ANNEXURE 2 SB Page 1 of 6 DIFFERENT NATURE OF PROJECTS HANDLED 1. CONSULTING & DESIGN ENGINEERING FOR URBAN UTILITY SYSTEM DEVELOPMENT: Development of Bangalore Water Supply & Sewerage System Stage IV, Phase 2 Role & Employer : Project Engineer, Tata Consulting Engineers Ltd. Client & Duty Location : Bangalore Water Supply & Sewerage Board, Mumbai & Jamshedpur, India Duration : Jan. 2009 to Feb.2014 Nature of Activity : Office based Consulting Engineering & Project Management Consultancy Project Background & Features : This project envisaged augmenting water supply to Bangalore City by an additional 500 MLD to improve the per capita water supply from 105 to 150 L and to increase the waste water treatment facility from 650 MLD to 1053 MLD by installing waste water treatment facilities of 405 ML capacity. This task also comprised of distribution improvement component which aims to reduce the unaccounted for water from the present values to 16% in an area of about 300 Sq. Km covering 3 lacs connections. Development of Solid Waste Management & Treatment Facility at Taloja, Maharashtra Role & Employer : Project Engineer, Tata Consulting Engineers Ltd. Client & Duty Location : Mumbai Metropolitan Regional Development Authority (MMRDA) ,Jamshedpur, India Duration : Jan. 2009 to Aug. 2010 Nature of Activity : Office based Consulting Engineering & Project Management Consultancy Project Background & Features : MMRDA in association with National Environmental Engineering Research Institute (NEERI) has conceptualized a first of its kind regional landfill site with an integrated Solid Waste Management & Treatment facility at Taloja, Maharashtra, catering to 13 urban local bodies. TCE was appointed to carry out techno commercial feasibility for this development by providing best combination of available technologies for Solid Waste Management and processing in line with legal, commercial and technological viabilities. Development of Sewerage System under - Nabadiganta Water Management Limited, Kolkata Role & Employer : Manager Process Design ,Jamshedpur Utility & Service Company Ltd. Client & Duty Location : Nabadiganta Water Management Limited (Kolkata), Jamshedpur, India Duration : October,2009 to Jan.2012 Nature of Activity : Office based Design Engineering & EPC supporting Project Background & Features : The system has a capacity to handle 3 Million Gallons of Water per Day to serve about 2.3 Lakh populations. This development comprised of development of a Sewage Treatment Plant of 2 MGD capacity, an intermediate pumping station and sewer line network spread for 18 km. Refurbishment of Sewage Treatment Plant in Bara, Jamshedpur Role & Employer : Project Manager Construction, Jamshedpur Utility & Service Company Ltd. Client & Duty Location : Internal Project, Jamshedpur Duration : April,2010 to Dec.,2010 Nature of Activity : Site Based Project Management of Construction Project Background & Features : 45MLD capacity Sewage Treatment Plant based on Conventional Activated Sludge Process with sludge handling facilities like Anaerobic Sludge Digestion and Centrifuge for dewatering. The objective of this task was to recover from the frequent upset caused in the biological treatment system. Development of Sewage Treatment Facility in Pakyong, Sikkim, India Role & Employer : Project Manager, JB Enviro Consultants Pvt. Ltd. Client & Duty Location : The Water Security & PHE Department, Govt. of Sikkim, Pakyong, Gangtok(Sikkim) & Kolkata, India Duration : Ongoing ( Status : DPR has prepared & submitted ) Nature of Activity : Office based Consulting Engineering & Project Management Consultancy Project Background & Features : The only airport of the state of Sikkim is in the process of development in Pakyong near Gangtok. To serve the existing community and the potential community growth, 3 sewage treatment plants and sewer line network was planned to be developed. JBECPL has been deployed as an engineering consultant for this job. The DPR has already been submitted for. Three STP having capacity of 8, 5 & 5.5 MLD was proposed. Plotting sewer line & STP in the uneven contour of mountain area of Pakyong is the real challenge associated with this job.

