SAP PS FAQ with Answers @@ How I can control the System Status across user profiles? @@ Can anyone tell me how to revoke a system released status to system partially released status for Proj definitions? $$ Unlike the CO module, there is no transaction to revoke the status of "released" in PS. You will have to talk to SAP about getting a program built to do that as you are talking about changing native SAP source code... I have a problem when trying to settle one of WBS with message Sender: WBS OO/03-1870 Duyong Virtual Pipeline Manager E No source assignment found for cost element 990232 ********** If you want to settle any amount in a WBS (a sender), the cost element needs to be included in your Source Assignment configuration in the IMG under "Settlement" via Project Systems. Also you have to have your allocation structure set up. Both these must include cost element 990232, either within a range or within a Cost element group.

Upload: prasad-punupu

Post on 04-Dec-2015

344 views

Category:

Documents


38 download

DESCRIPTION

PS

TRANSCRIPT

Page 1: SAP PS FAQ With Answers

SAP PS FAQ with Answers

@@ How I can control the System Status across user profiles?

@@ Can anyone tell me how to revoke a system released status to system partially released status for Proj definitions?

$$ Unlike the CO module, there is no transaction to revoke the status of "released" in PS. You will have to talk to SAP about getting a program built to do that as you are talking about changing native SAP source code...

I have a problem when trying to settle one of WBS with message

Sender: WBS OO/03-1870 Duyong Virtual Pipeline Manager

E No source assignment found for cost element 990232

********** If you want to settle any amount in a WBS (a sender), the cost element needs to be included in your Source Assignment configuration in the IMG under "Settlement" via Project Systems. Also you have to have your allocation structure set up. Both these must include cost element 990232, either within a range or within a Cost element group.

If you have cost element groups already assigned in these two structures, then you only need to use Tx. KAH2 to update the relevant cost element group with this cost element (990232).

$$

Page 2: SAP PS FAQ With Answers

Can u help me in the settlement of Project System? Actually we are facing problem in the settlement of those WBS against which down payment, clearing documents have been posted. When we run CJ88 system is showing error “Complete Allocation Structure". However it is working for WBS for which there is no down payment posted.

SERVICE CONDITION IN NETWORK ACTIVITY

@@ We have inconsistency result for service condition in Network Activity. Example case like this:

We maintain Service Condition for level Service X with price 100 USD, for level Plant 0010 Vendor 20160 with price 200 USD and for Vendor 20160 with price 300 USD. During assign Service in the activity, we put vendor 20160 and get the price always coming from Service Condition for Service (100 USD), not service condition for Vendor with appropriate plant . I really appreciate someone who gives advice to solve this problem.

________________________________________________________________

CJI4 & CJI3

We utilize CJI3 to obtain actual data pertaining to costs in PS. I would like to view the plan via CJI4, however I am unable to retrieve the plan data in this transaction.

I have been unable to find the correct settings to allow plan to show.

I am missing the boat on this one.

What do I need to activate in order to see plan via CJI4

***** Do you have a detailed plan? I have never really used CJI4, but in my brief testing, I believe that one must have a detailed cost plan (i.e. primary cost planned by cost element and by period) in order for this to work.

Page 3: SAP PS FAQ With Answers

***** Does your site have SAP-IM, Investment Module? It works well with PS from a planning perspective.

PM - INTEGRATION

What I need is TX, Menu path and settings required for integration issue to

following integration issues:

1: PM with MM

- Stocking Spare parts

- Procurement of direct material

- Procurement of external services

2: PM with PP

- Availability with Machine work centers

- Production resources / tools

3: PM with Cost Accounting:

- Maintenance Cost

- Internal Activity Allocation

- Order Settlement

4: PM with Project System:

- Availability of Funds

- Maintenance Budget

5: PM with FI

Page 4: SAP PS FAQ With Answers

- G/L standard chart of Account

- Invoice Receipt

6: Asset Accounting:

- Tangible Assets

- Acquisition Value

- Residual book value

7: Personnel:

- Work Time Entry

8: Sales and Distribution:

- Maintenance of External devices

9: Quality Assurance:

- Maintenance of test Equipment

Hope I will get a reasonable support after this tabulation

BUDGET CHECKING

I'm working in 4.6 version

My client using PS module for maintain project which one of the activity consist of component to be generate become reservation. We also using Investment Management for budgeting. The question is How to make system do budget checking when the user generate reservation?

Cause current condition, the system only do budget checking if I generate the component become requisition. For reservation even the budget is

Page 5: SAP PS FAQ With Answers

not enough the reservation can be created.

_________________________________________________________________

CREATE DATE OF RESERVATION FROM PS

I try to find the creation date of a reservation that coming from Project System , but I can't find where it is.

Really appreciate If anybody tell me where and what table that save it .

****** I am not exactly sure about this, but you may have to make sure that "Change Document" is active for material components. Go to OPUV for change of the network type. The date may not be recorded unless change document is active. After that finding the table might be fairly easy.

CN33 PDM-PS INTERFACE RUNNING WITH CHANGE NUMBER

We currently run CN33 on projects individually in foreground. We wish to

implement running CN33 using the change number functionality within CN33.

Parameters for the change number are as follows:

Notification is created and then a Change master is created. Dates used on

change master is header data. We then change our WBS BOM with the change

master created earlier.

We run CN33 with the change master in the appropriate change area in the

interface. What I expect is that the parts assigned to the change master

will be evaluated to relevance of the change in comparison to the BOM and

current reservations. However, what the program does is deletes all

components off of the network, only remaining parts are the ones relating

to the change master. I would have expected that the program would leave

the existing components on the network and only select those items under

Page 6: SAP PS FAQ With Answers

the change number to be altered.

Has anyone implemented the CN33 functionality using the change number

functionality?

Is there / are there additional configuration needed to make this

functionality work as I have outlined??

CJ40 & CJR2 - COST PLANNING

Can anybody tell me when should we use Tx Code CJR2 and Tx CJ40 for planning of Primary costs and Activity (planned activity type in cost center)

****** CJR2 is for entering planned values degregated into several cost

elements, so you can get richer results when comparing plan/actual reports, where you can see deviations by cost element. In cj40 you just plan a total value, with no cost element specification.

****** Thanks for ur reply. Even primary cost - against primary cost elements and activity costs - against activity types can be done through CJ40. Even we can do unit costing from CJ40.

I wanted to know when should v use CJR2. How it is differing form CJ40.

******* Manually posting for activity costs - against activity types can be done

through CJ40, but when input via BDC or LSMW, tcode I get some difficulties when trying with tcode CJ40 but not CJR2.

Result will be same.

Page 7: SAP PS FAQ With Answers

CREATE PROJECT WITH MATERIAL

Does anyone know how to create the Project with Material assigned to it? I know it is CJ20N but is there a pre-requisite?

What I want to do now is to create the Reservation with mvt type 281 in MB21 but this is not allowed. Someone say this is controlled in PS, it is?

****** U can create project in CJ20N by copying std template or copying operative project.

Select activities and assign material component, maintain item category "L"-STOCKABLE u will get reservation.

______________________________________________________________

FIXED ASSET

Can anybody tell me how to creating fixed-asset after full settlement a

WBS automatically ?

As I understand fixed asset created manually after a project status TECO

or close.

****** Presently I am working on such thing which is your need.But to explain you, I would like to know first how AUC & settlement on AUC is being handled at your end ?

SKF GROUP IN PLANNING PROFILE

Can anybody tell me significance of SKF Groups in Planning profile. How cost planning is done against statistical key figures ?

Page 8: SAP PS FAQ With Answers

As I understand SKFs are used in Progress Measurement in PS.

REPORT GENERATORS

I am currently using the MM module in SAP and we are 4.6C we have certain

staff who are with IT programming back ground (with certified SQL,PL SQL,

etc..) and like to generate certain specific reports for our module and we

requested our IT application and support division to provide access to

SQVI,SE16,SE38 or similar transaction to create our own MM customized

report.

The application people said that these reports could not be given to

Functional user as they may access other tables. Is there a way to block

tables at the profile level(Functional level) when using any of the report

generator?

******* Tables normally have an authorization group attached to them, a security role can be created that allows access to certain authorization groups only (authorization object S_TABU_DIS).

I agree with your IT support team that users should not have access to SE16 and SE38 in a production environment, and that reports (even utilizing SQVI) should be written in a development client first, tested and then moved into the production environment (the normal change control process

PROJECT PAYMENTS

We are currently using the project systems module to handle customer projects. We are in 46C. When we create a customer invoice we also enter the WBS element that the revenue will be assigned to.

Page 9: SAP PS FAQ With Answers

The problem is when we get the payment. We want to identify how much money we have received for every project. When we post the payment there is no revenue/cost account involved.

Do you know a way to either transfer money to the projects or identifying the project whenever we post a customer payment?

_____________________________________________________________________

MULTIPLE SALES ORDERS ASSIGNED TO ONE PROJECT

Is it possible to assign 2 or more sales orders (VA01) to one project. Currently, we are utilizing templates to create the project structure automatically during the creating of the sales order (in 4.6C). I am attempting to have the system associate 2 orders to one project AND allow consolidation invoicing to produce 1 invoice for both orders.

Any ideas or existing documentation on this?

******** As far as I know this is not possible. I would say you first have to create the project and then assign the sales order to it at WBS level.

******* You can attach WBS(s) of a project to more than one sales order. This is

how we are using it.

******* Could you please provide the method you are using to assign multiple sales orders to one project? Are you utilizing networks? Are you creating a separate WBS element within the project for each sales order?

******* Yes we do create separate WBS within project for each Sales Order.

Page 10: SAP PS FAQ With Answers

PROJECT SYSTEMS - DIP SUMMARIZATION

I have got a problem with the DIP material summarization in projects. I have created a usage for Quotation and Sales Pricing. I am using materials characteristics and the settings in the IMG is

Char Relevant - On;

Mat Determination - On;

No Summarization - OFF;

Structuring - OFF.

Using the Planned Costs (Totals) as the Source, my material determination criteria has

three elements - two different revenue streams (labour) and materials as the

last entry.

My material settings are –

Mat Direct - On ;Individual - Off ;Use Quantity - Off ; Conversion Qty - Off.

My material settings has a set (ZSET_CS_MATERIALS) with a range *(asterisk) to zzzzzzzzzzzzz. During the DP81 transaction no errors are recorded but when the simulate quotation is processed then summarization of the various labour elements is accurate and

complete but the material transfers each item individually. I need to have the quoted value summarized on a single line within the quotation/sales order. I have a material created in MM as the revenue stream for the Material BOM and this is linked to a WBSE as an account assignment in the Sales inquiry - VA11.

Page 11: SAP PS FAQ With Answers

Please help as I have tried OSS and other local colleagues to no avail!

AVAILABILITY CONTROL

I was hoping someone could help me with a problem I'm having. Our project structure is set up as follows:

WBS Level 1 - Installation Project

WBS Level 2 - Task 1

WBS Level 2 - Task 2

WBS Level 2 - Task 3

WBS Level 2 - Task 4

WBS Level 2 - Task 5

WBS Level 2 - Task 6

WBS Level 2 - Task 7

WBS Level 2 - Billing

Currently, the billing element is on the last WBS. This is a stand alone WBS with no activities or networks under it. All the other WBS's have activities and networks under them.

My question is this - All the revenue and material cost hit the Billing WBS.

Can we exclude that from budget availability control? We are trying to control the mount of TIME that is being charged to the various activities. Costs of materials are what they are, and are not controlled by the program managers that manage this project. So, we would like to add up all the cost from all of the WBS elements EXCEPT the billing WBS, and then compare that # to the budget for availability control purposes.

_____________________________________________________________________

Page 12: SAP PS FAQ With Answers

UNABLE TO SETTLE ASSET THRU CJ88

We are on 4.OB.

