TENDER CONSTRUCTION OF BOYS HOSTEL FOR SCHOOL OF PLANNING AND ARCHITECTURE (SPA) IN VILLAGE BHOURI AT BHOPAL.VOLUME-II

(NIT NO-NBCC/SBG (PW)/SPA (Bhopal)/17) (NIT, TECHNICAL SPECIFICATION, BOQ & TENDER DRAWINGS)

SBG (PW), NBCC Ltd., NBCC Place, Pragati Vihar, New Delhi-110003 TEL. 011-46990042, E-MAIL- [email protected]

Seal & Signature of Contractor

Seal & Signature of NBCC

2

(NIT NO-NBCC/SBG (PW)/SPA (Bhopal)/17)TENDER CONSTRUCTION OF BOYS HOSTEL FOR SCHOOL OF PLANNING AND ARCHITECTURE (SPA) IN VILLAGE BHOURI AT BHOPAL.

ISSUED TO : M/s .... ...

SBG (PW), NBCC Ltd., NBCC Place, Pragati Vihar, New Delhi-110003 TEL. 011-46990042, E-MAIL- [email protected]

Seal & Signature of Contractor 2 Seal & Signature of NBCC

Seal & Signature of Contractor

Seal & Signature of NBCC

3

NATIONAL BUILDINGS CONSTRUCTION CORPORATION LIMITED (A GOVT. OF INDIA ENTERPRISE)

INDEXSECTIO N1. 2. 3. 4. 5. 6. 7. 8. 9. 10. 11. 12

DESCRIPTIONNIT MEMORANDUM PARTICULAR SPECIFICATIONS CIVIL ELECTRICAL LIFT LIST OF APPROVED MAKES QUOTING SHEET ABSTRACT OF COST BOQ CIVIL WORK/PHE/HORT. BOQ ELECTRICAL/STREET LIGHT/LIFT/FIRE/SOLAR DRAWINGS

PAGE NO.

5 6 8 9 89 205 237 260 261 262-301 302-341AVAILABLE AT OFFICE

Seal & Signature of Contractor

Seal & Signature of NBCC

4

NOTICE INVITING TENDER

Seal & Signature of Contractor

Seal & Signature of NBCC

5

National Buildings Construction Corporation Limited (A Govt. of India Enterprise)( SBG (PW)

NBCC Place, Bhisham Pitamah Marg, Pragati Vihar New Delhi

Date:- 12.01.2012

NIT NO-NBCC/SBG (PW)/SPA (Bhopal)/17Sealed tenders on percentage rate basis are invited from the Construction contractors/ firms pre-qualified by Corporate Office, NBCC in Civil works category, (C-1) and Specialized Projects Category in appropriate groups i.e. R10-25 Crore and above for Construction and Development work for SPA at Bhopal. S.No Description Estimated Cost/ (R in lacs) EMD/ (R in lacs) 1Construction of Boys Hostel Block at School of Planning and Architecture (SPA) in Village Bhouri at Bhopal. R1444.00

Sale of Tender up to 5:00 PM

Time & date of submission of tender

Time & date of opening of tenders

Time & date of Pre Bid Meeting at above mentioned address 11.30 AM on 30.01.12

27.01.12R 28.88

Up to 3:00 PM on 02.02.12

3:30 PM on 02.02.12

The completion period for this work is 15 months. Detailed tender documents can be purchased from the office of undersigned on any working day as per details given above on payment of R25000.00 (R Twenty five thousand only) towards cost of tender documents (non refundable) through Demand Draft in favour of NBCC Ltd., payable at New Delhi. The same will be received at above mentioned address on due date and time as mentioned in the table. NBCC reserves the right to accept or reject any or all the tender in part or full without assigning any reason whatsoever.Sr. General Manager SBG (PW)

Seal & Signature of Contractor

Seal & Signature of NBCC

6Annexure-A MEMORANDUM Sl. No.i) Name of work

Description

Cl. No.

Values/Description to be applicable for relevant clause(s)CONST. OF BOYS HOSTEL BLOCK FOR SCHOOL OF PLANNING AND ARCHITECTURE (SPA) IN VILLAGE BHOURI AT BHOPAL. NIT NO-NBCC/SBG (PW)/SPA (Bhopal)/2011/17 SPA BHOPAL Percentage Rate

ii)

Client/Owner

iii) iv)

Type of Tender Earnest Money Deposit NIT

R 28.88 Lacs (Rupees Twenty Eighty Lacs Eighty EightThousand Only)

v)

Estimated Cost

NIT

R 1444.00Lacs (Rupees One Thousands FourHundred and Forty Four Lacs Only) Total work to be completed in 15 (Fifteen Months) in accordance with the time schedule of completion of work in the tender documents.

vi)

Time for completion of work

NIT

vii) viii)

Mobilization Advance Interest Rate on Mobilization Advance Schedule of Rates applicable

8.0 8.0

___% (____Percent) of Contract Value.N/ACivil works : DSR-2007 Sanitary works : DSR-2007 Electrical works : SR-2007 90 (Ninety) Days 5.00% (Five Percent only) of contract value within 15 days after issue of Letter of Award. 5.00% (Five Percent only) of the contract amount, which shall be deducted in the manner set out in this contract. The date of start of contract shall be reckoned 10 days after the date of issue of telegram/letter/telex/FAX of Letter of Award of acceptance of tender.

ix)

69.0

x) xi)

Validity of Tender Performance Guarantee

4.0 9.0

xii)

Security Deposit/Retention Money

10.0

xiii)

Time allowed for starting the work

43.0

xiv)

Defect Liability Period

74.0

12(Twelve) Months from the date of taking over of works.

xv)

Recovery rate of work force supplied by NBCC to Contractor

28.5

R 12,500/- (Rupees Twelve Thousand FiveHundred only) for each man per month.

Seal & Signature of Contractor

Seal & Signature of NBCC

74. Should this tender be accepted, I/we agree to abide by and fulfill all terms and conditions referred to above and as contained in tender documents elsewhere and in default thereof, to forfeit and pay NBCC, or its successors or its authorized nominees such sums of money as are stipulated in the notice inviting tenders and tender documents. I/we hereby pay the earnest money of amount as mentioned in the Memorandum to this Form of Tender in favour of NBCC Limited payable at place as mentioned in the NIT/ITT.

5.

6.

If I/we fail to commence the work within 10 days of the date of issue of Letter of Intent and/or I/we fail to sign the agreement as per Clause84 of General Conditions of Contract and/or I/we fail to submit performance guarantee as per Clause 09 of General Conditions of Contract, I/we agree that NBCC shall, without prejudice to any other right or remedy, be at liberty to cancel the Letter of Intent and to forfeit the said earnest money as specified above. I/we are also enclosing herewith the Acceptance letter on the prescribed pro-forma as referred to in condition of NIT.

7.

Dated the______________day of_______________ SIGNATURE OF TENDERER

NAME (CAPITAL LETTERS) :_______________________

ADDRESS

________________________________ ________________________________

SEAL OF TENDERER SIGNATURE OF WITNESS NAME (CAPITAL LETTERS):_______________________

OCCUPATION

_______________________

Seal & Signature of Contractor

Seal & Signature of NBCC

8

PARTICULAR SPECIFICATIONS

Seal & Signature of Contractor

Seal & Signature of NBCC

9

SPECIFICATIONS FOR CIVIL WORKS

Seal & Signature of Contractor

Seal & Signature of NBCC

10

SPECIFICATIONS FOR CIVIL WORKS

I.

CURTAIN WALL GLAZING

1.

Scope of work

1.1

Preliminary requirements i) The contractor shall design test, fabricate, deliver, install and guarantee all construction necessary to provide a complete curtain wall system for the proposed building, all in conformity with the drawing as shown. Specification and all relevant construction regulations including providing any measures that may be required to that end, notwithstanding any omissions or inadequacies of the drawings. The curtail wall system shall also include the following activities: a) Metal frames, glass glazing, spandrels, ventilators, finish hardware, copings metal closure, windows etc. All anchors attachments, reinforcement and steel reinforcing for the systems required for the complete installations. All thermal insulation associated with the system. All fire protection associated with the system. All copings and closure and metal cladding to complete the system.

ii)

iii)

b)

c) d) e)

Seal & Signature of Contractor

Seal & Signature of NBCC

11f) All sealing and flushing including sealing at junctions with other trades to achieve complete water tightness in the system. Isolation of dissimilar metals and moving parts. Anticorrosive treatment on all metals used in the system. Polyester powder coating aluminum sections.

g) h)

i) iv)

The contractor shall also be responsible for providing the following: a) Engineering proposal, shop drawings, engineering data and structural calculations in connection with the design of the curtain wall system. Mock-ups, samples and test units. Performance testing of the curtain wall framing and glazing assembly. Co-ordination with the work of other trade. Insulation with glass wool 48 kg/cum at spandrels area. Protection All final exterior and interior cleaning and finishing of the curtain wall system. As built record drawings and photographs Guarantees and warranties.

b) c)

d) e) f) g)

h) i)

Seal & Signature of Contractor

Seal & Signature of NBCC

12j) k) All hoisting, scaffolding, staging and temporary services. Conceptualizing and design of a suitable maintenance system for curtain glazing.

v)

The water tightness and structural stability of the whole curtain wall system are prime responsibility of the contractor. Any defect or leakage found within the guarantee period shall be sealed and made good all at the risk and cost of the contractor. The curtain wall system shall be designed to provide for expansion and construction of components which will be caused by an ambient temperature range without causing buckling, stress on glass, failure of joint sealants, undue stress on structural elements or other detrimental effects, specific details should be designed to accommodate thermal and building movements.