Upload: banerjee-suvranil

Post on 20-Feb-2016

5 views

Category:

Documents


0 download

DESCRIPTION

Resume of an Environmental Engineering professional with 14 years of experience

TRANSCRIPT

Page 1: Resume SBN 11 16

ANNEXURE 2SB

Page 1 of 6

DIFFERENT NATURE OF PROJECTS HANDLED

1. CONSULTING & DESIGN ENGINEERING FOR URBAN UTILITY SYSTEM DEVELOPMENT:

Development of Bangalore Water Supply & Sewerage System – Stage IV, Phase 2

Role & Employer : Project Engineer, Tata Consulting Engineers Ltd.

Client & Duty Location : Bangalore Water Supply & Sewerage Board, Mumbai & Jamshedpur, India

Duration : Jan. 2009 to Feb.2014

Nature of Activity : Office based Consulting Engineering & Project Management Consultancy

Project Background & Features :

This project envisaged augmenting water supply to Bangalore City by an additional 500 MLD to improve the per capita water

supply from 105 to 150 L and to increase the waste water treatment facility from 650 MLD to 1053 MLD by installing waste water

treatment facilities of 405 ML capacity. This task also comprised of distribution improvement component which aims to reduce

the unaccounted for water from the present values to 16% in an area of about 300 Sq. Km covering 3 lacs connections.

Development of Solid Waste Management & Treatment Facility at Taloja, Maharashtra

Role & Employer : Project Engineer, Tata Consulting Engineers Ltd.

Client & Duty Location : Mumbai Metropolitan Regional Development Authority (MMRDA) ,Jamshedpur, India

Duration : Jan. 2009 to Aug. 2010

Nature of Activity : Office based Consulting Engineering & Project Management Consultancy

Project Background & Features :

MMRDA in association with National Environmental Engineering Research Institute (NEERI) has conceptualized a first of its kind

regional landfill site with an integrated Solid Waste Management & Treatment facility at Taloja, Maharashtra, catering to 13

urban local bodies. TCE was appointed to carry out techno commercial feasibility for this development by providing best

combination of available technologies for Solid Waste Management and processing in line with legal, commercial and

technological viabilities.

Development of Sewerage System under - Nabadiganta Water Management Limited, Kolkata

Role & Employer : Manager – Process Design ,Jamshedpur Utility & Service Company Ltd.

Client & Duty Location : Nabadiganta Water Management Limited (Kolkata), Jamshedpur, India

Duration : October,2009 to Jan.2012

Nature of Activity : Office based Design Engineering & EPC supporting

Project Background & Features :

The system has a capacity to handle 3 Million Gallons of Water per Day to serve about 2.3 Lakh populations. This development

comprised of development of a Sewage Treatment Plant of 2 MGD capacity, an intermediate pumping station and sewer line

network spread for 18 km.

Refurbishment of Sewage Treatment Plant in Bara, Jamshedpur

Role & Employer : Project Manager – Construction, Jamshedpur Utility & Service Company Ltd.

Client & Duty Location : Internal Project, Jamshedpur

Duration : April,2010 to Dec.,2010

Nature of Activity : Site Based Project Management of Construction

Project Background & Features :

45MLD capacity Sewage Treatment Plant based on Conventional Activated Sludge Process with sludge handling facilities like

Anaerobic Sludge Digestion and Centrifuge for dewatering. The objective of this task was to recover from the frequent upset

caused in the biological treatment system.

Development of Sewage Treatment Facility in Pakyong, Sikkim, India

Role & Employer : Project Manager, JB Enviro Consultants Pvt. Ltd.

Client & Duty Location : The Water Security & PHE Department, Govt. of Sikkim, Pakyong, Gangtok(Sikkim) & Kolkata, India

Duration : Ongoing ( Status : DPR has prepared & submitted )

Nature of Activity : Office based Consulting Engineering & Project Management Consultancy

Project Background & Features :

The only airport of the state of Sikkim is in the process of development in Pakyong near Gangtok. To serve the existing

community and the potential community growth, 3 sewage treatment plants and sewer line network was planned to be

developed. JBECPL has been deployed as an engineering consultant for this job. The DPR has already been submitted for.

Three STP having capacity of 8, 5 & 5.5 MLD was proposed. Plotting sewer line & STP in the uneven contour of mountain area

of Pakyong is the real challenge associated with this job.

