public version contains request for confidential treatment · pdf filepublic version contains...

185
PUBLIC VERSION CONTAINS REQUEST FOR CONFIDENTIAL TREATMENT February 16, 2016 The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: ISO New England Inc., Eversource Energy Service Company Docket No. ER16-116 Dear Secretary Bose: On October 19, 2015, Eversource Energy Service Company (“Eversource”) submitted, on behalf of its transmission-owning affiliate, The Connecticut Light and Power Company (“CL&P”), a cost treatment proposal and related tariff revisions to Attachment F of Section II of ISO New England Transmission, Markets and Rates Tariff to recover approximately $15.7 million incurred by CL&P in planning and developing the Central Connecticut Reliability Project (“CCRP”), a component of the New England East West Solution (“NEEWS”) transmission project. On December 16, 2015, the Commission Staff issued a Deficiency Letter asking Eversource to provide additional information on certain categories of costs relating to CCRP, including system planning studies, Allowance for Funds Used During Construction (“AFUDC”), and siting and permitting work. On December 31, 2015, the Commission granted Eversource Energy’s motion for an extension of time to submit the requested information by February 15, 2016. David B. Raskin 202 429 6254 [email protected] 1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com

Upload: buiduong

Post on 21-Mar-2018

246 views

Category:

Documents


2 download

TRANSCRIPT

PUBLIC VERSION

CONTAINS REQUEST FOR CONFIDENTIAL TREATMENT

February 16, 2016

The Honorable Kimberly D. Bose Secretary Federal Energy Regulatory Commission 888 First Street, N.E. Washington, D.C. 20426 Re: ISO New England Inc., Eversource Energy Service Company Docket No. ER16-116 Dear Secretary Bose:

On October 19, 2015, Eversource Energy Service Company (“Eversource”) submitted, on behalf of its transmission-owning affiliate, The Connecticut Light and Power Company (“CL&P”), a cost treatment proposal and related tariff revisions to Attachment F of Section II of ISO New England Transmission, Markets and Rates Tariff to recover approximately $15.7 million incurred by CL&P in planning and developing the Central Connecticut Reliability Project (“CCRP”), a component of the New England East West Solution (“NEEWS”) transmission project.

On December 16, 2015, the Commission Staff issued a Deficiency Letter asking

Eversource to provide additional information on certain categories of costs relating to CCRP, including system planning studies, Allowance for Funds Used During Construction (“AFUDC”), and siting and permitting work. On December 31, 2015, the Commission granted Eversource Energy’s motion for an extension of time to submit the requested information by February 15, 2016.

David B. Raskin 202 429 6254 [email protected]

1330 Connecticut Avenue, NW Washington, DC 20036-1795 202 429 3000 main www.steptoe.com

Kimberly D. Bose, Secretary February 16, 2016 Page 2 of 3

Eversource hereby submits this filing in response to Commission Staff’s December 16, 2016 Deficiency Letter.1 In response to Commission Staff’s request, Eversource is submitting in this filing a number of documents, including copies of invoices, work orders, and other documents relating to third-party consultants who provided assistance to Eversource in connection with the NEEWS Project, including CCRP. As explained further below, Eversource respectfully requests confidential treatment for those materials.

Request for Confidential Treatment Eversource requests confidential treatment for materials and information related to its

vendors and the vendors’ employees. Vendor-specific information, including pricing and employee related information, is competitively sensitive, and disclosure of this information could cause business injury both to Eversource and its vendors. Vendor-specific negotiations/pricing and employee information ordinarily are not made public, and public disclosure of such information could expose Eversource’s and/or its vendors’ pricing positions to competitors. To prevent disclosure of amounts that specific vendors charged, Eversource is retaining in the public version of this filing the amounts that such vendors charged but redacting vendor names and other identifying information associated with such amounts. In addition, certain attachments to this filing contain confidential vendor-specific information and/or information relating to the vendor’s employees throughout the document. As to these documents, Eversource requests confidential treatment for the entire documents.

Pursuant to Order No. 769 and the Commission’s regulations regarding privileged

materials thereunder,2 Eversource provides a public version and a privileged/confidential version of its filing. In the public version, Eversource has redacted certain portions of the Responses and Attachments 3 to 13, 15, 20, and 22 relating to vendor names, as well as removing the vendors’ invoices in Attachments 16, 17, 18, and 21. In the non-public version, Eversource has identified and highlighted the portions of the Responses and attachments that are confidential. In addition, pursuant to the Commission’s regulations, Eversource has marked the confidential version with the designation “CONTAINS PRIVILEGED/CONFIDENTIAL INFORMATION – DO NOT RELEASE.” Eversource also includes with this filing a proposed protective agreement (Appendix A), which individuals may sign to gain access to the confidential materials.3 In addition, in compliance with Commission Staff’s directive in Question No. 5, Eversource is providing proposed tariff revisions to Attachment F of the ISO New England Inc. (“ISO-NE”) Transmission, Markets and Services Tariff (“Tariff”) based upon the currently effective version of Attachment F, as approved by the Commission in Docket No. ER15-1629.

1 Because February 15, 2016 was a federal holiday (President’s Day) and the Commission was

not open for business, Eversource Energy is submitting its Response to the Deficiency Letter today. 2 Filing of Privileged Materials and Answers to Motions, Order No. 769, 141 FERC ¶ 61,049

(2012); see also 18 C.F.R. § 388.112 (2015). 3 Eversource’s October 19, 2015 filing included a proposed form of protective agreement under

Section 388.112 of the Commission’s regulations in connection with its request that certain documents related to Mr. Boguslawski’s testimony be treated as Critical Energy Infrastructure Information (“CEII”).

Kimberly D. Bose, Secretary February 16, 2016 Page 3 of 3

If you have any questions concerning this Response, please do not hesitate to contact the undersigned.

Respectfully submitted, /s/

Phyllis E. Lemell Assistant General Counsel Rosemary K. Leitz Senior Counsel Eversource Energy Service Company P.O. Box 270 Hartford, CT 06141-0270

David B. Raskin Viet H. Ngo Steptoe & Johnson LLP 1330 Connecticut Avenue, NW Washington, DC 20036

Counsel for Eversource Energy Service Company

cc: Jonathan Fernandez Service List (w/attachment)

Eversource Energy Service Company Docket No. ER16-116

Response to Commission Staff Request for Information February 16, 2016

Page 1 of 20

FERC Staff Question No. 1: Eversource’s filing provides the testimony of John C. Case, which reports $916,702 in system planning costs. Identify, quantify and explain in detail the various system planning studies that comprise this cost category.

Response:

Table 1 identifies the system planning studies and associated work performed in connection with the NEEWS Project, including CCRP, identifies the entity that performed the work (including whether it was performed by Eversource’s internal labor or outside consultants), and quantifies the costs associated with each study.4 Further, Eversource explains in detail each system planning study below.

Table 1: System Planning Costs

4 As Mr. Case explains in his testimony, the system planning studies were performed for the

NEEWS Project as a whole, and the associated costs were allocated to the individual NEEWS components, including CCRP, based upon a ratio of each component’s estimated cost relative to Eversource’s total costs for the three NEEWS components. See Testimony of John C. Case (Exhibit No. EE-200) at 6-7. The allocations were approximately as follows: CCRP: 25%; GSRP: 55%; and IRP: 20%. The costs listed in Table 1 represent system planning costs that were allocated to CCRP based upon the 25% ratio. Id.

System Planning Study Source/Vendor Amounts

A

Needs Analysis, Solutions Report, thermal and stability studies, National Grid and ISO-NE coordination and presentations, and support for all aspects of system planning studies

Eversource internal labor (including overheads and indirects)

$275,797

B Alternatives Analysis $221,578

C High Voltage DC Alternative Analysis $18,183

D Temporary Overvoltage Study

$152,376

E Economic Analysis and System Modeling

$168,650

F Transmission Stability Analysis $84,163

G Electromagnetic Field (EMF) Power Flow Modeling $3,098

H One line power flow simulations of needs/solutions $1,696

I Misc. Corrections ($8,839)

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 2 of 20

The $916,702 of system planning costs attributable to CCRP are identified by Eversource’s internal labor (discussed further in subsection A) and contract work/outside services (discussed further in subsections B to H). A. System Planning Study Support - Eversource Internal Labor - $275,797 Eversource’s internal planners and engineers were responsible for the overall planning process and system planning studies related to the NEEWS Project, including CCRP, as well as interactions with regulators, ISO-NE and New England stakeholders. As Mr. David Boguslawski explained in his testimony, there were numerous studies and efforts related to the planning and development of the NEEWS Project, including CCRP.5 These studies were often broad in scope, long in duration, and iterative. There were overlapping issues among the studies, and an Eversource employee was often involved in several system planning studies related to NEEWS throughout the day. Eversource’s planners and engineers were involved in all aspects of the NEEWS/CCRP system planning studies identified in Table 1 above, including the Needs Analysis and Option Analysis/Solutions Report.6 In addition, Eversource’s personnel worked on two additional studies that ISO-NE required in order to reassess the reliability needs of the NEEWS Project, including CCRP: (1) needs re-assessment and confirmation of need in 2010; and (2) verification of solutions and NEPOOL Task Force presentations. As Mr. Boguslawski explains in his testimony, the NEEWS Project was a major, complex addition to the New England 345-kV transmission system.7 Where there were limitations on internal resources due to workload issues, or if the expertise for highly specialized studies was not available internally, Eversource retained outside consultants and engineering firms to assist with the system planning studies. The costs for the outside consultants associated with a specific NEEWS/CCRP planning study are provided below, as well as a detailed explanation of the study:

5 See Direct Testimony of David H. Boguslawski (Exhibit No. EE-100) at 7-9, 13-14 (describing

how the system planners from Eversource and National Grid worked with ISO-NE with respect to the Southern New England Electric Transmission Reinforcement (“SNETR”) Study/Needs Analysis and the Options Analysis and Solution Report. See also Prepared Joint Testimony of David B. Boguslawski of Northeast Utilities Service Company and Paul Renaud of National Grid USA (filed on September 18, 2008 in Docket No. ER08-1548) at 11-12.

6 The ISO-NE planning process includes a Needs Assessment that examines the adequacy of the regional transmission system to maintain reliability while promoting the operation of efficient wholesale electric markets in New England.

7 See Boguslawski Testimony (Exhibit No. EE-100) at 2.

Total System Planning Costs $916,702

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 3 of 20

B. Alternatives Analysis - $221,578

The firms of were retained to assist in developing the alternatives analysis for NEEWS, including CCRP. After determining the electrical need for the NEEWS Project, it was necessary for Eversource planners (working in conjunction with ISO-NE) to establish preferred solutions that would address the needs, and that are feasible, constructible and economical. This effort involved an analysis of numerous electrical scenarios and contingencies, with a large volume of iterations to support the complex NEEWS project. C. High Voltage DC Alternative Analysis - $18,183

Eversource retained to assist with the study of a high voltage direct current (HVDC) solution design option. As an alternative to the standard overhead three phase alternating current design, an HVDC option was studied to test its reliability and other system modifications that such a design would entail. An HVDC alternative would eliminate the high temporary overvoltages and could be more visually appealing since it would require only two conductors rather than three. D. Temporary Overvoltage Study - $152,376

provided support for the Temporary

Overvoltage Study. In the planning process, there was a possibility that a significant portion of CCRP would have to be undergrounded.8 Capacitance of large scale cables that are utilized in underground transmission is much larger than that of an overhead line. This capacitance can lead to high sustained voltages that could cause damage to utility or customer equipment and could result in extended outages. The impact of this capacitance on the transmission network and how to mitigate the impact is analyzed in a Temporary Overvoltage study. E. Economic Analysis and System Modeling - $168,650

Eversource hired to perform economic analysis and system modeling studies to demonstrate the impact that system congestion and the proposed

8 Under Connecticut laws, there is a rebuttable presumption that transmission facilities 345-kV and above should be undergrounded where adjacent to certain land uses. See Testimony of Prepared Joint Direct Testimony of David B. Boguslawski of Northeast Utilities Service Company and Paul Renaud of National Grid USA at 49 (filed on September 17, 2008 in Docket No. ER08-1548) (citing Conn. Gen. Stats. § 16-50p(i), as amended by Public Act 07-04). In addition, Connecticut siting legislation (the Public Utilities Environmental Standards Act) expresses a preference for underground transmission solutions, which the Connecticut Siting Council considers in balancing considerations of need, cost, and environmental impact (See CGS Sec. 16-50l(vi), 16-50p(a)(3)(D), and 16-50r(b)). Accordingly, to secure approval, a proposed overhead transmission line must be compared to a thoroughly investigated, feasible underground alternative and shown to be decisively superior with respect to cost and/or environmental impact.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 4 of 20