vi)

1.1.1 Quality consideration and other activities i) The contractor while submitting the detailed design calculations should submit the following information on the quality of materials to be used and other aspects as detailed below: a) b) Metal quality, finishes and thickness Glass quality, coating and thickness and proposed manufacturers brand names. Aluminum extracted sections including mullions and transoms together with structural calculations and proposed manufactures brand name and also the name of agency proposed for fabrications work. Arrangement and jointing of components. Field connections especially mullion to mullion and transom to mullion.

c)

d) e)

Seal & Signature of Contractor

Seal & Signature of NBCC

13f) Fixing and anchorage system of typical wall unit together with structural calculations. Drainage system and provision in respect of water leakage in the curtain wall system. Provisions for thermal movements. Sealant and sealing methods. Glazing method Wind load and seismic load and any other specific load considered in the design.

g)

h) i) j) k)

ii)

Tolerances : Any Parts of the curtain wall, when completed, shall be within the following tolerances: a) Deviation from plumb, level or dimensioned angle must not exceed 3mm per 3.5m length of any member, or 6mm in any total run in any line. Deviation from theoretical position on plan or elevation, including deviation from plumb, level or dimensioned angle must not exceed 9mm total at any location. Change in deviation must not exceed 3mm for any 3.5m run in any direction.

b)

c)

1.1.1.1 1.12.1 1.1.2.1.

Execution of work Performance Testing General Requirements

i)

Mock-up units shall be constructed by the contractor and tested to determine the structure stability as well as air and water

Seal & Signature of Contractor

Seal & Signature of NBCC

14infiltration or leakage at glazing beads and all other joints designed into the face of the building. ii) After the approval of structural calculations and the drawing for construction of the curtain wall one test unit for performance testing of the curtain wall shall be constructed by the contractor at an independent laboratory or at a laboratory approved by the client / Engineer-in-Charge / Architect. Erect mock-up under manufacturers / Fabricators direct supervision and employ workmen as they would be employed during the actual erection at the job site. The contractor shall submit to the client / Engineer-in-Charge / architect the test procedures to be adopted, test schedule and location for testing before the work of actual testing is taken up. Prior to the fabrication of test units, the contractor shall submit shop drawings and design calculations of the test unit for approval of the client / Engineer-in-Charge / Architect. The contractor shall not start the work of erection of curtain was on site till the approval for the successful completion of the mock up test and clear instruction in writing to start the work is received from the client / Engineer-in-charge / architect. The decision of the client / Engineer-in-Charge / architect in respect of the procedure to be adopted, in conducting the mock up test and the judgment over the net results, shall be final and binding n the contractor.

iii)

iv)

v)

vi)

vii)

1.1.2.1.2

Test of wind pressure i) The equivalent load of wind pressure or wind suction shall be given to the test unit as increasing or decreasing the inside pressure in the pressure chamber at which the test unit is fixed. The static wind pressure shall be applied up to 1.5 kpa at maximum wind pressure.

ii)

Seal & Signature of Contractor

Seal & Signature of NBCC

15

iii)

The variation of dynamic pressure shall be of any approximate sine curve line. Deflection on each observational points of the test unit shall be observed and recorded under static pressure as described above. Any damage and harmful permanent deformation on any parts except seating materials shall not be found at maximum wind pressure. The deflection on the main structural parts in this condition shall not exceed: a) b) c) 1/175 of the span between supports or 20mm, whichever is less for vertical elements. 1/250 of the span between supports for horizontal elements. The extent of recovery of deformation, 15 minutes after the removal of the test load, is to be at least 95%.

iv)

v)

vi)

1.1.2.1.3

Test of Lateral Deflection per floor height

i)

Lateral deflection per floor height shall occur on the test unit, when the structural frame which fixes the test unit is deflected horizontally. The deflection of every + 2.5mm shall be increased up to + 13mm on the test unit (static deflection test). The dynamic deflection shall be applied up to + 13mm. The variation of dynamic deflection shall be of an approximate sine curve line, one period of 3 seconds.

ii)

iii) iv)

Seal & Signature of Contractor

Seal & Signature of NBCC

16

v)

The dimensions of the deflection on each observational point of the test unit shall be measured under the condition as described above and the damage shall be observed. Any dimensions and harmful permanent deformation shall not be found in any parts of the curtain wall except the damage to sea ant at maximum deflection.

vi)

1.1.2.1.3

Water-tightness Test i) ii) iii) iv) Water shall be sprinkled to the Test unit under wind pressure. Pressure shall not be applied to the test unit. The volume of the sprinkling water in one minute shall be 5 liters per sq.m minimum (0.1 gal./sq.ft). All water leakage and drainage system at the joint and the openable sash of the curtain wall system shall be observed from the outside of the chamber. Hold the test two times, in sequence as described below, conforming to the above mentioned conditions: Install the test unit. a) b) Hold first water tightness test. c) Hold test of wind pressure as described above. d) Hold second water tightness test. e) Lateral deflection test. Water leakage shall not be observed inside at all parts of the test unit during first water tightness test.

v)

vi)

1.2 1.2.1

Glazing Sheet Glass, Frosted Sheet Glass i) Sheet glass shall be flat, transparent and clear as judged by unaided eye. It may however passes slight tint when viewed edge wise. Sheet glass shall be of selected quality (SQ) or ordinary quality (OQ) as per IS : 2835. Glass shall be free from cracks. Unless otherwise specified ordinary quality sheet glass shall be used.

Seal & Signature of Contractor

Seal & Signature of NBCC

17ii) Dimensions : Normal thickness and range of thickness of sheet glass shall be as per table below tolerance on our size (length and width) shall be + 2.0mm.

Normal Thickness (mm) 6.3

Range of Thickness (mm) 6.0 to 6.6

Weight (kg/sqm) 15.5

iii)

Glass panes shall be free from flaws, specks or bubbles. All panes shall have properly squared comes and straight edges. The glass panes shall be so cut that it fits slightly loose in the frames. Glazing shall be provided on the outside of the frames unless otherwise specified. Fixing of glass panes shall be done with aluminum beading. Fabricator shall drill appropriate holes for screws. Normally the beading are fixed with screws spaced not more than 10cm from each corner and intermediate not more than 20cm apart. When the glass panes are fixed with aluminum beading having mitred joints, epoxy resin or silicon sealant shall be applied between glass panes and sash bars and also between glass panes and the beading. All glass panes shall be fixed within the aluminum framing by use of C.P brass or stainless steel screws and the joints sealed with epoxy resin or silicon sealant to make the unit completely water proof. Glazing or caulking compound around the perimeter of glass shall not be permitted. Fixed glass panes shall be supported by setting blocks. There shall be no whistling or rating. For normal size glass panes glazing clips are not provided. Four glazing clips may be provided per glass pane for a size larger than 30cm X 60 cm for all types. Where the glass panes sizes exceed 80cm X 200cm 6 glazing clips shall be used. In case of doors, windows and ventilators without horizontal glazing bars, the glazing clips may be spaced according to the slots provided in the vertical

iv)

v)

vi)

vii)

Seal & Signature of Contractor

Seal & Signature of NBCC

18members only if the spacing does not exceed 30 cm otherwise minimum 30cm spacing or as specified shall be maintained. viii) The aluminium anodized extruded glazing beads or snap beading to be used should also be the product from the manufacturer of aluminium extruded sections used for fabricating the doors windows etc. no manufactured by local units shall be permitted to be used.

1.3

Aluminium panel i) Aluminium sheets for use as kick panels shall be 1.25mm thick aluminum alloy sheet conforming to IS : 737 1986. Aluminium alloy sheets for use in general paneling work shall be of types and thickness as specified and conforming to the requirements of IS : 737. aluminium sheets shall be of approved make manufactured by reputed manufacturers. Aluminium panel may be prefabricated units manufactured on modular or non-modular dimension. Fixing : The required size of panel keeping sufficient margin to be inserted inside the section shall be cut to correct size and fixed firmly in the frame with CP brass or aluminium screws. Joints sealed with epoxy resin or silicon sealant to make the unit water proof.

ii)

iii)

iv)

2.0

ITALIAN MARBLE WORK 2.1 Polished Italian Marble shall be hard, sound, dense and homogeneous in texture with crystalline texture as far as possible. It shall generally be uniform in colour and free from stains, cracks, decay and weathering.

Seal & Signature of Contractor

Seal & Signature of NBCC

192.2 Moisture absorption after 24 hrs immersion in cold water should be less than 0.4% by weight and its hardness on Mhos scale shall be more than 3. Before starting the work, the contractor shall get samples of marbles approved by the Engineer in-charge. Approved sampled shall be kept in the custody of the Engineer-in-Charge and the Italian Marble supplied and used on the work shall conform to samples with regard to soundness, colour, veining and general texture. Base concrete or the RCC slab on which the Italian Marble slabs are to be laid shall be cleaned, wetted and mopped. The bedding for the Italian Marble slabs shall be with cement mortar 1:4 (1 cement : 4 coarse sand) as given in the description of the item. The mortar used for jointing shall be as specified the item. The average thickness of the bedding mortar under the slab shall be 20mm and the thickness at any place under the slab shall be not less than 12mm. All Italian marble stone shall be wetted before placing in position. These shall than be floated on mortar and bedded properly in position with wooden mallets without the use of chips or under pinning of any sort. When necessary jib crane or other mechanical appliances shall be used to hoist the heavy pieces of stones and place these in to correct positions, care being taken that the corners of the stone are not damaged. Stone shall be covered with gunny bags, before putting chain or rope is passed over it, and it shall be handled carefully. No piece which has been damaged shall be used in work. The matching or grains shall be carried out as directed by the Engineer-in-Charge. The work shall be suitably protected from damage during construction. The junction between wall plaster and floor shall be finished neatly and without waviness.