While executing transaction CJ88 (Project Systems) in test run mode we are getting the following error message.

T Message text

Sender: WBS F101C-0003-HTG High Temp. Generator for VAC-2 of jainpur

E Complete settlement structure A1

Further on double clicking the message it shows the following

"Complete settlement structure A1 "

Message no. KD503

Diagnosis

During settlement, the sender debits are put into groups (settlement assignments), to be settled under the same settlement cost element. This assignment takes place in the settlement structure saved in the settlement rule for the sender under settlement parameters.

Cost element 300710 cannot be assigned to a settlement cost assignment in settlement structure A1 and therefore cannot be assigned to a settlement cost element.

The Cost element 300710 is a stock projects account( balance sheet item).The category of cost element is 90 ( Statistical).

Page 13: SAP PS FAQ With Answers

The WBS element F101c-0003-HTG,Down payment was made against a PO which was assigned to this WBS element. This down payment has already been cleared against invoices booked later.

When we display Actual Line items for Projects the costs booked against cost element 300710 is already been issued to consumption projects, from there it will be settled to asset via transaction code CJ88.

******** You will need to amend your allocation structure A1 to include Cost element 300710 temporarily, so that you can complete the settlement of this project,. Note it should not transfer any costs from this cost elements if there are none, but it still needs to be included in the allocation structure.

Then amend it back once that project has been settled..

******* Thanks for the solution. But I have few queries:

1. If I do it temporarily and settle the assets will this problem will repeat in the future?

2. What changes I have to do so that I do not get this problem again in the future?

3. Since 300710 is an "Stock Projects” GL Account, why I have to create it as cost element?

*******

1. If I do it temporarily and settle the assets, will this problem will repeat in the future ?

The problem will not repeat itself if costs are not assigned to a projects that are outside of the range of cost elements within the allocation structure A1.

Page 14: SAP PS FAQ With Answers

2. What changes I have to do so that I do not get this problem again in the future ?

You could put a validation rule into the system to stop postings aoutside of the allocation structure (transaction OKC7 or OKC9 - I cannot remember whch one).

3. Since 300710 is an "Stock Projects " GL Account, why I have to create it as cost element ?

You sat that the category of cost element is 90 ( Statistical). This appears to suggest that there is a cost element for 300710 as you were able to post costs to a CO object using it hene you will not need to recreate it ...

SAP PS SCHEDULING

We are now using SAP 46C, not long ago, my management is contemplating no to use the scheduling function in PS. Which means that the users will no longer requires entering duration, and performing scheduling. I'm abit concern over the implication of this. Would someone able to advise me what will be the impact if scheduling is not carry out.

******** By giving the duration in the activity the system can give the total duration for the projects. t also gives the critical path and non path. One can do scheduling into the future or backward scheduling. Also the duration and dependency like Finish Start , Start

Start , Finish finish ad Start start can be given between the various activities in a project. This helps bring in project time, cost and schedule in one platform and increases the power of Project System. Also the progress on each activity can be tracked by

activity confirmation and actual and schedule dates are available in the system in a graphical display.

********* Depends if you are using MRP for material requirements, Then, you can have moments that you have out of stock situations, with all other consequences involved.

Are you using capacity planning? On this you will have the same issue , that your will have moments in your planning that resource does not comply with reality. So all depends if you are using project system for material and resource planning.

Page 15: SAP PS FAQ With Answers

If answer is YES, then you have to take action.

If NO then your manager is right, so you are using Project system only for COST Management.

___________________________________________________________________

LOG: PLANT MAINTENANCE AND SAP DMS

We are Oil & Gas Company running SAP R/3 4.6B. WE have implemented the

following modules: FI/CO, MM, PM, HR. We are implementing DMS (Document

Management System) at this time.

The main focus for this implementation is to create documents in DMS and

then link them to our technical objects in PM. We have done this successfully for documents in MS Word and BMP files (scanned documents). Our plan at this time is to link AutoCAD drawings to the technical objects.

WE can do it through the System --> Link option in SAP. However, we want to

create a DIR in SAP DMS and then link the DIR as a document in the technical

object.

Our plan is to load Volo View at the client end for users to look at the

drawings. Are there any special options settings on the VoloViev side? The

challenge we are facing is storing the document (checkin) in our database (using KPRO). We are getting the message that the document cannot be stored (error in storing document). What extra settings do I need for AutoCAD that I did not need for the other applications type?

Page 16: SAP PS FAQ With Answers

PLANNED DELIVERY DATE IN EXTERNAL ACTIVITY

Do anyone have idea / know what is the impact filling “Planned Delivery date" on " Delivery date " in the PR service?

******** Currently I have no access to an R/3-system but I am quite sure the planned delivery date is scheduled based on the start date of the activity and the delivery time entered. Populating this field manually might set a constraint to network scheduling.

DELETING AN ACTIVITY WHICH HAS A PURCHASE REQ

I have a network with internal activity which has a material component ordered for it. The purchase Requisition has been created for the component. The PR reflects as a commitment on the budget/actual/commit reports.

I now want to set the deletion on this activity as we don't require the component anymore.

The system give me an error saying that a Pur. Req commitment exists and I cannot delete. How do I set the deletion flag on this activity???

******** You must first delete purchase requisition and the material assigned to this

activity. Then you can set deletion flag on activity

MULTIPLE ACCOUNT ASSIGNMENTS

I'm currently working on a project using 3.1I.

In MM I'm trying to create a purchase order for a material which is made up of 3 sub-components.

Page 17: SAP PS FAQ With Answers

This is a subcontract material - so at the top level the material valuation class is 7900 and represents the subcontract labour and through auto acct assignment goes to the correct GL acct - subcon labour.

However the 3 sub-components are of valuation class 7950 and I want these to show against another GL acct - purchased parts consumed.

These costs are being pulled through and reported on using PS. But everything is coming through on the one GL acct from the top level - subcon labour.

acct assignment category D is being used and even though multiple acct assignments is set an error message appears saying that multiple account assignments is not allowed.

Does anyone have any suggestions as to how to get this to use the required accounts? If acct assignment category is NOT used then the accounts are OK but this means that nothing is shown on the project.

******* What PO type are you using?

******* PO type is NB

FIELD SELECTION ON COMPONENT DETAIL IN NETWORKS

We want to set the following fields below as "Required/mandatory" fields on the component

Detail screen in networks (on the Purch. Data Tab), but in customizing there is no option

to set this on component level???

Where else can I set this or how should I go about it ???

Page 18: SAP PS FAQ With Answers

Price - [RESBD-GPREIS}

Recipient - [RESBD -WEMPF]

Unloading Point - [RESBD-ABLAD]

Material Group - [RESBD-MATKL]

Purch Group - [RESBD-EKGRP]

Cost Element - [RESBD-SAKNR]

******** Are you try the behavior of the enhancement for material components in

networks?

CNEX0009 Material components

I think they are no more options in customizing

NO COMMITMENT ON PROJECT

We have created a reservation for a Stock Component on an activity for a project. It has

been released and has been specified as procurement type "Requisition + reservation for

WBS element". A reservation number has been generated and also a requisition number.

The problem is that on the report "Plan/actual/commitment..../" the commitment shows as 0 ??? Why doesn't this pick up the commitment value ??

********* In our configuration the commitment is created by the PO. The requisition only represents an internal level commitment. I believe the binding commitment that will carry forward into PS will come from the PO. Take the next step with the PO and see if the PS commitment posts from that. Also verify your Req assignments.

__________________________________________________________________

Page 19: SAP PS FAQ With Answers

REVENUE PROJECT

When we have a revenue project, one common expense for example rental might be used for both OPEX and cost of sales. In Financial statement version, the P/L is drawn by GL codes.

In this case, how do we segregate rental expense to distinguish between rental under OPEX or rental under cost of sales?

UTILIZE THE BAPI_NETWORK_MAINTAIN FOR VERSION NETWORK

SAP Version 4.6C

Trying to utilize the BAPI_NETWORK_MAINTAIN for version network. Normally

networks are in table CAUFV but versions are in table VSCAUFV_CN. Normally Activity work hours are in AFVV but versions are in table VSAFVV_CN. Can you utilize the BAPI_NETWORK_MAINTAIN so that it updates the version network activity? Or is there another FM I can utilize to update the activity hours for a version network activity?

This is what I think the code should look like for setting up the variable for the FM but cannot determine what value v-objkey must be to get the version network updated. Or perhaps there is something else wrong with my code.

i_method_project-objecttype = 'NETWORKACTIVITY' .

i_method_project-method = 'UPDATE'.

i_method_project-objectkey = v-objkey.

i_method_project-refnumber = '000001' .

APPEND i_method_project.

i_method_project-objecttype = ' ' .

i_method_project-method = 'SAVE'.

i_method_project-objectkey = ' '.

i_method_project-refnumber = ' ' .

Page 20: SAP PS FAQ With Answers

APPEND i_method_project.

i_activity-network = v-objkey.

i_activity-activity = i-vornr.

i_activity-work_activity = i-ismnw .

APPEND i_activity.

i_activity_update-network = v-objkey.

i_activity_update-activity = i-vornr.

i_activity_update-work_activity = 'X'.

APPEND i_activity_update.

i_network-network = v-objkey.

APPEND i_network.

* Network activity updating

CALL FUNCTION 'BAPI_NETWORK_MAINTAIN'

IMPORTING

return = bapireturn1

TABLES

i_method_project = i_method_project

i_network = i_network

i_activity = i_activity

e_message = e_message.

STATISTICAL WBS

Could you anybody give explanation or documentation about WBS statistical ?

Page 21: SAP PS FAQ With Answers

CJ20N NEED TO ADD BUTTON FOR CREATING/DELETING PIRS

Wish to add push buttons to CJ20N screen to give users the ability to create all the PIRs and another button to delete all the PIRs for the project. I cannot find a BADI in this function, so I need to know how to add the push buttons to the screen. I've also looked for user exits that would give me the functionality to do this but have not found anything

under the development class CNPB. The CJ20N transaction contains screen 4000 (User-Specific Options) or 4005 (User-Specific Options (Subscreen)). What options are available for the two subscreens for meeting my needs?

___________________________________________________________________

PS BUSINESS CONTENTS

Any of PS experts worked with BW please respond.

We are activating Business Content related to PS module in our BW 3.0B environment. I would appreciate your feed back on how to implement PS contents from your experience.

So far we come up with some errors as follows:

Object UPDR 8GUT493MN580Y5LZDRRRONEYY could not be found

This happened earlier activating one of the BC cube (0PS_C02) where many errors were listed related to update rules (6 of them). We are now trying update rules individually and came up with same error.

Any experience or idea about this error. No long text available for the error

(message no. RS_EXCEPTION230).

******* I had the same problem and have solved it as follow: First you have to select the update rules (for example) and transfer them (you have to select the option 'Transfer', of the 'Transfer command), you will see that they will be activated without error, next step you can simulate them or include them into an order to transport to another environment.

Page 22: SAP PS FAQ With Answers

DELAY REQUISITION

Does anyone know a way to add components to a released activity (status REL) but hold the entries so that they don't automatically get submitted for PO creation (not hit a purchasing backlog)?

We'd like to create components on activities that are released, but not allow them to be converted to a PO until ready

******* I can't really give you a solution to your problem, I would however really be obliged if you could let me know exactly what the business case is (if there is one) in which you are trying to achieve the objective.

******* Try in the order transaction, IW31 or IW32, in the Components tab, there

is a column called "Res./Purch. req.". It can be set to Immediately (create purch req upon order save), Release (create upon release), or Never (never create purchase req.

