Project Update September 10, 2012

Upload: city-of-pearland

Post on 06-Mar-2016

218 views

Category:

Documents


0 download

DESCRIPTION

monthly update

TRANSCRIPT

Page 1: September 2012 Monthly Reports

Project Update

September 10, 2012

Page 2: September 2012 Monthly Reports

Roadway Projects

Page 3: September 2012 Monthly Reports

• Restriping lanes for ‘Left Only’

• New lane assignment signs

• Re-programming traffic signal

Pearland Pkwy/John Lizer Intersection

Page 4: September 2012 Monthly Reports

• Consultant submitted request for Categorical

Exclusion (CE)

• CE status confirmed by TxDOT Austin

Environmental Division

• Held Public Meeting August 7th and meeting was

well attended

• Staff completed review of 30% plans

Pearland Parkway

Page 5: September 2012 Monthly Reports

• Awaiting FHWA Authorization to Advertise and

bid at this time

• Current updated cost estimate $3.65 million

ITS Project

Page 6: September 2012 Monthly Reports

• Max Road & Fite Road

– SOQs received and under evaluation

TIP Projects Update

Page 7: September 2012 Monthly Reports

• Miller Ranch Road

– Opened on August 8th

• O’Day Road

– Scheduled to be open August 20th

• Old Alvin Road

– Scheduled for end of summer completion

– Behind schedule

TxDOT Off-System Bridge

Replacements

Page 8: September 2012 Monthly Reports

• TxDOT and City completed walk-through on the

signals and punch list was created and returned to

TxDOT

• TxDOT and the contractor are preparing to

schedule installation of the NazTec controllers in

the signals on this project

• CDM Smith will program new controllers at the

Traffic Operations Center for installation in mid

September

• Signals are being integrated into the ITS project

Cullen Parkway – Phase I

Page 9: September 2012 Monthly Reports

• Paving of two lanes is now complete from the tie-

in north of McHard Road to the Beltway except

one section at the north end

• Final pavement section will be poured the week of

August 27th

• All intersections on the west side are now in

• Bridge deck, rail and approaches are now

completed on west side of project

• Grading of right-of-way is now largely complete

on west side, sidewalks and sound walls complete

Cullen Parkway – Phase II

Page 10: September 2012 Monthly Reports
Page 11: September 2012 Monthly Reports

Phase I Streetlights– McDonald/Willits to Clear Creek

• Completed construction

• Completed Substantial Completion and CenterPoint inspection

• CenterPoint initiated the install of street light poles

Dixie Farm Road

Page 12: September 2012 Monthly Reports
Page 13: September 2012 Monthly Reports

Phase II – Mary’s Creek Bypass to SH35

• No evident work on punch list – paver band repair grading for drainage near Cowart’s Creek

Dixie Farm Road

Page 14: September 2012 Monthly Reports

• Water barriers and barrels at the intersection were removed

• Medians mowed per one year scheduled maintenance requirement

• Met with Contractor to discuss intersection completion, including installation of stop bar

• Water and irrigation meters transferred out of contractor account to City’s

• Parks Department walk through with subcontractor before assuming maintenance responsibility

Walnut Reconstruction

Page 15: September 2012 Monthly Reports

• The City and Contractor agreed on a resolution on

all outstanding issues

• Contractor performing corrective work and should

be complete in two weeks, weather permitting

• Contractor agreed to extend pipe for 10 driveways to

prevent soil erosion under pavement and to regrade

swales and roadside ditches to attain positive

drainage

Orange Street

Page 16: September 2012 Monthly Reports

• Coordinated with private utilities; CPE Gas initiated

relocation of 6” gas main; AT&T and Comcast have

not started yet

• Coordination meeting with County, CR59 Engineer,

Business Center Dr. CM/CI consultant and Design

Engineer

• Obtained TxDOT permit

• 100% plans and specs revised, approved and signed

• Initiated advertisement for bids

Business Center Drive

Page 17: September 2012 Monthly Reports

• Broadway/Main Street intersections replacement continues – Final segment of the Broadway/Main Street intersection

should be completed in mid September

• Paving work – Work will now begin to focus on the area north of FM 518

and south of Orange Street – The intersection was poured back Saturday, August 25th

and opened for school traffic early Monday morning – E. Plum intersection will be closed end of September for

reconstruction, requiring approximately 10 days to complete

• Bridge work continuing • Drainage

– Contractor preparing to begin work on the storm trunk lines along the east side of the project

SH35 – BW8 to FM518

Page 18: September 2012 Monthly Reports
Page 19: September 2012 Monthly Reports

• Consultant submittal received a “No Objections” from BNSF

• Plans are being finalized for submittal to TxDOT

• Staff plan to coordinate with BNSF lane reconstruction, BNSF repairs, and replacement of a portion of equipment at the crossing with the railroad’s track maintenance supervisor