Page 2: Resume SBN 11 16

Page 2 of 6

Development of Sewage Treatment Facility in Champdani Town, Hooghly, West Bengal, India

Role & Employer : Project Manager, JB Enviro Consultants Pvt. Ltd.

Client & Duty Location : Kolkata Metropolitan Development Authority (KMDA), Hooghly, West Bengal & Kolkata, India

Location : Champdani, Hooghly, West Bengal, India

Duration : March,2014- May2015

Nature of Activity : Office based Consulting Engineering & Project Management Consultancy

Project Background & Features :

The National Ganga River Basin Authority (NGRBA), India has decided that no untreated municipal wastewater and industrial

effluents would be allowed to enter River Ganga after 2020 under “Mission Clean Ganga”. Kolkata Metropolitan Development

Agency (KMDA) has been identified as the nodal agency for implementing the objectives of NGRBA in the State of West Bengal.

JBECPL has been deployed by KMDA to provide the necessary engineering consultancy services for preparation of a DPR and

submission to NGBRA. A centralized sewage treatment facility estimated at 15.5 MLD having Sequential Batch Reactor (SBR)

was proposed in Champdani of Hooghly district in the state of West Bengal. Wastewater will be treated to tertiary level treatment

before disposal to nearby DVC canal with provision of reuse of the effluent is provided.

Development of Storm Water Drainage Scheme for Jalpaiguri Town, West Bengal, India

Role & Employer : Project Manager, JB Enviro Consultants Pvt. Ltd.

Client & Duty Location : Jalpaiguri Municipality, Jalpaiguri Town, West Bengal & Kolkata , India

Duration : March,2014- Nov.2014

Nature of Activity : Office based Consulting Engineering & Project Management Consultancy

Project Background & Features :

Jalpaiguri is located in the plains of North Bengal by the right bank of river Tista. Occasional flooding has been and still is a

chronic problem in Jalpaiguri. During monsoon, a vast area near the State Highway becomes inundated and plinths of many

houses remain submerged for hours together. Such water-logging results sufferings of people and causes outbreak of various

diseases during this season. JBECPL has been engaged by Jalpaiguri Municipality to provide the necessary consultancy

services for preparation of a DPR for development of storm line network.

2. CONSULTING & DESIGN ENGINEERING FOR INDUSTRIAL POLLUTION CONTROL SYSTEM DEVELOPMENT:

Capacity augmentation of Coke Plant Effluent Treatment system of Tata Steel

Role & Employer : i. Consultant side Project Engineer for Tata Consulting Engineers Ltd. ii. Internal consultant - Project Management, Jamshedpur Utility & Service Company (JUSCO) Ltd. iii. Client side internal engineering consultant for Tata Steel Ltd.

Client & Duty Location : Tata Steel Ltd., Jamshedpur, India

Duration : Nov.2008 to Sept. 2012

Nature of Activity : Site based Consulting Engineering & Project Management Consultancy.

Project Background & Features :

Steel making capacity rise (5 MTPA to 10 MTPA) of Tata Steel caused increased demand of coke. This demand rise was

planned to be supported by augmentation of existing coke oven batteries and installation of some new batteries. This ensured

higher waste water generation from coke oven plant in increased production scenario. The existing ETP was supported with

double stage activated sludge process and clarification unit and its design capacity was 120 m3/hr where as the existing

operating load was 75 m3/hr. The future expansion extrapolated nearly 225 m

3/hr of waste water generation. So the ETP was

planned for augmentation with the above mentioned scope in a difficult brown-field environment. Tata Consulting Engineers Ltd.

was deployed as the Consulting Engineer & JUSCO was deployed as the local sub-contractor of Advent for this project. Advent,

USA was the technology supplier.

Development of new Effluent Treatment Plant at Cold Rolling Mill, Bara of Tata Steel

Role & Employer

:

i. Consultant side Project Engineer for Tata Consulting Engineers Ltd. ii. Internal consultant - Project Management, Jamshedpur Utility & Service Company (JUSCO) Ltd. iii. Client side internal engineering consultant for Tata Steel Ltd.

