Colombian PBN implementation: El Dorado case study SDM WORKSHOP ON PBN XAVIER OUTTERS SME & PROJECT MANAGER NAVBLUE SAS 19.10.2017

Upload: others

Post on 10-May-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Colombian PBN implementation:El Dorado case studySDM WORKSHOP ON PBN

XAVIER OUTTERSSME & PROJECT MANAGERNAVBLUE SAS

19.10.2017

Page 2: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Electronic Flight Bag

Databases

Avionics

- ROPS+

- FlySmart+- Charts+- Mission+

- Navigation+- Airport+

PILOTS

Dispatch

Crew management

Pre-flight

- N’Flight Planning- N’Tracking- N’Performance- N’RAIM

- N’Crew- N’RAIDOThe picture can't be displayed.

DISPATCHERS

- ADOC- AODB

Post-flight

- AIRFASE- ANALYTICS

FLIGHT OPS ENG.

Airport

Airspace

- ELISE by NAVBLUE

- GNSS by NAVBLUE

- DESIGN by NAVBLUE

- ASSESS by NAVBLUE

ANSP & Airports

Consulting

- YourOps

NAVBLUE is a services company, wholly owned by Airbus, dedicated to Flight Operations & Air Traffic Management Solutions.

Page 3: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

03 Challenges and lessons learnt

02 KPIs, solutions, expected benefits

01 Project Overview

Page 4: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Project OverviewCHAPTER 01

Page 5: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

5

PAX numbers within Latin American region grew 23% from 2012-2016

Page 6: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Bogota PAX grew more than 60% in only 6 years… with a 15% increase of airport operations

6

Page 7: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Project ObjectivesInternational Cooperation Agreement to Redesign the Airspace & Optimize Airside Capacity at Bogota El Dorado Airport

To position Bogotá El Dorado international airport as one of the most efficient international terminals in Latin America by increasing its capacity and airspace efficiency through: Introduction of PBN Reduction of aircraft separation within the TMA Implementation of independent and simultaneous parallel

runways operations Improvement of ground operations Update of regulations & operations manuals Enhancement of ATC capability with theoretical & practical

On-The-Job Training (OJT)

7

Page 8: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Bogota urgently needed an airspace turnaround

• ATCOs vector ~100% of arriving aircrafts (high workload)

• Encounter/dispersed flows

• Inefficient use of runways

• Holding patterns

• Bottleneck at VOR

• Limited access to RWY 31L/R

8

Bogota’s ATCOs constantly outperform their own limits!

Reference Day 09/10/2015

Page 9: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

9

• Uneven sectors work balance (North Sector taking most of the load)

• Excessive radio comms. due the 100% vectoring of arrivals.

• Job dissatisfaction

• Increased workload due to continuous traffic increase within TMA

TMA workload needed to be balanced

Page 10: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

KPIs, solutions, expected benefits CHAPTER 02

Page 11: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

11

Desired outcome and solution matrix (1/2)

• Matrix matching existing situation against a desired outcome.

• Identified solutions matching any combination of safety, capacity, efficiency, environment, or access factors.

• First two main items required GAP / Solutions to increase capacity and user RNAV to improve access and efficiency within Bogota TMA

Page 12: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

12

Desired outcome and solution matrix (1/2)

• Further desired outcome items looked to balance ATC sector workload and reduce complexity by implementing RNAV SIDs and STARs.

• Simultaneous independent approaches to balance capacity.

• Design facilitated CCO and CDO operations, and balanced city-pair flows.

• Radio transmissions dropped significantly reducing both ATC and crew workload.

Page 13: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

SKBO TMA - PBN Expected Benefits

• Increase in airspace capacity (simulation runs):

o RNW13: 92 ops per hour (29.2% increase)

o RNW31: 68 ops per hour (126% increase)

• Reduction in ATCOs workload (60% less communications per aircraft)

• Flexibilization of restricted military airspace

• Reduced workload for pilots.

• Expected financial efficiencies for up to US100M/year

Page 14: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Bogota CONOPSRunway 13

14

• Independent trajectories with altitude separation

• Reduced ATCO workload due to repeatable trajectories and predicted trajectory distances.

• Reduces crew workload based on strategic coding of trajectories in NavDB.

• Reduced ATCO intervention• Improved safety

Page 15: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Point of Merge System

• All aircraft sent direct AMVES (point merge).

• Better traffic management compared to sending aircraft to previous VOR due to specifically designed RNAV system.

• Non-RNAV aircraft vectored to VOR to complete conventional procedure.

