Replacement of a Legacy CIS (Customer

Information System) with SAP CR&B

SAP for Utilities Conference – 2013

Presented by: Thomas J. Pierpoint, Director, Business Applications

Page 2: Replacement of legacy cis with sap cr&b at phi

2

Topics

About Pepco Holdings, Inc.

A moment of recognition

Background of customer information systems at PHI

Decision options around the going-forward path

Process used to make the decisions

Overall timeline of key activities

Moving forward on our SolutionOne project

Q&A

Page 3: Replacement of legacy cis with sap cr&b at phi

3

About Pepco Holdings, Inc.

Approximately 2 million customer

accounts in Delaware, the District of

Columbia, Maryland and New Jersey

Total population served is 5.6 million

Three T&D operating companies provide

regulated electricity service

• Atlantic City Electric,

• Delmarva Power (gas & electric)

• Pepco (including one of the top four

largest underground systems in the

country)

Pepco Energy Service provides energy

efficiency and renewable energy services

Photo by Rick Giammaria, Staff Photographer, PHI

Page 4: Replacement of legacy cis with sap cr&b at phi

4

Pepco Holdings, Inc. Quick Facts

Incorporated in 2002

Service territory:

8,340 square miles

Customers served

• Atlantic City Electric:

– 545,000 – electric

• Delmarva Power:

– 503,000 – electric

– 125,000 – natural gas

• Pepco:

– 793,000 – electric

Total population served:

5.6 million

Page 5: Replacement of legacy cis with sap cr&b at phi

5

At PHI, each day we…

Handle 13,000 customer phone calls

Respond to and restore 144 electrical outages

Read 60,000 meters and send out the same number of accurate bills

Connect 46 additional customers (17,000 per year)

Reconnect and/or disconnect 455 customers

Replace 16 poles (nearly 6,000 per year)

Deliver 135 million kWh of electricity

Deliver 64,000 Mcf gas to 118,000 gas customers

Incur $1.4 million in construction costs

Maintain 3,500 miles of transmission lines and 30,000 miles of

distribution lines

Maintain 530 substations and 400,000 distribution transformers

Page 6: Replacement of legacy cis with sap cr&b at phi

6 Work Management Workshop July 28 2009

The vast networks of electrification have had the

biggest impact on the quality of life and represents the

greatest engineering achievement of the 20th century Astronaut Neil Armstrong on behalf of the

National Academy of Engineering

The interconnected electric grid in North America is

the most complex machine ever invented Special panel of Leaders

from over 200 organizations convened by the

Electrical Power Research Institute

Electrification powers almost every pursuit and

enterprise in modern society National Academy of Engineering

A moment of recognition

Thank you to all that serve this critical industry!

Photo courtesy of EPRI

Page 7: Replacement of legacy cis with sap cr&b at phi

7

Current Systems Landscape*

SAP ECC

CO – Controlling (CCA/IO)

FI – Finance (GL/AP/AR/T&E)

AM – Asset Management

PS – Project System

MM – Materials Management (PUR/IM)

PM – Plant Maintenance

CS – Customer Service

SD – Sales & Distribution

HR – Human Resources (PA/PD/OM)

PY - Payroll

FERC

CATS

FSCM – Dispute & Collections

GRC – Compliance Calibrator

Dolphin PTS

UFA – Utility Financial Accelerator

PPM – Portfolio & Project Management

* This info is intended only for high-level discussion purposes at the SAP Utilities

Conference and is greatly simplified with most systems and details removed

Customer Mobile & Web

Legacy Customer

Information Systems

Other Systems

Business Warehouse

Enterprise Portal

SAP - BPC

SAP GUI

Solution Manager

Page 8: Replacement of legacy cis with sap cr&b at phi

8

Background of the customer information systems at PHI

There are three T&D utility operating companies at PHI and two CIS systems

C3 for Atlantic City Electric and Delmarva Power

CIS for Pepco

These systems provide numerous benefits through the automation of many customer service activities such as billing, call center, and the movement of work tickets to field groups.

Both systems are largely based upon technologies implemented 30-35 years ago.