NEEWS Project, including CCRP, would have on electricity prices. This economic modeling was heavily dependent on power flows and congestion analysis across various electrical interfaces. Additional economic studies were performed to identify other benefits that a project may provide, such as the impact of the project on tax revenues and jobs. F. Transmission System Stability Analysis - $84,163

was hired to assist Eversource’s planning staff with performing the stability

analysis. Stability analysis is a required study to connect a new transmission project to the existing electrical system, and to demonstrate that the project will not have an adverse system impact. Stability analysis analyzes the dynamics of a power system to determine system performance following a disturbance, to ensure that the disturbance does not result in potential cascading issues. G. Electromagnetic Field power flow modeling - $3,098

assisted Eversource’s planning staff in an analysis of load flow data for

purposes of optimizing the line phasing to minimize Electromagnetic Fields (EMF) of the NEEWS Project. EMF for various project configurations must be studied in connection with the regulatory approval process. The NEEWS Project affected EMF levels along the proposed and alternative routes, and as a result EMF was required to be studied as part of the siting filings. H. One line power flow simulations of needs/solutions - $1,696

Eversource employed s proprietary software simulation models as a resource tool to communicate the complex nature of the power system needs and solutions for the NEEWS Project to stakeholders. These models demonstrated system performance, showed the system deficiencies (needs) and how to address those needs (solutions) with one –line diagrams simulating the power flows on the system, before and after the project was completed. I. Miscellaneous corrections - ($8,839) In 2008 and 2009, charges totaling $8,839 were removed from system planning as part of normal cost review procedures. Corrections for these charges to system planning are reflected as credits to the CCRP work order.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 5 of 20

FERC Staff Question No. 2:

The testimony of John C. Case reports an Allowance for Funds Used During Construction (AFUDC) of $2,489,576. Eversource explains that CL&P accrued AFUDC for the period prior to the Commission granting authorization for CL&P to include CWIP in Local Network Service rates under the ISO New England Tariff in Docket No. ER08-1548. For the AFUDC that Eversource accrued on the CCRP prior to June 1, 2011, provide an excel spreadsheet table showing the CWIP balance that the AFUDC rate was applied to, the AFUDC accrued by year, and the total amount of AFUDC accrued for all of those years combined. Show the amounts accrued for both borrowed funds and other funds.

Response:

See Attachment 1, which is an excel spreadsheet table that shows the CWIP balances for the period March 2007 through May 2011, the AFUDC accrued on a per month basis, and the total amount of AFUDC accrued for the relevant period.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 6 of 20

FERC Staff Question No. 3:

The testimony of John C. Case explains that Eversource incurred $3,366,425 in siting and permitting work for the CCRP, which included the cost of “outreach with the affected towns […], including 19 meetings with town officials, by the project team.”

3. Provide the following information for the costs incurred in the siting and permitting work:

a. Identify all individual charges incurred by date. b. Explain how each individual charge relates to the CCRP. In the explanation, specify

whether the sites and permits are the same as they were for the originally anticipated project.

c. If any expense is not directly related to the CCRP, explain why these costs were not written off to expense.

Response to (a):

Table 2 identifies the major activities that were performed in connection with the $3,366,425 of siting and permitting costs for CCRP, identifies the entity that performed the work (including whether it was performed by Eversource’s internal labor or outside consultants), and quantifies the costs associated with each category.

Table 2: Siting and Permitting Costs

Major Categories of Activities Relating to

CCRP Siting and Permitting Source/Vendor Amounts

Attachment No.

A* Support for all aspects of siting and permitting efforts

Eversource internal labor (including overheads and indirects)

$445,104

2

B* Staff augmentation, project management/support for siting and permitting

$2,528,863 3

C SNETR9 Environmental Feasibility Study of

Routes $42,685

4

D Central Connecticut LIDAR (laser based light detection and ranging) Survey

$4,909 5

E NEEWS Assumptions Analysis $21,960 6

F Development environmental sampling plan, material handling guideline, execution plan

$3,185

7

9 The Southern New England Electric Transmission Reinforcement (“SNETR”) was an earlier

name for the suite of transmission solutions that became NEEWS Project.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 7 of 20

G Consultant for Video Broadcasting Service - expertise in photo, lighting, camera

$718 8

H NEEWS Economic Assessment $1,932 9

I** NEEWS Brochure Design $1,771 10

J** NEEWS Information kiosks for permitting & outreach

$5,507 11

K** Public Relations - Assistance in communications plan and strategy

$318,729 12

L Meals $24 13

M Work Order Adjustments ($8,962)

Total Siting and Permitting $3,366,425

* Portions of the costs in Categories A and B are associated with public outreach and education activities, as explained further in the Response to Question 4. ** The entirety of the costs in Categories I, J, and K relate to services associated with CCRP public outreach and education activities (as discussed in the Response to Question 4). In addition to Table 2 above, the corresponding attachment labeled in the last column identify all individual charges by date:10

• Attachment 2 provides charge information by month for Eversource’s internal labor (Item A in the table);

• Attachment 3 provides charge information by month for (Item B); and • Attachments 4-13 provides charge information by month for Items C through L

Response to (b): All of the charges/activities identified in Table 2 and the supporting attachments (Attachments 2 to 13) are attributable to the siting and permitting of CCRP. The preferred “site” for CCRP and the permits expected to be required for it never changed from the project’s inception until it was subsumed into the Greater Hartford Central Connecticut Reliability Project (“GHCC”) 115-kV projects. However, various alternative routes and variations, including an all underground route, were necessarily investigated. The preferred site for the 345-kV CCRP transmission line was an approximately 37 mile long right-of-way between CL&P’s Frost Bridge Substation in Watertown, CT and its North Bloomfield Substation in Bloomfield, CT. The principal permits expected to be required were a certificate of environmental compatibility and public need from the Connecticut Siting Council and a Section 404 permit from the United States Army Corps of

10 In Attachment 2, Eversource is providing charge information for the CCRP-related siting and

permitting work for its internal employees on monthly basis for comparability with other data. Eversource notes that its employees are paid on a bi-weekly basis.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 8 of 20

Engineers. The need for which CCRP was originally designed (increasing transfer capacity from east to west across the Western Connecticut Import Interface) will be addressed by a proposed underground line between two different substations (Newington and Southwest Hartford). This is the GHCC 115-kV project, which is still in development. However, another 115-kV overhead transmission line project in the Greater Hartford suite of 115-kV projects is proposed to be constructed on a 10.4 mile segment of the right-of-way previously designated for CCRP. This is the Frost Bridge to Campville project, for which a Siting Council application was filed in December 2015. The same major permits will be required for this project as would have been required for CCRP.11 Some of the environmental analyses of the preferred route, as well as many of the outreach efforts undertaken for CCRP have been useful in composing and prosecuting the Frost Bridge to Campville siting and permitting applications. The segment of right-of-way on which the Frost Bridge to Campville line is proposed to be built traverses four of the eight towns that would have been hosts to the CCRP line (Watertown, Thomaston, Harwinton, and Litchfield). Below Eversource provides a more detailed discussion of each category of activities/charges incurred in connection with the siting and permitting of CCRP.12 A. Siting and Permitting Support - Eversource Internal Labor $445,104

Eversource employees and personnel worked on a number of activities relating to the siting/permitting of CCRP, including the following activities, which were required as part of the state and local regulatory proceedings and permitting processes for CCRP:

1. Alternatives route analysis a. Environmental feasibility and characterization for comparison of all potential

alternatives was performed. In the evaluation of project alternatives, it was necessary to evaluate each alternative based upon its environmental impacts in order to provide insight into the feasibility, potential siting and permitting risks, and benefits of the project in relation to other alternatives.

2. Development of Municipal Consultation Filing (“MCF”)

11 As explained further in the Mr. Boguslawski’s testimony, ISO-NE approved the NEEWS

Project under Section I.3.9 of the ISO-NE Tariff in September 2008; subsequent to this approval, ISO-NE re-evaluated the reliability needs for the NEEWS components to reflect changes in system conditions. See Boguslawski (Exhibit No. EE-100) at 3-4;15-20.

12 In his testimony, Mr. Boguslawski describes the circumstances surrounding the development and evolution of CCRP as one originally designed component of an overall integrated transmission project that was redesigned and subsumed into a successor transmission project. See Exhibit No. EE-100 at 2-5. Mr. Boguslawski also explains that based upon the circumstances surrounding CCRP, it would be reasonable and appropriate to recover the CCRP costs as part of the NEEWS Project, rather than part of the new GHCC project. As Mr. Boguslawski explains, the new GHCC project was not proposed as a transmission project until July 2014 and did not receive Section I.3.9 approval from ISO-NE until April 16, 2015. Id. 33-34.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 9 of 20

a. Once Eversource selected the preferred alternative routes for the project, Eversource developed the MCF, which was required as part of the state siting process for CCRP. The MCF content and volume is very similar to the actual siting filing and is used to help explain the project to the affected municipalities. The development of the MCF included environmental field work, such as wetlands flagging and characterization, and quantifying and minimizing impacts to resource areas. This also included the drafting and review of the MCF documents. After completing the filing, public outreach is conducted (see item 5, below), in the form of delivering and explaining the MCF to the affected municipalities and later receiving informed comments and input from the affected municipalities. This input is then considered in the finalization of the siting filing.

3. Work Activities related to the pre-filing of the siting application and preparation of the application included:

i. Preparation for and presentation to the Local Inland Wetland Commission for Locational Review.

ii. Connecticut Department of Environmental Protection Natural Diversity Database (Threatened and Endangered species) consultation and review

iii. Development of the Connecticut Siting Council application, including the solutions report.

4. Army Corps of Engineers Permit application a. An Army Corps of Engineers (“ACOE”) permit is a lengthy, involved process

(typically 12-18 months) and requires an intensive amount of investigation and documentation to be prepared in advance of a filing. Work began on this regulatory filing immediately after Eversource identified a preferred solution for CCRP, and the CCRP team advanced several of the efforts required to support an ACOE permit application, including but not limited to:

i. Phase 1 Environmental Assessment (Hazardous material investigation); ii. Phase 1 cultural resource review; and

iii. U.S. Fish and Wildlife preparation and consultation

5. Public outreach and education efforts relating to CCRP a. As a state regulated utility, Eversource engages in public outreach and education

activities at the outset of every major utility project, including transmission projects. Such public outreach and education, including the municipal consultation process, is not only required under Connecticut laws as part of the siting process, but is also important to maintain Eversource’s standing in the communities we serve, and is good corporate stewardship. Public outreach and education includes the pre-siting efforts that inform and educate landowners and homeowners who may be impacted by the project, as well as the various stakeholders (municipalities, communities, businesses, local organizations, and environmental groups). This public outreach and education process is essential to

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 10 of 20

alleviate concerns, answer questions, and address solutions that are related to transmission siting. The specific public outreach and education activities, including the municipal consultation process, that were performed in connection with CCRP are discussed further in the response to Question No. 4. As explained in the Response to Question No. 4, none of the costs that are included as part of the CCRP public outreach and education efforts are costs that related to lobbying activities or to influence public officials with respect to the siting/permitting of CCRP.

B. Siting and Permitting Support - $2,528,863

Due to the large size and scope of the NEEWS Project, including CCRP, it was necessary for Eversource to retain outside support to augment its internal staff to ensure compliance with regulatory filings in accordance with the required project schedule. Eversource retained

, a well-recognized fully integrated engineering, architecture, construction, environmental, and consulting firm that provides consulting services relating to, among other things, transmission construction. was engaged to provide expertise and resources in several project areas, including the siting and permitting of the NEEWS Project, including CCRP. personnel provided support and assistance with respect to the siting/permitting work activities performed by Eversource’ employees, as discussed above. Individuals at involved in the siting and permitting activities had their time and charges allocated to the appropriate category of costs, but not to specific tasks or activities within those categories. C. Environmental Feasibility Study of Routes - $42,685

performed a high-level analysis and comparison of the environmental aspects of the various NEEWS Project routes, and associated mapping of the routes. This work provided the basis for performing a quantitative and qualitative comparison of the possible routes to facilitate the selection of feasible and preferred routes. D. LIDAR Survey - $4,909

performed a laser based light detection and ranging (“LIDAR”) survey

of the proposed CCRP route, providing a topographical survey with input on terrain and vegetation along the project corridor, which assisted Eversource’s efforts in designing the transmission line. E. NEEWS Assumptions Analysis - $21,960 Eversource retained an internationally recognized expert in bulk power reliability, to review the assumptions that were used in the planning and development of NEEWS, including CCRP. Mr. Loehr also advised Eversource as to the reliability standards and

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 11 of 20

criteria of North American Electric Reliability, Northeast Power Coordinating Council, and ISO-NE. F. Project Environmental Plans Development - $3,185 Eversource retained an environmental and infrastructure consulting, to develop several plans for the NEEWS Project, including an environmental sampling plan, material (contaminated soil and water) handling guideline, and an execution plan. G. Video Broadcast Services - $718 The NEEWS Project siting work required the assistance of various video services, including recording project information videos for the open houses, which were conducted as part of Eversource’s public outreach and education efforts. H. NEEWS Economic Assessment - $1,932

worked with the NEEWS Project team as an independent economist responsible for reviewing the economic models and job analysis projections for the NEEWS Project. I. NEEWS Brochure - $1,771 The was hired to assist in developing all NEEWS information brochures, mapping, and handouts as part of Eversource’s public outreach and education efforts.

