september 5, 2014

38
SEPTEMBER 5, 2014 PUBLIC VERSION Maine 2014 Outage Coordination CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

Upload: tanya-finley

Post on 01-Jan-2016

25 views

Category:

Documents


0 download

DESCRIPTION

September 5, 2014. PUBLIC VERSION. Maine 2014 Outage Coordination. CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE. Agenda. Welcome, Introductions and Safety Expectations and Goals for Meeting MPRP Project Update Other CMP/EMERA Maine Projects - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: September 5, 2014

SEPTEMBER 5, 2014

PUBLIC VERSION

Maine 2014 Outage Coordination

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

Page 2: September 5, 2014

Agenda• Welcome, Introductions and Safety

• Expectations and Goals for Meeting

• MPRP Project Update

• Other CMP/EMERA Maine Projects

• Specific Outage Discussion, Key Fall 2014/Spring 2015 outages

• Questions

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 2

Page 3: September 5, 2014

Expectations/Goals

• Communicate significant planned 2014/2015 Maine transmission equipment outages that could impact generation constraints

• Communicate specific outage coordination changes to limit impact on potential generation constraints

• Respond to outage coordination questions from the audience

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 3

Page 4: September 5, 2014

MPRP Project Statistics

• 452 miles of new or rebuilt 345kV and 115kV Transmission• 183 miles of new 345kV Transmission• 105 miles of new 115kV Transmission• 5 miles of Rebuilt 345kV Transmission• 140 miles of rebuilt 115kV Transmission• 8 miles of rebuilt 34.5kV Sub Transmission• 11 miles of 345kV and 115kV line terminations

• 5 new Greenfield Substations• Albion, Coopers, Monmouth, Larrabee, Raven

• 6 Major Substation expansions• Maguire, South Gorham, Surowiec, Gulf Island, Belfast,

Livermore Falls

• 50 Remote end substation expansions or modifications

• 60 - Transmission line crossings

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 4

Page 5: September 5, 2014

Northern Loop Construction

• Construction Status– Belfast 115kV tap completed

• Near term construction activities– Coopers Mills Road Substation energization– Construction of one new 345kV line and one new 115kV line

• Future construction activities– None

5CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

Page 6: September 5, 2014

Central Loop Construction

• Construction Status– Livermore Falls Substation energized– New 115kV line from Rumford to Larrabee Road energized

• Near term construction activities– Construction of one new 345kV line and rebuild of two 345kV lines

• Future construction activities– Completion of 115kV rebuilds– Completion of one new 345kV line and rebuild of two 345kV lines– Completion of Coopers Mills Road tie-ins and energization

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 6

Page 7: September 5, 2014

Southern Loop• Construction Status

– Maguire Road 345kV energization– Construction of new Maguire Road – Eliot 345kV line complete

• Near term construction activities– Eliot Substation final energization– Maguire Road Substation final energization

• Future construction activities– None

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 7

Page 8: September 5, 2014

CMP/EMERA Maine Capital and Maintenance Work

• Other Non-MPRP CMP Capital and Maintenance Work that affects the transmission system– Transmission Line Structure Replacements both Capital and

Maintenance– System Planning related Substation rebuilds or expansions to support

future reliability needs– Substation equipment replacements or upgrades to address

maintenance concerns– Transmission Line re-rates or rebuilds to increase capacity– Substation maintenance equipment inspections and relay testing– Regulatory required relay and equipment trip checks

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 8

Page 9: September 5, 2014

Maine 2014/2015 Transmission Outages

• Changes to plan typically result in increased construction cost– Costs include overtime, additional contractor resources, expedited

material, additional engineering and outage coordination resources, environmental mitigation, schedule and remobilization costs, permitting, etc.

• Outages that have the potential for significant impact to generators in 2014/2015 will be discussed– Long (greater than one week) duration outages – Significant potential generation constraints

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 9

Page 10: September 5, 2014

CMP Outage Applications

• Central Maine Power had 1,400 outage applications in 2013

• There have been 517 transmission (>34.5kV) and 185 sub-transmission (34.5kV) outage applications in 2014

• The MPRP Project has submitted 975 outage applications for the project through March 19, 2014

• The outages range in duration from a few hours to eleven months in length

• The MPRP team anticipates that there will be an additional 300 – 400 outages needed to finish the program

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 10

Page 11: September 5, 2014

TRANSMISSION SYSTEM LIMITATIONSAll facility in and single facility out conditions

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE

Page 12: September 5, 2014

Transmission System Limits Impact On Generation Constraints• Two categories of transmission system interface limits