Client & Duty Location : Tata Steel Ltd., Jamshedpur, India

Duration : Jan. 2009 to Feb.2014

Nature of Activity : Site based Consulting Engineering & Project Management Consultancy

Project Background & Features :

Tata Steel has developed a Cold Rolling Mill of 2.5 MTPA capacity along with 0.5 MTPA push pull hot role pickling line. 0.5

MTPA acid regeneration plant and Roll Grinder at Bara factory in Jamshedpur. TCE was deployed as the Consulting Engineer

for this project. An ETP of 80 m3/hr capacity was installed in this project by Voltas.

Capacity up gradation of Air Pollution Control System in Tata Steel

Role & Employer : i. Consultant side Project Engineer for Tata Consulting Engineers Ltd.

Page 3: Resume SBN 11 16

Page 3 of 6

ii. Client side internal engineering consultant for Tata Steel Ltd. Client & Duty Location : Tata Steel Ltd., Jamshedpur, India

Duration : Sept. 2008 to Feb.2014

Nature of Activity : Site based Consulting Engineering & Project Management Consultancy

Project Background & Features :

This project was targeted to balance the air pollution emission in course of stage –wise steelmaking capacity enhancement (5

MTPA to 10 MTPA) of Tata Steel. TCE was deployed as the Consulting Engineer for this project. Installation/Retrofication of one

Waste Gas & one Dedusting ESP for Sinter Plant no: 2 & 3 and Power House 4 and 24 no: of Bag Filter in Refractory Process

Unit of the factory was the scope of services of the project modules I was attached with. The capacity upgradation of the air

pollution devices was planned in such a way that augmented level of air purification with present operating load will ensure the

emission within the prescribed standard of air pollutant stack discharge of Central Pollution Control Board, India during future

enhanced steel manufacturing scenario. Fl Smidth & HSC was two major suppliers of ESP & Fabric Filters for this assignment.

Installation of Continuous Emission Monitoring System in Tata Steel Limited.

Role & Employer : Project engineer in TCE, Tata Consulting Engineers Ltd.

Client & Duty Location : Tata Steel Ltd., Jamshedpur, India

Duration : Sept. 2008 to Feb.2011

Nature of Activity : Site based Consulting Engineering & Project Management Consultancy

Project Background & Features :

This project was targeted to develop a continuous air pollution emission system in Tats Steel factory. Installation of sensor

based online air emission quality monitoring system for both ambient & stack was under the scope of service. TCE was

deployed as the Consulting Engineer for this project. IT implementation team & Instrumentation team was co-worker in this

assignment. One of the major suppliers of the project was Chemtrol.

Refurbishment of existing effluent treatment plant of The Tinplate Company of India Limited.

Role & Employer : Project Manager, Jamshedpur Utility & Service Company

Client & Duty Location : The Tinplate Company of India Ltd., Jamshedpur, India

Duration : May,2011 to Nov.2011

Nature of Activity : Site based Design Engineering & EPC supporting

Project Background & Features :

Both the effluent treatment plant of Cold Rolling Mill & Electroplating Tinning Line was underperforming in terms of removal of

Chemical Oxygen Demand & the latter one also for removal of Cr6+

(The high rate solid contact clarifier was not working

properly). Refurbishment accomplished with these objectives for both ETP.

Modification of existing effluent treatment plant of Tata Cummins Limited.

Role & Employer : Project Manager, Jamshedpur Utility & Service Company

Client & Duty Location : Tata Cummins Ltd., Jamshedpur, India

Duration : August,2011 to Jan.2012

Nature of Activity : Site based Design Engineering & EPC supporting

Project Background & Features :

The existing effluent treatment plant was underperforming due to ineffectiveness of exiting diffused aeration system and

membranes of Reverse Osmosis Unit. Both these unit was augmented under this assignment.

Construction of new package type Sewage Treatment Plant at Tata Cummins Limited

Role & Employer : Project Manager, Jamshedpur Utility & Service Company

Client & Duty Location : Tata Cummins Ltd., Jamshedpur, India

Duration : August,2011 to Jan.2012

Nature of Activity : Supervision OF Engineering, Procurement & Construction.

Project Background & Features :

For this assignment a modular sewage treatment of capacity was installed for the waste water generated from office, kitchen &

workers room. The target was to reuse the water for industrial cooling & landscaping.

