prime Contractor BMP Description: Sanitary Waste
Installation Schedule: Maintenance and Inspection:
All sanitary waste will be collected from the portable units a minimum of once per week as required by local regulation.
Responsible Staff: Prime Contractor
3.2 Establish Proper Building Material Staging Areas
BMP Description: Petroleum Products Installation Schedule: Maintenance and Inspection:
All onsite vehicles will be monitored for leaks and receive regular preventive maintenance to reduce the chance of leakage. Petroleum products will be stored in tightly sealed containers which are clearly labeled. Petroleum storage tanks must have secondary containment that will hold 110% of the capacity of the tank. Any asphalt substances used onsite will be applied according to the manufacturer’s recommendations.
Responsible Staff: All Contractors
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
15
BMP Description: Fertilizers
Installation Schedule: Maintenance and Inspection:
Fertilizers used will be applies only in the minimum amounts recommended by the manufacturer. Once applied, fertilizer will be worked into the soil to limit exposure to storm water. Storage will be in a covered shed. The contents of any partially used bags fertilizer will be transferred to a sealable plastic bin to avoid spills.
Responsible Staff: Landscape Contractor BMP Description: Paints
Installation Schedule: Maintenance and Inspection:
All containers will be tightly sealed and stored when not required for use. Excess paint will not be discharged to the storm sewer system but will be properly disposed of according to manufacturers’’ instructions of State and local regulations.
Responsible Staff: All Contractors BMP Description: Hazardous Products
Installation Schedule: Maintenance and Inspection:
- Products will be kept in original containers unless they are not resalable
- Original labels and material safety date will be retained; they contain important product information
- If surplus product must be disposed of, manufacturer’s or local State recommended methods for proper disposal will be followed
Responsible Staff: All Contractors
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
16
3.3 Designate Washout Areas
BMP Description: Concrete Trucks
Installation Schedule:
Maintenance and Inspection:
Concrete trucks will be allowed to wash out on the site as long as waster is contained and disposed of with methods approved by Owner.
Responsible Staff: Concrete Contractor
3.4 Establish Proper Equipment/Vehicle Fueling and Maintenance Practices
BMP Description: N/A – Refueling will not be allowed on site Installation Schedule: N/A Maintenance and Inspection:
N/A
Responsible Staff: N/A
3.5 Control Equipment/Vehicle Washing
BMP Description: N/A Installation Schedule: N/A Maintenance and Inspection:
N/A
Responsible Staff: N/A
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
17
3.6 Spill Prevention and Control Plan
- Manufacturers’ recommended methods for spill cleanup will be clearly posted and site personnel will be made aware of the procedures and the locations of the information and cleanup supplies.
- Materials and equipment necessary for spill cleanup will be kept in the material storage area onsite. Equipment and materials will include but not limited to brooms, dust pans, mops, rags, gloves, goggles, kitty litter, sand, sawdust, and plastic and metal trash containers specifically for this purpose.
- All spills will be cleaned up immediately after discovery. - The spill area will be kept well ventilated and personnel will wear
appropriate protective clothing to prevent injury from contact with a hazardous substance.
- Spills of toxic or hazardous material will be reported to the appropriate State or local government agency, regardless of the size
- The spill prevention plan will be adjusted to include measures to prevent this type of spill from reoccurring and how to clean up the spill if there is another one. A description of the spill, what caused it, and the cleanup measures will also be included.
- Each prime contractor foreman/superintendent will be responsible for the day-to-day site operations associated with their work and will be the spill prevention and cleanup coordinator. He will designate another individual who will become responsible for prevention and cleanup. The names of the responsible individual will be posted in the material storage area and in the office trailer onsite.