• Wide Area – 13 Interfaces– Typically Include 345 kV and 115 kV facilities

• New Brunswick to New England Interface• New England to New Brunswick Interface• New England to New Brunswick + Keene Road Export Interface• Orrington South Interface• Orrington North Interface• Orrington Import Interface• Maine Yankee South Interface• Surowiec South Interface• Maine to New Hampshire Interface• New Hampshire to Maine Interface• Seabrook South Interface• Northern New England Scobie & 394 Interface• North to South Interface

– All lines in limits typically range from ~1000 MW to ~4000 MW– Single Line Out Limits typically reduce limits by ~500 MW to ~800 MW

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 12

Page 13: September 5, 2014

Transmission System Limits Impact On Generation Constraints

• Local Area - 7 Interfaces– Typically include 115 kV facilities

• Keene Road Export Interface• Bangor Hydro Export Interface• Keene Road + Bangor Hydro Export Interface• Wyman Hydro Export Interface• Inner Rumford Export Interface• Outer Rumford Export Interface• Western Maine Export Interface

– All lines in limits typically range from ~150 MW to ~500 MW– Single Line Out Limits typically reduce limits by ~50 MW to 100 MW– Most significant recent generations constraints have been from local

area constraints

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 13

Page 14: September 5, 2014

2014 Maine Major Outages - Update

• 115 kV Outage Condition B Western Maine – 3rd Qtr 2013 – 4th Qtr 2013 ~ 3 month duration (Completed)– 2nd Qtr 2014 ~ 2 week duration (Completed)

• 345 kV Outage Condition L Northern Maine Area– 1st and 2nd Qtr 2014 ~ 7 weeks (Completed)

• 115 kV Outage Condition M Western Maine– 2nd Qtr 2014 ~ 1 week (Completed)

• 345 kV and 115 kV Outage Condition N Central Maine– 2nd Qtr 2014 ~ 1 week (Completed)

• 345 kV Outage Condition O Northern Maine– 1st outage 3rd Qtr 2014 ~ 1 week (Completed live line)

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 14

Page 15: September 5, 2014

2013-14 Maine Major Outages – Update (cont.)

• 345 kV Outage Condition O Northern Maine– 2nd outage 3rd Qtr 2014 ~ 2 weeks – 3rd outage 1st Qtr 2015 ~ 1 week

• 345 kV Outage Condition P Southern Maine– 3rd Qtr 2014 ~ 1 week– 4th Qtr 2014 ~2 weeks

• 345 kV Outage Condition Q Southern Maine– 4th Qtr 2014 ~ 4 weeks

15

Page 16: September 5, 2014

2013-14 Maine Major Outages – Update (cont.)

• 345 kV Outage Condition R Southern Maine– 1st Outage 3rd Qtr 2014 ~ 4 weeks– 2nd Outage 4th Qtr 2014 ~ 5 weeks

• 115 kV Outage Condition S Central Maine– 4th Qtr 2014 through 1st Qtr 2015 ~ 2 months

• 345 kV Outage Condition T Central Maine– 1st Qtr 2015 ~ 2 weeks

16

Page 17: September 5, 2014

345 kV Outage Condition O Northern Maine

• Most difficult outage to coordinate in New England– Historically Requires:

• Many contingencies result in controlled islanding of the Maritimes• Must run specific generators• Do not exceed limits on specific generators• Minimum New Brunswick-New England Interface transfers• Maximum Orrington South Interface transfers• Results in almost all generators inside the Bangor Hydro + Keene Road

Export Interface cannot operate• Interface Limits

– New Brunswick-New England Interface MINIMUM 200 MW – 300 MW– Orrington South Interface limit 200 MW – 300 MW

17

Page 18: September 5, 2014

345 kV Outage Condition O Northern Maine (cont.)

• Potential options to be assessed, partial MPRP completions:– Assess if some of the outage can be accomplished live-line – Will assess a completely different approach to the outage to

determine if it is more reliable, increases transfer capabilities, reduces impacts on generators ability to operate• Eliminates 1st contingency controlled islanding of the Maritimes• Reduces must run of specific generators• Reduces do not exceed limits on specific generators• Generators inside the Bangor Hydro + Keene Road Export Interface able to

compete for limited transfer capability

• 1st outage – Originally scheduled for 3rd Qtr 2014 ~ 1 week– Already completed entire outage live line – No impact to generation or interface transfer limit reductions

18

Page 19: September 5, 2014

345 kV Outage Condition O Northern Maine (cont.)