******** Thanks, but IW32 is for PM order change. We are working with PS Network activities. Our first attempt at solving the problem was to set the "Res./Purch req" field to "Never" using CJ20N, but the field is grayed out and cannot be changed

******** If you create a new component, you are able to change the "immediately"/"from release" - if you have not configured it to be always something else. i assume that you have configured it to be gray.

******** We did identify that it the field could be initially changed in the table view (component overview). But once "immediately" was set, it could not be undone. I guess this makes sense since the req number has been generated.

Page 23: SAP PS FAQ With Answers

I have looked and cant find where this is configured. Do you have any ideas?

******* If you go in SPRO and go to field selection for networks, then select the network header screen. This will give the option on field [CAUFVD-AUDISP] which can be set as input, required or display

******* Go to t code OPUU and set indicator 1 for Res./Purc. req. as 1 (Never) and save the same. It will solve your problem.

PROJECT PLANNING R/3

Can anyone tell me the best method to plan for detail project cost?

CONFIGURABLE BILL OF MATERIAL

Is there any way to use configurable materials with Project? We created a variant material, configured it, and added it to a project. That worked. Is there any way to have the configuration screen appear in project as it will for a sales order? I am shooting in the dark here other than trial and error on the configuration profile screen.

We have many engineering changes and are also struggling with how to mesh that with configurable bills. Is there any way to get a result BOM and change it independently of the super BOM (for one time only customer order specific engineering)?

********

Yes, configurable Material Masters can be used within Project Systems. The approach to this solution is different than Variant Configuration that you may be used to using a KMAT with all the other associated Master Data. It is recommended not to use KMAT.

Page 24: SAP PS FAQ With Answers

Create a HALB or FERT, make sure the Item Category(s) are for Configuration, on Basic Data 2 select "Material is Configurable, assign the Variant Class with the Characteristics and no Costing or Accounting views.

Create the Configuration Profile for the Material Master and for the Standard Network. This is the link.

The Super (configurable) BOM should be created within the Standard Network as a Standard BOM, not a Material BOM. This will Allocate the Components to what is known as a Standard Object. This is a Structure that will pull this data together in a Project.

Add any Object Dependencies to the BOM items that require Configuration.

Allocate your Network Parameters for Sales Order to complete the Master Data requirements.

It all works great once in place. MTO is the way to go for our Project Systems business and this solution is perfect.

MC$6

When we are evaluating our suppliers for on time delivery we are using MC$6 however the Weighted Delivery Time seems to be calculating length of time to deliver from Purchase Order date to GR date - is there a way of configuring the system to measure from expected delivery date to actual delivery date or should I be using another TX to measure this KPI

TRAVEL-COMMITMENT-WBS

We need to create commitments for travel requests in WBS elements and then see if there is any available budget. Is there any way of doing this maybe via Funds Management?

Page 25: SAP PS FAQ With Answers

SETTLEMENT PROFILE

As we have to create settlement profile for project definition, WBS & networks.

As i understand networks settles to lower level WBS, lower level WBS settle to billing level WBS. Now i want to know where does the Billing level settle to And the project definition settle to We need to create the settlement profile for each of them

we are not using COPA

**********

1 - You never settle the project definition. If you put a settlement profile there, it is only a default value for WBS elements.

2 - To define settlement you must define a settlement profile, which says: should I settle or not ? Do I control the complete settlement or not before closing? What is the type(s) of receivers for the settlement?

But it's not enough to do the settlement; you also need a settlement schema which says: What are the costs elements for which we want to settle the costs? What is (are) the cost element(s) with which the settlement is done? ....

3 - For the billing level, It depends of your business scenario

3.1 - You use projects but their live is short (some days) and you don't need to calculate WIP.

3.1.1 - So you can not settle this WBS element and define settlement profile with 'no settlement'

3.1.2 - Or you can settle this WBS, element to any cost object, usually consolidating WBS (but you can choose SD order or CO order, ..).

3.2 - You use project with a not short live (some months), then you need to calculate WIP (by means of Result Analysis calculation)

3.2.1 - You can choose the billing WBS element as the WIP object (usual choice), that is the object on which you calculate Result Analysis, and then you must settle it as in 3.1.2. . And it's mandatory to settle the WBS element in order to update WIP accounts in FI (posting to FI which is define in the customizing

Page 26: SAP PS FAQ With Answers

of Result Analysis). Warning, in this case, the settlement schema (CO settlement) is different as above, because you must

not settle the costs but the results of Result Analysis calculation, that is Cost Of Sales, Reserves,

3.2.2 - Or you can choose the SD order as the WIP object. In this case, you settle the WBS element to SD order item. You customize and calculate the Result Analysis on SD order ITEM and you must settle this order item.

*********

The Settlement rule that you see on the Project Definition is there to be used to populate the settlement rule onto the WBS elements prior to saving the project. The Project Definition is not a cost object, and therefore cannot send or receive costs.

The billing element can settle to a sales order or orderable items on a sales order (sort of the inverse of the line items on a Purchase Order). On revenue projects, the billing element can receive revenues, and can be settled to a GL account.

Out of morbid curiosity - why don't you have a PS Consultant on your project? If you do have one, they must be one of those $60 an hour pseudo-consultants that have resulted in the depressed rates and depressing lack of quality that we are seeing in the marketplace...

ATTACHING DOCUMENTS TO A PROJECT

I would like to attach word documents or Excel spreadsheets from my hard-drive to a SAP PS project/WBS.

I know how to do this in Project builder (CJ20N), but we only use CJ02/CJ01 as this

client.

We also are not using a document management system.

What is the simplest way I can attach documents in CJ02??

Page 27: SAP PS FAQ With Answers

******** You can try the following:

CJ02 -> Services for object (top left corner icon) -> Create attachment -> select your file from your local drive.

System will copy the file from your local drive.

Then view the attachment list.

******** What you mentioned works in CJ20n (Project Builder). I cannot find the

services for object icon on CJ02?? Were you able to do this on CJ02?

*******

Kallol is quite correct... It is the icon just under the icon and depending which side of the icon you select either a menu comes up or another icon bar. If you select the left side of the icon and then the furthest left icon on the icon bar whe it appears, you should be able to attach any document that you wish...

CONFIGURABLE NETWORK

I am creating an operative network by copying from a configurable standard network. I assign characteristic value during creation. But I can not change these value in operative network. Network is not created from sales document. It is created in Project system.

The document says Choose Extra --> Configuration--> Characteristic value assignment.

My problem is that Characteristic value assignment is unhighlighted. I can not select it.

Page 28: SAP PS FAQ With Answers

MULTIPLE ASSIGNMENT OF PROJECTS

I have been trying some new functionality in SAP 4.6c. Try to link a project to multiple IM positions. I have managed to link the project to 2 IM positions with a percentage of

budget set for each.

The system does not seem to find the measures when I run IM52 to put budget onto the

project?

How do I assign budget to this project with multiple assignments?

RA FOR CUSTOMER PROJECT

I am trying to configure RA in Project System which is Customer Project. In this project the client needs the WIP figure project wise.

Our structure is a) 1st level WBS is the Billing & planning element

b) 2nd level WBS is Acct Assig & Planning

c) network attached to 2nd level WBS

Config is:

Created RA key( AUFT)with RA method -Inventory Determination "WIP at Actual Costs" for Objects Not Carrying Revenue(Is this a correct method ?)

& settlement rule -settle to the Cost center

The RA type is F-WIP Calculation on Basis of Actual Costs

The Profit Indicator is O-No Profit Realization

Profit basis-C-Costs and revenue on basis of cost element planning data

We have attached the RA key to all the WBS & to Network type

Page 29: SAP PS FAQ With Answers

We have made goods issue to network which is attached to 2nd level WBS. The status of the 2nd level WBS is REL

On running the RA(trn KKAJ) on the 1st level no data is selected & in the Log shows no error

Is there any config details which i should need to see to get the WIP-?

********* Why t code KKAJ is run??? . Go to t code CJ02 and release the WBS elements acc

******* The all the levels of WBS elements is already Released

******* I am very familiar with Investment Projects. To what extent is Customer Projects different? If I were to rephrase my question knowing Investment Projects how much time and effort will be required for mastering Customer Projects

******* 1 - You must set the RA key only on the WBS elements for which you want WIP. As I can understand, only on the 1st level.

2 - And you must define the adequate value for "Project structure" parameter

("B" I think), in the RA Key customizing

RETURNING BUDGET TO PREVIOUS FISCAL YEAR

I have a project from FY 2003 (Original Budget 200,000) which has been carried forward to FY 2004. In the FY 2004 250,000 has been supplemented to the project.

Page 30: SAP PS FAQ With Answers

The project is now complete and we want to return 50,000 of funds back to the FY 2004, to use elsewhere.

The system (Transaction IM52) will not allow me to return funds to 2004, it only allows

supplements. How do I return these funds to 2004?????

******** You can supplement from IM, but you return from Projects using the "Return from project" transaction CJ35.

OPEN PS PROBLEM

I have OpenPS4MSP version 2.01.00, and MS Project 2000.

I opened an existing MSP project. On a standard MS Project view, Gannt Chart for example, I have a text description of each task in the "Task Name" columns. When I switch to the Open PS view in MS Project, the contents of the "Task Name" column appear in the "ID" column, and the "Description" column is blank. The ID column is what PS uses for the mask. So for example, instead of my project definition being D-12999-01, it uploads to PS as "Turbine Project". Any ideas on how to fix this? Thanks!

********

Sorry, I haven't experienced this one... I imagine that you downloaded to MSP using the export feature in CN41. I would check OSS to see if there is a note...

*******

Open PS is a nice tool. but there are loads of OSS notes you'll have to apply making it work properly.

Furthermore it really depends upon what release of SAP you're on.

We, being on release 4.6C, had to apply at least 4 or 5 notes in order to

Page 31: SAP PS FAQ With Answers

make it work properly.

Open PS only works with all the features if you're on release 4.7 or 4.6

with additional notes applied.

You should really check OSS or post a customer message, as I haven't been

able to find all the relevant notes myself.

FISCAL YEAR CHANGE FOR PROJECTS

Does anyone have a good procedure which gives the details for changing IM fiscal year and carrying forward projects?? When do we use CJCO, CJCF, IM27, IM27_repeat etc,

Also, does anyone know how to view an attachment (PPT) which SAP has referred to in a SAP (note 444444.)

******** A summary of our projects year end steps is as follows:

CJCF to carry forward commitments

CJCO to carry forward project budgets

IMCAOV to carry forward IM budget

IM27 Create new IM structure

IM27_REPEAT Carry forward measures and budgets to new structure

IM27_CLOSE Close the old IM structure (NOTE: Cannot be reversed)

IM22 Update new IM structure, eg. Add/delete nodes

PROJECT SYSTEM VS FUNDS MANAGEMENT FOR BUDGET CREATION, TRACKING AND REPORTING

We are in the process of implementing the SAP Cash Management Module. We are currently using Project System, to create project numbers (WBS) which are used in Funds Management, to track and report budgets by Business Areas.

Page 32: SAP PS FAQ With Answers

We are quasi-government organization and our business requires having approved budgets.

My question is can Project System be configured with similar functionality as Funds Management for budget creation, funds availability checking, transfers, appropriations, encumbrances, tracking and reporting?

******** As far as I know the short answer is yes. However, you will want to give careful consideration to how you structure your fund and cost centers.

******* Yes, the full functionality of budgeting and availability control is available to PS. Check in the IMG under PS Budgeting to set up the budget profile...

BAPI TO GENERATE WBS ELEMENT GROUP

Does anybody know some BAPI for the transaction CJSG - Generate WBS Element Group ?

RELEASE STRATEGY FOR PLANT MAINTENANCE ORDERS

I have multiple maintenance order types in my SAP Plant Maintenance Module.

Everyone who create maintenance order also have authorization to release this order.

