Page 1: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 2: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 3: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

River-channel for:• Monsoon floods/sewerage disposal of Karachi.

Construction of Lyari Expressway:• Unauthorized settlements along “Right-of-Way” on banks/ river bed. Relocation of affectees :• To create space for construction of Expressway• To provide better living environment• Allotment of 80 Sq. yds. Plot per unit free of cost and

cash Compensation @ Rs. 50,000/- per family unit.

Page 4: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 5: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 6: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 7: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

Displaced from Resettled atUpper reach

• Gulshan Town• Gulberg Town• Liaquatabad Town• Scheme-33

• Taiser Town, Scheme-45

Middle reach• Site Town • Hasan Olia Village• Mianwali Colony

• BaldiaTown , Scheme-29

Lower reach • Keamari Town • Saddar Town • Lyari Town • Jamshed Town

• Hawksbay, Scheme-42

Page 8: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 9: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

First Stage Initial Surveys… by Revenue Group of Offices, CDGK

Second Stage Verification of Survey Lists …..by Team of Revenue Department in collaboration with public representatives.

Third Stage Re-verification ….by the Committee comprising of larger group of Revenue officers & public representatives.

Fourth Stage Payment of cash compensation and allotment of 80 sq yds plot (free of cost) to the affectees as per verified survey lists of Revenue Department, CDGK in open katchery ……..by the LERP.

Fifth Stage Payment of compensation of leased property under the law…..by the Revenue Department CDGK.

Page 10: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

Name of Resettlement siteArea

(Acres)

Planned Plots

(80 Sq. yards)

Hawksbay Scheme-42 Sectors- 6, 9 & 10 218 5984

Taiser Town Scheme-45 Sectors-35, 36, 36-A & part of Sector 50,51

667 16153

Baldia Township Scheme-29 Sector-21B 144 2924

Lastly added areas at Taiser Town for accommodating revised 30011- family units (under development)

( Less)

Total

205

1234

-(20)

1214

5520

30581

-(550)

30031

Page 11: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

The affected family units from 14,811 (Original PC1) to 24,419 (Revised PC1) and 30011 (Re-revised PC-I) as communicated by the Revenue Department, CDGK, were revised which attributed to the following reasons:-

i.The decision of High Court to count each Level of Multi-storied Building as a Separate Unit.

i.Difference in Initial & Final Survey List by counting of number of families per premises “one family” instead of treating them as Single Unit.

i.Changes in the Right-of-Way of LEW by the N.H.A

Commercial units (not compensated) Religious Buildings include 56-Mosques, 6-Imam Bargahs &

9-Churchs & 1- Temple (relocated).

Page 12: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

Name of Resettlement siteArea

(Acres)

Planned Plots

(80 Sq. yards)

Hawksbay Scheme-42 Sectors- 6, 9 & 10 218 5984

Taiser Town Scheme-45 Sectors-35, 36, 36-A & part of Sector 50,51

667 16153

Baldia Township Scheme-29 Sector-21B 144 2924

Lastly added areas at Taiser Town for accommodating revised 30011- family units (under development)

( Less)

Total

205

1234

-(20)

1214

5520

30581

-(550)

30031

Page 13: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 14: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 15: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 16: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 17: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 18: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 19: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 20: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 21: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 22: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 23: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 24: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 25: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 26: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 27: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 28: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 29: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 30: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 31: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 32: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 33: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 34: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 35: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 36: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 37: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 38: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 39: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks
Page 40: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

1. No funds have been released since 2008-09.2. Non availability of funds for the past years created a collapse like situation and has

taken over the Project as:-

a. Development works stopped for non clearance of the liabilities.b. Schooling discontinued for more than 6500 students due to non-payment of salaries to community teachers.c. Karachi Electric Supply Company Limited issued disconnection notices to resettlement sites resulting in stoppage of water supply for developed and undeveloped resettlement sectors.e. No salary paid to Project staff for the last 1 year.

3. Requests to Governments for provision of funds remained un-responded.

4. More than 500 affectees have filed Constitutional Petitions in the High Court of Sindh against Federal, Provincial & CDGK, as their names were appearing in the list of the affectees prepared by the Revenue Office, CDGK. It was intimated to the Court that no funds have been received from the Government and so no facilitation money could be paid to the affectees.

Page 41: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks

• Clearance of remaining 5.3km of LEW-ROW & liabilities.

• Clearance of created liabilities of allotment of 80-Sqyds plot/family-unit and corresponding award of Normal Compensation Package.

• Permission / Decision from the Government to hand over different sectors like sanitation, water supply, sewerage, schools, streets lights, roads etc. to relevant Departments/Organizations for day to day maintenance.

• Permission of the Government to prepare “Status Position” & “Completion Report”, so that project can be wind up, as it is not possible to continue the project without funds.

Page 42: River-channel for: Monsoon floods/sewerage disposal of Karachi. Construction of Lyari Expressway: Unauthorized settlements along Right-of-Way on banks