J. NEEWS Information Kiosks for Permitting and Outreach - $5,507

The NEEWS Project team developed kiosks for the open houses related to the NEEWS Project, including CCRP, that were subject specific (i.e., EMF, engineering, vegetation management).

, an exhibit company, designed and constructed the kiosks that were used during the NEEWS open house events. The charges for this vendor and allocated to CCRP were primarily associated with the storage fees and that were incurred for the time between open house events.

K. Communication Plans and Public Outreach Strategy – $318,729

Eversource retained , a public relations and strategic communications firm, to assist in the development of NEEWS communications plans, stakeholder identification, and public outreach and education. Specifically, this firm was retained to assist in organizing, managing, supporting and executing communications with key

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 12 of 20

stakeholders in support of the overall NEEWS Project, including CCRP. The services that this firm provided to CCRP are discussed further in the Response to subpart (d) to Question 4.

L. Meals - $24 Eversource’s records show that in November 2010, there was a charge of $24 for food service from the on-site cafeteria at Eversource’s Berlin, CT facility.

M. Work order adjustments In 2008, there was a net credit in the amount of $7,435 in the CCRP work order, and in 2009, a credit in the amount of $1,527 was recorded to the CCRP work order. It appears that both credits belong to Eversource’s three NEEWS components, not just CCRP. Eversource is researching both issues and will adjust the CCRP work order, as appropriate. Response to (c): All of the charges included in Table 2 were directly related to CCRP – i.e., they were charges incurred by CL&P to plan and develop the original design of CCRP as part of the costs of the overall NEEWS Project. Even those charges that were common to the NEEWS components (i.e., referred to as “NEEWS Programmatic Costs” in the filing and explained further in Mr. Case’s testimony), and allocated to CCRP, were directly related to CCRP because those common efforts/activities allowed CCRP (and the other NEEWS components) to benefit from the prior and shared experience, lessons learned and work efforts. This resulted in more efficient and streamlined process and quicker resolution of issues related to the NEEWS Project, including CCRP. These are appropriate capital costs for CCRP and were not written off to expense. In addition, to ensure costs are tracked and recorded accurately, Eversource project managers, cost analysts and contract administrators reviewed timesheets, invoices and schedules and budgets regularly to ensure proper charging as part of Eversource’s accounting process.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 13 of 20

FERC Staff Question No. 4:

Identify the siting and permitting costs associated with public outreach and education and provide the following details:

a. Identify the specific activities for which these costs were incurred and the individual cost of each specific activity.

b. Explain why each activity was necessary for the CCRP. c. Provide documents that plainly explain the nature and purpose of the expenditures

and the intended outcome after the expenditures were made. d. Explain whether third-party consultants were utilized to perform public outreach

and education and if so, provide the names, and the roles of the consultants, as well as copies of the invoices, work orders, and contracts describing the nature of the consultants’ work for these activities.

Response to (a): Within the siting and permitting category of costs for CCRP, approximately $656,195 are charges associated with Eversource’s public outreach and education. Table 3 identifies the major activities/tasks and the associated costs related to Eversource’s public outreach and education efforts.

Table 3: Public Outreach and Education Costs

Siting and Permitting – Public

Outreach/Education (O&E)Activities Source/Vendor Amounts

Attachment No.

A Support for all aspects of public outreach and education efforts

Eversource internal labor (including overheads and indirects)

$250,153

14

B Staff augmentation, project management/support for public outreach and education

$80,035 15

I Design NEEWS Brochure $1,771 10, 16

J NEEWS Information kiosks for permitting & outreach (storage)

$5,507 11, 17

K Public Relations – Assistance in communications plan and strategy

$318,729 12, 18

Total Siting and Permitting Public Outreach/Education

$656,195

Note that the charge information provided in Table 3 relating to public outreach and education is a subset of the information provided in Table 2: Siting and Permitting Costs.

A portion of the charges attributable to the siting and permitting in categories A and B (i.e., Eversource internal labor and charges), as well as the entirety of the charges attributable to categories I, J, and K were associated with employees performing public outreach and

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 14 of 20

education functions. The major public outreach and education activities related to NEEWS, including CCRP, are set forth below:

• Developed proactive public outreach and education plans for various issues pertaining to the following:

• Stakeholder identification • Business interruption/coordination, including farmland and

crop loss • Landowner Issues, such as easement acquisition, right of way

encroachment reviews and removals, planning for landowner wood retention from clearing activities, and access roads.

• Construction protocols, such as vegetation and clearing activities.

• Parks and trails and public recreation areas

• Established and monitored the NEEWS Project communication tools, such as:

• A dedicated Project Hotline and email link from the website to facilitate inquiries from stakeholders, with a targeted response time of 24 hours or the next business day

• A comprehensive project website (www.NEEWSprojects.com)

• NEEWS informational brochures

• Consultation meetings with municipal officials

• As discussed further below, Eversource was required under Connecticut law (Conn. Gen. Stat. § 16-50l (e)) to consult with the municipality in which the transmission project is proposed to be located and with others affected at least sixty days prior to the filing of a siting application with the Connecticut Siting Council.

• Develop and staff public open houses

• NEEWS information kiosks

In connection with Commission Staff’s question for the costs of individual activities, Eversource’s employees who worked on public outreach and education activities relating to the

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 15 of 20

NEEWS Project, including CCRP, did not keep track of their time based upon specific work activities, but charged their time to a CCRP work order.13

In addition to Eversource’s internal labor, Eversource also retained third party consultants, as identified in Table 3, and the public outreach and education related services that they provided are discussed further below and in the Response to Question No. 3.

Response to (b): The major activities identified in Table 3 above are related to Eversource’s public outreach and education activities as part of Eversource’s effort to site and permit the NEEWS Project, including CCRP. In the 2008 order granting NEEWS transmission incentives under Order No. 679, the Commission recognized the significant risks that the NEEWS Project faced, including “multiple regulatory risks associated with siting and permitting authorization, as well as public opposition to the routing of the Project components.”14 To mitigate these risks, it was necessary for Eversource to have an effective public outreach and education program in place for the suite NEEWS Projects, including CCRP, to communicate and provide relevant information related to the NEEWS Project to the public and affected stakeholders in New England, including Eversource’s customers, affected towns and municipalities, homeowners and residents, neighboring utilities, businesses, organizations, community groups and federal and state regulators.

Unlike a newly-created, stand-alone entity that seeks to develop a proposed transmission project (such as a Transco), CL&P is a state regulated utility, and along with its other operating company affiliates, has been providing electric distribution and transmission service to customers in New England for many decades. As existing regulated utilities providing reliable electric services to the public, regulatory obligations and good corporate stewardship requires frequent and comprehensive education and dialogue with customers, regulators and other interested entities. As the Commission recognizes, building new transmission facilities faces a host of complex challenges, and siting of transmission cannot be conducted efficiently or timely without such extensive outreach and communication. Eversource has successfully used this outreach process to build some of the most challenging regionally-needed transmission reliability projects in New England.

13 See Case Testimony (Exhibit No. EE-200) at 17-18 (describing that Eversource tracks and

record NEEWS costs on a component-by-component basis and that CCRP, like other project components, was assigned a specific project number that served as the “parent” work order number and there were several other sub work orders that rolled up to the CCRP parent project number).

14 See Northeast Utilities Service Co., 125 FERC ¶ 61,183 P 31 (2008) (“2008 NEEWS Incentive Order”), rehearing denied, 135 FERC ¶ 61,270 (2011).

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 16 of 20

Not only were Eversource’s public outreach and education efforts important for good corporate stewardship purposes, they were also required under Connecticut laws. Specifically, related to its siting application process, under a Connecticut siting laws, Eversource was required to engage in a municipal consultation process prior to submitting its siting application with the Connecticut Siting Council and other state and local agencies.15 Specifically, Connecticut General Statutes § 16-50l (e) provides as follows:

… at least sixty days prior to the filing of an application with the council, the applicant shall consult with the municipality in which the facility may be located and with any other municipality required to be served with a copy of the application under subdivision (1) of subsection (b) of this section [any adjoining municipality having a boundary not more than 2500 feet from such facility] concerning the proposed and alternative sites of the facility… Such consultation with the municipality shall include, but not be limited to good faith efforts to meet with the chief elected official of the municipality. At the time of the consultation, the applicant shall provide the chief elected official with any technical reports concerning the public need, the site selection process and the environmental effects of the proposed facility.

Once the required initial contact with the municipal chief elected official is made, the town typically requests broader official consultations and presentations to the public. Thus, in connection with the municipal consultation requirement discussed above, Eversource held informational and briefing meetings with municipal officials in the affected municipalities and towns in Connecticut. Several of these meetings were public Board of Selectmen meetings. Eversource’s records indicate that the NEEWS Project team had the following meetings with Connecticut municipalities and towns specific to CCRP:

• Watertown on January 29, 2009 and October 8, 2009;

• Thomaston on April 1, 2009 and September 1, 2009;

• Simsbury on April 2, 2009 and September 14, 2009;

• New Hartford on March 20, 2009;

• Litchfield on March 10, 2009 and August 18, 2009;

15 In the 2008 NEEWS Incentive Order, the Commission noted that this municipal consultation

process is designed to obtain input and comments from the public and government representatives in each of the Connecticut municipalities in which the preferred or alternative routes of the proposed project is located. See NEEWS 2008 Order at P 32.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 17 of 20

• Harwinton on March 19, 2009 and August 19, 2009;

• Canton on January 29, 2009 and October 7, 2009; and

• Bloomfield on March 23, 2009.16

In these meetings, the NEEWS Project team typically provided an overview of the NEEWS Project, including CCRP, and the reliability need on the transmission system that the NEEWS Project and its components were designed to address, the proposed project scope, project benefits, and expected timeline. To provide Commission Staff information as to the purpose of these meetings, Attachment 19 contains a PowerPoint presentation dated October 8, 2009 that was used to provide a briefing to the Town Manager of the Town of Watertown. This presentation is consistent with the public outreach conducted in similar meetings with public and municipal officials. Eversource believes that its public outreach and education efforts were effective in informing and educating the public and stakeholders of the NEEWS Project, including CCRP, and was an important factor in the timely and cost-effective construction of a major transmission project that provides benefits to customers in New England. In particular, Eversource’s component projects of NEEWS that have been completed (the Greater Springfield Reliability Project (“GSRP”) and Interstate Reliability Project (“IRP”)) were completed and placed in service on or ahead of schedule, and on or under budget. Eversource believes that this was directly attributable to the effective public outreach and education efforts that Eversource undertook.

Response to (c) and (d): Table 3 identifies the third-party consultants who assisted Eversource with its public outreach and education efforts. A description of the services that these third-party consultants provided to Eversource is discussed below. In addition, Eversource is providing documents that further describe the scope of the consultants’ work, as well as related invoices with respect to the public outreach and education assistance provided to Eversource. Of the five third-party consultants identified in Table 3, the two principal firms that provided public outreach and education assistance to Eversource were: (1) ; and (2)

16 Citing to page 10 of John Case’s testimony (Exhibit No. EE-200), Commission Staff stated

Eversource had “19 meetings with town officials, by the project team.” At the referenced page, Mr. Case did not specify the number of meetings that Eversource had with town officials.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 18 of 20

The public outreach and education services that agreed to provide to Eversource is set forth in the 2009 New England East-West Solution Project Execution Plan. This document sets forth all the various services that agreed to provide to Eversource, including public outreach and education services. The executive summary and relevant excerpts from the Project Execution Plan pertaining to public outreach and education services are attached in Attachment 20. In particular, the document noted the significant public opposition risks to a major transmission project such as the NEEWS Project and its components, and sets forth a comprehensive strategy to mitigate these risks through effective communications with stakeholders, including municipalities, residents, businesses, community-based organizations, through the various phases of siting and construction of the transmission project. The staff member who assisted Eversource’s public outreach and education efforts consisted of one person ( Public Relations Manager). provided input into Eversource’s public outreach and education plans and strategies that would eventually be responsible for executing during the project. provided public outreach and education related services between January 2009 and April 2011. Invoices associated with time for each of those months are identified and included in Attachment 21. The total costs allocated to the public outreach category reflect a combination of time/billable hours plus an allocated amount for overhead costs, such as general office charges.17

is a public relations firm with capabilities in brand management, media, public, municipal, government and investor relations. was hired to assist in the development of public outreach and education strategies and plans to communicate information on the NEEWS Project to potential project stakeholders. Specifically, helped to plan, organize, manage and support outreach activities with a particular focus on preparing for and successfully executing outreach associated with Connecticut’s mandatory MCF process. also provided support and assistance to the public outreach and education activities performed by Eversource’s employees, as discussed in the response to Question No. 4(a) above. did not engage in lobbying activities for the NEEWS Project or CCRP.18 The scope of public outreach and

17 See also note c of Attachment 3 (describing how the allocated portion was determined). 18 Consistent with the Commission’s Uniform System of Accounts, Eversource records lobbying

activities to FERC Account No. 426.4, which provides that lobbying activities consist of “expenditures for the purpose of influencing public opinion with respect to the election or appointment of public officials, referenda, legislation, or ordinances…or approval, modification, or revocation of franchisees; or for the purpose of influencing the decisions of public officials.” Eversource’s activities that fall into the scope of Account 426.4 were not charged to the NEEWS Project, including CCRP, but recorded to FERC Account 426.4 in accordance with the Commission’s rules, and not recovered in transmission rates.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 19 of 20

education services provided by is set forth in Attachment 22.19

Two employees supported Eversource’s public outreach and education efforts: (1) ; and (2) were hired on a fixed-

price monthly amount, and all associated monthly invoices for their services charged to CCRP are provided in Attachment 18.