Now I want if any user create capital order (An Order Type) he can not release himself. There should be some release strategy only for capital orders. How do I do this?

__________________________________________________________________

CREATING PROJECT IN PS

Page 33: SAP PS FAQ With Answers

Please tell me which are the various notification types (or requests) from which projects can be created directly. In my situation i need somebody to send me a notification (request) and i have to create a project is PS directly. No manual retyping of data. The

requestor can then view the project from the notification (request)

PRICING CONDITIONS POSTING TO A WBS ELEMENT

I have been told that a SD pricing condition can be directed or captured by a WBS element as a cost. Can anyone confirm this for me and if so how do i configure it. Any help is much appreciated.

CJ20N CONTROL

I have a client who wants me to build a job role with CJ20N, where the user can create/change settlement rules but can not perform status changes (especially can not set TECO). Can you please help me to identify the object that controls status change.

AMOUNT OPTION SETTLEMENT MISSING

During Implementation, the amount column was removed or hidden from site on the settlement screen through transaction CJ20n. Can anyone assist with retrieving this column. Unsure where it resides in SPRO.

********

Please check in IMG->Plant Maintenance and Customer Service->Basic Settings->General Order Settlement->Maintain Settlement Profiles.

Check your settlement profile. Tick field Indicators: Amount settlement

******** You have to go to the IMG and under PS / costs / automatic transactions /

settlement / settlement profile, select the profile you're using, and click on the checkbox that allows for amount settlement.

Page 34: SAP PS FAQ With Answers

NETWORK ACTIVITY

When I create an external activity in a network, the Res/Pur.Req field is initially set to IMMEDIATELY, but once I enter, it is being changed to NEVER?? Why is it changing to NEVER???

It is set to IMMEDIATELY in the IMG network config

I also get a message saying "Operations not released: Network header is TFRE”???

What does this TFRE mean??? Could this TFRE be causing the change from IMMEDIATE to NEVER??? Please help!!

******** Can we restrict users by Network activity?

******** By network activity type (E/C/W) in object C_AFVG_TYP.

C_AFKO_ACT may be necessary in combination spec. for cost handling.

ASSIGNED VALUE IN BUDGET

I am on 4.6c. I am finding " RESIDUAL ORDER PLAN' is getting assigned to

budget. Amount from this gets reduced from available budget.

Will somebody explain the meaning of "RESIDUAL ORDER PLAN" How it gets

assigned??

******** The assigned value in budgeting it the cost excluding the cost on cost

Page 35: SAP PS FAQ With Answers

elements excluded from budget availability control.

PS REPORT

I've tried to run the PS standard hierarchy report and the PS cost elements report for the same project, however, the cost figures are different. What could be the possible causes?

******* Will you specify report number/ T codes?

******* The hierarchy report is S_ALR_87013532 and the cost element report is S_ALR_87013543.

PROJECT SYSTEMS

I am a user in IT company I have to create WBS elements in Project systems in SAP for Four Fixed contract could some body help me in giving the steps involved in creating WBS elements.

Could somebody enlighten me on Project Systems.

********

For a nice overview of PS visit the Help Portal http://help.sap.com and

go to the SAP Systems Tab then to the IMG section.

CJ01 is one way to create the WBS you require. Are you using Networks?

__________________________________________________________________

DATES IN EASY COST PLANNING

Page 36: SAP PS FAQ With Answers

When project costs are planned in Easy Cost planning, the validity date in taken automatically from the WBS or determined based on the costing variant. This leads to costs being displayed as assigned to a specific year in the cost reports.

Is there a way to distribute planned costs (in Easy Cost planning) in future years (as one can do in manual planning - cj40 or per cost element)?

PS_COST REPORT S_ALR_87013532

Project cost report S_ALR_87013532 does not give rolled up values for actuals if it is run for down level WBS elements whereas it shows values of actuals properly rolled up to it=92s superior WBS while running same report for project definition.

For Example: Actuals at last level WBS 3001 & WBS 3002 are 2500 $ each. So actuals for it=92s superior WBS 2001 does not show 5000$ while running report for WBS 2001. However if same report is run for project definition, then actuals for superior WBS 2001 is shown as 5000$.

Is there any settings in IMG for this or this is a bug?

______________________________________________________________________

SYSTEM STATUS

How I can control ate the System Status across user profiles?

***** Can anyone tell me how to revoke a system released status to system partially released status for Proj Definitions?

***** Unlike the CO module, there is no transaction to revoke the status of

"released" in PS. You will have to talk to SAP about getting a program

built to do that as you are talking about changing native SAP source code...

Page 37: SAP PS FAQ With Answers

USER STATUS OF INDIVIDUAL WBS ELEMENTS

I need to select all the WBS elements that can be billed. As per my understanding, the WBS elements whose system status is either "Released" or "Technically Completed" can be billed. Also we are supposed to check the user status of the WBS elements.

Now when I am trying to check the status of the WBS elements in JEST table (field STAT), then it gives me a range of status starting from "E0001" to "E0020" and "I0001" to "I0063." My question is that how do I know the meaning of these individual statuses and on what basis should I select these WBS elements.

******* You can check the meaning of this status in table "TJ02T". All descriptions are available there.

********

I just checked the table that you have referred. Here I am able to see all the texts for System status.

However, could you also tell me, where can I find the explanation for the user Statuses. I have been told that the user status start from 'E' whereas the system status with an 'I'.

Also can u help me in the logic of selecting all the WBS elements which a person can put his bills against?

This is the first time I am working on PS module, so I am not very clear of all the basics.

*******

User status text can be found in TJ30T. Since a user status can be duplicated between object. By that I mean that E0001 can have a different text or meaning on a WBS than on a order, you first need to identify the Status profile (STSMA).

Page 38: SAP PS FAQ With Answers

To do this look it up in table JSTO using the object number of the WBS.

Code below is old and you might want to change the selections and maybe just select the fields needed, but the tables are correct

SELECT SINGLE * FROM JSTO

WHERE OBJNR = "WBS OBJECT NUMBER".

SELECT * FROM JEST

WHERE OBJNR = "WBS OBJECT NUMBER"

AND STAT BETWEEN 'E0001' AND 'E9999'

AND INACT = ' '.

SELECT SINGLE * FROM TJ30T

WHERE STSMA = JSTO-STSMA

AND ESTAT = JEST-STAT

AND SPRAS = 'E'.

PS-COST REPORTS

There is plan cost from network having activity elements.

The cost report S_ALR_87013533 shows value rolled up from activity element to activity ...network...and then to WBS in the plan cost column as well as Rem ord plan column.

However upon posting actual work hrs thru CAT to network activity , the Remordplan value is still appearing against WBS in Remordplan column .

Can someone tell me what is the reason here?

Page 39: SAP PS FAQ With Answers

********

PO having acct. assignment to network shows commitment in cost report S_ALR_87013533 against PO. Then GR is created and commitment reduced to actuals.

Then GR reversal (return delivery to vendor) is made and actuals reduced to commitment.

However making a GR again for same item and qty, commitment does not get reduced and actuals are not shown in S_ALR_87013533.

What could be the reason for this discrepancy?

COMPONENT SCHEDULING

I am currently using SAP v4.6, where we assign materials to activities on operative networks. Currently the materials finish date lines up with the finish date of the activity.

I am desperate to find a way in which I can:

1) Assign a material to an activity, where the start date of the material lines up with the start date of the activity.

2) Assign materials at different points across the same activity. Note the same materials are used on numerous networks and maybe required to be scheduled differently depending on the network.

*********** You need to click the radio button "Align with start Date" this will

allow the material to align with the start date of the activity. Any other activities following the first activity should be scheduled, then it will also adopt the relevant activity date.

Page 40: SAP PS FAQ With Answers

********** I have tried this and the finish date of the material lines up with the start date of the activity.

I need the start date of the material to line up with the start date of the activity. Then all lower levels of the BOM will be planned so that they are available for the start of the activity.

********

First check whether u has made relationship b/w the activities or not. Also check whether u have scheduled the activities or not. If not do that, mtl will automatically take the dates from the activity

*********

In response to your second request of assigning materials at different points across the same activity.

There are a few different ways to assign different dates for material within the same Activity. The first 2 ways (which were talked about in previous responses) were the use of the 'ST' (start date) and 'FD' (finish date). to provide more flexibility using these references, you can use the 'Offset' field in junction with the 'Oper. LTO unit'. You can have a date for a material after the Start or Finish date by placing a positive value in the 'Offset' field along with the appropriate unit in the 'Oper. LTO unit' field. You also can use negative values(2-, 5-, etc.) along with the appropriate unit to have materials available before the Start or Finish date. The scheduled dates of these materials will follow any scheduling changes you do to your Network that might affect the Activity's dates.

The last method to specify different dates is to use the 'RD' radio button and then populate the "Reqmts date' field with the date thaqt you want the materials on. The only drawback to useing this method is that these dates will never change even if you adjust the dates on the Activity itself.

BUDGET CHECK ON L CATEGORY

Page 41: SAP PS FAQ With Answers

Is it possible to establish a budget check in the following cases? If so please inform me about how it can be done:

1. A budget check is required for materials that are procured with the Item category in PS-L (project stock) / account assignment category in MM =96 Q. I need the check in place at the Requisition level or at the PO level. The amount of the requisition or the PO should check against the budget that I have assigned for that project to the higher level WBS.

2. I am using a Gen. Cost activity for creating a planning estimate for procurement of services and materials. The cost activity upon saving gives a message that says =93saved temporarily=94. Since no document is generated I assumed that the value of the Cost activity cannot be checked against the budget assigned to the higher level WBS.

PLEASE INFORM ME IF THERE IS A WAY I CAN MAKE THIS BUDGET CHECK WORK.

DEFAULT COST CENTRE ON PROJECT

My users enter the cost centre on the root WBS element. How can I get this to default to all other WBS element below? I have tried substitution using the superior WBS element, but this causes the initial root WBS to blank out.

Where do I find the field PROJ-KOSTL (cost centre) in the project (in CJ20n) as this field does not appear in the project definition, but exists in the table proj ?? Where do we input this field?

****** I guess your cost center field of the project definition is currently hidden

by field status customizing.

Use transaction OPUJ to manage your field status. Make sure that you take into account the 'influences', which can define the field status dependent on project profile etc.

Page 42: SAP PS FAQ With Answers

****** Here is a tip: Try to use field level on your substitution

rules. I have used it for the same cause and it worked.

It isn�t possible to input cost center in P.Def. level. It exists into table PROJ because of the automatic settlement rule. PROJ-KOSTL is managed indirectly by responsible field.

SUBSTITUTIONS

I have a request to do a field to field substitution when creating the project definition. In order to prevent the need to enter data multiple times into required fields within all the levels of the WBS structure, it is required that we use substitution. In this way, data entered into fields on the Project Definition, Level 1 or Level 2 WBS element can be defaulted down through the structure to the corresponding lower level WBS elements.

I have created a substitution using transaction GGB1 Project System->WBS element, however I cannot seem to get it to work. I have set the prerequisite to "TRUE" and I've ran program RGUGBR00 to generate the substitution.

Do any of you use substitutions in this way? Any ideas on what I'm doing wrong here?

****** What field do you need to substitute?

****** About 10 fields in total. Here's one: PRPS-FUNC_AREA

what needs to happen is, the value in the Level 1 field needs to populate all sublevels for that WBS element field.

Page 43: SAP PS FAQ With Answers

****** Did you try to use project profiles to achieve this instead? You could have multiple profiles in which you set the default values. These values will then replicated through your project.

****** Use t-code OPSN for Substitution & OPSI for assigning validation to the

project/WBS. I do use substitution in duplicating the Project def to

description & short-ID.

