National Aeronautics and Space Administration Independent Programmatic Analysis for Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23, 2016 Jonathan Drexler (GRC), Lead Programmatic Analyst Bill Lawson (GSFC), Cost Analyst Steve Wilson (JSC), Schedule/JCL Analyst www.nasa.gov

Upload: others

Post on 22-Jun-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

Independent Programmatic Analysis forRadiation Budget Instrument (RBI) Project

At Preliminary Design Review (PDR)

NASA Cost Symposium 2016

August 23, 2016

Jonathan Drexler (GRC), Lead Programmatic AnalystBill Lawson (GSFC), Cost AnalystSteve Wilson (JSC), Schedule/JCL Analyst

www.nasa.gov

Page 2: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Agenda

• Independent Reviews and Background

• Process and Procedures– Cost Assessment– Schedule Assessment– JCL Assessment

• Lessons Learned

Page 3: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov 3

Background• On October 22nd, 2015: NASA Associate Administrator (AA) memo to

reorganize and realign the Agency's independent assessment function – Independent Project Assessment Office (IPAO) disbanded.– Independent assessment of programs and projects continue under the

responsibility and accountability of the Mission Directorates with support from the Centers.

• Radiation Budget Instrument (LaRC) – Late November/early December– First OCFO staffing requirement– Preliminary Design Review (PDR) in April ’16, including JCL

• Programmatic team identified:– Jonathan Drexler, GRC, Programmatic Lead– Bill Lawson, GSFC, Cost Analyst– Steve Wilson, JSC, Schedule/JCL Analyst

Page 4: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Independent Assessments Overview

• The Standing Review Board (SRB) is an independent advisory board that performs the principle independent Life Cycle reviews.

– One SRB for each program or project– Conducts all 7120.5-required independent

reviews for that program or project throughout its life cycle

– Category 1 Projects & Category 2 projects with a life cycle cost > $250M

• SRBs provide the Agency a non-advocate, objective, and competent assessment of the Program/project as it advances through its key decision points (KDP)– RBI -> PDR then KDP-C

• SRB to objectively assesses:– Alignment with and contribution to Agency

strategic goals and adequacy of requirements flow down from those.

– Adequacy of management approach. – Adequacy of technical approach, as defined by

NPR 7123.1 entrance and success criteria. – Adequacy of the integrated cost and schedule

estimate and funding strategy in accordance with NPD 1000.5.

– Adequacy and availability of resources other than budget.

– Adequacy of the risk management approachand risk identification and mitigation per NPR 8000.4.

Review Manager

Subject Matter Expert (SME)

Chair

SME SME

Page 5: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Page 6: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

RBI Other Key Information• New Instrument Development:

– Follow-on to CERES Instrument

– Mass: ~76 kg (CBE) / 90 kg (allocation)

– Power: ~67 W

• JCL (Tecolote on contract to implement)– Joint Analysis of Cost and Schedule (JACS), ~1600 lines Microsoft Project

– Based on Harris IMS, Langley tasks mainly Hammock tasks

• Schedule Considerations– Deterministic schedule includes 6.5 months of funded schedule margin

– All margin at the end

Page 7: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Agenda

• Independent Reviews and Background

• Process and Procedures– Cost Assessment– Schedule Assessment– JCL Assessment

• Lessons Learned

Page 8: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Cost Assessment• Objective: Develop a parametric, benchmark cost estimate then

compare that to RBI plan

• Master Equipment List (MEL) serves as the backbone of this analysis

• Commercial tool set used for RBI cost analysis– PRICE-H for Hardware, SEER-H for Focal Plane, SEER-SEM for Software,

ACEIT for generating S-Curve

• Consistent with the Project:‒ 1 Flight Unit‒ 1 Engineering Development Unit

Page 9: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Desired Implementation Flow

Detailed (e.g, card level)Master Equipment List

(MEL)

Curveball: • 23 Line Master Equipment List

(MEL); not down to component level• MEL not a DRD• Needed to develop a workaround