Refurbishment of existing effluent treatment plant of Dhunseri Petrochem Limited

Role & Employer : Project Manager, JB Enviro Consultants Pvt. Ltd

Client & Duty Location : Dhunseri Petrochem Ltd., Haldia & Kolkata, India

Duration : August,2014 to Till Date

Nature of Activity : Site based Consulting Engineering & Project Management Consultancy

Project Background & Features :

The existing effluent treatment plant was underperforming due to ineffectiveness of exiting surface aeration system and up-flow

anaerobic sludge blanket (UASB) unit. Both these unit was augmented under this task.

Page 4: Resume SBN 11 16

Page 4 of 6

Installation of new effluent treatment plant in Raja Rani Agro Food Pvt. Limited

Role & Employer : Project Manager, JB Enviro Consultants Pvt. Ltd

Client & Duty Location : Raja Rani Agro Food Pvt. Ltd., Kolkata, India

Duration : June,2014 to February,2015

Nature of Activity : Site based Consulting Engineering & Project Management Consultancy

Project Background & Features :

Effluent Treatment Plant of 600 KLD capacity (Anaerobic Baffled Reactor Method, Oxidation Pond, Dual media filter and

activated carbon filter) was installed for recycling of treated waste water in to the process.

3. STABILIZATION & COMMISSIOINING ASSISTANCE INDUSTRIAL POLLUTION CONTROL SYSTEM:

Pilot Scale stabilization of Waste Water Treatment Plant in Paradip Refinery of Indian Oil Corporation Limited.

Role & Hirer : Consultant of Biological system stabilization, Asianol Spatiality Chemicals Pvt. Ltd. (ASCPL)

Client & Duty Location : WABAG India. Paradip & Kolkata, India

Duration : Sept. 2012 to Nov.2013

Nature of Activity : System Survey & Process Stabilization

Project Background & Features :

WABAG had a proposed collaborative plant trial study (through pilot plant observation) for stabilization of the biological treatment

system with Novozyme Biological Solution (application of molecule specific bio-augmented microbe). ASCPL is their Indian

representative and was accounted for to conduct the study.

Stabilization of Waste Water Treatment Plant in i. LPG Terminal of Indian Oil Petronas Limited, Haldia. ii. Haldia Refinery of Indian Oil Corporation Limited.

Role & Hirer : Consultant of Biological system stabilization , Asianol Spatiality Chemicals Pvt. Ltd. (ASCPL)

Client & Duty Location : Indian Oil Petronas Limited, Haldia. & Haldia Refinery -IOC Limited, Haldia & Kolkata, India

Duration : July 2007 to Jan 2008 (Indian Oil Petronas Ltd.),Sept. 2007 to July 2008 (IOC Ltd.)

Nature of Activity : System Survey & Process Stabilization

Project Background & Features :

Indian Oil Petronas and IOC Haldia Refinery decided to stabilize their waste water treatment plant by Novozyme Biological

Solution (application of molecule specific bio-augmented microbe). ASCPL was their Indian representative and was accounted

for to conduct the study of system survey, microbe screening.

4. CONSULTING & DESIGN ENGINEERING FOR UPSCALING OF RESEARCH PROJECTS:

Application of Coke Breeze as an adsorbent for Coke Oven Effluent Tertiary Treatment

Role & Employer : Chief Design Consultant, Tata Steel Ltd.

Client & Duty Location : Internal Project of Tata Steel Ltd. Jamshedpur, India

Duration : February,2012 to February,2014

Nature of Activity : Design Engineering of Pilot Scale Experimental setup, Consulting support to regular pilot scale

observation.

Project Background & Features :

Tertiary treatment through adsorption of critical parameters like Phenol, Cyanide and Thio-cyanide present in coke oven

biologically treated effluent by Coke Breeze (a coke making scrap) was effective in laboratory scale observation. The objective of

this study was further upscaling of the same. Effective management of a coke making solid waste and development of new

adsorbent for effluent treatment were two target benefits.

Removal of Phosphorus from Steel Making LD Slag

Role & Employer : Chief Design Consultant, Tata Steel Ltd.