***** Also set automatic substitution flag into project profile then you don’t need to run any program.

LOAD HISTORIC REAL COST INTO PROJECT

We've just gone live to SAP world, our FI accounting was iniciated on July'04 but our project started on 2003. Is there any way to load historic real cost to PEP elements? At this moment we use a neutral FI note that loads an historic cost center and PEP element with the same amount on credit and debit position. Is there a more easy and correct way?

___________________________________________________________________

'BASIC DATES', 'SCHEDULE DATES' AND 'ACTUAL DATES' TO BE CONFIGURED ED AS MANDATORY FIELDS.

We are in 4.OB.

While creating a network how can I make the key fields like 'Basic dates',

'schedule dates' and 'actual dates' to be configured as mandatory fields.

******* The only dates that you would make mandatory are the basic dates. This is usually done on the Project Definition and the network would automatically pick up the basic start (or in the case of backwards scheduling, the finish) date. The config is in the "field selection" screen on the WBS elements. The transaction code for this configuration is OPUJ.

Page 44: SAP PS FAQ With Answers

The forecast dates could be made mandatory, the actual dates you wouldn't normally make mandatory as these are usually populated only at the time of actual start or finish of an activity (usually through the confirmation)...

SCREEN FIELD SELECTION OF THE NOTIFICATION

In 4.0B is there any option by which we can make the damage, Cause code

fields mandatory.

i have checked in T.code OIAL (screen field selection of the notification);

did not find the required field.

DEFAULTING SHIP TO PARTY NO FOR 3RD PARTY MATERIALS

Our business process needs attachment of large number of 3 rd party materials (category 'N') manually to network activity which generate individual PR for each material. The PRs are converted unto purchase order by the MM department. We do not use BOM transfer for attaching materials.

The problem is - for every component that is attached, ship to party number should be given separately, whereas our typical project has only one ship to party, which is defined at the project definition level.

The question is whether there is any means of defaulting the ship to party from project definition so that repetitive entry and consequent errors can be avoided.

********* There are no config items that permit you to default a vendor on the material components of a network activity by project that I am aware of. However, here are some alternative suggestions (free of charge even):

***User Exit. In fact there is a User Exit CNEX0040 'Supply source determination in network ' I think that will give you what you want. CNEX0009 might be useful as well, use this in conjunction with option 3 below PIR.

1. Review OSS Note: 328466. It describes a mod that let's you use User PIDs to default in certain purchasing data, including LIF - Vendor. This however is user, not project specific.

Page 45: SAP PS FAQ With Answers

2. Don't assign a vendor in the Network Component. This only becomes Instead let purchasing take care of this by maintaining Source List ME01 for auto vendor assignment by material/plant when the PR is converted to a PO, which is a more standard solution.

3. Best option would be to maintain a source of supply through an info records ME12, by material, vendor, plant, purch org. This is not by project and you could have mult vendors per material. If you do then you will get a popup prompting you to choose the right vendor (and you can also do vendor evaluations and price simulations which is nice)

********

My query was for defaulting ship-to-party for the 3 rd party materials, not the vendor. We are maintaining source list for vendors and that's not an issue.

********

I'm not clear on your question, are you using:

1. 3rd party Purchase requisitions generated from the PS Network? Where you want to default in a delivery vendor on the PR Delivery Address tab? (Can't you use the 'Repeat On' button)?

2. Deliveries out of PS?

3. Partner functions.

Can you use a validation/substitution to enforce your logic?

MAINTAINING DURATION FOR SERVICES

I want to maintain duration of External Services in Project so that i can consider it while scheduling. My services are like laying of cables, so service order is given in units of Meter. Can anybody tell me how to take care of duration for Services?

Page 46: SAP PS FAQ With Answers

*******

There is an indicator in config item: OPSU, Sched Ext. Op (V_T430_CN-SCHEDEX) that will give your ext activities a duration based on the Planned Delivery time. does that help?

PLAN COST DISTRIBUTION AMONG PERIODS

I am implementing PS module including automatic cost planning based on activity elements (working activities) and material components. We no not need capacity planning as the company does not have own resources, external companies do the job.

I realized that in PS reports the cost occurs only at the end date of activity elements. This means even if the activity lasts 3 months the cost will be reported at the last month only.

Question: Is it possible to configure somehow the system in order to evenly distribute the total cost of external activities among the months of the total duration?

RE-ALLOCATION OF MATERIAL RESERVED ON WBS TO OTHER WBS ELEMENTS

Our client procures material in bulk which can then be used in various projects at later stages. For this matter the following process is used

1. Procurement of material against WBS is done by generating a PR and goes upto the complete cycle of procurement i.e. upto GRR. The stock is taken into Stores account.

2. The material upon requirement is transferred to various other WBS elements. Both WBS Elements are in the same project

Page 47: SAP PS FAQ With Answers

3. The problem occurs when material is to be moved from material WBS to other WBS elements as reservation is created w.r.f. to the material WBS.

can you tell us how can we move project stock procured against a WBS to another WBS within the same project

******* Use transaction MB1B with movement type 415Q

PS AVAILABILITY CONTROL IS ACTIVE - WBS BUDGET STILL EXCEEDED

As a rule, availability control functions correctly. However, our tolerance limits as set for our capex budget profile (supposed to be set automatically when budget is allocated) are now and then exceeded. There are no cost elements excluded in the IMG. Our availability control is based on the overall budget allocated. Can anybody advise as to what I should be looking at? Are secondary cost elements automatically excluded from availability control?

PS SETTLEMENTS

I want to schedule a background/batch job to run every night to run the Project settlements. I have succeeded in scheduling the job to run once weekly, but my problem is that the project settlement transaction requires the period to be input by the user. How do I overcome this and default the current period in the weekly scheduled job??? Is there a way to run this settlement as a job??

*********

If you are on 4.6 or higher use the Schedule Manager tcode: SCMA for all your month end/periodic processing. If not then:

Create a variant for your settlement screen by:

Page 48: SAP PS FAQ With Answers

- Going to the settlement transaction (CJ8G)

- Menu path Extras > Selection Variant > Create or goto SE38 and create Variants using program name SAPLKO71 or tcode CJ8V.

- Make the Posting Period a 'Selection Variable' and retrieve it's value from table Either Dynamic Date Calculations option or table TVARV. Your FICO guys are probably using this table (which itself is updated by a daily batch run) to create Selection Variables that are date driven

- Work with a BASIS person to schedule the job using SM36 with the variant you created.

SYSTEM/USER STATUS

In the WBS I have access to the historical of the System/ user status.

Is it possible to have access to the historical of the status of the network?

*******

Yes, it is in the same place, from CN22/CJ20N click on the 'System/User status' icon from the network header. Then menu path: Extras > Change Documents > For All

You have to turn on Change Docs for the Network Type/Plant config item: OPUV (note multiple flags depending on what object/level you want to activate this functionality)

MORE SUBSTITUTION PROBLEMS

I know the answer is right in front of me, but I can't see it. I'm hoping that some of you can see it.

I have created a user exit that will copy various values from the top level WBS element down through the entire project definition. Works great, client happy.

Now they want me to copy one value from the level 2 WBS element to the level 3 and 4 subordinate elements. What I can't seem to figure out is, how to determine which level I'm on when looping at table PRHI. Can any of you see how I can do it?

Page 49: SAP PS FAQ With Answers

Here's some of my code from the user exit that was copied from RGGBS000:

tables: prps, proj.

data: l_flag(1) type c,

im_prps like prps,

wa_prhi type prhi,

lt_prhi type table of prhi,

wa_prps type prps,

lt_prps type table of prps,

replace value '2'. "Yes(1) or No(2)

define subst_field.

&1 = &2.

l_flag = 'X'.

end-of-definition.

define fill_field.

if &1 is initial.

&1 = &2.

endif.

end-of-definition.

*save local copy of PRPS

Page 50: SAP PS FAQ With Answers

im_prps = prps.

* Determine all the subordinates of current WBS element

call function 'GET_TREE_FROM_PRHI'

exporting

i_pspnr = im_prps-pspnr

tables

psp_tree = lt_prhi

exceptions

input_error = 1

psp_hierarchy_error = 2

psp_not_found = 3

others = 4

.

loop at lt_prhi into wa_prhi.

if wa_prhi-up = im_prps-pspnr. "creating a sub level

*Get the values of the current level

call function 'CJDW_PRPS_GET'

exporting

posnr = wa_prhi-posnr

importing

e_prps = wa_prps

Page 51: SAP PS FAQ With Answers

exceptions

cancel = 1

not_found = 2

others = 3.

* Do the substitution

subst_field:

wa_prps-usr02 proj-zzfund_center,

wa_prps-zzdrain_basin im_prps-zzdrain_basin,

wa_prps-zzdistrict im_prps-zzdistrict,

wa_prps-zzlocation im_prps-zzlocation,

wa_prps-zzfunc_id im_prps-zzfunc_id,

wa_prps-zzutil_id im_prps-zzutil_id,

wa_prps-usr01 im_prps-usr01,

wa_prps-usr00 im_prps-usr00,

wa_prps-func_area im_prps-func_area,

wa_prps-usr10 im_prps-usr10.

* Do not overwrite lower structure value if one

* has been entered.

fill_field:

wa_prps-vernr im_prps-vernr.

fill_field:

wa_prps-astnr im_prps-astnr.

Page 52: SAP PS FAQ With Answers

if not im_prps-zzfund_center is initial.

subst_field:

wa_prps-usr02 im_prps-zzfund_center.

endif.

endif.

if not l_flag is initial.

* Update the project

call function 'CJDW_PRPS_MODIFY'

exporting

i_prps = wa_prps

exceptions

not_found = 1

posnr = 2

others = 3.

clear l_flag.

endif.

endloop.

endform.

******* PRPS-STUFE is the level

Page 53: SAP PS FAQ With Answers

SCHEDULING PS SETTLEMENTS

I want to schedule a background/batch job to run weekly to run the Project settlements. I have succeeded in scheduling the job to run once weekly, but my problem is that the project settlement transaction requires the period to be input by the user. How do I overcome this and default the current period in the weekly scheduled job ??? Is there a

way to run this settlement as a job??

FULFILLING PROJECT STOCK REQUIREMENTS FROM PLANT STOCK

We are using project stock from PS Network components. The situation is that we sometimes have bulk purchases of materials that once receipted sit in Plant Unrestricted stock. The requirements for the materials are being generated from within a WBS/project special stock segment (account Assignment = 'Q'). The problem is that even though we have sufficient stock on hand to meet the requirement at the plant level, we can't get MRP to match up that replenishment with the requirement generated from PS within the special stock/Project segment. Any suggestions what the proper MRP settings would be to get MRP/MD02 to work? More specifically, what MRP settings and Strategy Group would I use (I seem to remember using MRP Strat: '51 - Planning w/out final assembly /proj settlement')??

Right now we have a manual solution where we have to do a transfer posting to move the stock Plant->Project, then do an goods issue to consume the material, and finally manually delete the PS generated PR (b/c it is firmed). We would like to automate this through an MRP run. This must be a pretty common scenario (goods in Plant Unrestricted demand from a special stock segment) in using SD; I imagine PS settings to be pretty similar.

**********

To get a better clarity on the matter, may I ask why you have opted to procure materials account assigned to project, if the stock has to be reckoned in MRP. Will it not be better, if you take the 'Planned Independent Requirement'(PIR) route for bulk materials of the kind you described? If you assign strategy group 40 (?) to these materials, the materials will always be plant stock and any project specific (dependent requirements) will net-off against this.

*********

Page 54: SAP PS FAQ With Answers

Thanks for the reply. I agree that under normal circumstances you have certain commodities that are bulked purchased, for example using a Planned Indep Req coming from S&OP, and the requirement for this type of material also is in non-project stock based on the Material Master settings, so there is no issue for MRP.