CIS Industry Evolution

1st Gen

Late

1960’s

2nd

Gen

1970’s

3rd Gen

mid-1980’s

4th Gen

late

1990’s

5th Gen

early

2000’s

6th Gen

later

2000’s

CIS C3

Page 9: Replacement of legacy cis with sap cr&b at phi

9

These systems have performed very well for many years in

supporting a relatively stable business environment . . .

However, PHI is proactively making many changes to stay

ahead of accelerating change in our industry

Starting in 2005 major new capabilities were incrementally added to improve levels of customer service and provide new offerings including new rates, demand response, web, mobile, self-service with AMI as a key enabler.

The effort required to interface with the legacy systems can be complex and time-consuming. This is increasingly proving to be “critical path” in the deployment of further new functionality, especially for customer-facing deliverables.

The systems continue to perform core business processes very well, but there are many newer processes they do not fully enable. Workarounds are sometimes in place to address these limitations.

Page 10: Replacement of legacy cis with sap cr&b at phi

10

PHI has regularly evaluated the life-cycle of the existing

systems to determine the best path forward

An Evaluation of Options has been performed every 24-30

months since 2003 at PHI

Each option had pros and cons and the best course was to

“stay the course” and incrementally add new technologies

around the legacy systems

A high-level evaluation in late 2010 revealed that some

underlying factors would likely change and that a further,

more detailed evaluation was appropriate during 2011

Page 11: Replacement of legacy cis with sap cr&b at phi

11

The replacement of a legacy CIS is a big commitment for

any utility. A few of the Critical Success Factors for the

detailed analysis to evaluate replacement options include. .

Provide a structured, incremental approach including stage

gates

Engage all principal stakeholders

Expand the traditional cost-benefits analysis to include

possible emerging benefits from our changing industry

Page 12: Replacement of legacy cis with sap cr&b at phi

12

The structured, incremental analysis had key phases

with stage gates prior to the next phase

• Phase 0 was done in late 2010 and revealed that some underlying

factors would likely change. The recommendation was to perform the

next level of a detailed analysis.

• Phase I was done in the 1st quarter of 2011. This was a “Gap-Fit”

analysis that indicated substantial potential benefits of replacing the

existing CIS systems with a commercial technology. The

recommendation was to perform a more detailed analysis and make

preliminary plans for a possible project.

• Phase II was done in the 2nd and 3rd quarter of 2011 and drove to a

greater level of detail on scope of work, resource requirements, cost

estimates, and the viability of SAP CR&B for PHI. The recommendation

was to proceed with replacement of the legacy systems and set up a

formal and funded project.

Page 13: Replacement of legacy cis with sap cr&b at phi

13

Key stakeholders at PHI were engaged and involved

During the 1st quarter of 2011, 150 PHI personnel evaluated the

applicability, scope, cost, and schedule for their replacement of C3

and CIS with a commercial “off the shelf” (COTS) system from SAP or

Oracle.

This evaluation included 28 structured workshops to review key

business processes and to confirm the scope of a possible project.

Industry experts and PHI personnel conducted and facilitated the

workshops and performed demonstrations of the SAP system in

conjunction with SAP processes.

Accenture provided key support

for much of this effort

SAP and IBM provided support

and insight in targeted areas

Many other industry experts

also provided insights

Page 14: Replacement of legacy cis with sap cr&b at phi

14

The traditional costs-benefit models typically address a

number of important areas

• Preservation of the existing benefits gained by a current CIS

– These benefits are substantial at many utilities

– These benefits should not be ignored (or jeopardized)

• Direct support of legacy systems

– Mainframe and licenses, usually increasing as user base at a utility

shrinks

– Staff of specialists

• Continuing modifications to legacy systems

• Business process inefficiencies

• New and needed capabilities that have been identified

– Complex rates

– CRM

Page 15: Replacement of legacy cis with sap cr&b at phi

15

A traditional cost-benefit analysis should also include

considerations for a changing business environment

Newer variable, time-based rates

Increasing needs to extract data

Built-in business intelligence

Multi-channel, multi-device

communication, supporting a single

system of record for all customer

communications

Non-revenue products and services

such as demand response, energy

efficiency, or net metering

Will the pace, breadth and depth of future changes overwhelm the ability

of a utility to make timely and cost efficient changes to legacy systems?