2.3

2.4

2.5

2.6

2.7

2.8

2.9

Seal & Signature of Contractor

Seal & Signature of NBCC

202.10 Measurements the Italian marble stone flooring with different kind of Italian marble shall be measured separately and in square meter correct to two laces of decimal. Length and breadth shall be measured correct o a cm before laying, skirting, dado or wall plaster.

3.0

GALAVANIZE CHICKEN WIRE MESH 3.1 The Galvanize Chicken Wire Mesh should be 24 gauge 12mm size openings with uniform galvanization and it should be fix at the junction of concrete and masonry over lapping minimum 75mm.

4.0

M S RAILING 4.1 The M S railing shall be as per drawing & design consisting of 62mm outer dia and 50mm N.B, M.S pipe weight not less than 4.20kg/mtr in top and 50X6mm M.S flat in bottom of grill frame. 12 mm size vertical bar placed @ 15 cm centre to centre property welded in frame of M.S pipes & M.S flat.

4.2

5.0

STAINLESS STEEL RAILING Stainless Steel Railing of grade 304 of approved size by welding etc. to steel ladder railing, balcony railing and staircase including finishing, polishing etc. complete.

6.0

ACRYLIC NAME PLATE 5.1 5.2 5.3 Opaque milky white sheet for acrylic nameplate should not be less than 5mm thick, properly cut in required size. Computerized design letters, numbers, should not be less than 25mm in size pasted with high class adhesive. Name plate should be fixed on wall or locations where required with brass screws.

7.0

CABINATES / BUILT IN FURNITURE

Seal & Signature of Contractor

Seal & Signature of NBCC

21

6.1

Ward robe should made 19mm thick ISI marked, water proof, pre-laminated, veneered commercial 1st class quality board in partitions shelves and shutters. Inner sides of walls 6mm 1st class ISI marked waterproof ply shall be used. All fittings, locks, knobs, channels, fly rails, hangers, hooks, handles etc. should be stainless steel as per BIS specifications. All hinges used must be of stainless steel & ISI marked.

6.2

6.3

6.4 8.

SPIDER AND PATCH GLAZING

Spider and patch glazing as per elevation drawing, including providing 12mm thick clear specified float glass, as per approved duly toughened on horizontal tempering furnace in Tam glass Plant. The patch fitting would be of stainless steel SS 304 Grade and of Ozone make. The fitting should comprise of top patch; Bottom Patch; Corner Lock, floor machine; Over and Side; Panel patch fin type; and D shape Pull Handle or 32mm dia and 600mm length. The contractor shall work out the exact quantities required based on fitting selected and the elevation applicable for each shop front location and no extra amount shall be payable on this amount. The perimeter of the shop front glazing shall be grouted in the Masonry / RCC / Stone as per respective location, by using a channel of 32mm x 35mm height x 1.6mm thick. The fixing cannel shall be done by drilling holes with an electrical drill, inserting as per direction & design by Engineer-in-Charge / Architect.

9.

ALUMINIUM COMPOSITE SHEET CLADDING

Aluminium Composite Sheet Cladding using 4mm thick sheet of approved make consisting of a core of 3mm natural

Seal & Signature of Contractor

Seal & Signature of NBCC

22polyethylene core sandwiched between two skins (0.5mm each) of aluminium alloy with outer surface in all colour coating of PVDF paint in fully automatic coil coating process. The PVDF coated finished surface to be factory protected with selfadhesive peel off foil tested to withstand at least 6 months exposure to local weathering conditions. The composite sheet cut and bent to shaped profiles as required to, including perimeter extrusions base frame, extruded stiffeners, expansion fasteners & silicone sealant (Dow Corning 789) required for installation as per approved elevation drawing. Work includes necessary accessories complete in all respects as per direction & design by Engineer-in-Charge / Architect.

10.

INTEGRAL WATER PROOFING OF RCC WORKS.

SCOPE

Integral water proofing of all such parts of the structure that are most likely to come in contact with subsoil water, dampness etc. and pose danger of weakening the structure under attack of dampness and corrosion of the reinforcement. Parts of the structure like foundation rafts, strip footings, isolated column footings, foundations for shear and retaining wall etc.

The work of integral water proofing with crystalline water proofing material must be carried out as per the specifications and precautions stipulated in the product manual and under the specialized supervision of the authorized person of the manufacturer.

The work of integral water proofing must be carried out by the authorized applicator of crystalline water proofing, certified by the manufacturer.

Seal & Signature of Contractor

Seal & Signature of NBCC

23The contractor shall receive guarantee for guanine water proofing compound of the manufacturer and guarantee of integral water proofing of the RCC elements from the manufacturer and its authorized agency as applicator for a period of minimum of 10 years and the contractors shall furnish a written guarantee for water proofing, on bond paper for minimum of 10 years and extend / pass on the guarantee so received from the manufacturer to the NBCC / EMPLOYER.

APPLICATION

Providing, laying and casting integral Crystalline Water Proofing material for horizontal surface. Mixing approved brand of crystalline water proofing material like Xypex 2000 NF / Penetron etc., with RMC during mixing, with mixing the water proofing material with water-2 parts of water proofing to 5 parts of water and adding to the ingredients of RMC during mixing 0.7 to 0.8 kg of crystalline water proofing to 1 cu.mt of RMC, Thoroughly mixing to workable consistency and pouring and casting in position within 20 minutes, Vibrating with mechanical vibrators and compaction etc. complete as per direction of Engineer-in-Charge.

For all vertical surfaces of shear walls / retaining walls and all such areas and parts of walls where the percolation of water or dampness is due to subsoil absorption of water, the vertical surfaces of shear walls / retaining walls shall be treated with the concentrate of the crystalline water proofing material.

Applying in two coats of crystalline water proofing material concentrate with brushes / rollers of spray to ensure uniform application, over dried surface of concrete etc. complete as per direction of Engineer-in-Charge.

Seal & Signature of Contractor

Seal & Signature of NBCC

24INTERIOR FURNISHING ITEMS AND SPECIAL ITEMS

11.

GLASS PARTITIONS

11.1

General

Glass shall be clear float glass of the quality and finish shown in the drawing and schedules unless otherwise required. This shall be frosted / etched in design and pattern as per drawing. The contractor shall submit samples of all types f glass for approval. Delivered material shall match the approved samples. Packaged materials shall be delivered at site and stored in a dry, well ventilated location. Cutting of glass shall be in accordance with site measurements.

11.2

Thickness

All fixed panel shall be 12mm thick unless otherwise specified.

11.3

Edges

All exposed edges of glass / mirror shall be polished and grinded and mitred as per IS Specifications, wherever, it is indicated in the drawing.

11.4

Drilling & Cutting All drilling of holes shall be carried out at the stage of fabrication. No chipping, starring and other visible imperfections around holes will be accepted. Fabrication / cutting of glass / mirror shall be in accordance with site measurements. All edges

Seal & Signature of Contractor

Seal & Signature of NBCC

25shall be smoothened before fixing. No chipping, starring and otherwise visible imperfection around cut edges shall be accepted.

11.5

Protective Coating The Etched (frosted) surface shall be given chemical treatment as per manufacturers recommendation in order to have permanent stain free surface. The frosted etched surface should not absorb / retain any stains.

11.6 11.6.1

Fixing Glass shall be fixed as shown on the drawings or otherwise specified. Due rebates and tolerances as specified by the manufacturer of glass shall be provided at no extra cost. Screws shall be brass with collars and screws on domes unless otherwise required. The glasses shall be fixed in position with EPDM Gasket or as specified.

11.6.2

11.7

Protection of Glass

11.7.1

Glass shall be protected from paint, plaster, welding splatter, construction scum and the like. Should any such soiling occur, the glass shall be promptly and completely washed off as specified. Special care shall be taken by contractor to protect the glass / surface melamine polishing.

11.7.2

Glass generally shall be protected with temporary wooden barricades or other warning devices as a deterrent against passing objects through glazed openings.

Seal & Signature of Contractor

Seal & Signature of NBCC

2611.7.3 The contractor shall be responsible for protecting all glass in those areas of work forming part of this contract. The contractor shall replace at his own expense any broken or damaged glass caused through lack of adequate protection or care in installation or handling.

11.7.4

The contractor shall make his own investigation to guard against local sources of attach and damage and take all necessary precautions for operation.

11.8

Cleaning

When directed by the Architect / Engineer-in-Charge, the contractor shall remove all markings and labels from glass and wash the same with a mild neutral or slightly acidic solution as recommended by the glass manufacturer. Alkaline or abrasive agents shall not be used. 11.9 Completion On completion of installation the contractor shall leave all glass and fixings perfect to the satisfaction of the Architect / Engineerin-Charge. Providing and fixing of full height partition with 12mm thick toughened glass as shown in the drawings, frameless type using patch fittings as approved comprising of stainless steel, threaded rod, pivots with plug, top frame with removable pin with cover plate, top porch with plastic sockets for top pivot, bottom patch, back check suitable for 12mm thick heat strengthened clear toughened glass for fixed glazed portion with adjustable lock keeper plates in two part, floor sockets over panel strike boxes, to suit corner locks including cost of all materials, labour, machinery, fabrication, chasing in the floor chipping of walls, beams, columns, rectification of plaster, painting if required erection, installation, transportation all charges etc. complete as per design and drawing and direction of bank (make : Saint Gobin OR EQUIVALENT) as per direction of Engineer-in-Charge.