However, what happens is that we have components purchased for capital projects in project stock. For various business reasons we wind up with excess stock (sometimes b/c these are Oil and Gas projects at fairly remote sites/long lead times so they order a extra for the project, or just order extra in general to have critical components on hand, or sometimes b/c parts of the the project are cancelled delayed). So good that was initially intended or even receipted against a project wind up in general plant inventory. Then we a new future project is created, we don't want to order more of these goods, but use what is available.

Note we tried to accommodate this functionality with ATP availability checking, but it suffers the same lack of Plant stock visibility from Project requirements.

HIERARCHY ERROR WITH SENDER HIERARCHY 050

While running the settlement for WBS elements (Network attached) i get the following error.

"Hierarchy error with sender hierarchy 050". On displaying the technical help the following msg is displayed.

SAP Error Message:

Diagnosis

You want to settle a sender with settlement hierarchy number 050 to a receiver with hierarchy number 050 and settle the receiver in the same settlement run.

System Response

The sender is not settled:

Procedure

Page 55: SAP PS FAQ With Answers

There are two possible solutions:

1. Change the hierarchy number in the sender or receiver so that the number in the receiver is smaller than that in the sender.

This ensures that the receiver is processed after the sender and that both objects are settled completely in the settlement run.

2. Change the selection criteria so that they do not occur in the same settlement run.

********

The hierarchy determines the order of settlement. For example, network activities, first, and then subordinate WBS, then main WBS, etc. Generally the higher numbers settle first then the lower number. Sometimes, objects that settle to other objects may have the same or lower hierarchy number. This has to be corrected. To see the settlement hierarchy, open the settlement run in CJ20N or CJ20. Then click Settlement Rule>Settlement Hierarchy. You will see the sender number, the current object number and the receiver

number. The receiver should have the smallest number, sometimes 000, the receiver will heave the highest number and the current object will be in between.

********

I forgot to add, it sounds like your sender and receiver are both set to 050 for a hierarchy number

MULTIPLE WBS PER LINE ITEM

My query is cross-modular: for that I apologize in advance. Any help on any of the issues raised below will be much appreciated.

I=92m an R/3 4.7 end user in Procurement. We use MM in conjunction with PS to order materials and services. The company policy is to buy to project, not to stock. We often order the same material for different projects at once.

Page 56: SAP PS FAQ With Answers

In 4.7, we discovered the functionality for multiple accounting. So, each line item in the purchase requisition can have several WBS elements. This is then carried over into the purchase order.

The problem arises when goods are booked in. Our cost controller has noticed that for line items that have multiple accounting, the committed costs do not turn into actual costs even upon receipt of goods. As you know, all other costs are converted from committed to actual when goods are booked in. But the behavior of multiple accounting line items is not consistent with this general principle.

Also, multiple accounting line items do not hit the GRN Accrual account. This leads to a serious misreporting of costs at year end.

PAYMENT TERMS

One of our vendor is giving Discount of 5% on payment within 30 days.

Now If we pay within 15 days, 10days, 12days the Discount is to be calculated proportionately.

Now is there any provision in SAP to configure discount in such a way that from the baseline date of the Vendor invoice to payment date the system calculates the discount and posts the Discount entry automatically.

******* Try using TCode “OBB8"

*******

The problem is I will have to define for all days less than 30 days a rate to be calculated, Is there a feature where in The system takes the baseline date and calculates the discount on each invoice where payment is made less than 30days

Page 57: SAP PS FAQ With Answers

******** In the IMG TCode where you maintain your payment terms, you can enter

multiple lines for the different time periods and percentages the system should use. Try using that.

IMG->Financial Accounting->Accounts Receivable and....->Business

Transactions->Incoming Invoices->Maintain Terms of Payment

PS you are sending this to the wrong user group, why don't you join the

accounting group? Just a thought

SETTLEMENT ERRORS

When running Settlements, the following errors occur: Any ideas in how to go about solving these would be appreciated.

1) Acquisition value negative in area 01

2) Balance for transaction group 10 negative for the area 01

3) Maintain the Settlement rule of the sender

4) Complete allocation structure

5) Asset under construction not completely credited.

Also any ideas as to how I can improve my PS knowledge would be appreciated; I have just started on the PS Module.

Page 58: SAP PS FAQ With Answers

**********

i can give you certain guide lines as to why these error occur. and their possible workarounds.. and i hope you can do some further analysis.

For 1) and 2)

The area 01 possibly represents your controlling area (for internal cost accounting). The total value (sum of all credits and sum of all debits on your WBS Level) is amounting to zero in a particular period (Fiscal Year Period). which is not allowed. You cannot capitalize an Asset from a Net negative value. Try changing the period or check to

see if the costs are negative using reports S_ALR_87013542 / S_ALR_87013543.

For 3)

You have not specified where the cost will be settled after the settlement run.

To specify this you have to select the WBS Element. follow menu path

Edit --> Cost --> Settlement. There you have to specify the object category such as a Cost Center or WBS Element (depends on your configuration and Business Processes) next you specify the settlement receiver (either the cost center value or a WBS value)

For 4)

The Cost elements from which the cost is to be transferred have not been defined in the allocation structure (in your PS Configuration). It happens like this e.g

CR DR

Page 59: SAP PS FAQ With Answers

WBS = C.P.011

CE = 90010555 5000 USD

Asset = Printer

Asset Account = 600008963 5000 USD

In the above example the within the allocation structure the Cost Elements are defined. In your case the Cost Element CE 90010555 must be missing. for that you need to add the CE to you Cost Element group which has been assigned in the allocation structure.

For 5)

The errors are mostly interdependent, by correcting the above mentioned discrepancies you might not get this error message. And in case it persists please specify the scenario which you are performing.

These are a few hints to get you started; you may also consult your PS Consult. in this regard.

NEED TO REVERSE SETTLEMENT TO ACU FOR PREVIOUS YEAR

We are looking for an easy way to reverse entries for last year that were settled to the Asset Under Construction Account (AUC is still open). These entries need to be re-coded as expense items instead of AUC settlement items. Is there any way to do this "after the fact" instead of going back and reversing the entire settlement process to re-do these entries?

******* Correction - That heading should read AUC instead of ACU

BOM IN PS MODULE

Page 60: SAP PS FAQ With Answers

I am a just a beginner in PS, my knowledge about is very humble. I d like you to enlighten me? I am looking for a knowledge about the BOM flow of PS module

Can we upload BOM through PS module for create Reservation and Purchase requisition by Drawing number.

I heard possibility in PP module.

PREREQUISITE TO IMPLEMENT PROJECT STOCK

What are the prerequisites/setting needs to be done if I want to implement project stock (Q)? Currently the requirement we release from project is direct PR (PR with account assignment N) or normal reservation.

We need a guide to make it happen

*******

1. First in your project profile: OPSA, or in the project header itself, set 'Project Stock' to either valuated or non-valuated project stock depending on financial requirements.

2. Check PS Config item: OPS8 set Proj Prio as '1'. In here you build a Procurement key which you attach to your network profile in OPUU to default in for your activity components. You do not need to default this in, but if you don't your users will be prompted define the requisition type when they allocate a component to a network. Reservations or PRs to a WBS will be in Project stock, ones to a Network will be in plant stock.

3. Also check OPT1 for the GI/GR movement type for Project stock normally 281/581 respectively.

Page 61: SAP PS FAQ With Answers

4. Also check the indiv/collective indicator on your Material Master MRP4 screen. It should be 1 - individual or blank.

On your material master accounting 1 screen, check your valuation class so that Consumption is to the project.

5. If all your material master settings are correct, when you look at your component screen, for example from CJ20N, on the Proc Parameter tab you should see the following settings:

Value Flow/Quantity flow

Acct.assig.cat. Q

Special stock Q

Valuation

Consumption P

Movement type 281

For External Activities (non-components) in PS, check config item: OPTT. AcctAssgnCatProjects should be 'Q'.

Benefits of Proj Stock is that you'll see all cost, esp. commitments, imediately ag your project.

One drawback is that project stock is kept in its own stock segments (which enables project based cost/inventory reporting) however, I have not found an MRP strategy that automatically lets me fulfill Proj stock requirements from plant stock. You have to perform the transfer movement into Proj stock in this scenario. Also availability check is not configurable to look at both project and plant stock.

REVENUE RECOGNITION BY BILLING TYPE - PROJECT SYSTEM/SD?

My company wants to change the way we recognize revenue on Time & Material Clients. Right now we recognize all projects by Percentage of Completion. But this is not correct for T&M Clients since Overhead, ESE, & G/A is included in there rates.

Page 62: SAP PS FAQ With Answers

We want....what is billed to be recorded as the revenue not Percentage of Completion on T&M clients. I'm thinking we need to change the Results & Analysis Key for those specific project types. If yes, how would I go about this?

Or would Results & Analysis be manual.

PROJECT ACTUAL COST STATEMENT

We use PS with WBS elements and Networks. As part of the monthly closing we run the settlement for the 1 Level WBS elements and all the cost is accumulated to the 1 Level WBS element from lower level networks and Activities.

Now we are unable to view any report through which we can view our project cost report at the WBS/Network level with respect to the cost elements. (Since all the cost has rolled up to the 1 WBS level after settlement).

Logically speaking i think when we structure our projects into WBS we should be able to monitor our costs and also be able to retrieve this information for historical purposes.

Presently this is the scenario

Before Settlement:

ID (COST) [Cost El.]

CX001 - Project

CX001 - WBS 1

CX001-01 - WBS 1.1 (Procurement)

Network 1 (1000 USD) [80001]

Activity 1

Page 63: SAP PS FAQ With Answers

CX001-02 - WBS 1.2 (Services) (2000 USD) [80001]

After Settlement:

ID (COST) [Cost El.]

CX001 - Project

CX001 - WBS 1 (3000 USD) [80001]

CX001-01 - WBS 1.1 (Procurement)

Network 1

Activity 1

CX001-02 - WBS 1.2 (Services)

We have used reports S_ALR_87013542/S_ALR_87013543 but are unable to assess cost for the various WBS/Networks at the Cost Element level after settlement.

*********

Try CNS41...

I hope you will be able to see the desired result...if you need further assistance kindly feel free to mail me.

******* If you are settling using original cost elements rather than secondary

settlement elements you will have this problem. If you want to view costs by cost element at the lower levels either change your settlement structures or use report CJI3 eliminating lines with Dr/Cr category of O and/or A.

Page 64: SAP PS FAQ With Answers

******** thanks for the help... it does show the cost, but i still have the same prob. that is after the settlement is run im not able to see the cost by Cost Element wise.

I have tried CJI3 but it does not show the Project Structure and shows a detailed set of line items which is not required.

Here is what is required:

1) Cost to be viewed Cost Element wise

2) Be able to select the Cost Elements or Cost Element Group as a selection parameter.

I’m sure Project Systems has a set of reports that can show the cost on the various project structures even after the settlement has been run.

********

Thanks, could you suggest what exactly do you think that requires to be changed in the settlement structures. I might ask my CO consult to look in this direction because presently we are unable to view cost by Cost Elements through any PS reports.

As far as I have seen we have an allocation structure defined as the settlement profile and that contains a Cost Element Group.

PS INTEGRATION WITH MM

On 4.7 and my goal is to integrate PS with MM or have network activity triggering the purchasing process through requisitions, purchase order, etc. I'm not creating any materials though, only using descriptions.

Page 65: SAP PS FAQ With Answers

I'm stuck with transaction CN21 - creating network, assigning external activities to be exact. I have checked the configuration transactions like OPUU, OPSP, OPSC, OPSU, OPUV, but whenever I enter the Cost Element value in the activity detail screen my

entry gets wiped out and I keep getting prompted to reenter it. I have already entered all the other inputs, but this one keeps from creating a requisition. Is this some kind of screen variant for network or something else? What is the validation here?

