raised flange connection - winddays · design of flange connection 7 •foundation flange design...
TRANSCRIPT
.................................................................................................
Raised Flange ConnectionWinddays 2016 - Innovations at Eneco Luchterduinen
Wybren de Vries
Foundations Package Manager
16 June 2016
.................................................................................................
........................................................................
Eneco Luchterduinen
2
• Located 23km off the Dutch coast
of Noordwijk
• Area 25.5km²
• Water depth of 18-24
• Average annual wind speed of
9.3 m/s at 80.8m
• Installed capacity of 129MW
• 43 Vestas 3MW V112 turbines
• Expected production of more than
4,000 full load hours (FLH)
• Landfall at Noordwijk
• Grid access point at Tennet
150kV station 8km inshoreInnovations:
• 2 foundations without scour protection
• All 43 foundations with raised flange connection
• Innovative metocean buoy
.................................................................................................
........................................................................
Introducing an innovation
• Risk reduction
– No grout connection – No certification risk
• Cost reduction
– Reduction of grout overlap -> less steel
– Reduction of grout curing time -> faster installation
3
Raised flange connection
.................................................................................................
........................................................................
The Raised Flange Connection concept
1. No grout connection, no TP: single
foundation element
2. Tower bolted directly onto monopile
3. Pile driving on monopile flange
4. Large pile driving forces: secondary
steel installed separately offshore
5. No J-tubes: internal free-hanging
cable
6. Corrosion protection: ICCP anodes
integrated in boatlanding
4
Boatlanding
Airtight platform
External platform
.................................................................................................
........................................................................
Parties involved
5
• Supply Wind turbine, • Design tower & flange
connection• WT load calculations• Design foundations
Certification:• Foundation primary steel,• Secondary steel • Loads• Tower• Flange connection
EPCI:Design, supply installation• WTG Foundations• Cables• OHVS
.................................................................................................
........................................................................
Design requirements
• Flange:
– Must withstand pile driving– Avoid impact with hammer– Adequate corrosion protection
• Monopile
– Install within 0.5° of vertical– Provide corrosion protection when ICCP inactive– Include attachments for secondary steel mounting
• Secondary Steel
– Minimise number of lifts– Easy offshore installation– Cable hang-offs on internal airtight platform– Incorporation of ICCP in access arrangement
6
.................................................................................................
........................................................................
Design of flange connection
7
• Foundation flange design
adapted for pile driving
• Flat driving surface
• Downward inclined flange
• Larger thickness
• Acceptance on basis of FE
analysis
• Verification of stresses in
tower wall and bolts
• Better understanding of
load levels and paths
.................................................................................................
........................................................................
Secondary steel details: Main Platform
8
.................................................................................................
........................................................................
Secondary steel details: Boatlanding
9
ICCP anodes
Stabbing pins below waterline
Bolted connection above waterline
Resting platformssupported on boatlanding
.................................................................................................
........................................................................
Secondary steel: Airtight platform
10
.................................................................................................
........................................................................
Design - Challenges
11
Design of stubs & attachments:
• Stiffeners to resist driving
accelerations
• Long curved weld extensions
• FE analysis to determine SCFs
FE analysis of Flange Design:
• Pile driving on driving face (40mm)
• Waviness of flange included
• FE analysis to determine Stresses
and SCFs
.................................................................................................
........................................................................
Installation – Mock up/ Pre-assembly
• Full scale trial fit in Hoboken
• Lot of attention for details during design and construction
• Improvements to vessel during installation
• Small damages to coating and a few to steel structures
12
.................................................................................................
........................................................................
Installation - Sequence
13
Transport on Aeolus
Pile upending Lifting pile into position over gripper
Lifting hammer onto pile
.................................................................................................
........................................................................
Installation - Sequence
14
Pile driving, with gripper engaged
Lifting boatlandinginto position
Disengaging gripper
Foundation inspection
Flange measurement
.................................................................................................
........................................................................
Installation - Results
• Second MP out of vertical, exceeding tolerance; wedge adapter flange installed
• Cycle times showed strong learning curve
• New vessel with few teething problems
• Gripper worked very well
• Average inclination < 0.1 degree
• No damage to flanges
• No Lost Time Incidents
15
.................................................................................................
........................................................................
Monitoring
16
• Aim: determine bolt tension variations and tower wall strains
• Strain gauges on 8 bolts
• Strains gauges on tower wall above flange
.................................................................................................
........................................................................
Conclusion
17
Questions?