Seal & Signature of Contractor

Seal & Signature of NBCC

27

12.

GENERAL SPECIFICATIONS FOR ALL INTERIOR WORK / LAMINATED WORKS AND FRAMING

WOOD

CARPENTRY AND JOINERY

12.1

Drawings and Dimensions Drawings shall not be scaled. Figured dimensions shall be strictly followed, large-scale drawings / details shall super cede small scale drawings. The contractor shall verify all dimensions and information given in the drawings for existing conditions of site.

The Contractor shall be fully responsible for any error, difficulty in execution / damage incurred owing to discrepancy in drawings which has been overlooked by him and has not been brought to the notice of Architect / Engineer-in-Charge.

12.2

Rough Carpentry material All framing and other concealed wood members shall be of specified quantity of timber as shown in drawings and as per the direction of the Architect / Engineer-in-Charge. Wood shall be seasoned to a moisture content as per provision of the IS Code.

12.3

Joinery Materials Finished joinery including frames for doors, partitions, etc. shall be with straight grained best quality Indian teakwood unless noted otherwise, free from knots and other blemishes and imperfection. All joinery work shall be securely mortised and tenoned and glued

Seal & Signature of Contractor

Seal & Signature of NBCC

28with best quality waterproof glue. All sections and dimensions to be shown and wood work screws of appropriate size and of approved make shall be used. Wherever practicable means of fastening the various parts together shall be concealed. All work (both carpentry and joinery) shall be to the dimensions shown on drawings.

All interior wood finish, doors and cabinet work shall be smoothly treated and sanded after erection, until all defects are entirely removed. Any works showing splits, saw, sand paper or other defecting marks or other defects shall be rejected. All exposed wood and plywood shall be straight grained of matches grain and colour and shall be approved by the Architect / Engineer-inCharge before being fabricated.

12.4

Wooden Frames Frames where asked for shall be of first class Jammu Kailwood for partitions hillock and C.P. teak wood for furniture or as specified and planed to obtain the required size as described in the item. Sawing shall be truly straight and square and in the direction of the grains and scantling shall be accurately planed smooth to the required dimensions before the same is fixed in position. A tolerance of 2.3 mm shall be allowed in the finished cross section. Joints shall be simple, neat and strong. All mortise and tenon joints, mitred joints, scarves etc. shall fit in fully and accurately without wedging or tilling. The contact surfaces of all joints shall be treated with bulk type synthetic resin adhesive.

12.5

Particle Board The Particle Board shall be approved Commercial veneered threelayer flat pressed Teakwood Particle Board conforming to IS 8087 1985 Type I bonded with BWP type Phenol Formaldehyde Synthetic resin of the thickness as mentioned in the item and drawings.

Seal & Signature of Contractor

Seal & Signature of NBCC

29

12.6

Plywood / Ply board / Block board / Commercial boards Plywood / Ply board / Block board / Commercial boards shall be of approved make, boiling waterproof grade (BFW), bonded with high quality Phenol Formaldehyde Synthetic Resin, Exterior Grade treated with preservatives to make it resistant to termites, rot, fungus and other wood destroying organisms conforming to relevant IS Specifications. The Plywood shall be good quality, close grained Plywood suitable for veneering, painting or bonding plastic laminates as specified. Expose edges shall be finished with edge strip of solid teakwood, tongued and grooved and glued or as detailed. The block boards shall be built up board with blocks upto 35mm thick. Block boards shall be approved make, boil resistant type bonding and veneered on both faces with identical sheets or as specified.

12.7

Timber Timber required for framing and other wood members shall be well seasoned, kiln dried and of good quality with a moisture content of 12% nominal. All timber shall be uniform in texture, free from large loose, dead or cluster knots, veins, shakes, fungal growth, bore holes, rot, decay, discoloration, soft and spongy spots, hollow, pockets, pits or center heart, box heart pitch pockets, streaks, insect attacks and all other defects and blemishes which would affect strength, usability and shall be flat, straight, non splitting and dressed on all side. It shall be matched for colours and graining. Teakwood shall be of 1st class C.P Indian teakwood and soft Indian teak wood. Wood wherever specified is of 1st class Jammu Kailwood for partitions and paneling and hillock / teak wood for furniture or as specified.

12.8

Laminate Veneer (a) Decorative laminated veneer sheeting shall be of the brand & catalogue, number and colour indicated. The

Seal & Signature of Contractor

Seal & Signature of NBCC

30laminated veneer shall be 1.5mm thick on flat surfaces and 1 mm thick on curved surfaces unless otherwise approved. Teak veneers shall be well matched and thickness shall be 4mm. (b) Laminates shall be veneered to mounting surface with an approved adhesive, used in strict accordance with the manufacturers instructions. Rubber based adhesive shall not be used. No surface glanding of laminate will be allowed. Unless otherwise specified, all laminate shall have standard plain colour suede satin / plain / matt or as specified. Samples of laminate showing the surfaces texture and shade shall be submitted for approval before fixing. The veneer shall be as specified and shall be equal or superior quality to that laid down in IS 1659-1960 or as approved. The contractor shall submit a one square meter sample of each finished veneer type for approval.

(c) (d)

(e)

(f)

(g)

12.9

Wood preservative treatment Wood preservative of specified quality and approved make shall be used for all wood work done by the contractor. Treatment shall be done after the surface is made free from dirt, dust, any is made free from dirt, dust, any foreign matter and all rough spots and papered and cleaned. The surface must be perfectly dry before treatment is commenced. In addition to above, all portions of timber in joinery work, abutting against or embedded in masonry or concrete shall be painted with boiling coal tar before being placed in position. The rate would be made for the same.

Seal & Signature of Contractor

Seal & Signature of NBCC

3112.10 Fire retardant paints on Wood Work All wood work done by the contractor shall be painted/coated with fire retarding pint of brand approved by Architect/Engineer-incharge, CBRI and fire authorities. The painting work shall be done as per manufacturers specifications by soft brushes and by pencil brushes in corners etc. The rate would include providing all material, brushes etc. No extra payment would be made for the same.

12.11

Framing Framing shall be as specified or required size and at required spacing as indicted in the drawings and all specifications described in subsidiary frames of partition shall apply. The frames shall be fixed to the ceiling and floor with gun metal dash fasteners only. The frames with fixed in position shall be fairly and truly leveled.

12.12

Hard Wares

All hard wares shall be of the approved quality and conforming to relevant I.S. specification. Samples of all hard wares shall be got approved from the Architect/Engineer-in-char before placing order for bulk procurement. Brass hard wares where asked for shall be zinc plated. All hard wares shall function smoothly without any friction or crack when fixed in position. The approved samples shall be kept in safe custody of Architect/Engineer-in-charge for checking the correctness of materials procured in comparison with approved sample. All door hinges, latches, door tracks, door closers, floor springs etc. Shall be as specified of an approved make and shall have written guarantee for trouble free performance, free maintenance and replacement as may be needed during defect t liability period is essential. The rates shall be inclusive of all materials and lab our for complete execution of the item.

Seal & Signature of Contractor

Seal & Signature of NBCC

3212.13 Fastenings

Screws and other fastening etc., shall be of standard make of brass or unless otherwise shown on drawings. Exposed screws etc. shall be of brass or other non-corrosive metal. Exposed fastenings shall match the finish of hardware. Power driven fasteners may be used for fastening to concrete, brick masonry and steel work.

Where screws show on a finished surface, they shall unless otherwise detailed, be sunk and the hole plugged with a wood plug of the same wood and grain of the finished surface. Nails on finished surfaces shall be neatly punched and the hole filled with wood filler to match. Fixing by means of wooden plugs will be permitted only where it is required.

12.14

Floor Spring and Pivot

Hydraulically regulated floor spring and pivot shall conform to I.S. for heavy duty performance. Suitable adjustments shall be made such that the closing time can be raised five seconds to twenty five seconds. The oil filling shall work well in all seasons and shall not show any signs of leakages of oil under working conditions. Payments shall be made per number and shall be inclusive of supply of all accessories, fixing the door pivot/floor spring, anodizing/painting etc. complete as per direction of Architect/Engineer-in-charge.

12.15

Timber Fixing

The carpentry timber shall be fixed with nails, spikes, dash fasteners, bolts, screws, hangers, stirrups, anchors, ties or any other accessories which are suitable to develop the full strength

Seal & Signature of Contractor

Seal & Signature of NBCC

33of the member to which they are supported and to which they are attached, as directed.

12.16

Fixing in Masonry/Concrete Carpentry timber where fixed to solid masonry or concrete shall be secured with expansion bolts or other positive methods of mechanical fastening. Carpentry timber where fixed into hollow masonry shall be secured with toggle bolts and steel with bolts, nuts and washers.

12.17

Storage of Sheet materials Sheet materials shall be t5ransported and stored flat, with sufficient support to prevent bowing and wrapping and to prevent damage to edges and corners. Sheet materials shall protected from weather and kept off the ground and in dry, well ventilated conditions.

12.18

Samples The contractor shall submit samples of all materials/items including samples of veneer assemblies for approval. All materials pre-fabricated, delivered and assembled shall be in accordance with the approved samples.