New, adaptable credit and

collections services

Increasing levels of CRM

capabilities

Consolidation and accuracy of

master data, especially related to

customers

Page 16: Replacement of legacy cis with sap cr&b at phi

16

Guiding principles were established early in this effort

Quality First - The quality of the implementation is paramount.

Design for Flexibility and Adaptability - Architecture must facilitate rapid

implementation of future enhancements.

Virtue in Simplicity, with the scope including three core components:

- fundamental CIS functionality

- functionality to meet public commitments

- some additional, value adding, out of the box capabilities

Change the Process, Not the System - A bias toward process change to

conform to out of the box functionality.

Not Everything is a Day One Deliverable - Deliverables will be pushed

to Phase 2 if they shift focus from a high quality implementation of the

three core deliverables.

Page 17: Replacement of legacy cis with sap cr&b at phi

17

Guiding principles were established early in this effort

Good Ideas Don't All Have to be Built – Some new functions can be

obtained by “innovation through adoption” of best functionality built by

other utilities.

What is the Impact on Customer Care and Operations? - Project

decisions need to be made with a clear understanding of the potential

impact on the operating areas.

Dedicated Team - Allow the assigned resources to focus exclusively on

this project and seek to capitalize on their fresh perspectives.

Page 18: Replacement of legacy cis with sap cr&b at phi

18

Timeline of initial activities

2010 2011 2012

8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7

We Are Here

Phase 0

Analysis

Phase 1

Gap-Fit

Phase 2

Detailed Plan & Budget

Software

Selection

Select TPA

for SI Bid

Select Project

Leaders & Team

Selection of

System Integrator

BOD

Approval

Executive Approval

to Proceed

Executive Approval

to Proceed

Executive Approval

Stage Gate/Decision Point

Page 19: Replacement of legacy cis with sap cr&b at phi

19

Moving Forward with SolutionOne

19

Page 20: Replacement of legacy cis with sap cr&b at phi

20

Timeline of activities

2012 2013 2014 2015

8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5 6 7 8 9 10 11 12 1 2 3 4 5

Plan

Analyze

Design

Build

Test

Assembly Product ORT

Final Testing, Deploy, Stabilize & Ongoing Support

Page 21: Replacement of legacy cis with sap cr&b at phi

21

Primary Objectives of Business Readiness

• Reduce the intensity and duration of the transition period

following the Go-Live to better serve our customers

• Prepare our employees

– Communication venues for our leaders

– Develop and execute a plan to utilize Customer Care

resources at key stages of project

– Collaborate with Change Management team on detailed

training, communications, and knowledge transfer plans

Page 22: Replacement of legacy cis with sap cr&b at phi

22

A great deal of attention is focused on the User Experience

Customer Info Alerts IVR Data

Navigation

Bar Flyout Menu

Messages

Page 23: Replacement of legacy cis with sap cr&b at phi

23

We will continue to deliver a solid customer experience

during the systems transition

• PHI mobile applications and web sites are

heavily used by our customers and the general

public

• Billing information to our customers

• Electric outage and restoration information to

our customers as well as the public

• These sites are heavily accessed, especially

during a storm or event

• A key enabler is a solid foundation of business

processes and technologies that needs to be

maintained during the transition of systems

Photo by Rick Giammaria,

Staff Photographer, PHI

Page 24: Replacement of legacy cis with sap cr&b at phi

24

Collaboration

and Teamwork…

Page 25: Replacement of legacy cis with sap cr&b at phi

25

… are Key to

Success

Page 26: Replacement of legacy cis with sap cr&b at phi

26

Questions, thoughts, comments?

Again, thank you to all of you that support our

industry and have contributed to the many advances!

Photo by Rick Giammaria, Staff Photographer, PHI

Contacts:

Tom Pierpoint

Director, Business Applications

[email protected]

Mike Poncia

Director, SolutionOne Project

[email protected]

Page 27: Replacement of legacy cis with sap cr&b at phi

27 A collaboration of:

Tom Pierpoint

Pepco Holdings Inc

[email protected]