royal lake dredging and restoration project: pardon our dust meeting may 9, 2016

63
A Fairfax County, VA, publication Department of Public Works and Environmental Services Working for You! Royal Lake Dredging and Restoration Project Pardon Our Dust Meeting May 9, 2016

Upload: fairfax-county

Post on 22-Mar-2017

1.364 views

Category:

News & Politics


0 download

TRANSCRIPT

Page 1: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

A Fairfax County, VA, publication

Department of Public Works and Environmental Services

Working for You!

Royal Lake Dredging and Restoration ProjectPardon Our Dust Meeting

May 9, 2016

Page 2: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

2

Royal Lake Dredging and Restoration

Agenda • Opening Remarks – Supervisor Cook

• Project Background - Stormwater Planning Division– Background– Major Project Elements– Summary of previous Pohick watershed dredging projects –

Lake Barton, Huntsman Lake, and Woodglen Lake

• Maintenance of Traffic, Trail Management, Tentative Construction Schedule – ASI Constructors

• Royal Lake Biology and fish save efforts – Stormwater Planning Division

• Construction Timeline Summary and Safety during construction – Stormwater Planning Division, Utilities Design and Construction Division, Park Authority

• Q&A

Page 3: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

3

Royal Lake Dredging and Restoration

Royal Lake – Quick Facts

• Drainage area = 2,477 Acres (3.67 square miles)

• Lake surface area = 37.5 acres

• Sediment pool capacity = 416,000 cubic yards (CY)

• Current sediment in lake =100,400 CY

• Estimated annual sediment load =4,400 CY / year 50 feet

100,400 CY

Page 4: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

4

Royal Lake Dredging and Restoration

Items of Work Dredging up to 51,220 CY of sediment (Phase I area) Access road improvement Demolition of the existing decanting basin fence and dewatering

structures Regrading of the existing decanting basin Temporary construction of a staging area and safety fence E&S and Control of Water measures Construction of two sediment forebay berms/weirs Construction of 340 feet of shoreline stabilization Construction of 130 feet of stream bank stabilization Installation of one new ACB ramp Replacement of an existing boat ramp with ACB ramp Installation of 65 fish habitat structures Restoration, seeding and landscaping of disturbed areas

Page 5: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

5

Royal Lake Dredging and Restoration

Scope of Work

A1 A2

B2B1

Zone Volume (CY)

A1 33,500

A2 5,600

B1 12,000

B2 3,800

Page 6: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

6

Royal Lake Dredging and Restoration

Water Depth

Page 7: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

7

Royal Lake Dredging and Restoration

Grading Plan

Page 8: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

8

Royal Lake Dredging and Restoration

Grading Plan

Page 9: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

9

Royal Lake Dredging and Restoration

Sediment Disposal Site – I-95 Landfill Complex

Page 10: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

10

Royal Lake Dredging and Restoration

Alternate disposal site – Noman Cole Pollution Control Plant

Page 11: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

11

Royal Lake Dredging and Restoration

Decanting Basin Restoration

Restored Decanting Basin

Page 12: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

12

Royal Lake Dredging and Restoration

Royal Lake – Riser Modifications, Existing and Proposed Lake Bottom

• The riser modifications will facilitate drawdown for future maintenance dredging and also includes a deep water release mechanism for improving downstream water quality.

• Proposed lake bottom will restore the estimated original contours and depth of the lake (in Phase I area).

Page 13: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

13

Royal Lake Dredging and Restoration

Shoreline Restoration: Existing Condition

Page 14: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

14

Royal Lake Dredging and Restoration

Shoreline Protection

Page 15: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

15

Royal Lake Dredging and Restoration

Placement of Fish Habitat Structures

TREE BRANCH PILES

Rock Rubble Piles

Page 16: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

16

Royal Lake Dredging and Restoration

Stream Stabilization

Page 17: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Pohick Creek Dredging and Lake Restoration Projects

Project Goals• Restore sediment pool capacity

– Downstream water quality benefits– Aesthetics

• Improve lake water quality and habitat• Provide long term maintenance improvements

Lake Barton: 2011Huntsman Lake: 2014Woodglen Lake: 2015Royal Lake: 2016

Page 18: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Sources of Sediment

Page 20: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Lake Barton Dredging in Progress

Page 21: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Disposal Site – Sediment Reuse

• Topsoil for landfill cover• Topsoil product for resale

Page 22: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Huntsman Lake Dam Rehabilitation Project Fish Relocation (May 2013)

Page 23: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Huntsman Lake - Forebays

bank stabilizationaquatic bench

forebay

forebay berms

maintenance access

sanitary sewer

dam embankment

Page 24: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

24

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 25: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

25

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 26: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

26

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 27: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

27

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 28: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

28

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 29: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

29

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 30: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

30

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 31: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