I have also checked accounting configuration (OBC4) and controlling (OKKP) configuration, but couldn't find anything whether about the PS integration or cost element setup.

Any PS/MM experts out there?

STOCK MATERIAL RESERVATION FOR WBS

I need urgent help to resolve one of our user requirements. The scenario is that a Project is created having only one WBS which has budget figure assigned to it (as well as Budget release). The requirement is to create reservation of stock material for the Project (WBS). Is it possible to create stock material reservation for WBS, if yes how can it be done?

(The reservation for stock material is possible for a network (activity) assigned to the WBS but we do not want to use Networks (activities) at all and want to make reservation against the WBS directly.

*******

You can do this as mentioned below.

1) Type TCode MB21 - This is a transaction code for creating a material reservation.

Page 66: SAP PS FAQ With Answers

2) After you type in TCode MB21 a screen will appear where in a FIELD "Movement type" will be there. In this field enter material movement type 221.This is a material movement type for a material from warehouse, for a project.

3) Afterward you will get a normal screen used for material reservation, wherein you will find a field

"WBS element". Here you enter a WBS element for which you want to create a reservation.

Hope this will serve you purpose.

LINE ITEM ANALYSIS

We are working with the materials supplied by the customer. Since materials are free supplied materials, so we keep the materials in non-valuated stores and issued to site sub-contractor.

Now management wants to create standard BOQ for each project and do the planned vs actual line item analysis.

Can any body help me how to analyze the planned vs actual line items as materials will be non-valuated items?

We are issuing materials from non-valuated stores. suppose if we define standard BOQ for project and want to do the analysis for planned vs actual line item consumption. How to do the same and by which TCode

STATUS OF WBS ELEMENT

Is there anyway of knowing the list of WBS elements and whether they are in TECO Status or not? I checked with Technically Complete Date (TADAT) in WBS Master Data Table (PRPS). But would like to know if there is any other field just for the status of WBS (like knowing the status as Release, Close etc)

************

Page 67: SAP PS FAQ With Answers

The table JEST contains the statuses applied to a given WBS element. Unfortunately, JEST uses Object Number from PRPS (not WBS Element Number) and stores statuses by code, so I typically, when using a tool like SQ01, have to join PRPS to JEST and possibly TJ02T (if I need the text for the status and not just the code - TECO has the code I0045 for example).

Another option is to use an overview like CN41 which has a column containing a list of all statuses by object in a project structure or structures.

***********

This is a good FM to use AIP9_STATUS_READ just feed it the Object number in the case of the WBS it will be PRxxxxxxx

give it a go see how you get on. I too used to go through all the messing with JEST, TJ02T TJ03t etc.... but this FM makes life easier.

********** Use report CN41 and use the choose fields option to show status.

********* Why not try FM 'GET_STATUS_FOR_PS_OBJECT_RFC',

You don't need to know the object number, you can find the status of any PS object by just passing the appropriate key i.e. project number, WBS number, network number, network and activity number or network number, activity number and activity element number.

PS – PROJECT / WBS COMPARISON REPORT

Is there any report in the PS module which will give the cost/detail comparison between the two projects / WBS?

Page 68: SAP PS FAQ With Answers

LINE ITEM ANALYSIS IN NON-VALUATED STOCK

We are working with the materials supplied by the customer. Since materials are free supplied materials, so we keep the materials in non-valuated stores and issued to site sub-contractor.

Now management wants to create standard BOQ for each project and do the planned vs actual line item analysis.

Can any body help me how to analyze the planned vs actual line items as materials will be non-valuated items.

---------------------------------------------------------------------------------------------------------

SALES ORDER TO PROJECT

I made a sales order for a specific material and project got opened automatically

can you tell me how SAP came to know that we have to open a project?

Where are the settings?

****** Your material is linked to a network. Check CN08.

PS BASIC QUESTION

I am in the process of studying FI-PS-SD integration for our client, who is in to the business of manufacturing.

Client is considering each customer order as a project for them. This is more like Make to order scenario.

In this implementation PS module is the driver.

I would like to know what's need to be done from SD side in this case apart from just assigning WBS element of the project to the sales order.

Page 69: SAP PS FAQ With Answers

Is there are some special item categories for which we can assign the WBS? How it gets linked to the Project? How the Data flows to it?

how is planning done? How do we settle the project against the Sales order

if any body has worked on such kind of project, Can he share his knowledge/document, which will be helpful for me for going ahead.

********

Generally you use assembly processing within the SD order to create the project and network subsequent structure. � The operative project is linked into the Order ==> Project Definition ==> And Network This is covered in detail the SAP Documentation on how to accomplish this Under Assembly Processing

COPY PS STRUCTURE

We use PS "Assembly Processing" to creat our projects when creating the SD order. A project structure is created and thereafter, Service Orders and all related activity is attached to the PS structure.

My question, once we create the project and all the related PM orders, we would like to change the PLANT at which all these activities are scheduled. The plant would need to be changed on SD, PM and PS, at least.

Business reason: We service Business Jets and sometimes the aircraft is scheduled to be serviced in AAA location but due to resources or other conditions, the aircraft will be serviced at BBB location.

Any Ideas?

PS COST REPORT PAINTER

Page 70: SAP PS FAQ With Answers

I would like to know if is it possible to obtain in a PS hierarchy and cost class detail all real/plan cost for a range defined by a Year-Period to Year-Period.

The standard S_ALR_87013542 when you put year 2004 and period range compares this period for each year instead considering the range and accumulate the cost that's what we need.

********** Access de RWCOOM table and the work around indicated on SAP NOTE 653930 to solve the hierarchy of WBS in this kind of reports.

SORT PS TEXT IN DESCENDING ORDER - COLUMN CREATED ON DATE

Appreciate if you can let us if it is Possible to sort PS Text by created (date) column in descending order

Scenario: Edit / Display a project in the project planning board (TCode; CJ2B or CJ2C). Select the WBS and use menu path -> Details -> PS text.

On the screen �PS text overview, if the Text Type is the same , then all the PS text pertaining to the WBS are sorted on the Description column in Alphabetical Order.

Is is possible to sort on the Created (date) column and in descending order ?

PS TEXT SORT BY CREATED DATE

I need urgent help to resolve a issue. We enter multiple PS text against WBS. The PS Text when displayed (PS Text Overview), when displayed is sorted alphabetical order.

The user requirement is that the PS text should be sorted by date created. Is it possible to achieve this and how can it be done.

Page 71: SAP PS FAQ With Answers

CONFIGURE NETWORK FOR COLLECTIVE PR

In my present configuration, when we booked the material through network, it gives reservation. Now we want to generate the collective PR for non-stock item.

How to configure the network profile so that, when we want to generate the PR, it should generate the collective PR for the same. Right no it gives individual PR for each line item,

********** If you go to transaction OPUV, in the configuration you will see where you can make a setting for your network parameters to do collective requisitions...

******** In the TCode OPUV, You have to check the "CollctveRequstn" checkbox to enable the generation of single requisition against multiple line items, also note that you will have to create a new network within the same WBS to create a new requisition. (if required)

LINE ITEM ANALYSIS {BOQ,CUSTOMIZATION}

We have two type of project one is trading and the second is non-trading type. In trading we create WBS and network and materials booked and issued from the valuated stores through reservation created through network. So in this case, we are able to do planned vs actual cost analysis using the transaction YFPSR

But in non-trading, we do not create any network and no reservation is created by the system. We directly post the material to WBS by creating manual reservation. The materials are issued through non-valuated stores. Now we want to create BOQ for trading and non-trading also, so that we can analyze the planned Vs actual line item in term of quantity (for non-trading), as materials are issued from non-valuated stores.

Is it possible to create BOQ for non-trading project and do the line item analysis for planned vs actual in term of numbers, and if yes, how changes have to be made in customization?

Page 72: SAP PS FAQ With Answers

POSSIBILITY OF TWO DIFFERENT PS CUSTOMIZING IN SAME CLIENT AND COMPANY

I am not a PS expert in SAP (only initiate!) and i'd like to know if it's possible to have two different project configuration in the PS module, for same client system, same company?

For instance it would be to enable to manage project on one way for spare parts projects, and on the other one for main assembly projects of the factory with products forecasts (which would then be used in SOP)..

I guess so but i am not sure!

**********

Yes you can very well do it.

A lot of flexibility exists by way of setting up different Project profiles. May you spell out the requirement a bit elaborately for support.

**********

Why don't you user two project profiles for this purpose and select the relevant one while executing the projects.

*********

I have advised the flexibility provided by project profiles to Matt and asked him to further elaborate his requirement so that further support can be given to him. Even though it seems you read the mail in a hurry and misunderstood the context thanks for your good intentions to support by advising.

Page 73: SAP PS FAQ With Answers

ACTIVITY WISE BUDGET ALLOCATION

Is it possible to allocate and release the budget activities wise? In present scenario, we allocate the budget at WBS level or you can say we allocate the budget to WBS.

The problem user is facing that we have activated availability check. The budget amount is combination of materials, services and road restoration. Some time, road restoration work consumes more than the estimated amount and in result; we are not able to use the materials for completion of work, as the control is at WBS level and not as activity level.

Please suggest the solution if possible.

CSER ERROR WHILE MATERIAL AVAILABILITY CHECK

Could any expert tell me how to get report which materials without info record maintained?

We created lots of material master in advance for selection of PR creation. Our material reservation through network (PS Module) need to find availability check.

System show CSER error while availability check.

DIFFERENCE BETWEEN INTERNAL & EXTERNAL ORDERS IN PP MODULE

Can any body tells me what is a difference between Internal & External order creation in SAP (Trans. KO01 & CO01)

PROGRESS ANALYSIS/RA/SETTLEMENT

I would like to know how do we do progress analysis and run RA .

I’ve created a project. Some activities with work centers, activity types, work centers.

Maintained RA keys.

Maintained progress version and measurement method for WBS ELEMENTS.

Went to CNE1 execute, then CNE5 i couldn’t find the values.

Page 74: SAP PS FAQ With Answers

When i go for KKA2/KKAJ am not getting values.

When i go to CJ88 it says no accured values so no settlement can be done.

Can any one of u guide me how to do Progress analysis, RA run and settlement please/..

-----------------------------------------------------------------------------------------------------------

VENDOR INVOICE CURRENCY

A Vendor is always invoiced in a foreign currency. While entering a vendor invoice the currency defaulted is the company code currency. The user forgets to change the currency. Is there a way to check or validate/substitute this so that the vendor currency is defaulted /pulled up always from the vendor master? At the time of invoice entry?

*********

Maybe you could have the field included in the list of fields that could be substituted (Class 008??). However, the next best thing that you could do is to create a fake substitution for a harmless field (the substitution should not change the field content nor

should there be any need for a change whatsoever for that field) through an exit. Use the exit to validate your requirement and issue an error message from within the exit if the validation fails. The exit should not change the field used for substitution. It is a bit crude, but could work.

PLAN COSTS OF THE PROJECT

I am creating a sales order via Va01 , project gets open automatically... I'm analyzing the report "S_ALR_87013531" Execute Drilldown Report Costs/Revenue/Expenditure/receipts ....in project System,

In this report each Activity wise Plan Costs are coming for the project. When I see the project each activity has Activity type assigned to it, and workcenter, duration, work....so .on

But I am not able to get from were are these plan cost are coming,,,,They are coming automatically as we are not feeding plan against the activity manually

Page 75: SAP PS FAQ With Answers

*********

Probably u have selected network costing. So it is calculating the plan cost

automatically

********

Can you explain me what is network costing???? I am new to PS?

*******

The Planned values are coming from the activity type cost/hour rate.