• 2nd outage – Originally scheduled for 4th Qtr 2014 ~ 2 weeks, moved to 3rd Qtr 2014

~2 weeks– Planning to perform the outage with a completely different approach

• Interface Limits– New Brunswick-New England Interface Limits ~250 MW, also slave to

Orrington South Interface Limits – Orrington South Limits ~250 MW - 400 MW – Keene Road Export Interface Limit 155 MW

– Moved to overlap other outages to minimize overall duration of restrictions• 1st Outage P – Surowiec South Limit of 50 MW – 400 MW• 1st Outage R

– Maine-New Hampshire Limit of 1000 MW – 1700 MW– Northern New England Scobie + 394 Interface Limits 1300 MW – 2950 MW

19

Page 20: September 5, 2014

345 kV Outage Condition O Northern Maine (cont.)

• 3rd outage 1st Qtr 2015 ~ 1 week– This outage has been repositioned to occur after additional key MPRP

facilities are completed that will increase limits– Planning to perform the outage with a completely different approach – Interface Limits

• New Brunswick-New England Interface Limits ~ 350 MW, also slave to Orrington South Interface Limits

• Orrington South Limits ~350 MW - 500 MW• Keene Road Export Limit 155 MW

20

Page 21: September 5, 2014

345 kV Outage Condition P Southern Maine

• 1st Outage 3rd Qtr 2014 ~ 1 week– Interface Limits

• Surowiec South Interface Limits 50 MW – 400 MW– Moved to overlap other outages

• Overlap reduces duration of significant interface limits• There is less exposure to southern interface congestion

– 2nd Outage O – Orrington South Limit of ~400 MW– 1st Outage R

» Maine-New Hampshire Limit of 1000 MW – 1700 MW» Northern New England Scobie + 394 Interface Limits 1300 MW – 2950

MW

• 2nd Outage 4th Qtr 2014 ~ 2 weeks– Interface Limits

• Surowiec South Interface Limits 50 MW – 400 MW

21

Page 22: September 5, 2014

345 kV Outage Condition Q Southern Maine

• 4th Qtr 2014 ~ 4 weeks– Interface Limits

• Surowiec South Interface Limits 50 MW – 400 MW– Outage timing has environmental considerations– Moved to overlap other outages

• Overlap reduces duration of significant interface limits• There is less exposure to southern interface congestion

– 2nd Outage R » Maine-New Hampshire Limit of 1000 MW – 1700 MW» Northern New England Scobie + 394 Interface Limits 1300 MW – 2950

MW

22

Page 23: September 5, 2014

345 kV Outage Condition R Southern Maine• 1st Outage 3rd Qtr 2014 ~ 4 weeks, 2nd Outage 4th Qtr 2014 ~ 5

weeks• Original plan for both outages

– Interface Limits» Maine-New Hampshire Interface Limits 200 MW – 300 MW

• Outages moved significantly until key MPRP facilities are completed• Interface Limits

– Maine-New Hampshire Interface Limits 1000 MW – 1700 MW– Northern New England Scobie + 394 Interface Limits 1300 MW – 2950 MW

• Moved to overlap other outages– Overlap reduces duration of significant interface limits– There is less exposure to southern interface congestion – 1st Outage 3rd Qtr 2014

» 2nd Outage O – Orrington South Limit of 400 MW» 1st Outage P – Surowiec South Interface Limits 50 MW – 400 MW

– 2nd Outage 4th Qtr 2014» Outage Q - Surowiec South Interface Limits 50 MW – 400 MW

• Outage duration extended to complete additional maintenance work not related to MPRP

23

Page 24: September 5, 2014

115 kV Outage Condition S Central Maine

• 4th Qtr 2014 through 1st Qtr 2015 ~ 2 months– Original plan

• Interface Limits– Wyman Hydro Export Interface Limits ~50 MW – ~75 MW

• Substantial impact to generators for a long duration

– Current plan• Construction sequencing modified to mitigate this exposure• Interface Limits

– Wyman Hydro Export Interface Limits ~150 MW – ~275 MW– Expecting ~150 MW limit for ~ 2 weeks in 4th Qtr 2014– Expecting close to ~275 MW limit for ~ 6 weeks

24

Page 25: September 5, 2014

345 kV Outage Condition T Central Maine

• 1st Qtr 2015 ~ 2 weeks– Original plan

• Interface Limits– Orrington South Interface limit ~ 500 MW

– This outage has been repositioned to occur • After additional key MPRP facilities are completed that will increase limits• Overlap 3rd Outage O for 1st week