Other Vendors Who Provided Services Related to Public Outreach and Education The two other outside consultants provided assistance related to Eversource’s public outreach and education efforts: The activities/services provided by these vendors are described in the Response to Question No. 3. As explained, the services provided by these consultants were relatively limited in scope, such as the design of the NEEWS information brochures and NEEWS kiosks for open house events to inform and educate the public of the NEEWS Project, including CCRP. Copies of the invoices of these consultants are provided in Attachments 16-17.

19 The individuals at who were engaged by Eversource for the public outreach/education

efforts associated with the NEEWS Project are not the same individuals who work for the separately-incorporated lobbying branch of . While Eversource has engaged the lobbying branch of for lobbying support at the corporate level, the charges associated with those efforts are charged to separate purchase orders that are specifically excluded from any project costs.

Eversource Energy Service Company Docket No. ER16-116-000

Response to Commission Staff Request for Information February 16, 2016

Page 20 of 20

FERC Staff Question No. 5:

Eversource’s proposed revisions to Attachment F of the ISO New England Tariff do not reflect tariff revisions included in the currently effective version of Attachment F, which were accepted by the Commission in Docket No. ER15-1629-000, effective June 1, 2015. Eversource is directed to have ISO New England re-submit the proposed revisions to Attachment F of the ISO New England Tariff to recover the approximately $15.7 million in costs for the CCRP based on the current effective version of the ISO New England Tariff.

Response: As directed by Commission Staff, Eversource is re-submitting its proposed tariff revisions to Attachment F of the ISO New England Tariff (clean and redlined) using the currently effective version of Attachment F, which was accepted by the Commission in Docket No. ER15-1629, effective June 1, 2015.

ATTACHMENT F

ANNUAL TRANSMISSION REVENUE REQUIREMENTS

The Transmission Revenue Requirements for each PTO will reflect the PTO’s costs with respect to Pool

Supported PTF and the HTF, including costs attributable to those PTOs deemed to own or support PTF

pursuant to Section II.49 of the Tariff. The Transmission Revenue Requirements will be an annual

calculation based on the previous year’s calendar data as shown, in the case of PTOs that are subject to

the Commission’s jurisdiction, in the PTO’s FERC Form 1 report for that year; provided, however, that if

a PTO is deemed to own or support PTF pursuant to Section II.49 of the Tariff, such PTO may include

the costs as incurred by its Related Person for PTF facilities and Transmission Support Expenses as the

basis for establishing its initial and subsequent Annual Transmission Revenue Requirements, only until

such PTO has a full calendar year of cost data under its ownership. Such PTO’s costs will be determined

from FERC Form 1 data if available, or if not available, from other supporting data certified by an auditor

of the PTO or Related Person, and in a format comparable to that used to report such costs in FERC Form

1. Such costs shall be based on actual data in lieu of allocated data if specifically identified in the Form 1

report in accordance with the following formula and Schedule 12:

I. The Transmission Revenue Requirement shall equal the sum of the PTO’s (A) Return and

Associated Income Taxes, (B) Transmission Depreciation and Amortization Expense, (C)

Transmission Related Amortization of Loss on Reacquired Debt, (D) Transmission Related

Amortization of Investment Tax Credits, (E) Transmission Related Municipal Tax Expense, (F)

Transmission Related Payroll Tax Expense, (G) Transmission Operation and Maintenance

Expense, (H) Transmission Related Administrative and General Expense, (I) Transmission

Related Integrated Facilities Charges, minus (J) Transmission Support Revenue, plus (K)

Transmission Support Expense, plus (L) Transmission Related Expense from Generators, plus

(M) Transmission Related Taxes and Fees Charge, minus (N) Revenue for Short-Term service

under the OATT and (O) Transmission Rents Received from Electric Property.

The details for implementation of Attachment F, as well as the definitions of the terms used in the

Attachment F formula, shall be established in accordance with the Attachment F Implementation Rule

contained in this OATT.

ATTACHMENT F

IMPLEMENTATION RULE

This rule sets forth details with respect to the determination each year of the Transmission Revenue

Requirements for each PTO. Such Transmission Revenue Requirements shall reflect the PTO’s costs for

Pool Transmission Facilities (“PTF”) and the Highgate Transmission Facilities (“HTF”), including costs

attributable to those PTOs deemed to own or support PTF pursuant to Section II.49 of the Tariff. The

Transmission Revenue Requirements for each PTO will reflect the PTO’s costs with respect to Pool

Supported PTF and the HTF. The Transmission Revenue Requirements will be an annual calculation

based on the previous year’s calendar data as shown, in the case of PTOs which are subject to the

Commission’s jurisdiction, in the PTO’s FERC Form 1 report for that year; provided, however, that if a

PTO is deemed to own or support PTF, such PTO may include the costs as incurred by its Related Person

for PTF facilities and Transmission Support Expenses as the basis for establishing its initial and

subsequent Annual Transmission Revenue Requirements, only until such PTO has a full calendar year of

cost data under its ownership. Such PTO’s costs will be determined from FERC Form 1 data if available,

or if not available, from other supporting data certified by an auditor of the PTO or Related Person, and in

a format comparable to that used to report such costs in FERC Form 1. Such costs shall be based on

actual data in lieu of allocated data if specifically identified in the Form 1 report in accordance with the

following formula and Schedule 12. The HTF Transmission Revenue Requirements shall be subject to the

limitations of inclusion of such costs as set forth in Appendix B to this Attachment. The owners of the

HTF, or their designated agent, will submit the annual HTF Transmission Revenue Requirements

calculation based on the previous calendar year's cost data from their FERC Form 1 or equivalent

information from their official books and records, as appropriate.

The Post-96 Transmission Revenue Requirement for each PTO that is based on data for calendar year

2004 or later shall include an Incremental Return and Associated Income Taxes on the PTO's PTF

transmission plant investments included in the Regional System Plan and placed in-service on or after

January 1,2004 (such investments referred to herein as "Post-2003 PTF Investment"). The Incremental

Return and Associated Income Taxes for Post-2003 PTF Investment shall incorporate an incentive ROE

adder of 100 basis points for plant investment placed in service by December 31, 2008 or as otherwise

permitted in Docket Nos. ER04-157, et al. for any projects included in the RSP, and shall incorporate any

incentive ROE adder approved by the FERC under Order No. 679 for other plant investments (however;

the 125 basis point ROE incentive adder granted to NEEWS under Order No. 679 in Docket No. ER08-

1548 and the 50 basis point ROE incentive adder for RTO participation shall not apply to the costs related

to the Central Connecticut Reliability Project, consistent with FERC’s order) and for MPRP CWIP and

NEEWS CWIP. The total ROE for any project, including any authorized ROE incentives for Post-2003

PTF Investment and any other incentive ROE approved by FERC under Order No. 679 shall be capped by

the top of the applicable zone of reasonableness determined by FERC for the relevant period. The data

used in determining each PTO's Incremental Return and Associated Taxes for Post-2003 Investment shall

be based on actual data in lieu of allocated data if specifically identified in the PTO's accounting records.

The Post-1996 Pool PTF Rate, as calculated pursuant to Schedule 9, shall include for each PTO a

Forecasted Transmission Revenue Requirement calculated in accordance with Appendix C to this

Attachment F Implementation Rule. Additionally, the Pre-1997 and Post-1996 Pool PTF Rates shall

include an Annual True-up calculated in accordance with Appendix C to this Attachment F

Implementation Rule.

The PTOs shall make an annual informational filing on or before July 31 of each year showing the Pool

PTF Rate in effect for the period beginning June 1 of that year through May 31 of the subsequent

year.Further, the informational filing with respect to the determination of the Pool PTF Rate will include a

breakdown by PTO of the amount of the change in PTF and HTF investment during the prior year and the

PTF and HTF retirements or additions causing such change to beginning and end-of-year PTF balances

and HTF balances (although beginning-of-year PTF balances and HTF balances are not used in the

formula itself), and any additions to PTF and HTF, retirements of PTF and HTF, and reclassifications of

PTF and HTF during the year for each PTO. If there are any corrections made to the information reflected

in the informational filing after it has been submitted, the PTOs will file corrections to the informational

filing. At least forty-five days before the informational filing is made with the Commission, the PTOs

shall make available to Transmission Customers and any other interested parties a draft of the proposed

filing for review and comment prior to the filing by posting such draft on the ISO website. The filing of

the information filing does not re-open the formula rate set forth below for review, but rather is

contestable only with respect to the accuracy of the information contained in the informational filing.

The ISO shall have the discretion to conduct audits of such charges, with advisory Stakeholder input on

the scope of audit, including on any agreed-upon procedures to be used by the auditor. In this provision,

the term “agreed-upon procedures” shall have the meaning afforded to it by the American Institute of

Certified Public Accountants.

I. DEFINITIONS

Capitalized terms not otherwise defined in the Tariff and as used in this rule have the following

definitions:

A. ALLOCATION FACTORS

1. Transmission Wages and Salaries Allocation Factor shall equal the ratio of Transmission-

related direct wages and salaries including those of affiliated Companies to the PTO’s

total direct wages and salaries including those of the Affiliates’ Companies and excluding

administrative and general wages and salaries.

2. PTF/HTF Transmission Plant Allocation Factor shall equal the ratio of PTF/HTF

Transmission Plant to Total Investment in Transmission Plant, excluding capital leases in

the Phase I/II HVDC-TF (Phase I/II HVDC-TF Leases).

3. Plant Allocation Factor shall equal the ratio of the sum of Total Investment in

Transmission Plant, excluding Phase I/II HVDC-TF Leases, and Transmission Related

Intangible and General Plant to Total Plant in service excluding Phase I/II HVDC-TF

Leases.

B. TERMS

Administrative and General Expense shall equal the PTO’s expenses as recorded in FERC

Account Nos. 920-935, excluding FERC Account Nos. 924, 928 and 930.1.

Amortization of Loss on Reacquired Debt shall equal the PTO’s expenses as recorded in FERC

Account No. 428.1.

Amortization of Investment Tax Credits shall equal the PTO’s credits as recorded in FERC

Account No. 411.4.

Depreciation Expense for Transmission Plant shall equal the PTO’s transmission expenses as

recorded in FERC Account No. 403.

General Plant shall equal the PTO’s gross plant balance as recorded in FERC Account Nos. 389-

399.

General Plant Depreciation and Amortization Expense shall equal the PTO’s general

expenses as recorded in FERC Account No. 403 and NSTAR Electric’s FERC Account No. 404

for items subject to amortization.

General Plant Amortization Reserve shall equal NSTAR Electric’s general reserve balance as

recorded in FERC Account No. 111.

HTF Transmission Plant shall equal the PTO's balance of investment in the Highgate

Transmission Facilities as recorded in FERC Account Nos. 350-359.

Intangible Plant shall equal NSTAR Electric’s gross plant balance as recorded in FERC Account

No. 303. The only allowable Intangible Plant for inclusion are software, patent or rights costs.

Intangible Plant Amortization Expense shall equal NSTAR Electric’s amortization expenses as

recorded in FERC Account Nos. 404-405. The only allowable Intangible Plant Amortization

Expense for inclusion is the amortization of software, patent or rights costs.

Intangible Plant Amortization Reserve shall equal NSTAR Electric’s amortization reserve

balance as recorded in FERC Account No. 111. The only allowable Intangible Plant

Amortization Reserve for inclusion is that related to the amortization of software, patent or rights

costs.

Maine Power Reliability Program Construction Work In Progress ("MPRP CWIP") shall

equal Central Maine Power Company's ("CMP's") MPRP CWIP balance as recorded in FERC

Account No. 107 for costs determined to be Pool- Supported PTF in accordance with Schedule 12

of this OATT.

New England East-West Solution Construction Work in Progress (“NEEWS CWIP”) shall

equal the NEEWS CWIP balances of The Connecticut Light and Power Company (“CL&P”) and

Western Massachusetts Electric Company (“WMECO”) and New England Power Company

(“NEP”) as recorded in FERC Account No. 107 for costs determined to be Pool-Supported PTF

in accordance with Schedule 12 of this OATT.