12.19

Delivery and Storage Shop fabricated items Ship fabricated items shall be delivered to the site of the work and installed/ fixed/placed in position and shall be properly protected whilst in transit. Installed work shall be adequately protected against soiling or damage. Damaged or soiled items shall be made good or replaced at the contractors own expense and to the satisfaction of the Architect/Engineer-in-charge.

Seal & Signature of Contractor

Seal & Signature of NBCC

34

13.

WOODEN PARTITION :

Providing and fixing full height partion Framework made in 50 x 50 mm wooden frame of Mirandi/chap/Kali/Malaysian Sal, Vertical frame to horizontal members and placed at a maximum of 600mm c/c both ways. The frames shall be securely fix to walls, floor, ceiling complete in all respect including making provisions for electrical conduits etc. and two coats of approved primer and fire retardant paint. a As per drawing and specifications and direction of architect/bank including providing and fixing framing both side with 9 mm thick BWR grade ply wood finished with 1 mm thick decorative laminate/veneer (with polishing) of approved shade and make as per design with moulding on edges. Rubber wood edging and molding as per design and sizes complete in all respect including polishing of wooden surfaces in natural shade with melamine. (Make: Formica, Sunmica, Kitply, Century Or Equivalents) as per direction of Engineer-in-charge.

14.

M.S. FRAME PARTITION:

Providing and fixing full height partition Framework made in 50 x 50 mm M S Frame. Vertical frame to horizontal members and placed at a maximum of 600mm c/c both ways. The frames shall be securely fix to wall, floor, ceiling complete in all respect including making provisions for electrical conduits etc. and two coats of approved primer and fire retardant paint. As per drawing and specifications and direction of architect/ bank including providing and fixing ramming both side with 9mm thick BWR grade ply wood finished with 1mm thick decorative laminate/veneer (with polishing) of approved shade and make as per design with moulding on edges. Rubber wood edging and molding as per design and sizes complete in all respect including polishing of wooden surfaces in natural shade with melamine. (Make: Formica, Sunmica, Kitply, Century OR EQUIVELENT) as per direction of Engineer-in-charge.

Seal & Signature of Contractor

Seal & Signature of NBCC

35

15.

SEMI HEIGHT PARTITION:

Providing & fixing partition panel of 75mm thickness and ht 1500 mm. Frame of CRC of 75 x75 mm & 75 x 25mm not less than 22 gauge. Snap on panel made of 12 mm pre laminated particle/MDF block board/fabric having raceway at two levels, one at skirting and one above/below the worktop. 5mm clear glass provided above 1125 mm ht upto 1500mm (facia finish in approved laminate /veneer) or equivalent as per direction of engineer-in-charge.

16.

WALL PANELING:

Providing and fixing full height wooden panel framework made in 50 x 25mm wooden frame of Mirandi/chap/Kail/Malaysian Sal, Vertical frame to horizontal members and placed at a maximum of 600mm c/c both ways. The frames shall be securely fix to walls, floor, ceiling complete in all respect including making provisions for electrical conduits etc. and two coats of approved primer and fire retardant paint, wood preservative as per drawing and specifications and direction of architect/Engineerin-charge including providing and fixing framing one side with 9mm thick BWR grade ply wood finished with 1mm thick decorative laminate of approved make and shade as per design with moulding on edges. Rubber wood edging and molding as per design and sixes complete in all respect including polishing of wooden surfaces in natural shade with melamine or equivalent as per direction of engineer-in-charge. (Make : Formica, Sunmica, Kitply, Century Or equivalent).

17.

FULLY GLAZED DOOR (FRAME LESS)

Providing and fixing of twin style fully glass door as shown in the drawing, frameless type using patch fittings as approved

Seal & Signature of Contractor

Seal & Signature of NBCC

36comprising of stainless steel, SS Handle size 300 (all doors)/400 mm (entrance only), threaded rod, pivots with plug, top frame with removable pin with cover plate, top proch with plastic sockets for top pivot, bottom patch with insert for floor spring spindles/pivot, floor pivot bearing double action floor spring and corner lock euro profiles, cylinder single throw bolts projection with security rosettes suitable for double action swing doors with mechanical back check suitable for 12mm thick heat strengthened clear toughened glass with adjustable lock keeper plates in two part, floor sockets over panel strike boxes, to suit corner locks including cost of all materials, labour, machinery, fabrication, chasing in the floor, chipping of walls, beams, columns, rectification of plaster, painting if required erection installation, transportation all charges etc complete as per design and drawing and to the satisfaction of Engineer-incharges. Bottom fitting:1 No. per door leaf-Top fitting:1 No per door leaf, pivot:1 No per door leaf, SS Handles as approved: 1 pair per door leaf, floor spring :1 No. per door leaf, Lock:1 No per door leaf (Rate shall include the cost of 12mm thick heat strengthened clear float glass including crystal clear polishing as per direction of Engineer-in-charge.

18.

WOODEN FLOORING

Providing and fixing of laminated 12mm thick wooden flooring with proper non glue fixing details and proper base and finishing as per manufactures specifications and to the satisfaction of the EIA/Architect as per direction of Engineer-in-charge. Flooring (Make: Unitex, Armstrong or equivalent)

19.

VINYL FLOORING

Providing and fixing of 2mm thick vinyl flooring of approved `make and brand in size 610mm x 610mmm weight 3 kg/m2/(max), tiles should be fire resistance, stain and chemical resistance, thermal resistance, fungi and bacterial resistance, as per confirming to ISO 1466 11999 class 4, etc., Vinyl flooring

Seal & Signature of Contractor

Seal & Signature of NBCC

37tiles shall be fixed over flooring surface in perfect dry condition, clean for any loose dust particles, floor surfaced cleaned with vacuum cleaner. Contractor shall ensure leveling of the sub floor and correct it for ant cracks and crevices before application.

The vinyl flooring tiles shall be fixed with application of approved glue/adhesive as per manufacturers specifications, with edge cutting and securing the ends near walls under the guidance/supervision and direction by Engineer-in-charge.

20.

GRID CEILING

Providing and fixing Grid ceiling of 600 x 600 mm size and 12 mm thickness comprising composite structural fiberglass core with non-woven mineral coated surface wrapped on two opposite edges and matching integral hinged support clip on other two edges and shall be downward accessible by disengaging hinge support rail on one side of panel from the TBar Flange or optional A-Mount rail flange without the use of tools. Pan3l shall swing hinge downward to provide complete access without removal of the panel from the ceiling or equivalent complete as per direction of engineer-in-charge. (Make: Almax, Armstrong or equivalent).

21.

WOODEN FALSE CEILING

Providing and fixing of wooden false ceiling with 12mm commercial ply and 4mm decorative veneer finish as per approved make, colour and texture with melamine polish as per design and specification of the EIA/Architect. Frame Work: Providing and fixing frame work of suspended wooden ceiling with perimeter/main runner and cross runner with 600 c/c both sides with hard wood battens 50 x 25 mm fixed to RCC surface i.e. ceiling with 10mm dia GI hangers fixed in brass dash

Seal & Signature of Contractor

Seal & Signature of NBCC

38fastener 12.5 x 40 mm etc. all complete with necessary drilling of holes, including fire retardant paint, primary coat complete, including making arrangement of fixing light, fixture grill and diffusers in the frame work complete work or equivalent as per direction of Engineer-in-charge.

22.

FIRE CHECK DOORS

Supply and fixing of 46mm thick steel fire check door of 120 minutes fire rating fabricated with 1.2mm thick galvanized sheet with infill of fire rated Acrylic Sealant and non-combustible core bonded to both faces of sheet with lock seam joints at stile edges and internal reinforcement at top, bottom and stile edges for tire rating. The doorframes are manufactured from 1.6mm thick galvanized steel sheet pressed from to double rebate profile of size 143mm x 57mm. The door frames and door shutters are finished with zinc chromate primer in accordance with BS 476 Part 22 and IS 3614 Part II for 2 Hrs. rating complete including all fitting, door closer and Panic bar complete as per direction of Engineer-in-charge.

Seal & Signature of Contractor

Seal & Signature of NBCC

3923. SPECIAL EFFECT FILM ON GLASS

Providing and fixing 3M Scotch cal special effect film on glass with sparkling effect with printing as per the graphic design and architects approval. A transparent liner prevents moisture absorption and lays flat for easier assembly of multi colour special effect graphics, from dusted and frosted crystal to fluorescent. This film is applied to flat, clear surfaces. Vertical exposure face of graphic is +/- 10 degrees from vertical 3 years MCS warranty from 3M India Ltd., & complete as per direction of Engineer-in-charge.

24.

SENSOR OPERATED AUTOMATIC DOORS

Single leaf Telescopic Sliding door of size 4200mm (W) x 2744mm (H) made from 6mm toughened glass encased in heavy duty aluminum door section duly powder coated or colour anodized consisting of 2 movable sliding leaves of sizes 1500 mm (W) x 2744mm (H) each & 1 fixed leaf of size 1200mm (W) 2744mm (H) as per drawings including Electromechanical lock with manual release, digital programmer switch, back up battery, DMCS software with all features complete as per direction of Engineer-in-charge.