Quiet Zone Railroad Crossing

Page 20: September 2012 Monthly Reports

• Paving completed today

• Striping will take 3-4 additional days

CR403 Rehab

Page 21: September 2012 Monthly Reports

Drainage Projects

Page 22: September 2012 Monthly Reports

Diversion Ditch

• DD4 has continued excavation of the diversion ditch west of CR 143 as weather permits

• Excavation has reached CR 100

Pump Station

• Concrete Poured for 1st layer of wet-well wall and removed forms

Re-grading of Roadside Ditches

• Consultant continued working to resolve utility conflicts on Wayne Dr. and depth of cover issues on Holland

Cowart Creek Diversion

Page 23: September 2012 Monthly Reports
Page 24: September 2012 Monthly Reports

• Reviewed and approved the design contract from GC

• Received 30% design plans for review

Westchester Sidewalk and Drainage

Page 25: September 2012 Monthly Reports

Facility Projects

Page 26: September 2012 Monthly Reports

• Review proposal and contract from Wilson Architectural Group for execution

• Design schedule for 60 days

• Schedule pre-development meeting for early September

Westside Library

Page 27: September 2012 Monthly Reports

• Submitted additional lavatory water temperature information today

PSB LEED Certification

Page 28: September 2012 Monthly Reports

Parks

Page 29: September 2012 Monthly Reports

• Prepared Construction and Construction Materials

Testing contracts for Council consideration and

approval

• Negotiated cost savings and completed (deductive)

Change Order No. 1

• Engineer/Architect submitted 60% plans for sports

complex

Sports Complex at Max Road

Page 30: September 2012 Monthly Reports

• Staff completed review of 60% plans

Dolores Fenwick Nature Center Phase II

Page 31: September 2012 Monthly Reports

• Project signs and silt fencing complete for both

parks

• Southgate layout approved

• Concrete and steel submittal approved

South Gate & Cypress Village Parks

Page 32: September 2012 Monthly Reports

• Completed review of Design Scope of Services

• Architectural portion of the design services

proposal are being negotiated to bring costs in line

with traditional services and fees

• Lead Consultant to determine if the full

architectural needs and requirements are being met

by the proposed scope

Shadow Creek Ranch Park

Page 33: September 2012 Monthly Reports

Utility Projects

Page 34: September 2012 Monthly Reports

City of Houston Interconnect

Alice Street Water Plant

• Several punch list items completed

• New chemical pumps installed

• Replacement flow meters installed

Page 35: September 2012 Monthly Reports

• Sand filter demolition complete

• Both filters (now chlorine contact basins) in

operation

Longwood WWTP Rehabilitation

Page 36: September 2012 Monthly Reports

• Construction trailer anchored with temporary utilities

• Demolition of thickener 100% complete. Grit removal complete

• Progress meeting held August 23rd

• Contractor on schedule with equipment submittals and major equipment buy out

• Bar screen and compactor scheduled for a.m. delivery on August 31st

Barry Rose WWTP Rehabilitation

Page 37: September 2012 Monthly Reports
Page 38: September 2012 Monthly Reports

• Engineer revising plans per staff comments

• Forester under contract for tree evaluation and

protection plans

• Complete tree evaluation and finalize alternative

to Woody Road alignment

Hatfield Basin Trunk Sewer

Page 39: September 2012 Monthly Reports

• Attended monthly progress meeting

• Contractor has completed approximately

60% of the lift station construction

• CenterPoint Energy has set the poles, hung

the transformers, and pulled the wires

Twin Creek Regional Lift Station

Page 40: September 2012 Monthly Reports
Page 41: September 2012 Monthly Reports

Far Northwest Wastewater Treatment

Plant Improvements

• Engineer submitted revised final PER

• Engineer submitted 60% plans for staff review

Page 42: September 2012 Monthly Reports

Old Alvin 20” Waterline

• Attended monthly progress meeting

• Continued working with the Acquisitions Manager

to acquire ROE and/or easements

• Assistant City Engineer reviewed and provided

additional comments on the 90% plan submittal

• Returned 90% plans with comments to consultant

Page 43: September 2012 Monthly Reports

BellaVita Waterline Interconnect

• Harris County approved plans

• Project advertised for bid on August 29th

• In discussions with Harris County Flood control

regarding value of easement acquisition for Harris

Co. Flood Control property

Page 44: September 2012 Monthly Reports

SH35 South Water Line

• Tie in complete with no issues

• Abandoned 8” waterline and filled with flowable

fill

• August 28th substantial completion walk through

Page 45: September 2012 Monthly Reports

• Attended monthly progress meeting

• Surveyor investigating depths of pipelines that are in conflict

• 20 Right of Entries not granted and Engineer reviewing locations to determine if geotechnical testing can work around them

• Hydraulic analysis complete and indicates the road will need to be raised approximately 3 feet above natural ground which would affect ROW width

• Engineer reviewing analysis to see if road can be lower to avoid cost of fill and ROW

McHard Road 16” Water Line &

Roadway PER

Page 46: September 2012 Monthly Reports

Project Update

Questions/Comments

September 10, 2012