– Overlap reduces duration of significant interface limits– 3rd Outage O limits are more restrictive on the Orrington South Interface ~ 500

MW• Outage T for 2nd week

– Interface Limits» Orrington South Interface limit ~600 MW

25

Page 26: September 5, 2014

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 26

Page 27: September 5, 2014

REFERENCESMPRP Geographic Overview

Significant Maine Interfaces

Page 28: September 5, 2014

MPRP Geographic Overview

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 28

Page 29: September 5, 2014

Wyman Hydro Export Interface

• Wyman Hydro Export– All lines in-service limits do

not currently exist– Single facility out limits exist

• Based upon two 115 kV lines remaining after limiting contingency

– Limits due to stability performance (damping)• 200 MW – 290 MW

– Behind the constraint . . . • ~ 360 MW of generation• ~ 215 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 29

Page 30: September 5, 2014

Inner Rumford Export Interface

• Inner Rumford Export– All lines in-service limits do

not currently exist– Single facility out limits exist

• Limit based upon one 115 kV line remaining after limiting contingency

– Limits due to stability performance (damping, unit stability and post-fault voltage recovery)• 75 MW – 215 MW

– Behind the constraint . . . • ~460 MW of generation• ~ 255 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 30

Page 31: September 5, 2014

Outer Rumford Export Interface

• Outer Rumford Export– All lines in-service limits do

not exist– Single facility out limits exist

• Limit based upon one 115 kV line remaining after limiting contingency

– Limits due to stability performance (damping, unit stability and post-fault voltage recovery)• 75 MW – 215 MW

– Behind the constraint . . . • ~645 MW of generation• ~ 255 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 31

Page 32: September 5, 2014

Western Maine Export Interface

• Western Maine Export– All lines in-service limits do

not exist– Single facility out limits

exist• Limit based upon one 115

kV line remaining after limiting contingency

– Limits due to stability performance (damping)• 300 MW – 500 MW

– Behind the constraint . . . • ~1050 MW of generation• ~ 470 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 32

Page 33: September 5, 2014

Keene Road Export Interface • Keene Road Export

– All lines in-service limit• 175 MW• Based upon one 115 kV

line remaining after limiting contingency

– Limits due to stability (post-fault voltage recovery)

– Facility out limits • 0 MW – 120 MW

– Behind the constraint . . . • ~320 MW of generation• ~ 90 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 33

Page 34: September 5, 2014

Bangor Hydro Export Interface

• Bangor Hydro Export – All lines in-service limits do

not exist– Single facility out limits exist

• Limit based upon two 115 kV lines and one or two 345/115 kV TX remaining after limiting contingency

– Limits due to stability performance (damping, instability)• 200 MW – 440 MW

– Behind the constraint . . . • ~940 MW of generation• ~270 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 34

Page 35: September 5, 2014

Bangor Hydro + Keene Road Export Interface

• Bangor Hydro + Keene Road Export – All lines in-service limits do not

exist– Single facility out limits exist

• Limit based upon two 115 kV lines and one or two 345/115 kV TX remaining after limiting contingency

– Limits due to stability performance (damping, instability)• 200 MW – 580 MW

– Behind the constraint . . . • ~1250 MW of generation• ~ 360 MW more proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 35

Page 36: September 5, 2014

Orrington Import Interface

• Orrington Import– All lines in-service limits do not

exist– Single facility out limits exist

• Limit based upon one 115 kV line remaining after limiting contingency

– Limits due to stability performance (post fault voltage recovery, inter Area instability)• 250 MW – 1250 MW

– Behind the constraint . . . • ~ 320 MW of generation• ~ 1000 MW New Brunswick• ~ 240 MW More proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 36

Page 37: September 5, 2014

Orrington South Interface

• Orrington South– All lines in-service limit is

1050 MW - 1200 MW– Single facility out limits exist

• Numerous combinations– Limits due to thermal,

voltage and stability performance • 200 MW – 1200 MW

– Behind the constraint . . . • ~ 1120 MW of generation• ~ 1000 MW New Brunswick• ~ 510 MW More proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 37

Page 38: September 5, 2014

Surowiec South Interface

• Surowiec South– All lines in-service limit is

1150 MW – Single facility out limits exist

• Numerous combinations– Limits due to stability

performance (damping, unit stability and post-fault voltage recovery) • 300 MW – 1150 MW

– Behind the constraint . . . • ~ 2480 MW of generation• ~ 1000 MW New Brunswick• ~ 1160 MW More proposed

CONTAINS CRITICAL ENERGY INFRASTRUCTURE INFORMATION – DO NOT RELEASE 38