Seal & Signature of Contractor

Seal & Signature of NBCC

40

SPECIFICATIONS FOR PLUMBING WORKS

Seal & Signature of Contractor

Seal & Signature of NBCC

411. SCOPE OF WORK

Following is the detail of scope of work included in this Tender:

a)

Installation of Pumps in the UG Tank complete as required starting from suction line from underground tank to O H Tank/distribution Ring Main Ball Valves, N R V Elect. Panel and Wiring for Motor Necessary foundation work for Pumps, Supports for Piping Bends, Tees Dead ends, Tail pcs. Valves, Vessel etc. as required.

b)

Laying of Soil, Waste, Rain water & Water Supply Lines should be as approved make and quality.

c)

Supports for vertical risers/vertical pipes. required.

Painting etc.,

as

d)

Pump & equipments, accessories and fitting as required.

e)

Installation, testing and commissioning of the entire installations to the satisfactions of employer, Consultant and Architects.

f)

Manual operated Electrical Driven System.

g)

Maintaining the installation minimum for a period of 12 month from the date of commissioning and imparting training to the workers/staff as asked for maintaining the installations as per IS Requirement and exercising.

Seal & Signature of Contractor

Seal & Signature of NBCC

42h) Earth pits and earth strip for earthling the body of the motors is being provided by the Electrical Contractor.

2.

SCHEME: The complete Building is being provided with following arrangements.

a)

Underground tank of capacity of adequate capacity with all arrangement.

the

b)

Manual operat3ed as well as automatic operated pump.

c)

Raw Water Lifting System.

3.

INSTALLATION SCHEMATIC The installation shall confirm to the schematic line diagram attached in the shape of drawings for pump house. Vertical riser/D Comer and Pipe layout drawing for building attached along with Tender Papers.

Since the Agency executing the job is responsible for obtaining the NOC from the Local Authorities, deviation, if any, with respect to the scheme and drawing attached may be brought out clearly in the Tender Paper while quoting for the job.

4.

SPECIFICATIONS

4.1.1 Work under Plumbing Services installation shall be carried out strictly in accordance with specifications attached with the tender.

Seal & Signature of Contractor

Seal & Signature of NBCC

434.1.2 Items not covered under these specification due to any ambiguity or misprints, or additional works, the work shall be carried out as per specifications or the latest NBCC Manual up to date amendments as applicable in the work.

5.

EXECUTION OF WORK

5.1.1 The Contractor should visit and examine the site of work and satisfy himself as to the nature of the existing roads and other means of communication and other details pertaining to the work and local conditions and facilities for obtaining his own information on all matters affecting the execution of work. No extra charge made in consequence of any misunderstanding, incorrect information on any of these points or on ground of insufficient description will be allowed. 5.1.2 The work shall be carried out in conformity with the plumbing drawings and within the requirements of Architectural, HVAC, Electrical, Structural and other specialized Services drawings. 5.1.3 The Contractor shall cooperate with all trades and agencies working on the site. He shall make provision for hanger/support, sleeves, structural openings and other requirements well in advance to prevent hold up of progress of the construction schedule. 5.1.4 On award of the work, Contractor shall submit a schedule of construction in the from of a PERT chart or BAR chart for approval of the Employer/ Architect/ Consultant. All dates and time schedule agreed upon should be strictly adhered to, within the stipulated time of completion/commissioning along with the specified phasing, if any. 6.

DRAWINGS

6.1.1 Drawings are diagrammatic but shall be followed as closely as actual construction permits. Any deviations made shall be in conformity with the Architectural and other services drawings and subject to the consent of consultant/employer.

Seal & Signature of Contractor

Seal & Signature of NBCC

446.1.2 Architectural drawings shall take precedence over Plumbing drawing or other services drawings as to all dimensions.

6.1.3 Contractor shall verify all dimensions at site and bring to the notice of the Site Engineer/Consultant all discrepancies or deviations noticed. Decision of the site Engineer/Consultant/Employer shall be final.

6.1.4. Large size details and manufacturers dimensions for materials to be incorporated shall take precedence over small-scale drawings.

6.1.5 Any drawings issued by the Architects/Consultant for the work are the property of the Architects/Consultant and shall not be lent, reproduced or used on any works other intended without the written permission of the Architects/Consultant.

7.

INSPECTION AND TESTING OF MATERIALS

Contractor shall be required to produce if required manufacturers test certificate for the particular materials supplied by him. The tests carried out shall be as per the relevant Indian Standards.

8.

METRIC CONVERSION

8.1.1 All dimensions and sizes of materials and equipment given in the tender document are commercial metric sizes.

8.1.2 Any weights, or sizes given in the tender having changed due to metric conversion, the nearest equivalent sizes accepted by Indian Standards shall be acceptable without any additional cost.

Seal & Signature of Contractor

Seal & Signature of NBCC

459. Reference Drawing

9.1.1 Contractor shall maintain one set of all drawings issued to him as reference drawings. These shall not be used on site. All important drawings shall be mounted on boards and placed in racks indexed. No drawings shall be rolled.

9.1.2 All corrections, deviations and change made on the site shall be shown on these reference drawings for final incorporation in the completion drawings. All changes to be made shall be initialed by the Consultant or Architects.

10.

Shop Drawings

Shop drawings shall be submitted under following conditions:

a) b) c)

Showing any changes in layout in the Plumbing drawings. Equipment layout, piping and wiring diagram. Manufacturer or Contractors fabrication drawings for any materials or equipment supplied by him.

11.

Completion drawings

11.1

On completion of work, contractor shall submit one complete set of original tracings and two prints of as built drawings to the Project Manager. These drawings shall have the following information. a) Run of all piping, diameters on all floors, vertical stacks and location of external services.

Seal & Signature of Contractor

Seal & Signature of NBCC

46b) Run of all Plumbing lines with diameters, locations of control valves, access panels. Locations of all mechanical equipment with layout and piping connections.

c)

11.2 Contractor shall provide one sets of catalogues, service manuals if required manufactures performance data and list of spare parts together with the name and address of the manufacture for all electrical and mechanical equipment provided by him.

11.2

All warranty cards given by the manufacturers shall be handed over to the Employer.

12

Contractors rates

1.1.1

Rates quoted in this tender shall be inclusive of cost of materials, labour, supervision, erection, tools, plant, scaffolding, service connections, transport to site, octroi and levies, breakage, wastage and all such expenses as may be necessary and required to completely do all the items of work and put them in a working condition. Rates quoted are for all heights and depths and in all positions as may be required for this work. All rates quoted are inclusive or cutting holes and chases in walls and floors and making good the same with cement mortar/concrete/water proofing of appropriate mix and strength as directed by Project Manager. Contractor shall provide holes, sleeves, recesses in the concrete and masonry work as the work proceeds. The Contractor shall furnish the vouchers and test certificates to prove that the materials are as specified and to indicate that the rates at which the materials are purchased in order to workout the rate analysis of non tendered items which he may be called upon to carryout.

1.1.2

1.1.3

1.1.4

Seal & Signature of Contractor

Seal & Signature of NBCC

47

13.

Testing

13.1.1

Piping and drainage works shall be tested as specified under the relevant clauses of the specifications. Tests shall be performed in presence of the Site Engineer/ Consultant. All materials and equipment found defective shall be replaced and whole work tested to meet the requirements of the specifications. Contractor shall perform all such tests as may be necessary and required by the local authorities to meet municipal or other bye laws in force. Contractor shall provide all labour, equipment and materials for the performance of the test.

13.1.2

13.1.3

13.1.4

13.1.5

14.

Site clearance and cleanup

14.1.1

The contractor shall, from time to time, clear away all debris and excess materials accumulated at the site. After the fixtures, equipment and appliances have been installed and commissioned, contractor shall clean-up the same and remove all plaster, paints, stains, stickers and other foreign matter or discoloration leaving the same in a ready to use condition. On completion of all works, contractor shall demolish all stores, remove all surplus materials and leave the site in a broom clean condition, failing which the same shall be done at Contractors risk and cost.

14.1.2

14.1.3

Seal & Signature of Contractor

Seal & Signature of NBCC

4815. Recovery of cost for materials issued to Contractors free of cost.

15.1.1

If any materials issued to the Contractor, free of cost, are damaged or pilfered, the cost of the same shall be recovered from the contractor on the basis or actual cost to owner which shall include all freight and transportation, excise duty, sales tax, Octroi, import duty etc, plus 10%. The decision on the actual cost given by the Employer shall be final and binding on the Contractor.

16.

Cutting of water proofing membrane No walls terraces shall be cut for making and opening after waterproofing has been done without approval of Site Engineer/ Architects. Cutting of water proofing membrane shall be done very carefully so as other portion of water proofing is not damaged. On completion of work at such place the water proofing membrane shall made good and ensured that the opening/ cutting is made fully water proof as per specifications and details of water proofing approved by Architects. Cutting of Structural members No structural member shall be chased or cut without the permission of the Project Manager. Materials supplied by employer The Contractor shall verify that all materials supplied by the Employer conform to the specifications of the relevant item in the tender. Any discrepancy found shall be brought to the notice of the Site Engineer.

16.1.1

17. 17.1 18 18. 18.1 18.2

19. 19.1

Materials Unless otherwise specified and expressly approved in writing by the Employer, only materials of makes and specification as mentioned in the list of approved makes attached with the specifications shall be used.

*********************

Seal & Signature of Contractor

Seal & Signature of NBCC

49TECHNICAL SPECIFICATIONS FOR PLUMBING WORKS

1.

Pipes

i)

All pipes within and outside the building in exposed location and shafts including connections buried under floor shall be APPROVED MAKE OF Pipes & fittings.

2.