Other Regulatory Assets/Liabilities - FAS 106 shall equal the net of the PTO's FAS 106

balance as recorded in FERC Account 182.3 and any FAS 106 balance as recorded in the PTO's

FERC Account No. 254.

Other Regulatory Assets/Liabilities - FAS 109 shall equal the net of the PTO's FAS 109

balance in FERC Account No. 182.3 and any FAS 109 balance as recorded in the PTO's FERC

Account No. 254.

Payroll Taxes shall equal those payroll expenses as recorded in the PTO's FERC Account Nos.

408.1.

Phase I/II HVDC-TF Leases shall equal the PTO's balance in capital leases as recorded in

FERC Account Nos. 350-359 and FERC Account Nos. 389-399.

Plant Held for Future Use shall equal the PTO's balance in FERC Account No.105.

Prepayments shall equal the PTO’s prepayment balance as recorded in FERC Account No. 165.

Property Insurance shall equal the PTO’s expenses as recorded in FERC Account No. 924.

PTF Transmission Plant shall equal the PTO’s transmission plant as defined in the Section II.49

of the OATT and determined in accordance with Appendix A of this Rule, which is entitled

“Rules for Determining Investment To be Included in PTF.”

PTF/HTF Transmission Plant Investment shall equal the PTO’s (a) PTF Transmission Plant

plus (b) HTF Transmission Plant.

Total Accumulated Deferred Income Taxes shall equal the net of the PTO’s deferred tax

balance as recorded in FERC Account Nos. 281-283 and the PTO’s deferred tax balance as

recorded in FERC Account No. 190.

Total Loss on Reacquired Debt shall equal the PTO’s expenses as recorded in FERC Account

189.

Total Municipal Tax Expense shall equal the PTO’s municipal tax expenses as recorded in

FERC Account Nos. 408.1.

Total Plant in Service shall equal the PTO’s total gross plant balance as recorded in FERC

Account Nos. 301-399.

Total Transmission Depreciation Reserve shall equal the PTO’s transmission reserve balance

as recorded in FERC Account 108.

Transmission Operation and Maintenance Expense shall equal the PTO’s expenses as

recorded in FERC Account Nos. 560, 561.5-561.8, 562-564 and 566-573, and shall exclude all

Phase I/II HVDC-TF expenses booked to accounts 560 through 573 and expenses already

included in Transmission Support Expense, as described in Section K which are included in

FERC Account Nos. 560-573.

Transmission Plant shall equal the PTO’s Gross Plant balance as recorded in FERC Account

Nos. 350-359.

Transmission Plant Materials and Supplies shall equal the PTO’s balance as assigned to

transmission, as recorded in FERC Account No. 154.

II. CALCULATION OF TRANSMISSION REVENUE REQUIREMENTS

The Transmission Revenue Requirement shall equal the sum of the PTO's (A) Return and Associated

Income Taxes (including the Incremental Return and Associated Income Taxes for Post-2003 PTF

Investment and for MPRP CWIP and NEEWS CWIP), (B) Transmission Depreciation and Amortization

Expense, (C) Transmission Related Amortization of Loss on Reacquired Debt, (D) Transmission Related

Amortization of Investment Tax Credits, (E) Transmission Related Municipal Tax Expense, (F)

Transmission Related Payroll Tax Expense, (G) Transmission Operation and Maintenance Expense, (H)

Transmission Related Administrative and General Expenses, (I) Transmission Related Integrated

Facilities Charges, minus (J) Transmission Support Revenue, plus (K) Transmission Support Expense,

plus (L) Transmission-Related Expense from Generators, plus (M) Transmission Related Taxes and Fees

Charge, minus (N) Revenue for Short-Term service under the OATT, (O) Transmission Rents Received

from Electric Property and (P) Transmission Revenues from MEPCO Grandfathered Transmission

Service Agreements. The Incremental Return and Associated Income Taxes for Post-2003 PTF

Investment for each PTO shall be calculated using the investment base components specifically identified

in Section A. 1 of the formula below.

A. Return and Associated Income Taxes shall equal the product of the Transmission Investment

Base and the Cost of Capital Rate. To calculate the Incremental Return and Associated Income

Taxes for Post-2003 PTF Investment and for MPRP CWIP and NEEWS CWIP, Transmission

Investment Base will only include Sections II.A. 1 .(a), (d), (e), (k), and (1) in the manner

indicated.

1. Transmission Investment Base

The Transmission Investment Base will be the year end balances of(a) PTF/HTF Transmission

Plant, plus (b) Transmission Related Intangible and General Plant, plus (c) Transmission Plant

Held for Future Use, less (d) Transmission Related Depreciation and Amortization Reserve, less

(e) Transmission Related Accumulated Deferred Taxes, plus (f) Transmission Related Loss on

Re.acquired Debt, plus (g) Other Regulatory Assets/Liabilities, plus (h)

Transmission Prepayments, plus (i) Transmission Materials and Supplies, plus (j) Transmission

Related Cash Working Capital, plus (k) MPRP CWIP, plus (l) NEEWS CWIP.

(a) PTF Transmission Plant will equal the balance of the PTO's PTF Investment in (a)

Transmission Plant plus (b) HTF Transmission Plant. This value excludes (i) the PTO's

Phase I/II HVDC-TF Leases, (ii) the portion of any facilities, the cost of which is directly

assigned under Schedule 11 to the OATT, to the Transmission Customer or a Generator

Owner or Interconnection Requester, (iii) the Pre-1997 PTF gross plant investment

associated with leased facilities occupied by the Phase II section of the Phase I/II HVDC-

TF. In order to calculate the Incremental Return and Associated Income Taxes for Post-

2003 PTF Investment, Post2003 PTF Transmission Plant shall be separately identified.

(b) Transmission Related Intangible and General Plant shall equal the sum of the PTO’s

balance of investment in Intangible Plant and General Plant multiplied by the

Transmission Wages and Salaries Allocation Factor and the PTF/HTF Transmission Plant

Allocation Factor.

(c) Transmission Plant Held for Future Use shall equal the PTO’s balance of Transmission-

related Plant Held for Future Use multiplied by the PTF/HTF Transmission Plant

Allocation Factor.

(d) Transmission Related Depreciation and Amortization Reserve shall equal the PTO’s

balance of Total Transmission Depreciation Reserve, plus the balance of Transmission

Related Intangible Plant Amortization Reserve, Transmission Related General Plant

Depreciation Reserve and Transmission Related General Plant Amortization Reserve.

Transmission Related Intangible Plant Amortization Reserve, Transmission Related

General Plant Depreciation Reserve and Transmission Related General Plant

Amortization Reserve shall equal the product of the sum of Intangible Plant Amortization

Reserve, General Plant Depreciation Reserve and General Plant Amortization Reserve,

and the Transmission Wages and Salaries Allocation Factor. This sum shall be multiplied

by the PTF/HTF Transmission Plant Allocation Factor. In order to calculate the

Incremental Return and Associated Income Taxes for Post-2003 PTF Investment,

Transmission Depreciation Reserve associated with Post-2003 PTF Investment shall

equal the PTO’s balance of Total Transmission Depreciation Reserve multiplied by the

ratio of Post-2003 PTF Transmission Plant to Total Investment in Transmission Plant,

excluding capital leases in the Phase I/II HVDC-TF Leases.

(e) Transmission Related Accumulated Deferred Taxes shall equal the PTO’s electric

balance of Total Accumulated Deferred Income Taxes, multiplied by the Plant Allocation

Factor, further multiplied by the PTF/HTF Transmission Plant Allocation Factor. To

calculate the Incremental Return and Associated Income Taxes for Post-2003 PTF

Investment, Transmission Related Accumulated Deferred Income Taxes associated with

Post-2003 PTF Investment shall equal the PTO’s balance of total property-related

accumulated deferred income taxes as recorded in FERC accounts 281 and 282,

multiplied by the ratio of Total Investment in Transmission Plant, excluding Phase I/II

HVDC-TF Leases, to Total Plant in Service excluding Phase I/II HVDC-TF Leases,

further multiplied by the ratio of Post-2003 PTF Transmission Plant to Total Investment

in Transmission Plant, excluding Phase I/II HVDC-TF Leases.

(f) Transmission Related Loss on Reacquired Debt shall equal the PTO’s electric balance of

Total Loss on Reacquired Debt multiplied by the Plant Allocation Factor, further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

(g) Other Regulatory Assets/Liabilities shall equal the PTO’s electric balance of any deferred

rate recovery of FAS 106 expenses multiplied by the Transmission Wages and Salaries

Allocation Factor, plus the PTO’s electric balance of FAS 109 multiplied by the Plant

Allocation Factor. This sum shall be multiplied by the PTF/HTF Transmission Plant

Allocation Factor.

(h) Transmission Prepayments shall equal the PTO's electric balance of prepayments

multiplied by the Transmission Wages and Salaries Allocation Factor and further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

(i) Transmission Materials and Supplies shall equal the PTO's electric balance of

Transmission Plant Materials and Supplies, multiplied by the PTF/HTF Transmission

Plant Allocation Factor.

(j) Transmission Related Cash Working Capital shall be a 12.5% allowance (45 days/360

days) of the PTO's Transmission Operation and Maintenance Expense, Transmission

Related Administrative and General Expense and Transmission Support Expense, to the

extent that Transmission Support Expense exceeds Transmission Support Revenue

included in Paragraph J of the formula.

(k) MPRP CWIP shall equal CMP's balance as recorded in FERC Account No. 107 for the

MPRP as authorized by Commission order and in accordance with CMP's Accounting

Procedures for MPRP CWIP. In order to calculate the Incremental Return and Associated

Income Taxes for MPRP CWIP, MPRP CWIP shall be separately identified.

(l) NEEWS CWIP shall equal CL&P, WMECO and NEP’s balances as recorded in FERC

Account No. 107 for the NEEWS as authorized by Commission order and in accordance

with the companies’ respective Accounting Procedures for NEEWS CWIP. In order to

calculate the Incremental Return and Associated Income Taxes for NEEWS CWIP,

NEEWS CWIP shall be separately identified.

2. Cost of Capital Rate

The Cost of Capital Rate will equal (a) the PTO's Weighted Cost of Capital, plus (b)

Federal Income Tax plus (e) State Income Tax.

(a) The Weighted Cost of Capital will be calculated based upon the capital structure at the

end of each year and will equal the sum of (i), (ii), and (iii) below. The Cost of Capital

Rate to be used in calculating the Incremental Return and Associated Income Taxes for

Post-2003 PTF Investment and for MPRP CWIP and NEEWS CWIP, shall only reflect

item (iii) below and shall apply in the manner indicated below.

(i) the long-term debt component, which equals the product of the actual weighted average

embedded cost to maturity of the PTO's long-term debt then outstanding and the ratio that

long-term debt is to the PTO's total capital.

(ii) the preferred stock component, which equals the product of the actual weighted average

embedded cost to maturity of the PTO's preferred stock then outstanding and the ratio

that preferred stock is to the PTO's total capital.

(iii) the return on equity component, shall be the product of the allowed ROE of the PTO's

common equity and the ratio that common equity is to the PTO's total capital. For pre-

1997 and post-1996 assets, the ROE is 11.07%. In order to calculate the Incremental

Return and Associated Income Taxes for Post-2003 PTF Investment and for MPRP

CWIP and NEEWS CWIP, the incremental return on equity shall be the product of: (1)

the PTO's incremental return on equity of 1.0% for plant investments associated with

projects included in the RSP and placed in service by December 31, 2008 or otherwise

permitted in Docket Nos. ER04-157, et al.; (2) any ROE incentive approved by the FERC

under Order No. 679 for other plant investments (however; the 125 basis point ROE

incentive adder granted to NEEWS under Order No. 679 in Docket No. ER08-1548 and

the 50 basis point ROE incentive adder for RTO participation shall not apply to the costs

related to the Central Connecticut Reliability Project, consistent with FERC’s order) and

MPRP CWIP and NEEWS CWIP, provided that the total ROE for any project, including

any such ROE incentives, shall be capped by the top of the applicable zone of

reasonableness determined by FERC for the relevant period, and (3) the ratio that

common equity is to the PTO's total capital) 1

(b) Federal Income Tax shall equal

(A+[(C+B)/D])(FT)

I-FT

where FT is the Federal Income Tax Rate and A is the sum of the preferred stock

component and the return on equity component, as determined in Sections ll.A.2.(a)(ii)

and (iii) above, B is Transmission Related Amortization of Investment Tax Credits, as

determined in Section II.D., below, C is the Equity AFUDC component of Transmission

Depreciation Expense, as defined in Section ll.B., and D is Transmission Investment

Base, as determined in Section II.A.1., above. In order to calculate the Incremental

Return and Associated Income Taxes for Post-2003 PTF Investment and for MPRP

CWIP and NEEWS CWIP, the incremental Federal Income Tax shall equal

(A’ * FT)

(1 -FT)

where FT is the Federal Income Tax Rate and A' is the incremental return on equity

component, as determined in Section II.A.2.(a)(iii) above.