31

Royal Lake Dredging and Restoration

Some Photos from the Huntsman Lake Dredging Project

Page 32: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

32

Major Project Elements

Improved access road

Sediment forebayLake dredging,

shoreline restoration, lake habitat improvement

Removal and restoration of decanting

basin

Reforestation areas

Stream stabilization

Riser modifications

Page 33: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

33

Lake Drawdown

Page 34: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

The Lake After Draining

Page 35: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch

Sediment Near the Forebay – To Be Removed

Page 36: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch

Sediment Being Loaded

Page 37: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016
Page 38: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

http://www.pwmag.com/erosion-control/dredging-up-savings_o_3.aspx

Page 39: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch

Forebay Berm

Page 40: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

Modifications & Repairs – Principal Spillway Riser

Page 41: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

Capital Facilities / Utilities Design and Construction Division / Transportation and Stormwater Construction Branch

Stream Restoration Work – Lake Inlet

Page 42: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

42

Royal Lake Dredging and Restoration

Site Access and Maintenance of Traffic Plan

Pommeroy Drive Access Point

Gainsborough Drive Access Point

Page 43: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

43

Royal Lake Dredging and Restoration

Neighborhood Truck Route

Page 44: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

44

Royal Lake Dredging and Restoration

Trail Management Plan

Page 45: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

45

Royal Lake Dredging and Restoration

Royal Lake Biology • Reptiles and Amphibians• Fish• Benthic organisms (bottom layer)

– Birds & mammals feeding on mussels

Page 46: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Frogs and Toads

46

http://www.fcps.edu/islandcreekes/ecology/bullfrog.htm

https://www.flickr.com/photos/dah_professor/3674098110/

http://capeannvernalpond.org/american-toad/

http://www.virginiaherpetologicalsociety.com/identification-keys/id-keys-frogs/Pseudacris.html

Page 47: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Frog/toad response to prior lake de-watering

• Huntsman Lake– “Never have I seen such a plague of toadlets.”

(Resident in Huntsman area)

• Bradley Acres Pond– Retrofitted SWM Wet pond– “It’s biblical,” said a resident

• Predaceous diving beetles• Toads and toadlets• 5-lined skinks

47

Page 48: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Turtles

48http://www.virginiaherpetologicalsociety.com/reptiles/turtles/yellow-bellied-slider/Yellow-bellied%20Slider%20(Trachemys%20scripta).jpg

http://www.virginiaherpetologicalsociety.com/reptiles/turtles/northern-red-bellied-cooter/northern_red-bellied_cooter.php

http://www.virginiaherpetologicalsociety.com/reptiles/turtles/turtles_of_virginia.htm

http://www.virginiaherpetologicalsociety.com/reptiles/turtles/red-eared-slider/red-eared.JPG

Page 49: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes – Electrofishing

49

Page 50: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes – Electrofishing

50

Page 51: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes – Electrofishing

51

Page 52: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes

52

Page 53: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes

53

Page 54: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes

54

Page 55: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Fishes - Release

55

Page 56: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

56

Freshwater Mussels – Mussel Life Cycle

http://www.fishwild.vt.edu/mussel/research/life_history.html

Page 57: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Pyganodon cataracta and Utterbackia imbecilis

57

Eastern FloaterP. cataracta

Paper PondshellU. imbecillis

Page 58: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

Woodglen Lake Dredging and Restoration

Project Benefits

• Removed over 40,000 CY of sediment• Facilitated future maintenance dredging operations by:

• Providing a 9,000 CY sediment forebay• Improving the existing access road• Providing truck staging areas

• Provided improvements and repairs for the principal spillway riser• Installed fish habitat structures within the lake• Provides the following annual (estimated ) reductions in the downstream

sediment and nutrient loadings:• Total Suspended Solids (TSS) 14.6 tons/year• Total Nitrogen (TN) 1,075 lbs/year• Total Phosphorus (TP) 67 lbs/year

Page 59: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

59

Royal Lake Dredging and Restoration

• Lake drawdown Scheduled to begin week of May 9th (this week!)

• Dredging activities to commence by mid-June, 2016• Project duration: 12 months• Lake will remain mostly drained for entire project• Lake filling after project completion is dependent on

rainfall conditions, and it is expected filling will be initiated by June, 2017

Summary of construction timeline

Page 60: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

60

Royal Lake Dredging and Restoration

Lake Drawdown and Safety

Page 61: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

61

Royal Lake Dredging and Restoration

Lake Drawdown and Safety

Page 62: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

62

Royal Lake Dredging and Restoration

Safety During Construction

• Contractor is required to comply with Fairfax County’s Construction Safety Resolution.

• For all residents, keeping safe means following two simple rules:

1. Please stay outside the construction limits at all times!2. Observe construction activities from a safe distance.

Page 63: Royal Lake Dredging and Restoration Project: Pardon Our Dust Meeting May 9, 2016

63

Royal Lake Dredging and Restoration

Contact information

Stormwater Planning Division 703-324-5500, TTY 711 or by email: Joe Riley-Ryan: [email protected] Dipmani Kumar: [email protected]

Utilities Design and Construction Division703-324-5111, TTY 711 or by email:Bill Nolan: [email protected]

Thank you.