Pipe Fittings

a)

Pipe fitting means tees, elbows, couplings, Unions, reducers etc. and all such connecting devices that are need to complete the piping work in its totality.

b)

Screwed fitting shall be approved type malleable with reinforced ring on all edges of the fitting suitable for screwed joints.

3.

Pipe Jointing:

3.1

Flanged Flanged joints shall be provided on:

Straight runs not exceeding 25-30 m on pipelines of 65mm dia and above and as directed by Project Manager.

For jointing all types of valves, apparatus pump, connections with other types of pipes, to water tanks and other places necessary and required as good for engineering practice.

Seal & Signature of Contractor

Seal & Signature of NBCC

50Flanged shall be as per Table E of IS specification with appropriate number of S.S. nuts and bolts, 3mm neoprene gasket complete as per relevant specifications.

3.2

Unions

Provide approved type of unions on pipelines 50mm dia and below in simila4r places as specified for flanges.

4.

Excavation

4.1

Excavation for pipe lines shall be in open trenches to levels and grades shown on the drawings or as required at site. Pipelines shall be buried with a minimum cover of 1.0 meter or as shown on drawings. Wherever required contractor shall support all trenches or adjoining structures with adequate timber supports. On completion of testing in the presence of the Project Manager and pipe protection, trenches shall be refilled with same excavated earth and consolidated. Contractor shall dispose off all surplus earth within a lead of 50m or as directed by the Project Manager.

4.2

4.3

4.4

5.

Anchor Thrust blocks

a)

Contractor shall provide suitably designed anchor blocks in cement concrete to encounter excess thrust due to water hammer and high pressure.

b)

Thrust blocks shall be provided at all bends, tees and such other location as determined by the Project Manager.

Seal & Signature of Contractor

Seal & Signature of NBCC

51

c)

Exact location, design, size and mix of the concrete blocks shall be as shown on the drawings or as directed by the Project manager prior to execution of work.

6.

Gun Metal Valves Valves of 50mm dia and below shall be heavy duty gunmetal Ball valves conforming to IS 778 class II with female screwed ends.

7.

Cast Iron butterfly Valves.

All valves 65mm dia and above shall be CI butter fly valves of class PN 1.0 conforming to IS 5312 with CI body, but rubber seat and Teflon seal.

8.

Non-return Valve

Non-return valves shall be CI double flanged with CI body and Gun metal internal parts conforming to IS 5312.

9.

Pipe protection

a)

All pipes above ground and in exposed location shall be painted with one coat of red oxide primer and two or more coats of synthetic enamel paint of approved colour.

b)

Where specified, pipes buried in floors or below ground shall be protected against corrosion by the application of PYP COAST as specified in schedule of quantities.

Seal & Signature of Contractor

Seal & Signature of NBCC

52

10.

Pipe Support All pipe clamps and supports shall be mild steel. When fabricated from chilly make G.I. Clamps, G.I. Threaded Rods & Dash Fasteners. Pipes shall be hung by means of expandable anchor fasteners of approved make and design. The hangers and clamps shall be fastened by means of galvanized nuts and bolts. The size/diameter of the anchor fasteners and the clamp shall be suitable to carry the weight of water filled pipe and dead weight normally encountered.

11. 11.1

Measurement All GI/CPVC/UPVC Pipes shall be measured per linear meter of the finished length and shall include all fittings, flanges, welding, jointing, clamps for fixing to walls or hangers, anchor fasteners painting and testing complete in all respect. Butterfly valves, check valves, a are measured by numbers and shall include all items necessary and required for fixing and as given in the specifications and schedule of quantities.

11.2

Seal & Signature of Contractor

Seal & Signature of NBCC

531. SANITARY FIXTURES & FITTINGS

1.1

Vitreous China Sanitary Ware All glazed Vitreous China Sanitary ware fixtures shall confirm to Indian Standard IS: 2556. The details, make and type to be provided are given in the Schedule of Quantities. The Vitreous China Sanitary ware shall be of first quality only. They shall be non-porous and fully vitreous, with all the visible portions perfectly glazed and should be absolutely free from hairline cracks pinholes and local depressions. It shall be perfectly symmetrical, uniform and with smooth curves. All sanitary fixtures and fitting shall be stored under covered roof and handled carefully to prevent any damage.

1.2

Chromium Plated Fittings All Chromium plated fittings shall be of brass/copper, heavy chromium plated, of the make and design approved by the Architects/Consultants. The fitting shall be cast fitting of screw type, machined and threaded properly for fixing to the supply pipes.

The chromium plating shall conform to Indian Standard IS: 482 (Electroplated coating of nickel and chromium of copper and copper alloys).

The fittings shall be supplied complete with chromium plated matching flanges wall cover plates, nuts and extension pieces of required lengths. Metallic washers where required shall also be of chromium plated brass. All bib cocks and stop cocks shall conform to Indian Standard IS: 781. Brass screw down pillar taps to IS: 1701 and all other fitting shall match the supply fitting in construction and appearance. All fixing accessories and screws shall be similar to fitting. All washers shall conform to Indian Standard IS: 4346.

Seal & Signature of Contractor

Seal & Signature of NBCC

54

All waste fitting (Waste, Chain, Overflow, Spreaders Caps etc.) shall be of brass/copper heavy chromium plated of the make and design specified and match the supply fittings. The shall con-form to Indian standard IS:2963.

Bottle traps (for wash basins, sinks, urinals etc) shall be deep seal (Min. 6 cm seal) cast brass bottle traps, heavy chromium plated. All bottle traps shall be provided with suitable cleaning eye, extension piece, flare nuts, all chromium plated.

Chromium plated brass flanges of suitable size shall be provided to screw the holes made for installing the pipes through walls, floors and columns. 2. INSTALLATION OF SANITARY FIXTURES AND FITTINGS

2.1

General Requirement The fixtures and fitting shall be provided with all such accessories as are required to complete the item in satisfactory working conditions, whether specifically mentioned or not in the schedule of quantities, specifications and drawings.

The sanitary fixtures and fittings shall be installed at the correct assigned position as shown on the drawings and as directed by the Owner/Architect/Interior Designer, and shall fully meet with the aesthetic and symmetrical requirements as demanded by the Architect/Interior Designer.

All fixtures and accessories shall be fixed in accordance with a set patter matching the tiles or interior finish as per Owner/Architect/Interior Designer requirements. Wherever necessary, the fitting shall be centered to dimensions and

Seal & Signature of Contractor

Seal & Signature of NBCC

55pattern as called for fixtures and fitting shall be installed by skilled workman with appropriate tools according to the best trade practice. Manufacturers instructions shall be followed for the installation of fixtures. Fixtures in all toilets shall be standard height mounting as specified/shown for on the drawings. Fixtures shall be mounted rigid, plumb, and true to alignment.

2.2

Mock up and Trial Assembly The installation of the sanitary fixtures and fittings shall be as per the shop drawings approved by the Owner/ Architect/ Consultant.

The contractor shall have to assemble for Mock Up atlas one set of each type of sanitary fixtures and fittings in order to determine precisely the required supply and disposal connections. Relevant instructions from manufacturers shall be followed as applicable. This trial assembly shall be developed to facilitate determining the location of puncture holes, holding devices etc., which will be required for final installation in position of all sanitary fixtures and fittings. The above assembly shall be subject to final approval by the Owner/Architect/Interior Designer.

The fixtures in the trial assemble can be reused for final installation without any additional payments for fixing or dismantling of the fixtures.

Seal & Signature of Contractor

Seal & Signature of NBCC

562.3 Supporting and Fixing Devices The contractor shall provide all supporting and fixing devices necessary to install the sanitary fixtures and fittings securely in position. The fixing devices shall be rigidly anchored into the building structure. The devices shall be rust resistant and shall be so fixed that they do not present an unsightly look in the final assembly. Where the location demands, the Owner/Architect/ interior Designer may instruct the contractor to provide chromium plated or other similarly finished fixing devices. In such circumstance the contractor shall arrange to supply the fixing devices and shall be installed complete with appropriate vibration isolating pads, washers and gaskets.

2.4

Final Installation The contractor shall install all sanitary fixtures and fittings in their final position in accordance with approved trial assemblies and as shown on drawings. The installation shall be complete with all supply and waste connections. The connection between building and piping system and the sanitary fixtures shall be through proper unions and flanges to facilitate removal/replacement of sanitary fixtures without disturbing the built in piping system. All unions and flanges shall match in appearance with other exposed fittings.

Fixtures shall be mounted rigid, plumb and to alignment. The outlets of water closet pans and similar appliances shall be examined to ensure that outlet ends are butting on the receiving pipes before making the joints. It shall be ensured that the receiving pipes are clear of obstruction. When fixtures are being mounted, attention shall be paid to the possibility of movement and settlement by other causes.

Seal & Signature of Contractor

Seal & Signature of NBCC

573.0 Protection against Damage

The contractor shall take every precaution to protect all sanitary fixtures against damage, misuse, cracking staining breakage and pilferage by providing proper wrapping and locking arrangement till the completion of the installation. At the time of handing over, the contractor shall clean, disinfect and polish all fixtures and fittings. Any fixtures and fittings found damaged, cracked chipped stained or scratched shall be removed and new fixtures and fittings free from defects shall be installed at his own cost to complete the work.

Seal & Signature of Contractor

Seal & Signature of NBCC

58INTERNAL DAINAGE (SOIL, WASTE, VENT AND RAIN WATER PIPES)

1.

Soil and waste Pipes shall be cast iron pipes and fittings as called for. In general wastes smaller than 65mm dia shall be of heavy class Galvanized MS. All rain water pipes shall be class A uPVC pipes of SWR system.