Client & Duty Location : Internal Project of Tata Steel Ltd. Jamshedpur, India

Duration : February,2012 to February,2014

Nature of Activity : Design of Pilot Plant set-up.

Project Background & Features :

Removal of Phosphorus content from 2-3 % to < 1% can make the material applicable to use as refluxing agent in Sinter Plant.

The research task was successful in laboratory scale by phosphorus removal through froth floatation process. Objective of this

study was further upscaling of the same to fit into pilot scale. Design of the pilot plant was a significant part of this study.

Development of water desalination system (RO based) to reduce Cl- & SO4

2- concentration in water intake of Haldia

Works, Tata Steel Ltd.

Page 5: Resume SBN 11 16

Page 5 of 6

Role & Employer : Project Leader, Tata Steel Ltd.

Client & Duty Location : Internal Project of Tata Steel Ltd. Jamshedpur, India

Duration : June,2012 to February,2014

Nature of Activity : Consulting support to regular implementation scale observation.

Project Background & Features :

Reuse of treated effluent generated from different unit process & operation of Tata Steel Ltd. was very challenging caused due

to presence of Cl- & SO4

2-. This was caused due to contaminated water intake (proximity to Bay of Bengal) in Haldia works and

thus the coke produced & waste water use to have significant concentration of this two parameter. The objective of this task was

to develop Reverse Osmosis based desalination system to ensure treated & less contaminated entry of sea water to the plant.

5. VENDOR SIDE PROJECT MANAGEMENT FOR INDUSTRIAL POLLUTION CONTROL SYSTEM DEVELOPMENT:

Capacity upgradation of Effluent Treatment Plant for Emami Paper Mill

Role & Employer : Project Engineer, Welltech Environmental Engineering Pvt. Ltd.

Client & Duty Location : Emami Paper Mill Ltd., Kolkata, India

Duration : Sept. 2004 to June .2006

Nature of Activity : Proposal & Contract Management; Site based Project Management.

Project Background & Features :

Upgradation of Effluent Treatment Plant to 2300 KLD of a paper factory of 50 TPD production capacity.

Installation of new Effluent Treatment Plant in Delta Fabrics Pvt. Ltd.

Role & Employer : Project Engineer, Welltech Environmental Engineering Pvt. Ltd.

Client & Duty Location : Delta Fabrics Pvt. Ltd., Kolkata, India

Duration : May. 2004 to July 2007

Nature of Activity : Proposal & Contract Management; Site based Project Management.

Project Background & Features :

Installation of new Effluent Treatment Plant of 50m3/day capacity for a dyeing and bleaching factory.

Installation of new Air Pollution Control Facility in Vedanta Aluminium Ltd.

Role & Employer : Project Engineer, Welltech Environmental Engineering Pvt. Ltd.

Client & Duty Location : Vedanta Aluminium Ltd., Jharsuguda, Orissa & Kolkata, India

Duration : October 2003 to April 2006

Nature of Activity : Proposal & Contract Management; Site based Project Management.

Project Background & Features :

Installation of dedusting bag filters ad cyclones in the factory.

6. ENVIRONMENTAL IMPACT ASSESSMENT (EIA) ASSIGNMENTS REPORTING JOBS:

Capacity Expansion of

i. Joda East Iron Ore Mines of Tata Steel & ii. West Bokaro Coal Mine of Tata Steel

Role & Employer : Functional Expert (Water, Air, Hazardous Waste and .Noise & Vibration), Tata Consulting Engineering Ltd.

Client & Duty Location : Tata Steel Ltd., Joda, Orissa & Jamshedpur, India

Duration : October 2008 to April 2010

Nature of Activity : Office based Consulting Engineering & Project Management.

Project Background & Features :

EIA study to receive consent to establishment & operate for expanding mining capacity of iron ore in Joda East Iron ore mine, Orissa

and construction of new washery & captive thermal power plant in West Bokaro Coal Mine to support rise of steel production target

from 5 MTPA to 10 MTPA of Tata Steel

Development of new cold rolling mill of Tata Steel in Bara, Jamshedpur

Role & Employer : Functional Expert (Water, Air, Hazardous Waste and .Noise & Vibration),Tata Consulting Engineering Ltd.

