  • 1

    RepublicAirportRunwaySafetyAreaProject

    PRE-BID MEETING

    NYSDOT Commissioner Briefing

    April27,2016

  • 2

    Outline WelcomeandIntroductions Presentation

    o PurposeandNeed

    o ProjectComponents

    o Phasing

    o ContractorInformation

    o DBE/SubcontractorOpportunities

    SiteVisit Q&A

  • 3

    RunwaySafetyAreaProject

    ProjectPurposeandHistoryo ImproveRunway119SafetyAreainaccordancewithFAAstatutes

    1stPhaseToAddressPerimeterRoadandRunwayRelocation

    WorkDoesNotExtendTotalRunwayLength

  • 4

    RunwaySafetyAreaProjectProject Components

  • 5

    RunwaySafetyAreaProject

    PROJECTTASKS PavementRemoval/Installation

    Shift412feetofrunway ModifytaxiwaythroatsandtaxiwaysassociatedwithRunway119

    Grading/Drainage RunwayandTaxiwayLighting/Signage AirfieldMarkings Landscaping

    RUNWAY 1/19 SHIFT

  • 6

    RunwaySafetyAreaProject

    PROJECTTASKS Excavation NewPavement;Approx.

    3,000feet Grading/Drainage Landscaping

    PERIMETER ROAD RELOCATION

  • 7

    RunwaySafetyAreaProject NYSDOT / FAA Design Criteria

    o All work contemplated under this contract is to be covered by and in conformity with the contract specifications. Where not specifically provided for in the contract specifications, the work shall be governed by the NYSDOT Standard Specifications (US Customary Units) of January 1, 2016 Letting. Contract plans have been designed in accordance with the latest FAA Advisory Circulars and NYSDOT policies and guidelines.

    NYSDOT / FAA Construction Specificationso https://www.dot.ny.gov/main/business-

    center/engineering/specificationso www.faa.gov

    Biddingo Prevailing Wage Rateso DBE Requirementso Bid Forms

  • 8

    RunwaySafetyAreaProject

    Runway1/19Shift RelocationofAirportPerimeterRoad

    o StartDate:July2016o ProjectDuration:180days

    ANTICIPATED SCHEDULE

  • 9

    RunwaySafetyAreaProject

    PHASING - OVERALL

  • 10

    RunwaySafetyAreaProject

    PHASING PHASE 1

  • 11

    RunwaySafetyAreaProject

    PHASING PHASE 2

  • 12

    RunwaySafetyAreaProject

    PHASING PHASE 3

  • 13

    RunwaySafetyAreaProject

    PHASING PHASE 4

  • 14

    RunwaySafetyAreaProject

    PHASING PHASE 5

  • 15

    RunwaySafetyAreaProject

    PHASING PHASE 6

  • 16

    RunwaySafetyAreaProject

    Runway 1-19 Typical Section

  • 17

    RunwaySafetyAreaProject

    Taxiway B5 & G1 / Runway 19 Typical Section

  • 18

    RunwaySafetyAreaProject

    Taxiway / Temporary Kilo Typical Section

  • 19

    RunwaySafetyAreaProject

    Miscellaneous Typical Sections

  • 20

    RunwaySafetyAreaProject

    Taxiway B5 & G1 / Runway 19 Typical Section

  • 21

    RunwaySafetyAreaProject

    Perimeter Road Typical Section

  • 22

    RunwaySafetyAreaProjectContractor Information

    Project Location and Accesso Staging Areao Haul Route

    Operational Safety Requirements; AC 150-5370-2o Runway and Taxiway Safety Areaso FAR Part 77 Restrictions

    Security Requirementso Badgingo Gate Guards

  • 23

    RunwaySafetyAreaProject

    STAGING AREA / HAUL ROUTE

  • 24

    DBEOpportunities

    ConsiderationsforDBEfirms DBEGoal 8.4% DBEsareavailableintheUCPDirectory;http://nysucp.net/ AbilityfortheDBEtoDeliverCompetitivePricing

    FederalAviationSpecificationRequiredForSomeAirportCommodities

  • 25

    RunwaySafetyAreaProjectTYPICAL SUBCONTRACTED WORK TYPES

    Work Type NYSDOT/FAA Work Code*

    PAINTINGRunway and Taxiway Marking P-620*

    EARTHWORKClearing and Grubbing P-151*Excavation, Subgrade and Embankment P-152*Geosynthetics P-154*Temporary Air and Water Pollution, Soil Erosion and Siltation Control

    P-156*

    BASES AND SUBBASESCrushed Aggregate Base Course/Subbase 304; P-209*

    HOT MIX ASPHALTHMA Pavements 402Hot Mix Asphalt (HMA) Pavement P-401*Bituminous Task Coat P-603Cold Milling of Bituminous Concrete Pavement 490, 627

    NYSDOTStandardSpecifications*FAAAdvisoryCircular150/537010;StandardsforSpecifyingConstructionofAirports

  • 26

    RunwaySafetyAreaProjectTYPICAL SUBCONTRACTED WORK TYPES (Contd)

    Work Type NYSDOT/FAA Work Code*

    INCIDENTAL CONSTRUCTIONPipe for Storm Drains and Culverts D-701*Pipes for Underdrains for Airports D-705*

    Manholes, Catch Basins, Inlets and Inspection Holes D-751*

    Seeding 610; T-901*

    Topsoiling T-905*Gravel, Crushed Stone 203; P-209*

    ELECTRICALUnderground Power Cable for Airports L-108*Airport Underground Electrical Duct Banks and Conduits L-110*Electrical Manholes and Junction Structures L-115*Airport Signage Systems L-123*Installation of Airport Lighting Systems L-125*

    NYSDOTStandardSpecifications*FAAAdvisoryCircular150/537010;StandardsforSpecifyingConstructionofAirports

  • 27

    Questions&Answers

    Questionsfrombiddersarebeingcollected

    UseSubmitQuestionsformorsendviaemailtoandrea.luft@aecom.com

    Questionsandanswerstobepostedontheprojectwebsitewww.republicairport.net/bidopportunity.htmonThursday,April28.LastQ&AupdateonTuesday,May3.

    Questionswillnotbeattributed(anonymous)

    Q&ASessiontoFollowSiteVisit