The soil pipes shall be circular with a minimum diameter of 100mm. Pipes shall be fixed by means of stout cast iron clamps in two sections, bolted together, built into the walls, wedged and neatly jointed as directed and approved by the Owner/Architect/Consultant. All bends, branches, swan neck and other parts shall conform to the requirement and standards as described for the pipes. Pipes shall be rested against the walls on suitable wooden cradles. Local Authority Regulations applicable to the installations shall be strictly followed.

Where indicated, the soil pipes shall be continued up wards without any diminution in its diameter, without any bend or angle to the height shown in the drawings. Joints throughout shall be made with molten lead as described under jointing of cast iron pipes. Soil pipes shall be painted as provided under painting. The soil pipes shall be covered on top with cast iron terminal outlets as directed and approved. All vertical soil pipes shall be firmly fixed to the walls with properly fixed clamps, and shall as for as possible be kept 50mm clear of wall. Waste pipes and fittings shall be of cast iron or galvanized mild steel pipes. Pipes shall be fixed. Jointed and painted as described in installation of soil, Waste and vent pipes.

All the fittings used for connections, between soil, waste and ventilation pipes and branch pipes shall be made by using pipe fittings with inspection doors for cleaning. The doors shall be provided with 3mm thick rubber insertion packing and when closed and bolted shall be air and water tight.

Seal & Signature of Contractor

Seal & Signature of NBCC

59

2.

Soil and waste Pipes shall be u.P.V.C. pipes and fittings as called for. In general wastes smaller than 63mm dia shall be of heavy class 10kg/cm2. All soil, Waste, Vent and rain water pipes shall be class A uPVC pipes of SWR system.

The soil pipes shall be circular with a minimum diameter of 110mm pipes shall be fixed by means of stout u.P.V.C clamps in two sections, bolted together, built into the walls, wedged and neatly jointed as directed and approved by the Owner/Architect/Consultant. All bends, branches, swan neck and other parts shall conform to the requirement and standards as described for the pipes. Pipes shall be rested against the walls on suitable wooden cradles. Local Authority Regulations applicable to the installations shall be strictly followed.

Where indicated, the soil pipes shall be continued up wards without any diminution in it diameter, without and bend or angle to the height shown in the drawings. Joints throughout shall be made with rubber rings described by the manufacturer under jointing of pipes. The soil pipes shall be clamped on top with M.S. iron terminal gaurds as directed and approved. All vertical soil pipes shall be firmly fixed to the walls with properly fixed clamps, and shall as far as possible be kept 50mm clear of wall. Waste pipes and fittings shall be of u.P.V.C. pipes. Pipes shall be fixed. Jointed and fixed as described in installation of soil, Waste and vent pipes.

Every waste pipe shall discharge above the grating of a properly trapped gully. The contractor shall ensure that this requirement is adequately met with . Wherever floor traps are provided, it shall be ensured that at least one wash is connected to such floor traps to avoid drying of water seal in the trap.

All the fittings used for connections, between soil, waste and ventilation pipes and branch pipes shall be made by using pipe

Seal & Signature of Contractor

Seal & Signature of NBCC

60fittings with inspection doors for cleaning. The doors shall be provided with 3mm thick rubber insertion packing and when closed and bolted shall be air and water tight.

3.0

PIPING MATERIALS

3.1

uPVC Pipes and Fittings

The pipes shall be round and shall be supplied in straight lengths with scooted ends. The internal and external surfaces of pipes shall be smooth, clean, free from grooving and other defects. The ends shall be cleanly cut and square with the axis of the pipe. The pipes shall be designated by external diameter and shall conform to SWR pipe system.

4.0

INSTALLATION OF SOIL, WASTE, VEN AND RAIN PIPES.

WATER

Soil, waste and vent pipes in shafts, under the floors etc shall consist of u.P.V.C. pipes as described earlier. Waste pipes from bottle trap to floor/urinal traps for wash basin, urinal and sink shall be of heavy class u.P.V.C. pipes and fittings. All horizontal pipes running below the slab and along the ceiling shall be fixed on structural adjustable clamps, sturdy hangers of the design as called for in the drawings. The pipes shall be laid in uniform slope and proper levels. All vertical pipes shall be truly vertical fixed by means of stout clamps in two sections, bolted together, built into the walls, wedged and neatly jointed. The branch pipes shall be connected to the stack at the same angle as that of fittings. All connections between soil waste and ventilating pipes and breach pipes shall be made by using pipe fitting with inspection doors for cleaning. Pipes shall be fixed in a manner as to provide easy accessibility for repair and maintenance and shall not cause obstruction in shafts. Where the horizontal run

Seal & Signature of Contractor

Seal & Signature of NBCC

61of the pipe is long or where the pipes cross over building expansion joints etc.,

suitable allowance shall be provided for any movements in the pipes by means of expansion joints etc., such that any such movement does not damage the installation in any way.

All u.P.V.C. pipes and fitting shall be jointed as per the manufacturers specification.

The jointed portion of the pipe shall be carefully leveled and aligned and the joint shall not be covered till the pipe line has been tested under pressure.

5.

Cutting and Making good:

Pipes shall be fixed and tested as building proceeds. The Contractor shall provide all necessary holes, cutouts and chases in structural members as building work proceeds. Wherever holes are cut or left originally they shall be made good with cement concrete 1:2:4: (1 cement: 2 coarse sand:4 stone aggregate 20mm nominal size) or cement mortar 1:2 coarse sand). Cured and the surface restored to original condition

6.

Painting

All M S Hangers shall be painted as per the shade and colour approved by the Project Manager:

Seal & Signature of Contractor

Seal & Signature of NBCC

627. Testing

7.1.

Before use at site, all u.P.V.C soil pipes soil pipes shall be tested by filling up with water for at least 10 minutes. After filling, pipes shall be inspected for below holes and cracks. All defective pipes shall be rejected and removed from the site within 48 hours.

Pipes shall be tested after installation by filling up the stack with water. All opening and connections shall be suitably plugged. The total head in the stack shall however not 3m exceed.

Alternatively, the Contractor may test all soil and waste stacks by a smoke testing machine. Smoke shall be pumped into the stack after plugging all inlets end connections. The top end shall however be left open. The stack shall then be observed for leakages and all defective pipes and fittings removed or repaired as directed by the Project Manager.

A test register shall be maintained and all entries shall be signed and dated by the Contractor and the Project Manager or his representative.

Seal & Signature of Contractor

Seal & Signature of NBCC

63

8.

WATER SUPPLY

1.0

PIPING SYSTEM

The piping system consists of SDR 11 Grade CPVC pipes and fitting conforming to relevant IS Codes. The sizes and makes is specified in the Schedule of Quantities.

For any internal works if specified in the BOQ the CPV pipes and fitting shall be embedded in the wall chase or run on the floor/ceiling unless otherwise specified. No unsightly exposed runs shall be permitted.

2.

PIPING MATERIAL

2.1

CPVC Pipes

The pipes shall be CPVC pipes and shall be uniform adherent reasonably smooth and free from any imperfections. The pipes and sockets shall be cleanly finished. All screw threads shall be clean and well cut. The ends shall be cut cleanly and square with the axis of the pipe.

The fittings also shall be SDR 11 Grade CPV. The size of pipes and fitting is specified in the schedule of quantities.

2.2

Valves & Controls

Seal & Signature of Contractor

Seal & Signature of NBCC

64All valves (gate, ball, check, safety) shall be of CPVC suitable for the particular service as called for. All valves shall be of the particular duty and design as called for.

3.

LAYING AND JOINTING OF PIPES

All pipes and fittings shall be fixed truly vertical and horizontal unless unavoidable. The pipes shall be fixed to walls with standard slotted angles U shape threaded bolts, nuts for clamping pipes to angles. Slotted angles shall be grouted to R C C work with dash fasteners. These slotted angles shall be spaced at regular intervals in straight lengths and heights at 1.8.M c/c

3.1.

Laying and jointing of pipes

The galvanized pipes and fittings shall run in wall chase or ceiling or as specified. The fixing shall be done by means of standard pattern holder bat clamps keeping he pipes about 1.5cm clears of the wall where to be laid on surface. Where it is specified to conceal the pipes, chasing may be adopted or pipes fixed in the shafts, ducts etc provided there is a sufficient space to work on the pipes with the usual tools. As far as possible, pipes may be buried for short distance provided adequate protection is given against damage and where so required special care to be taken at joints. Where directed by the Construction Manager /Architect, Pipe sleeves shall be fixed at a place the pipe is passing through a wall or floor for reception of the pipe and allow freedom for expansion and contraction and other movements. In case of pipe is embedded in walls or floors it should be of approved quality. Under the floors the pipes shall be laid in layer of sand filling.

CPVC pipes shall be jointed with male and female joints, using Solvent Adhesive, shall be taken to remove any burr from the

Seal & Signature of Contractor

Seal & Signature of NBCC

65end of the pipes jointing compound of proprietary make shall be used, according to the manufactures instructions. Pipes and joints laid for water supply shall be tested to a pressure of 7 kg per Sq. cm.

4.

PIPING MATERIAL

4.1

Galvanized Iron Pipes The pipes shall be galvanized mild steel welded (ERW) or (HFW) screwed and scooted conforming to the requirements of IS: 1239. The Galvanizing shall conform to IS:4736, the zinc coating shall be uniform, adherent reasonable smooth and free from such imperfections as flux ash and drop