royal lake dredging and restoration project update-june 2014
DESCRIPTION
Royal Lake Dredging and Restoration Project Update-June 2014TRANSCRIPT
Royal Lake: Meeting Agenda
Introductions and Opening Remarks Project Goal and Status Royal Lake Conditions Project Overview Site Access Dredging
– Phase I and Phase II– Dredging Alternatives
Lake Habitat and Shoreline Restoration Project Timeline Questions and Answers
Restore Sediment Pool Capacity– Downstream water quality benefits– Lake water quality– Aesthetics
Improve Lake Water Quality and Habitat Provide Long Term Maintenance Improvements
Project Goals and Benefits
Completed Data Collection Completed Lake Dredging and Management Plan Design Plans and Specifications
– Preliminary Design – Completed
– Final Design – Current design phase Permitting – In Progress Late 2014/Early 2015 – Complete Final Design and Permitting Dredging Projected to Start in Late Summer, 2015
Royal Lake: Project Status
Royal Lake Facts
Drainage Area = 2,477 acres (3.67 square miles)
Lake Surface Area = 37.5 acres
Sediment Pool Capacity = 416,000 cubic yards (CY)
Current Sediment in Lake = 103,000 CY*
Estimated Annual Sediment Load = 4,400 CY
50 feet
103,000 CY
* Based on a 2013 bathymetric survey
Royal Lake: Sediment Thickness
Royal Lake: Water Depth
Royal Lake: Sediment Sampling Results
Samples were analyzed for chemicals found in typical urban environments
All tests indicated significantly lower concentrations than state limits except for Arsenic
Nitrogen and Phosphorous levels were elevated With dredging of 103,000 CY:
– Approximately 8,500 lbs of Phosphorous will be removed– Approximately 102,000 lbs of Nitrogen will be removed
Total Wetlands Impact:– 0.85 Acre
All impacts within original footprint of lake
Royal Lake – Wetland Impact
Project Overview
Staging Areas
Sediment Forebays Lake grading to restore the original bottom elevation
Site Access and Staging
Access During Construction
Public Access: The park will remain open and existing parking lot will be available.
Access During Construction
Public Access: Pedestrian gates will be provided. Access through work areas and trails around the lake will be possible after work hours.
Staging Area 1 Potential Expansion
Berm/Cofferdam to be built
Area to be dewatered and backfilled to expand staging area after berm/cofferdam is built
Royal Lake: Dewatering Basin
Inactive dewatering basinto be filled in and restored
Staging area potential
expansion
Phase I and Phase II Dredging
PHASE II48,000 CY
PHASE I15,000 CY
PHASE I40,000 CY
Dredging Alternatives
1. Wet Dredging: Mechanically dredge deposited sediment and haul wet. Normal pool maintained. (Note: This option will still require lake drawdown for a short period of time to build the forebay berms)
2. Dry Dredging: Drain the lake and dry deposited sediment in place prior to hauling
3. Project will be bid out with the option to dredge wet or dry
Partial drawdown for Phase I dry dredging: drawing the lake partially to the Phase I dredging limits would leave a 15 acre pool; sediment would be dried in the dewatered section of the lake in place prior to hauling. Approximately 1/2 of the deposited sediment volume would be removed.
General Sequence– Establish access and staging areas– Conduct dredging utilizing barges– Haul wet sediment to disposal site
for drying
Pros– Less weather dependent– Quicker initial start to dredging– Less potential for schedule
extensions or delay
Concerns– Increased sediment handling effort
at disposal area– Potentially higher cost
Wet Dredging
General Sequence– Initiate drawdown of lake– Establish access and staging areas– Establish diversion channels within lake– Conduct dredging
Benefits– Higher daily sediment removal rates– Minimal sediment handling effort at disposal
area– Potentially lower cost
Concerns– Very weather dependent– Higher potential for delays due to weather– Even with a reduced pool, there will be a need
to relocate/salvage fish
Dry Dredging (Full or Partial Drawdown)
Royal Lake: Partial Drawdown
A partial drawdown would leave 15 acre pool with a maximum depth of 8 feet
Sediment to be removed = 55,000 CY
DRAW-DOWN 55,000 CY
Huntsman Lake (29 acres)
Huntsman Lake – Currently being dredged in the dry
Huntsman Lake Dam Rehabilitation Project Fish Relocation (May, 2013)
Huntsman Lake Improvements
forebay
forebay berms
dam embankment
Phase I dredging limits (34,500 CY)
Huntsman Lake Improvements
Huntsman Lake Dredging June, 2014
In-lake forebay Wetland planting Shoreline stabilization Fish habitat Fish stocking
Royal Lake Restoration
Fish habitat created from salvaged trees
Lake Barton: Fish stocking by Virginia Game and Inland Fisheries
Royal Lake: Shoreline Restoration
Shoreline Protection
Fish Habitat Structures
Community coordination at design and construction phase– Pardon Our Dust meeting to be scheduled after contractor selection
Late 2014/Early 2015: Complete final design Spring 2015: Bid advertisement Late summer 2015: Begin dredging Project Duration:
– Phase 1, Base Dredge: Dredge approximately 55,000 CY = 5 to 6 Months
– Phase 2, Full Dredge: 9 to 12 Months (total)
Lake may be drained/partially drained for project depending on bid results For the wet dredge option, the lake will still require lowering for a short period
to construct the forebays
Royal Lake Dredging and Restoration Project Timeline and Coordination
Contacts:Martin Chang [email protected] [email protected] [email protected]
Stormwater Planning DivisionFairfax County DPWES(703)324-5500, TY 711
Partners:
Royal Lake Dredging and Restoration