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
18
3.7 Allowable Non-Stormwater Discharge Management
- Water from the water line flushings - Pavements wash waters (where no spills or leaks of toxic of hazardous
materials have occurred) - Uncontaminated groundwater (from dewatering excavation) - Using detergent for washing pavement is not allowed
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
19
SECTION 4: SELECTING POST-CONSTRUCTION BMPs
BMP Description: Permeable Paving Installation Schedule: April 2010 Maintenance and Inspection:
It is recommended that permeable interlocking concrete pavements be inspected on an annual basis, preferably in spring after a major rain storm to verify that the stormwater is infiltrating into the system. Areas that have pooled water standing on the surface need to be addressed through remedial maintenance as opposed to routine maintenance. A monitoring well may be installed with the system in some instances and will provide for access to the bottom of the system for observation for rate of exfiltration. The monitoring well also could be used to take water samples to permit runoff quality analysis.
Responsible Staff: Owner
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
20
SECTION 5: INSPECTIONS
5.1 Inspections
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
21
5.2 Delegation of Authority
Duly Authorized Representative(s) or Position(s): Insert Company or Organization Name: TBD Insert Name: TBD Insert Position: TBD Insert Address: TBD Insert City, State, Zip Code: TBD Insert Telephone Number: TBD Insert Fax/Email: TBD Attach a copy of the signed delegation of authority form in Appendix K.
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
22
5.3 Corrective Action Log
Corrective Action Log: See Appendix F for sample Corrective Action Log
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
23
SECTION 6: RECORDKEEPING AND TRAINING
6.1 Recordkeeping
Records will be retained for a minimum period of at least 3 years after the permit is terminated. Date(s) when major grading activities occur: See Appendix I for sample Grading and Stabilization Activities Log Date(s) when construction activities temporarily or permanently cease on a portion of the site: See Appendix I for sample Grading and Stabilization Activities Log Date(s) when an area is either temporarily or permanently stabilized: See Appendix I for sample Grading and Stabilization Activities Log
6.2 Log of Changes to the SWPPP
Log of changes and updates to the SWPPP See Apendix G for sample SWPPP Amendment Log
6.3 Training
Individual(s) Responsible for Training: See Appendix J for sample Training Log Describe Training Conducted:
• General stormwater and BMP awareness training for staff and subcontractors:
• Detailed training for staff and subcontractors with specific stormwater responsibilities:
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
24
SECTION 7: FINAL STABILIZATION
See Appendix B – Landscape Plans.
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
25
SECTION 8: CERTIFICATION AND NOTIFICATION
I certify under penalty of law that this document and all attachments were prepared under my direction or supervision in accordance with a system designed to assure that qualified personnel properly gathered and evaluated the information submitted. Based on my inquiry of the person or persons who manage the system, or those persons directly responsible for gathering the information, the information submitted is, to the best of my knowledge and belief, true, accurate, and complete. I am aware that there are significant penalties for submitting false information, including the possibility of fine and imprisonment for knowing violations.
Name:
Title:
Signature: Date:
Contractor’s Certification
Signature Company Responsibility
Signed:
Title:
Date:
Excavating Contractor
Signed:
Title:
Date:
Site Utility Contractor
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
26
Signed:
Title:
Date:
Plumbing Contractor
Signed:
Title:
Date:
Electric Contractor
Signed:
Title:
Date:
General Trades Contractor
Signed:
Title:
Date:
Concrete Contractor
Signed:
Title:
Date:
Auger Cast Piles Contractor
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
27
SWPPP APPENDICES
Attach the following documentation to the SWPPP:
Appendix A – General Location Map
Appendix B – Site Maps
Appendix C – Construction General Permit
Appendix D – NOI and Acknowledgement Letter from EPA/State
Appendix E – Inspection Reports
Appendix F – Corrective Action Log (or in Part 5.3)
Appendix G – SWPPP Amendment Log (or in Part 6.2)
Appendix H – Subcontractor Certifications/Agreements
Appendix I – Grading and Stabilization Activities Log (or in Part 6.1)
Appendix J – Training Log
Appendix K – Delegation of Authority
Appendix L – Additional Information (i.e., Endangered Species and Historic Preservation Documentation)
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
28
Appendix A – General Location Map
Stormwater Pollution Prevention Plan (SWPPP) Waubonsee Community College – Aurora Campus
October 16, 2008 JJR, LLC
29
Appendix B – Site Maps