• Appropriate management of reduced separation down to 3nm.

15

Page 16: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

EDR CONOPSRunway 31

• Altitude separation• Reduced ATCO/ crew

workload• Reduced ATCO

intervention• Improved safety

16

Page 17: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

17

• Reduced span of control for each individual sector.

• Balanced workload across sectors based on inbound and outbound flow demands.

• Fewer conflicts to manage

• Reduced ATCO workload

• Reduced ATCO intervention

New TMA Sectors

Page 18: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Challenges and lessons learntCHAPTER 03

Page 19: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

19

CONOPS– Reference Day 09/10/2015 + 40% Traffic

Page 20: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Design• Access to RWY 31 for both RNP and non-

RNP capable aircraft = RNP AR trajectories + RNAV Visual published by Authority.

• Non-RNAV aircraft within the TMA = Kept selected non-RNAV SID’s and STARs published at lower altitudes + conventional ILS from BOG-VOR. NOTAM published that RNAV SIDs and STARs must be filed as a first requirement.

• Fast Track Project = KoM to Implementation in two years. Only way is for all stakeholders to be aligned with main scope and objective

•Jet Vs Turboprop = Trajectories designed considering faster aircraft overcoming slower aircraft.

20

ATC Training• Change a “20-year” with a “new” way of

working = Only way is with ATC to be part of the design, undergo and appropriate training, and commit to change.

• Knowledge transfer process (both ways) = understanding PBN benefits, allowing technology to help achieve goals, and trust that all parties (ATC, Operators, Regulators) are committed to success.

• Achieve change via training = tailored training program including simulations for all area and tower controllers, and On the Job Training to accompany ATC during initial implementation of operations.

Project Challenges and Lessons Learnt

Page 21: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

Stakeholders• Successful public-private collaboration =

Identify people that “don’t believe” and lead them to understand and then to “believe”. Commitment from all stakeholders is a must for the success of such a big project.

• Coming up with a final design = Discuss options separately with each stakeholder, then identify and resolve as best as possible items that don’t match. Solutions may not match all stakeholder “wants”, but an initial design can only be made better in time.

• Airspace needs to be shared by everyone.

21

Military Flexible Use of Airspace (FUA)• Use of Military airspace = Military forces

wishing to share exclusive use of airspace when not in use for the benefit of the overall commercial aviation industry.

• Military – Civil aviation FUA Letter of Agreement = Designed under international guidelines to ensure an appropriate agreement between both parties on how / when to use the mentioned airspace.

• Orderly FUA = Specific RNAV trajectories designed to be used by qualified commercial aircraft. Trajectories reduce overall arrival track miles, or allow use of airspace during adverse weather in other TMA Areas.

Project Challenges and Lessons Learnt

Page 22: Colombian PBN implementation: El Dorado case study · Colombian PBN implementation: El Dorado case study. SDM WORKSHOP ON PBN. XAVIER OUTTERS. SME & PROJECT MANAGER. NAVBLUE SAS

© AIRBUS S.A.S. ALL RIGHTS RESERVED. CONFIDENTIAL AND PROPRIETARY DOCUMENT. THIS DOCUMENT AND ALL INFORMATION CONTAINED HEREIN IS THE SOLE PROPERTY OF AIRBUS. NO INTELLECTUAL

PROPERTY RIGHTS ARE GRANTED BY THE DELIVERY

OF THIS DOCUMENT OR THE DISCLOSURE OF ITS CONTENT. THIS DOCUMENT SHALL NOT BE REPRODUCED OR DISCLOSED TO A THIRD PARTY WITHOUT THE EXPRESS WRITTEN CONSENT OF AIRBUS S.A.S. THIS

DOCUMENT AND ITS CONTENT SHALL NOT BE

USED FOR ANY PURPOSE OTHER THAN THAT FOR WHICH IT IS SUPPLIED. THE STATEMENTS MADE HEREIN DO NOT CONSTITUTE AN OFFER. THEY ARE BASED ON THE MENTIONED ASSUMPTIONS AND ARE

EXPRESSED IN GOOD FAITH. WHERE THE SUPPORTING

GROUNDS FOR THESE STATEMENTS ARE NOT SHOWN, AIRBUS S.A.S. WILL BE PLEASED TO EXPLAIN THE BASIS THEREOF. AIRBUS, ITS LOGO, A300, A310, A318, A319, A320, A321, A330, A340, A350,

A380, A400M ARE REGISTERED TRADEMARKS.

ContactXAVIER [email protected]: +33 776329054