Go to KP26/KP27 and check the hourly rate and you will get picture clear.

SALES ORDER SETTLEMENT TO CO-PA

I have created a Sales order and then released the project and confirm some of the activities afterwards....

Now One of my milestone has been achieved and I have billed 30% to the customer and amount is has been posted in the Revenue G/L Account against the WBS Element...

Now I want to settle that amount to CO-PA as this month end is coming and rest I will do afterwards as I want the customer profitability for the month.

Page 76: SAP PS FAQ With Answers

I have created the Settlement rule via CJB2 (Generate Settlement Rule) and I have seen CJ02 Profitability segment got attached to the WBS Element

Now I am running settlement via CJ88, it is not posting the following message is coming and nothing is displaying

*********

From what I know of this process, the billing amount should already be in CO-

PA, you don't have to settle the revenue. I'd check my CO-PA report to see if

the amount is already there?

*********

You can try out with transaction KO88 & please let me know if this is possible or not. Actually it should have been possible with CJ88.

********

When you assign a A PROJECT TO SALES ORDER, Costs and revenue flows against a WBS element ,then you have to settle it to CO-PA

LINKING THE PS TABLES

my requirement is as follows. i need to find the network, aufk-aufnr, and activity, afvc-vornr if the user inputs the project definition (proj-pspid) in the selection screen.

Page 77: SAP PS FAQ With Answers

Or if the user inputs the network, aufnr, and activity, vornr, in th selection screen, need to findout whether that activity comes under the network entered.

how i can link the tables proj, aufk and afvc???

********

Proj-PSPID to Caufv-PRONR, CAUFV-AUFPL (routing no. which is an internal

number for network) to AFVC-AUFPL. AFKO and CAUFV are both keyed on AUFNR.

All the activity IDs for that network will be AFVC-VORNR. There's probably a

good function module to do this, e.g. BAPI_NETWORK_GETDETAIL will bring back

all activities for a Network

HOW TO COMPARE PLAN VS ACTUAL BY USING RESULTS ANALYSIS

My requirement is to determine between Plan cost and Actual cost and take the higher value for settlement at every period end until the project is completely closed. I was told that it can be done via 'Results Analysis" but I have no idea how. Please suggest.

********

CPSP Split plan cost try this IP31 maintain plan cost display

*******

Thanks a lot. But the bottom line is the result in actual cost and it has to be automatic.

Page 78: SAP PS FAQ With Answers

For example, WBS A01 has plan cost = $10,000, and actual = $2,000.

At the end of period 07 project is not finished so I want to settle actual in amount of $10,000 to reserve expense.

In other word, at the end of period 08 project is still not finished, WBS A01 has plan cost $10,000 and actual cost is changed to $13,000. The settlement amount must be $13,000. Please advice.

PERSON ASSIGNMENT IN PS

I define a work center with:

- Work center category 0003=Labor and

- Capacity category

PS TRANSPORTING SUBSTITUTIONS/VALIDATIONS

I have created a new substitution for WBS elements. How do I go about transporting this in SAP??

We normally use transaction SCC1 to move transports from our Customizing Client to our Playpen. Can I move a PS substitution using SCC1??

PROJECT MASKING CHANGES

We have been using a single value key code for the project mask. We have now got to the point where we will need to change this value from 1 letter to 2 or 3 letters. (we are running out of letters)

I changed this in the IMG & I also changed the the edit object to allow users to input using a mask or not. Lastly I made sure the structure length was not selected, so the users can use any combination of one, two or three letters.

Page 79: SAP PS FAQ With Answers

When I test in the system to use a letter that was structured with a mask before i.e.: "P:00000-XX-XXXX-XXXXXXXX" & try to use the letters PRJ:001 for my new project. I get the error # CJ608 that the project is not following the masking.

My Question is -

Once I have used a letter value in the system when the masking was set to a single letter, can I not reuse the same letter in combination with additional letters, when I change the mask length to multiple values?

********* The answer is no. Once you have used a letter, and a mask is defined for it, you cannot use that letter in the first position of another project id...

MATERIALS IN WBS ELEMENTS

We currently order all of our materials for projects thru networks. We have a new situation that requires the ordering of materials through WBS elements.

I have looked at creating a new set of screen tabs in "Define Layout of WBS Element Detail Screens" but I am unable to locate a detail screen for material assignments.

Do I have to import it from client 000, customize/create a new screen or what?

***********

At least up until SAP 4.70 enterprise, you don't order materials through a WBS. You can only allocate material components to a network activity. You can use Easy Cost Planning (from CJ20n) to unit cost plan a material and then invoke the execution services to turn that cost line item into a PR or PO (account assignment 'P' as defined in config).

Page 80: SAP PS FAQ With Answers

However, you can allocate material components to a network and have them in project stock (spec stock indicator + accntg assgnmt = 'Q'). Do this through the config for the Procurment indicator (img tcode: OPS8) and by setting the material master Collective/Individual indicator to Individual or Both.

********

use MB21 and Movement type 221 to order materials for the WBS element this is standard functionality and has been around since ver 3.x

AVAC ACTIVATED VIA CJ20?

Is there anybody know whether status AVAC can be activated via transaction CJ20?

My user said that he has gone through CJ20, then the AVAC status for WBS was activated accidentally. Unfortunately he can not remember what he has done in CJ20. I have looking for many possibilities in CJ20, but can not find any steps to activated the AVAC status.

Appreciate if you can give me input about this matter.

*********

It is simply not possible. The transaction has nothing to do with it.

What I feel is that you have activated Automatic AVAC in Budget Profile. The user may have given the budget to the WBS and then he has gone to see that Structure using the transaction cj20. There on the detail screen he would have seen the AVAC and for that he may be questioning.

-----------------------------------------------------------------------------------------------

Page 81: SAP PS FAQ With Answers

STATISTICAL PROJECTS

Is it possible to write a rule that will not allow you to save a statistical project unless the cost center is filled in on the Control tab? I would also like to have a rule that won=A1=AFt allow you to save a real project that has a blank cost center in the settlement rule (assuming the settlement rule is filled in)."

Can someone give me the step by step answer to the above. This is very urgent.

**********

Dear friend try OPSI and red a bit about validation it may serve your purpose

********

Try TCode OPUJ and make profit center mandatory for project definition. Hope this will solve your purpose.

*********

I don’t think you read and understood my question. Nav_jan already responded with something more viable. Why would I make Profit center mandatory for writing rules? Anyway, no need to answer. OPSI did the trick

FULL PAGE PRINT OF THE PROJECT GANTT CHART (CJ20N)

Page 82: SAP PS FAQ With Answers

How to get a full page print of the Project Gantt Chart from the Project planning board? The current Print out is centered on the page, covering just 25 % of the page. It looks more like a rectangle in the center of the page.

The margins are all set to 0, and i have already tried tweaking the various options in the Page setup ,but have still not been able to produce a Full Page print out. I'm very sure that PS Gantt chart can be printed on a full page just like in MS Project and other tools.

*********

Have you set the page to landscape? Since you said yours is centered, try changing the page alignment (in Page Setup). To make it bigger, play around with the scaling.

********

I may be missing your question, but=85In MS Project simply drag the Gantt all the way over to the left (printing in MSP is WYSIWYG). Go into page setup, Legend, select =93none=94. Plotters are best for printing the Gantt. You can configure each Gantt view independently to display tasks names, dates, resources, etc. on the Gantt bars.

TEXT DESCRIPTION FOR TIME BARS IN PROJECT PLANNING BOARD

One of my clients have a requirement where he requires some text description over the Time bars (Planned Vs Actual) in the Gantt Chart on the Project planning board.

This text will highlight some important information for that particular activity. Is it possible to place any textual information on the Project planning board for informational purposes?

Page 83: SAP PS FAQ With Answers

I am new in PS, can any body explain me the meaning of OV03, WM12, WM13, WM13A, WM13B and WM13D courses

Integration between SAP PS with other modules like FI/CO/MM/PM/SD/PP/HR

1) Resources (+)

• Work center --> PP MODULE

• Capacity planning and capacity evaluation

• Workforce planning to HR resource --> HR MODULE

• Confirmation and working time sheet -->HR MODULE

2). Material (+)

• Work breakdown structure BOM-->PP MODULE

• Component assignment in the network

• Material procurement through in-house production or external--MM MODULE

3) procurement --> --MM MODULE

• Collective stock and project stock -->--MM MODULE

• Requirements grouping ----MM MODULE

4) Costs and Budget (++)

• Cost planning in the work breakdown structure --> FI/CO MODULE

• Network costing --> FI/CO MODULE

• Budgeting and availability control -->FI/CO MODULE

Page 84: SAP PS FAQ With Answers

• Commitment and actual costs through account assignment and order assignment -->FI/CO MODULE

5). Revenue and Payments (+)

• Revenue and payment planning in the project -->FI/CO MODULE

• Sales pricing and quotation creation --> SD MODULE

• Resource-related billing --> SD MODULE

• Milestone billing and down payment processing--> SD MODULE

6) Period-End Closing (+)

• Interest calculation -->FI/CO MODULE

• Incoming orders -->FI/CO MODULE

• Settlement -->FI/CO MODULE

ake To Order:

Make-to-Order (Customer Requirements):

Creating a Sales Order

Checking Requirements Using MRP

Requirements Planning

Converting the Planned Order into a Production Order

Confirming the Production Order

Checking the Settlement of the Production Order

Creating a Delivery

Creating a Billing Document

Checking Costs and Revenues on the Sales Order

Page 85: SAP PS FAQ With Answers

Configuration Settings:

Create material master by maintaining general item category group- 0001(make to order)

Availability check - 02

Transportation Group - 0001

go to va01 and raise sales order

item category:TAk

Schedule line category : cp

Requirement type KE

Requirement class 040

Check TOR and avalability check

special stock : E

VOV7

of TAK

billing relivence : A

Pricing :X

go to mb1c

maintain stock with a special stock indicator E

mavement type 61

Special stock E

specify sales order number line item number and saveit

go to VL01N main data

Go to VF01

save it

Page 86: SAP PS FAQ With Answers

There are extensive options that enable you to procure components especially for specific sales order items.

You may, however, want to use a different planning strategy to procure components without sales orders. This allows you to keep your replenishment lead time to a minimum. You can do this by:

Planning on the basis of the finished product (see Planning Without Final Assembly (50) or Planning with a Planning Material (60))

Planning at component level (see Strategies for Planning Components)

Using consumption-based or Kanban-controlled components

Customer stock can exist on any BOM level. See Stockkeeping at Different BOM Levels for more information.

Because production is closely linked to sales orders, this results in a customer section in the stock/requirements list.

Unplanned goods receipts (such as returns) cannot, as a rule, be used for other sales orders, even if they are in working order, unless they are adapted to meet a customer's needs.

In the basic make-to-order strategy, Make-to-Order Production (20), no specific product structures are required. This means that it does not matter if the material has a BOM or not. The material can be produced in-house, or it can be procured externally. No planning is involved in this strategy.

Planning Without Final Assembly (50) and Planning with a Planning Material (60) do require a specific product structure (i.e. a BOM, which means materials are always produced in-house). These planning strategies assume that you want to plan procurement (production or purchasing) of your components by planning the finished products. This means that you need to have a fairly stable demand for your finished products. If, however, you can plan more easily at component level than at finished product level, see Strategies for Planning Components.

Refer to the following links:

http://www50.sap.com/businessmaps/092BF1DFEEB2456DADD0DD0284EBE8A2.htm

http://help.sap.com/saphelp_ides/helpdata/en/51/95368ea1fa11d189ba0000e829fbbd/content.htm

Page 87: SAP PS FAQ With Answers

http://help.sap.com/saphelp_ides/helpdata/en/51/95368ea1fa11d189ba0000e829fbbd/content.htm