Page 10: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

RBI Cost Assessment

Project

14 ModuleMass-Tree plus

PDR presentations,engineering judgment

Assessment: • Budget appears sufficient

Page 11: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Schedule Assessment• Benchmark against Historical

– Data Set: ACIS, APS-Glory, CERES, EVE, GSPEC-OCO, HMI, HRC, IRIS, TOMS

• NICM Cross-check

• Health Check with STAT Tool

• Probabilistic Critical Path Assessment (*More later)

• Assessment -> Project schedule is aggressive

Page 12: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

JCL Assessment

• Use the Project JCL as the starting point− Inform SRB on Project assumptions

− Provide framework for SRB adjustments

• Two-step process with SRB members input1. Uncertainty – Cost & Schedule

2. JCL Risks

SRB

Page 13: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

JCL Uncertainty Assessment Framework• JCL assessment framework for uncertainty:

– Based on project’s JCL inputs– D&D activities end at A&T; A&T leads into I&T– Each block represents a group of tasks

• Framework for SRB member input– Don’t differentiate between cost and schedule uncertainty– Independent of discrete risks

Work ElementHW Design and

DevelopmentAssembly & Test (EDU)

Assembly & Test (FU)

Big

Seve

n Subsystem #1 Medium Medium HighSubsystem #2 Medium Medium HighSubsystem #3 Low Medium MediumSubsystem #4 Low Medium HighSubsystem #5 Low Medium MediumSubsystem #6 Medium Medium HighSubsystem #7 Medium Medium MediumSubsystem #8 Medium Medium MediumSubsystem #9 Low Low Low

Integration & Test #1 HighIntegration & Test #2 High

Page 14: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

JCL Uncertainty Score Descriptions

• Mapping of scoring-to-characteristic descriptions calibrates assessment

– Sourced from industry best practices and previous SRB and NASA project analyses

– Categories consistent with project

• Scoring Approach– Scores are a general reflection of

task/WBS item characteristics– Medium [2] is considered Nominal– More scoring bins above nominal based

upon trends from NASA and DOD projects

Page 15: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov15

SRB JCL Uncertainty Assessment • Highlights show were SRB made changes to the JCL

• SRB increased uncertainty mostly in downstream areas (Assembly & Test as well as Integration and Test)

Work ElementHW Design and

DevelopmentAssembly & Test (EDU)

Assembly & Test (FU)

Big

Seve

n Subsystem #1 Medium Medium -> High High -> MediumSubsystem #2 Medium Medium -> High High -> MediumSubsystem #3 Low -> Medium Medium -> High HighSubsystem #4 Low Medium HighSubsystem #5 Low Medium MediumSubsystem #6 Medium Medium HighSubsystem #7 Medium Medium -> High Medium -> HighSubsystem #8 Medium -> High Medium MediumSubsystem #9 Low -> Medium Low -> Medium Low -> Medium

Integration & Test #1 High -> Very HighIntegration & Test #2 High

Page 16: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

SRB JCL Discrete Risk Assessment• Individually assessed Project Risks:

– Risk Register– LxC– Impact: task level and s-curve

RED = Changes since 20 day Data Drop

• Concern –> 3 Driving schedule Risks

• SRB provided 26 candidate risks:1. Potential Risks for Inclusion (12)2. Parking Lot (4)3. Already covered by uncertainty (10)

• SRB Actions:– Deleted (1), adjusted LxC (2), SRB Risks (10) * Risk impacts are assessed individually;

not correlated to the consequence score

Page 17: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

SRB JCL Assessment

SRB Uncertainty

SRB Adjusted RisksProject Risk LxC

Impact on Schedule

S-Curve - DaysRisk #1 3x3 44Risk #2 2x4 21Risk #3 2x4 12Risk #4 2x3 6Risk #5 2x3 5Risk #6 2x3 7Risk #7 3x2 4Risk #8 2x2 0Risk #9 2x3 0