(c) State Income Tax shall equal

(A+[(C+B)/D] + Federal Income Tax)(ST)

1 -ST

where ST is the State Income Tax Rate, A is the sum of the preferred stock component

and return on equity component determined in Sections II.A.2.(a)(ii) and (iii) above, B is

the Amortization of Investment Tax Credits as determined in Section ll.D.below, C is the

equity AFUDC component of Transmission Depreciation Expense, as defined in Section

1 FERC Form-730 contains a list of transmission projects for which FERC has granted incentives under Order No.

679.

II.B.. D is the Transmission Investment Base, as determined in II.A.1., above and Federal

Income Tax is the rate determined in Section II.A.2.(b) above. In order to calculate the

Incremental Return and Associated Income Taxes for Post-2003 PTF Investment and for

MPRP CWIP and NEEWS CWIP, the incremental State Income Tax shall equal

(A’ + Federal Income Tax)(ST)

(1 – ST)

where ST is the State Income Tax Rate, A’ is the incremental return on equity component

determined in Section II.A.2.(a)(iii) above, and Federal Income Tax is the rate

determined in Section II.A.2.(b) above.

B. Transmission Depreciation and Amortization Expense shall equal the PTF/HTF Transmission

Plant Allocation Factor, multiplied by the sum of (i) the PTO’s Depreciation Expense for

Transmission Plant, plus (ii) an allocation of Intangible Plant Amortization Expense and (iii)

General Plant Depreciation and Amortization Expense calculated by multiplying the sum of (a)

Intangible Plant Amortization Expense and (b) General Plant Depreciation and Amortization

Expense by the Transmission Wages and Salaries Allocation Factor.

C. Transmission Related Amortization of Loss on Reacquired Debt shall equal the PTO’s electric

Amortization of Loss on Reacquired Debt multiplied by the Plant Allocation Factor, and further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

D. Transmission Related Amortization of Investment Tax Credits shall equal the PTO’s electric

Amortization of Investment Tax Credits multiplied by the Plant Allocation Factor, and further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

E. Transmission Related Municipal Tax Expense shall equal the PTO’s total electric municipal tax

expense multiplied by the Plant Allocation Factor, and further multiplied by the PTF/HTF

Transmission Plant Allocation Factor.

F. Transmission Related Payroll Tax Expense shall equal the PTO’s total electric payroll tax

expense, multiplied by the Transmission Wages and Salaries Allocation Factor, further multiplied

by the PTF/HTF Transmission Plant Allocation Factor.

G. Transmission Operation and Maintenance Expense shall equal the PTO’s Transmission Operation

and Maintenance Expenses multiplied by the PTF/HTF Transmission Plant Allocation Factor.

H. Transmission Related Administrative and General Expenses shall equal the sum of the PTO’s (1)

Administrative and General Expenses multiplied by the Transmission Wages and Salaries

Allocation Factor, (2) Property Insurance multiplied by the Transmission Plant Allocation Factor,

and (3) Expenses included in Account 928 related to FERC Assessments multiplied by Plant

Allocation Factor, plus any other Federal and State transmission related expenses or assessments,

plus specific transmission related expenses included in Account 930.1. This sum shall be

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

I. Transmission Related Integrated Facilities Charges shall equal the PTO’s transmission payments

to Affiliates for use of the PTF and HTF integrated transmission facilities of those Affiliates.

J. Transmission Support Revenues shall equal the PTO’s revenue received for PTF and HTF

transmission support but excluding the support payments to PTOs or their designee pursuant to

Schedule 11 and excluding the support payments to PTOs or their designee pursuant to Schedule

12 Part 1(a) and Part B.2, and excluding support payments, if any, made to PTOs or their

respective designee pursuant to Part II.C of this OATT.

K. Transmission Support Expense shall equal the expense paid by (1) PTOs, (2) Transmission

Customers or (3) Related Persons pursuant to Section II.49 of the Tariff for PTF and HTF

transmission support other than expenses for payments made for congestion rights or for

transmission facilities or facility upgrades placed in service on or after January 1, 1997, where the

support obligation is required to be borne by particular PTOs or other entities in accordance with

the OATT. Transmission Support Expenses by any entity other than a PTO, included in this

provision, shall be capped at that entity’s annual payment for Regional Network Service or its

Point To Point Service for each individual Point To Point transaction from the resource with

which the support payment is associated.

L. Transmission-Related Expense from Generators shall equal the expenses from generators that

both (1) the PTO Administrative Committee determines should be included as transmission

expense as a result of the impact of such generators on reducing transmission costs that would

otherwise be required to be paid by Transmission Customers and (2) are reflected in a filing made

by the PTOs with the Commission under Section 205 of the Federal Power Act and accepted by

the Commission for recovery under the OATT.

M. Transmission Related Taxes and Fees Charge shall include any fee or assessment imposed by any

governmental authority on service provided under this Section which is not specifically identified

under any other section of this rule.

N. Revenues for Short-Term service under the OATT shall be revenues distributed to each PTO for

short term service provided under the OATT, received after March 1, 1999. These revenues will

be credited pro-rata between pre-1997 and post-1996 PTF revenue requirements in proportion to

pre-1997 and post-1996 PTF Transmission Plant.

O. Transmission Rents Received from Electric Property shall equal any Account 454 Rents from

electric property, associated with PTF and HTF Transmission Plant as defined in Section

II.A.1.(a) above but not reflected as a credit in Transmission Support Revenues in paragraph K of

this Attachment.

P. Transmission Revenues from MGTSAs shall equal any MGTSA revenues recorded in Account

456.

APPENDIX A TO ATTACHMENT F

IMPLEMENTATION RULE RULES FOR DETERMINING

INVESTMENT TO BE INCLUDED IN PTF

Section A – Transmission Lines*

Section B – Terminal Facilities*

Section C – Right of Way*

Effective June 1, 1998

*The following provision shall apply to Sections A, B and C below:

Of those transmission facilities that are upgrades, modifications or additions to the New England

Transmission System on and after January 1, 2004, only those that: (i) are rated 115kV or above, and (ii)

otherwise meet the non-voltage criteria specified in Section II.49 of this OATT shall be classified as PTF.

Those transmission facilities that were PTF on December 31, 2003, and any upgrades to such facilities

that meet the definition of PTF specified in this OATT, shall remain classified as PTF for all purposes

under the Transmission, Markets and Services Tariff.

Section A: Rules for Determining Transmission Line Investment to be Included in PTF

Pool Transmission Facilities (PTF) are the transmission facilities owned by PTO rated 69 kV or above

required to allow energy from significant power sources to move freely on the New England transmission

network, and include:

1. All transmission lines and associated facilities owned by the PTOs rated 69 kV and above,

except:

a. those which are required to serve local load only, thereby contributing little or no parallel

capability to the transmission network,

b. generator leads, which are defined as the radial transmission from a generator bus to the

nearest point on the transmission network,

c. lines that are normally operated open.

d. those that are classified as MTF.

2. Terminal facilities (including substation facilities such as transformers, circuit breakers, and

associated equipment) required to interconnect the lines which constitute PTF (see Section B).

3. If a PTO with significant generation in its system (initially 25 MW) is connected to the New

England Transmission System and none of the transmission facilities owned by the PTO qualify

to be included in PTF as defined in “1” and “2” above, then such PTO’s connection to PTF will

constitute PTF if both of the following requirements are met for this connection:

a. The connection is rated 69 kV or above.

b. The connection is the principal transmission link between the PTO and the remainder of

the ISO PTF network.

The PTF facilities covered by this provision shall consist of a single line from the point of connection on

the transmission network to the first bus within the PTO’s system.

4. R/W and land required for the installation of PTF facilities listed in “1”, “2”, or “3” (see Section

C).

The following examples indicate the intent of the above definitions:

a. Radial tap lines to local load are excluded.

b. Lines which loop, from two geographically separate points on the transmission network,

the supply to the load bus from the transmission network are included.

c. Lines which loop, from two geographically separate points on the transmission network,

the connections between a generator bus, and the transmission network are included.

d. Radial connection or connections from a generating station to a single substation or

switching station on the transmission network are excluded unless the requirements of

paragraph 3 above are met.

e. The cost of a PTF line will include only those costs associated with that line. When other

facilities require rebuilding or undergrounding to permit the construction of a PTF

facility, the investment costs in the relocated or undergrounded facility will not be

included.

f. Where multiple circuit structures support a mixture of PTF and Non-PTF circuits, the

total cost of the multiple circuit structures will be allocated between the circuits in

accordance with the ratio of costs of comparable individual structures.

The PTOs shall review at least annually the status of transmission lines and related facilities and

determine whether such facilities constitute PTF and shall prepare and keep current a schedule or catalog

of PTF facilities.

All new facilities being installed should be properly classified at the time the facilities are approved under

Section I.3.9 of the Transmission, Markets and Services Tariff.

Transmission facilities owned or supported by a Related Person of a PTO which are rated 69 kV or above

and are required to allow Energy from significant power sources to move freely on the New England

Transmission System shall also constitute PTF provided (i) such Related Person files with the ISO its

consent to such treatment; and (ii) the ISO determines in consultation with the PTO Administrative

Committee determines that treatment of the facility as PTF will facilitate accomplishment of the ISO’s

objectives. If such facilities constitute PTF pursuant to this paragraph, they shall be treated as “owned” or

“supported,” as applicable, by a PTO for purposes of the OATT and the other provisions of the TOA,

including the ability to include the cost associated with such PTF and any Transmission Support Expenses

for support of PTF made by its Related Person in that PTO’s Annual Transmission Revenue

Requirements pursuant to Attachment F of the OATT.

Section B: Rules for Determining Terminal Investment to be Included in PTF

Terminal Investment is investment associated with the terminal facilities of electrical lines, including

substation facilities such as transformers, circuit breakers, disconnects and airbreaks, bus conductor,

related protection equipment and other related facilities (see paragraph 7).

1. The investment in terminal facilities shall be included where these facilities are identifiable and

serve directly for terminating and/or switching PTF lines.

2. In cases where a line terminal is used in conjunction with both PTF and Non-PTF lines and/or

facilities, it will be considered a PTF facility providing the terminal facility is at 69 kV or above

and carries any power flow at 69 kV or above through parallel paths within the interconnected

network under normal operation. PTF equipment is any element of the transmission system in

those parallel paths. Any equipment not in these parallel paths is Non-PTF.

3. Where line terminals are installed solely for Non-PTF facilities, and do not carry any power flow

at 69 kV or above through parallel paths within the interconnected network under normal

operation, such terminal cost shall not be included in PTF.

4. A two-winding transformer which connects PTF facilities at both terminals along with any

switcher which can be identified as pertaining solely to the transformer, will be included in their

entirety as PTF.

5. An autotransformer or three winding transformer which connects PTF facilities at two (2) or more

terminals, along with any switchgear which can be identified as pertaining solely to the PTF-

connected terminals of the transformer, will be included in their entirety as PTF. An

autotransformer or three winding transformer which is connected to PTF at only one terminal will

not be PTF.

6. When a transformer supplies only Non-PTF facilities, the entire transformer installation,

including the high side disconnect switch or circuit breaker and associated structures or tap lines

shall be excluded from PTF except for the portion of line terminal facilities covered by paragraph

2.

7. Other facilities – the investment in that portion of a multi-use substation or switching station

which is identifiable as serving a PTF function shall be included in PTF, while the investment in

such facilities which are identifiable as serving a Non-PTF function shall be excluded. The

investment in land, structures, ground mats, fences, ducts, lighting, etc., can often be identified

and thus allocated. The investment in other facilities in the substation or switching station,

excluding transformers, which are not identifiable as serving either a PTF or a Non-PTF function

and general overheads shall be allocated to PTF on the basis of the ratio of the investment in

those facilities identified as PTF to the sum of the investments in the facilities which are

identified as serving PTF and Non-PTF functions; the equipment cost of power transformers shall

not be included in this calculation for determining the division of investment, since this would

produce a distorted balance.

8. Alternate method of allocating the cost of terminal facilities – In those cases where the major

portion of the investment has been lumped and utility plant records do not permit the accurate

assignment of costs to specific terminals, the total investment may be prorated to PTF and Non-

PTF according to the number of terminals serving PTF and Non-PTF facilities.

9. In cases where microwave facilities are used in whole or part for PTF purposes, a prorated

portion of such investment shall be included in PTF based on the PTF and Non-PTF functions

served by the microwave facilities except where these facilities are otherwise supported under the

Microwave Sharing Agreement dated June 1, 1970 among some of the New England utilities.

10. Generator unit transformers and generator circuit breakers shall be excluded from PTF, unless

otherwise included by paragraphs 1 or 5.

11. In cases where remote control (Supervisory Control) and telemetering facilities are used in whole

or in part for PTF purposes, a prorated portion of such investment shall be included in PTF based

on the PTF and Non-PTF functions served by these facilities.