Client & Duty Location : Tata Steel Ltd., West Bokaro, Jharkhand, India

Duration : June 2009 to April 2010

Nature of Activity : Office based Consulting Engineering & Project Management.

Project Background & Features :

EIA study required for getting consent to establishment & operate for construction of new cold rolling unit to support rise of steel

production target from 5 MTPA to 10 MTPA of Tata Steel.

Page 6: Resume SBN 11 16

Page 6 of 6 P.T.O. (For Annexure 3)

Please consider the environment before printing this document!

Continuous Annealing and Pickling Line development job in Tata Steel, Jamshedpur

Role & Employer : Functional Expert (Water, Air, Hazardous Waste and .Noise & Vibration),Tata Consulting Engineering Ltd.

Client & Location : Tata Steel Ltd., West Bokaro, Jharkhand, India

Duration : October 2009 to September, 2010

Nature of Activity : Office based Consulting Engineering & Project Management.

Project Background & Features :

This was a JV project with Nippon Steel. EIA study required for getting consent to establishment & operate for construction of new

annealing and pickling plant to support rise of steel production target from 5 MTPA to 10 MTPA of Tata Steel.

Construction of Real Estate & Commercial infrastructure as :

1. New Refugee Rehabilitation and Residential Project in Bonhooghly, Kolkata 2. New Residential & Commercial Project in 117 BT Road, Kamarhati, Kolkata 3. New Hosiery Park, Howrah

Role & Employer : Functional Expert (Water, Air, Hazardous Waste and .Noise & Vibration),JB Enviro Consultants Pvt. Ltd.

Client & Location : (1) R&R Dept., West Bengal Govt. (2) Ujjal Barter Trading Co: (3) West Bengal Hosiery Association

Kolkata, India.

Duration : October 2009 to September, 2010

Nature of Activity : Office based Consulting Engineering & Project Management(Arrangement of baseline information

collection, Environmental Modelling, Impact Assessment including microclimatic effects, Environment

Management Planning, Technical presentation to statutory agency, Report Generation, Public Hearing,

Social Impact study.

7. ENVIRONMENTAL SITE ASSESSMENT (ESA) & DUE DILIGENCE REPORTING JOBS:

Phase I ESA study for expansion of Beck India Limited

Role & Employer : Project Engineer, Tata Consulting Engineers Ltd.

Client & Duty Location : Beck India Ltd., , Gujarat & Mumbai, India

Duration : September 2008 to October, 2008

Nature of Activity : Site based Consulting Engineering (Information collection on site use history, Review of pollution

documents, Identification of existing and potential source of contamination, Reporting)

Phase II ESA study for construction of new office building of Tata Consulting Engineers Ltd. In Jamshedpur

Role & Employer : Project Engineer, Tata Consulting Engineers Ltd.

Client & Duty Location : Internal Project, Tata Consulting Engineers Ltd., Jamshedpur, India

Duration : April. 2009 to July 2009

Nature of Activity : Site based Consulting Engineering (Surface & Sub-surface soil, Surface & Ground water

,sediment sampling, Use of transportation model for contaminant migration study)

8. INDUSTRIAL RISK ASSESSMENT & HAZARD STUDY:

HAZOP Study for different Gas Holders

Role & Employer : Project Engineer, Tata Consulting Engineers Ltd.

Client & Location : Tata Steel Ltd., Jamshedpur, India

Duration : November,2008 to April,2009

Nature of Activity : Site based Consulting Engineering (Working with multi-disciplinary team, Study of PFDs & PIDs,

Quantification of probability and consequence of all possible events, Using by HAZOP PRO Software.)

Project Background & Features :

Study of holders of the process gas from BF, BOF units

Risk Analysis of stamp charging coke oven batteries

Role & Employer : Project Engineer, Tata Consulting Engineers Ltd.

Client & Location : Tata Steel Ltd., Jamshedpur, India

Duration : September,2009 to March, 2010

Nature of Activity : Site based Consulting Engineering (Working with multi-disciplinary team, Study of PFDs & PIDs,

Quantification of probability and consequence of all possible events, Reporting by PHAST Software.)

Project Background & Features :

Part of comparative cost-benefit study of stamp & top charging coke oven batteries during steel production rise.

Kolkata, India 26-09-2015