Risk #10 1x3 0Risk #11 2x1 0

Additional SRB Risks

Min Most Max3x3 SRB Additional Risk #1 5 15 30 SS#12x4 SRB Additional Risk #2 10 20 40 SS#12x3 SRB Additional Risk #3 15 30 45 SS#22x3 SRB Additional Risk #4 10 20 30 SS#32x4 SRB Additional Risk #5 10 20 40 SS#42x3 SRB Additional Risk #6 10 20 30 SS#53x2 SRB Additional Risk #7 5 10 15 I&T#12x2 SRB Additional Risk #8 5 10 20 I&T#12x3 SRB Additional Risk #9 10 30 45 SS#62x3 SRB Additional Risk #10 10 20 30 SS#6

Impact (WD)AREALxC Description

Assessment: • Low Confidence

Page 18: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Agenda

• Independent Reviews and Background

• Process and Procedures– Cost Assessment– Schedule Assessment– JCL Assessment

• Lessons Learned

Page 19: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Probabilistic Critical PathNarrows universe of technical assessment areas an assessor should investigate. Ask: Are these PCP logical links appropriate? Example: L1-to-L1 VCTAsk: Parallelism for critical items appropriate given resource constraints, hidden interdependencies?

Discovery: The PCP is the gateway to

focused technical schedule assessment.

Page 20: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

How do we Assess Uncertainty?

1 First looked at History

What was done by other SRBs?

2 Considered CADRe

Are there any ‘standards’? References?3Decided to use the Project Distributions

Focus needs to be on the assessment not differing assumptions (distributions)!

• Uncertainty drives these models!

• How do we ensure consistency across SRBs, Programs, Projects, Mission Directorates and Centers?

Page 21: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov 21

Qualitative Descriptors MatterUncertainty Buckets

• Uncertainty distributions provided by project– Assessment also used the same nomenclature– Not much difference between Low and Med

• SRB reluctance to suggest changes from “Med” to “High”

Project Schedule Distributions

LognormalParameters (Mean, St Dev)

AlternateDistribution

Name

Low Log(102,15) Low

Medium Log(105,15) Low+

High Log(115,20) Med

Very High Log(120,25) Med+

Highest Log(125,25) High

• An alternate naming system likely would’ve produced a much different assessment by SRB

Work ElementHW Design and

DevelopmentAssembly & Test (EDU)

Assembly & Test (FU)

Big

Seve

n Subsystem #1 Low+ Low+ MediumSubsystem #2 Low+ Low+ MediumSubsystem #3 Low Low+ Low+Subsystem #4 Low Low+ MediumSubsystem #5 Low Low+ Low+Subsystem #6 Low+ Low+ MediumSubsystem #7 Low+ Low+ Low+Subsystem #8 Low+ Low+ Low+Subsystem #9 Low Low Low

Integration & Test #1 MediumIntegration & Test #2 Medium

Page 22: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Considerations• Be flexible!

– Definitely have a plan & know what you’d like to do– Nature of these reviews tend to be very fluid– Examples

• Lacked a useful MEL for parametric estimates• Additional SRB Risks post-site review

• Engage early with the SRB Chair, RM, and the SRB– Limited time at site review; pre-brief as much as possible– When caucusing with SRB, try to avoid going last!

• Be prepared to teach at each step– SRB’s need training!– Not all SRB members understand programmatic analysis

Page 23: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Process Considerations• Where does data/models go now that we’re done?

Who gets access?– Still awaiting final instructions on what to do with the data

• Travel Controls– Funding provided to a Center-managed WBS; therefore, the actual

travel to support SRB counted against internal Center controls (causing problems for existing Center travel needs)

– Why isn’t travel held by the MD? Just provide a WBS to charge.– Some logistics still need to be ironed out

• Training!– Analysts supporting the new process need it– SRB Chairs, Review Managers and other SRB Members do too!

Page 24: Radiation Belt Instrument (RBI) Project Preliminary Design ... · Radiation Budget Instrument (RBI) Project At Preliminary Design Review (PDR) NASA Cost Symposium 2016 August 23,

National Aeronautics and Space Administration

www.nasa.gov

Most Important Lesson Learned

• When Charley Hunt bribes you with a beer as he signs you up for this, FOLLOW THROUGH!– See you at the bar at tonight!