12. The PTO Administrative Committee may designate appropriate facilities as PTF.

Section C: Rules for Determining PTF R/W Costs

1. If a R/W has only PTF lines and no Non-PTF lines are expected to be added, the entire cost of the

R/W is to be included as PTF.

2. If the R/W has only PTF lines but includes additional unused R/W which was purchased for

future use by Non-PTF lines, the cost of the additional R/W is not to be included as PTF.

3. If the R/W contains both PTF and Non-PTF lines, the R/W cost to be assigned to PTF is to be

determined as follows:

a. Where new or additional R/W is required to permit the construction of PTF line(s) and

the added R/W is adequate to contain the new PTF, the cost of the new R/W is to be

assigned to the PTF line(s), (even if the PTF line is located on the old R/W).

b. Where an existing R/W is used (without additional R/W), the amount allocated to PTF

will be determined in accordance with paragraph 4.

c. Where a R/W is widened, but the new facilities, either PTF or Non-PTF, require partial

use of the existing R/W, the incremental cost of the new R/W will be assigned to the new

facilities. The width of the original R/W will be added to the width of the new R/W and

the combined width will be allocated between PTF and Non-PTF as in paragraph 4. The

cost of the old R/W and the combined width will be allocated between PTF and Non-PTF

as in paragraph 4. The cost of the old R/W will be allocated to the new facilities in

proportion to the width of the old R/W assigned to the new facilities. Thus, the R/W for

the new facilities will be the additional R/W plus a share of the old R/W.

4. In allocating R/W between PTF and Non-PTF lines, each shall bear a share of the R/W in

accordance with the following formulae.

a. Determine the R/W width required for each facility if constructed independently using

appropriate type structures.

b. Allocate the actual R/W width to each facility in the proportion its independent R/W

requirement would be to the sum of the independent R/W requirements.

5. R/W and land held for future PTF facilities may be included in PTF facilities only if specifically

approved by the PTO Administrative Committee included under paragraph 1.

ATTACHMENT 1 TO APPENDIX A TO

ATTACHMENT F IMPLEMENTATION RULE

Examples of the Methods for Distinguishing PTF

from Non-PTF Terminal Facilities

in a Number of Typical Substation Configurations

APPENDIX B TO ATTACHMENT F IMPLEMENTATION RULE

HTF TRANSITION SCHEDULE

The inclusion of HTF Annual Transmission Revenue Requirements in Attachment F (and the calculation

of the Pool PTF Rate) to this OATT will be limited by the provisions of this schedule.

VELCO, as a PTO and acting as agent for the HTF owners, may include the HTF Annual Transmission

revenue Requirements (i.e., HTF Transmission Plant) within the Attachment F calculations. Additionally,

the total HTF Annual Transmission Revenue Requirements included shall be limited to the following:

Year 1: A maximum of $1.2M in Year 1. For the sole purpose of this Schedule, “Year 1” shall be

defined as the first full year after the Operations Date:

Year 2: A maximum of $2.0M in Year 2. For the sole purpose of this Schedule, “Year 2” shall be

defined as the second full year after the Operations Date;

Year 3: A maximum of $2.8M in Year 3. For the sole purpose of this Schedule, “Year 3” shall be

defined as the third full year after the Operations Date;

Year 4: A maximum of $3.5M in Year 4. For the sole purpose of this Schedule, “Year 4” shall be

defined as the fourth full year after the Operations Date;

and

Year 5 and thereafter: All HTF Annual Transmission Revenue Requirements shall be included in

Attachment F.

ATTACHMENT F IMPLEMENTATION RULE

APPENDIX C

I. DEFINITIONS

(i) Annual True-up – Pre-1997 (ATU): shall be the difference between the actual Pre-1997 Annual

Transmission Revenue Requirements and the as-billed Pre-1997 Annual Transmission Revenue

Requirements, adjusted to include interest pursuant to Part II below. The actual Pre-1997 Annual

Transmission Revenue Requirements shall be an after-the-fact calculation and shall be

determined at the conclusion of each rate-effective period, i.e. June 1 through May 31 of each

year, by application of the Attachment F formula rate and each PTO’s relevant Pre-1997 PTF cost

data for the most recently concluded calendar year. The as-billed Pre-1997 Annual Transmission

Revenue Requirements shall be those Pre-1997 Annual Transmission Revenue Requirements

used to establish the RNS rates that were made effective on June 1 of the most recently concluded

calendar year.

(ii) Annual True-up – Post-1996 (ATU’): shall be the difference between the actual Post-1996

Annual Transmission Revenue Requirements and the as-billed Post-1996 Annual Transmission

Revenue Requirements, adjusted to include interest pursuant to Part II below. The actual Post-

1996 Annual Transmission Revenue Requirements shall be an after-the-fact calculation and shall

be determined at the conclusion of each rate-effective period, i.e. June 1 through May 31 of each

year, by application of the Attachment F formula rate and each PTO's relevant Post-1996 PTF

cost data for the most recently concluded calendar year.The as-billed Post-1996 Annual

Transmission Revenue Requirements shall be those Post-1996 Annual Transmission Revenue

Requirements used to establish the RNS rates that were made effective on June 1 of the most

recently concluded calendar year and which included the sum of the Post-1996 Transmission

Revenue Requirements for the year prior to the most recently concluded calendar year plus the

Forecasted Transmission Revenue Requirements for the most recently concluded calendar year.

(iii) Forecast Period: The calendar year immediately following the calendar year for which the most

recent FERC Form 1 data is available.

(iv) Forecasted Transmission Plant Additions (FTPA): shall equal an estimate of the PTO's Post-1996

PTF plant additions for the Forecast Period.

(v) Forecasted MPRP CWIP (FCWIP): shall equal CMP's estimated incremental change in

MPRPCWIP for the Forecast Period.

(vi) Carrying Charge Factor (CCF): shall reflect the most recent calendar year data used in determining

Post-1996 Annual Transmission Revenue Requirements and shall equal the sum of Attachment F

Sections II.A, excluding MPRP CWIP and NEEWS CWIP, through II.H divided by Attachment F

Section II.A.1.a.

(vii) MPRP Cost of Capital Rate (MCOC): shall be determined in accordance with Attachment F

Section II.A.2.

(viii) Forecasted Transmission Revenue Requirement (FTRR): shall equal FTPA multiplied by the

CCF plus FCWIP multiplied by the MCOC, plus FCCWIP multiplied by CCOC, plus FWCWIP

multiplied by WCOC, plus FNCWIP multiplied by NCOC, as shown:

FTRR = FTPA * CCF + (FCWIP * MCOC) + (FCCWIP * CCOC) + (FWCWIP * WCOC) +

(FNCWIP * NCOC)

(ix) Forecasted CL&P NEEWS CWIP (FCCWIP): shall equal CL&P’s estimated incremental change

in NEEWS CWIP for the Forecast Period.

(x) Forecasted WMECO NEEWS CWIP (FWCWIP): shall equal WMECO’s estimated incremental

change in NEEWS CWIP for the Forecast Period.

(xi) NEEWS CL&P Cost of Capital Rate (CCOC): shall be determined in accordance with

Attachment F Section II.A.2.

(xii) NEEWS WMECO Cost of Capital Rate (WCOC): shall be determined in accordance with

Attachment F Section II.A.2.

(xiii) Forecasted NEP NEEWS CWIP (FNCWIP): shall equal NEP’s estimated incremental change in

NEEWS CWIP for the Forecast Period.

(xiv) NEEWS NEP Cost of Capital Rate (NCOC): shall be determined in accordance with Attachment

F Section II.A.2.

II. INTEREST ON ANNUAL TRUE-UPS

Interest on the Annual True-up amounts (i.e., interest applicable to any over or under collection) shall be

calculated in accordance with the methodology specified in the Commission’s regulations at 18 C.F.R. §

35.19a (a) (2) (iii).

III. INFORMATIONAL FILINGS

The PTOs’ annual informational filing shall include supporting documentation for their estimated capital

additions to be placed in service during the current calendar year as well as supporting documentation

pertaining to any annual true-up and interest calculations.

ATTACHMENT F

ANNUAL TRANSMISSION REVENUE REQUIREMENTS

The Transmission Revenue Requirements for each PTO will reflect the PTO’s costs with respect to Pool

Supported PTF and the HTF, including costs attributable to those PTOs deemed to own or support PTF

pursuant to Section II.49 of the Tariff. The Transmission Revenue Requirements will be an annual

calculation based on the previous year’s calendar data as shown, in the case of PTOs that are subject to

the Commission’s jurisdiction, in the PTO’s FERC Form 1 report for that year; provided, however, that if

a PTO is deemed to own or support PTF pursuant to Section II.49 of the Tariff, such PTO may include

the costs as incurred by its Related Person for PTF facilities and Transmission Support Expenses as the

basis for establishing its initial and subsequent Annual Transmission Revenue Requirements, only until

such PTO has a full calendar year of cost data under its ownership. Such PTO’s costs will be determined

from FERC Form 1 data if available, or if not available, from other supporting data certified by an auditor

of the PTO or Related Person, and in a format comparable to that used to report such costs in FERC Form

1. Such costs shall be based on actual data in lieu of allocated data if specifically identified in the Form 1

report in accordance with the following formula and Schedule 12:

I. The Transmission Revenue Requirement shall equal the sum of the PTO’s (A) Return and

Associated Income Taxes, (B) Transmission Depreciation and Amortization Expense, (C)

Transmission Related Amortization of Loss on Reacquired Debt, (D) Transmission Related

Amortization of Investment Tax Credits, (E) Transmission Related Municipal Tax Expense, (F)

Transmission Related Payroll Tax Expense, (G) Transmission Operation and Maintenance

Expense, (H) Transmission Related Administrative and General Expense, (I) Transmission

Related Integrated Facilities Charges, minus (J) Transmission Support Revenue, plus (K)

Transmission Support Expense, plus (L) Transmission Related Expense from Generators, plus

(M) Transmission Related Taxes and Fees Charge, minus (N) Revenue for Short-Term service

under the OATT and (O) Transmission Rents Received from Electric Property.

The details for implementation of Attachment F, as well as the definitions of the terms used in the

Attachment F formula, shall be established in accordance with the Attachment F Implementation Rule

contained in this OATT.

ATTACHMENT F

IMPLEMENTATION RULE

This rule sets forth details with respect to the determination each year of the Transmission Revenue

Requirements for each PTO. Such Transmission Revenue Requirements shall reflect the PTO’s costs for

Pool Transmission Facilities (“PTF”) and the Highgate Transmission Facilities (“HTF”), including costs

attributable to those PTOs deemed to own or support PTF pursuant to Section II.49 of the Tariff. The

Transmission Revenue Requirements for each PTO will reflect the PTO’s costs with respect to Pool

Supported PTF and the HTF. The Transmission Revenue Requirements will be an annual calculation

based on the previous year’s calendar data as shown, in the case of PTOs which are subject to the

Commission’s jurisdiction, in the PTO’s FERC Form 1 report for that year; provided, however, that if a

PTO is deemed to own or support PTF, such PTO may include the costs as incurred by its Related Person

for PTF facilities and Transmission Support Expenses as the basis for establishing its initial and

subsequent Annual Transmission Revenue Requirements, only until such PTO has a full calendar year of

cost data under its ownership. Such PTO’s costs will be determined from FERC Form 1 data if available,

or if not available, from other supporting data certified by an auditor of the PTO or Related Person, and in

a format comparable to that used to report such costs in FERC Form 1. Such costs shall be based on

actual data in lieu of allocated data if specifically identified in the Form 1 report in accordance with the

following formula and Schedule 12. The HTF Transmission Revenue Requirements shall be subject to the

limitations of inclusion of such costs as set forth in Appendix B to this Attachment. The owners of the

HTF, or their designated agent, will submit the annual HTF Transmission Revenue Requirements

calculation based on the previous calendar year's cost data from their FERC Form 1 or equivalent

information from their official books and records, as appropriate.

The Post-96 Transmission Revenue Requirement for each PTO that is based on data for calendar year

2004 or later shall include an Incremental Return and Associated Income Taxes on the PTO's PTF

transmission plant investments included in the Regional System Plan and placed in-service on or after

January 1,2004 (such investments referred to herein as "Post-2003 PTF Investment"). The Incremental

Return and Associated Income Taxes for Post-2003 PTF Investment shall incorporate an incentive ROE

adder of 100 basis points for plant investment placed in service by December 31, 2008 or as otherwise

permitted in Docket Nos. ER04-157, et al. for any projects included in the RSP, and shall incorporate any

incentive ROE adder approved by the FERC under Order No. 679 for other plant investments (however;

the 125 basis point ROE incentive adder granted to NEEWS under Order No. 679 in Docket No. ER08-

1548 and the 50 basis point ROE incentive adder for RTO participation shall not apply to the costs related

to the Central Connecticut Reliability Project, consistent with FERC’s order) and for MPRP CWIP and

NEEWS CWIP. The total ROE for any project, including any authorized ROE incentives for Post-2003

PTF Investment and any other incentive ROE approved by FERC under Order No. 679 shall be capped by

the top of the applicable zone of reasonableness determined by FERC for the relevant period. The data

used in determining each PTO's Incremental Return and Associated Taxes for Post-2003 Investment shall

be based on actual data in lieu of allocated data if specifically identified in the PTO's accounting records.

The Post-1996 Pool PTF Rate, as calculated pursuant to Schedule 9, shall include for each PTO a

Forecasted Transmission Revenue Requirement calculated in accordance with Appendix C to this

Attachment F Implementation Rule. Additionally, the Pre-1997 and Post-1996 Pool PTF Rates shall

include an Annual True-up calculated in accordance with Appendix C to this Attachment F

Implementation Rule.

The PTOs shall make an annual informational filing on or before July 31 of each year showing the Pool

PTF Rate in effect for the period beginning June 1 of that year through May 31 of the subsequent

year.Further, the informational filing with respect to the determination of the Pool PTF Rate will include a

breakdown by PTO of the amount of the change in PTF and HTF investment during the prior year and the

PTF and HTF retirements or additions causing such change to beginning and end-of-year PTF balances

and HTF balances (although beginning-of-year PTF balances and HTF balances are not used in the

formula itself), and any additions to PTF and HTF, retirements of PTF and HTF, and reclassifications of

PTF and HTF during the year for each PTO. If there are any corrections made to the information reflected

in the informational filing after it has been submitted, the PTOs will file corrections to the informational

filing. At least forty-five days before the informational filing is made with the Commission, the PTOs

shall make available to Transmission Customers and any other interested parties a draft of the proposed

filing for review and comment prior to the filing by posting such draft on the ISO website. The filing of

the information filing does not re-open the formula rate set forth below for review, but rather is

contestable only with respect to the accuracy of the information contained in the informational filing.

The ISO shall have the discretion to conduct audits of such charges, with advisory Stakeholder input on

the scope of audit, including on any agreed-upon procedures to be used by the auditor. In this provision,

the term “agreed-upon procedures” shall have the meaning afforded to it by the American Institute of

Certified Public Accountants.

I. DEFINITIONS

Capitalized terms not otherwise defined in the Tariff and as used in this rule have the following

definitions:

A. ALLOCATION FACTORS

1. Transmission Wages and Salaries Allocation Factor shall equal the ratio of Transmission-

related direct wages and salaries including those of affiliated Companies to the PTO’s

total direct wages and salaries including those of the Affiliates’ Companies and excluding

administrative and general wages and salaries.

2. PTF/HTF Transmission Plant Allocation Factor shall equal the ratio of PTF/HTF

Transmission Plant to Total Investment in Transmission Plant, excluding capital leases in

the Phase I/II HVDC-TF (Phase I/II HVDC-TF Leases).

3. Plant Allocation Factor shall equal the ratio of the sum of Total Investment in

Transmission Plant, excluding Phase I/II HVDC-TF Leases, and Transmission Related

Intangible and General Plant to Total Plant in service excluding Phase I/II HVDC-TF

Leases.

B. TERMS

Administrative and General Expense shall equal the PTO’s expenses as recorded in FERC

Account Nos. 920-935, excluding FERC Account Nos. 924, 928 and 930.1.

Amortization of Loss on Reacquired Debt shall equal the PTO’s expenses as recorded in FERC

Account No. 428.1.

Amortization of Investment Tax Credits shall equal the PTO’s credits as recorded in FERC

Account No. 411.4.

Depreciation Expense for Transmission Plant shall equal the PTO’s transmission expenses as

recorded in FERC Account No. 403.

General Plant shall equal the PTO’s gross plant balance as recorded in FERC Account Nos. 389-

399.

General Plant Depreciation and Amortization Expense shall equal the PTO’s general

expenses as recorded in FERC Account No. 403 and NSTAR Electric’s FERC Account No. 404

for items subject to amortization.

General Plant Amortization Reserve shall equal NSTAR Electric’s general reserve balance as

recorded in FERC Account No. 111.

HTF Transmission Plant shall equal the PTO's balance of investment in the Highgate

Transmission Facilities as recorded in FERC Account Nos. 350-359.

Intangible Plant shall equal NSTAR Electric’s gross plant balance as recorded in FERC Account

No. 303. The only allowable Intangible Plant for inclusion are software, patent or rights costs.

Intangible Plant Amortization Expense shall equal NSTAR Electric’s amortization expenses as

recorded in FERC Account Nos. 404-405. The only allowable Intangible Plant Amortization

Expense for inclusion is the amortization of software, patent or rights costs.

Intangible Plant Amortization Reserve shall equal NSTAR Electric’s amortization reserve

balance as recorded in FERC Account No. 111. The only allowable Intangible Plant

Amortization Reserve for inclusion is that related to the amortization of software, patent or rights

costs.

Maine Power Reliability Program Construction Work In Progress ("MPRP CWIP") shall

equal Central Maine Power Company's ("CMP's") MPRP CWIP balance as recorded in FERC

Account No. 107 for costs determined to be Pool- Supported PTF in accordance with Schedule 12

of this OATT.

New England East-West Solution Construction Work in Progress (“NEEWS CWIP”) shall

equal the NEEWS CWIP balances of The Connecticut Light and Power Company (“CL&P”) and

Western Massachusetts Electric Company (“WMECO”) and New England Power Company

(“NEP”) as recorded in FERC Account No. 107 for costs determined to be Pool-Supported PTF

in accordance with Schedule 12 of this OATT.

Other Regulatory Assets/Liabilities - FAS 106 shall equal the net of the PTO's FAS 106

balance as recorded in FERC Account 182.3 and any FAS 106 balance as recorded in the PTO's

FERC Account No. 254.

Other Regulatory Assets/Liabilities - FAS 109 shall equal the net of the PTO's FAS 109

balance in FERC Account No. 182.3 and any FAS 109 balance as recorded in the PTO's FERC

Account No. 254.

Payroll Taxes shall equal those payroll expenses as recorded in the PTO's FERC Account Nos.

408.1.

Phase I/II HVDC-TF Leases shall equal the PTO's balance in capital leases as recorded in

FERC Account Nos. 350-359 and FERC Account Nos. 389-399.

Plant Held for Future Use shall equal the PTO's balance in FERC Account No.105.

Prepayments shall equal the PTO’s prepayment balance as recorded in FERC Account No. 165.

Property Insurance shall equal the PTO’s expenses as recorded in FERC Account No. 924.

PTF Transmission Plant shall equal the PTO’s transmission plant as defined in the Section II.49

of the OATT and determined in accordance with Appendix A of this Rule, which is entitled

“Rules for Determining Investment To be Included in PTF.”

PTF/HTF Transmission Plant Investment shall equal the PTO’s (a) PTF Transmission Plant

plus (b) HTF Transmission Plant.

Total Accumulated Deferred Income Taxes shall equal the net of the PTO’s deferred tax

balance as recorded in FERC Account Nos. 281-283 and the PTO’s deferred tax balance as

recorded in FERC Account No. 190.

Total Loss on Reacquired Debt shall equal the PTO’s expenses as recorded in FERC Account

189.

Total Municipal Tax Expense shall equal the PTO’s municipal tax expenses as recorded in

FERC Account Nos. 408.1.

Total Plant in Service shall equal the PTO’s total gross plant balance as recorded in FERC

Account Nos. 301-399.

Total Transmission Depreciation Reserve shall equal the PTO’s transmission reserve balance

as recorded in FERC Account 108.

Transmission Operation and Maintenance Expense shall equal the PTO’s expenses as

recorded in FERC Account Nos. 560, 561.5-561.8, 562-564 and 566-573, and shall exclude all

Phase I/II HVDC-TF expenses booked to accounts 560 through 573 and expenses already

included in Transmission Support Expense, as described in Section K which are included in

FERC Account Nos. 560-573.

Transmission Plant shall equal the PTO’s Gross Plant balance as recorded in FERC Account

Nos. 350-359.

Transmission Plant Materials and Supplies shall equal the PTO’s balance as assigned to

transmission, as recorded in FERC Account No. 154.

II. CALCULATION OF TRANSMISSION REVENUE REQUIREMENTS

The Transmission Revenue Requirement shall equal the sum of the PTO's (A) Return and Associated

Income Taxes (including the Incremental Return and Associated Income Taxes for Post-2003 PTF

Investment and for MPRP CWIP and NEEWS CWIP), (B) Transmission Depreciation and Amortization

Expense, (C) Transmission Related Amortization of Loss on Reacquired Debt, (D) Transmission Related

Amortization of Investment Tax Credits, (E) Transmission Related Municipal Tax Expense, (F)

Transmission Related Payroll Tax Expense, (G) Transmission Operation and Maintenance Expense, (H)

Transmission Related Administrative and General Expenses, (I) Transmission Related Integrated

Facilities Charges, minus (J) Transmission Support Revenue, plus (K) Transmission Support Expense,

plus (L) Transmission-Related Expense from Generators, plus (M) Transmission Related Taxes and Fees

Charge, minus (N) Revenue for Short-Term service under the OATT, (O) Transmission Rents Received

from Electric Property and (P) Transmission Revenues from MEPCO Grandfathered Transmission

Service Agreements. The Incremental Return and Associated Income Taxes for Post-2003 PTF

Investment for each PTO shall be calculated using the investment base components specifically identified

in Section A. 1 of the formula below.

A. Return and Associated Income Taxes shall equal the product of the Transmission Investment

Base and the Cost of Capital Rate. To calculate the Incremental Return and Associated Income

Taxes for Post-2003 PTF Investment and for MPRP CWIP and NEEWS CWIP, Transmission

Investment Base will only include Sections II.A. 1 .(a), (d), (e), (k), and (1) in the manner

indicated.

1. Transmission Investment Base

The Transmission Investment Base will be the year end balances of(a) PTF/HTF Transmission

Plant, plus (b) Transmission Related Intangible and General Plant, plus (c) Transmission Plant

Held for Future Use, less (d) Transmission Related Depreciation and Amortization Reserve, less

(e) Transmission Related Accumulated Deferred Taxes, plus (f) Transmission Related Loss on

Re.acquired Debt, plus (g) Other Regulatory Assets/Liabilities, plus (h)

Transmission Prepayments, plus (i) Transmission Materials and Supplies, plus (j) Transmission

Related Cash Working Capital, plus (k) MPRP CWIP, plus (l) NEEWS CWIP.

(a) PTF Transmission Plant will equal the balance of the PTO's PTF Investment in (a)

Transmission Plant plus (b) HTF Transmission Plant. This value excludes (i) the PTO's

Phase I/II HVDC-TF Leases, (ii) the portion of any facilities, the cost of which is directly

assigned under Schedule 11 to the OATT, to the Transmission Customer or a Generator

Owner or Interconnection Requester, (iii) the Pre-1997 PTF gross plant investment

associated with leased facilities occupied by the Phase II section of the Phase I/II HVDC-

TF. In order to calculate the Incremental Return and Associated Income Taxes for Post-

2003 PTF Investment, Post2003 PTF Transmission Plant shall be separately identified.

(b) Transmission Related Intangible and General Plant shall equal the sum of the PTO’s

balance of investment in Intangible Plant and General Plant multiplied by the

Transmission Wages and Salaries Allocation Factor and the PTF/HTF Transmission Plant

Allocation Factor.

(c) Transmission Plant Held for Future Use shall equal the PTO’s balance of Transmission-

related Plant Held for Future Use multiplied by the PTF/HTF Transmission Plant

Allocation Factor.

(d) Transmission Related Depreciation and Amortization Reserve shall equal the PTO’s

balance of Total Transmission Depreciation Reserve, plus the balance of Transmission

Related Intangible Plant Amortization Reserve, Transmission Related General Plant

Depreciation Reserve and Transmission Related General Plant Amortization Reserve.

Transmission Related Intangible Plant Amortization Reserve, Transmission Related

General Plant Depreciation Reserve and Transmission Related General Plant

Amortization Reserve shall equal the product of the sum of Intangible Plant Amortization

Reserve, General Plant Depreciation Reserve and General Plant Amortization Reserve,

and the Transmission Wages and Salaries Allocation Factor. This sum shall be multiplied

by the PTF/HTF Transmission Plant Allocation Factor. In order to calculate the

Incremental Return and Associated Income Taxes for Post-2003 PTF Investment,

Transmission Depreciation Reserve associated with Post-2003 PTF Investment shall

equal the PTO’s balance of Total Transmission Depreciation Reserve multiplied by the

ratio of Post-2003 PTF Transmission Plant to Total Investment in Transmission Plant,

excluding capital leases in the Phase I/II HVDC-TF Leases.

(e) Transmission Related Accumulated Deferred Taxes shall equal the PTO’s electric

balance of Total Accumulated Deferred Income Taxes, multiplied by the Plant Allocation

Factor, further multiplied by the PTF/HTF Transmission Plant Allocation Factor. To

calculate the Incremental Return and Associated Income Taxes for Post-2003 PTF

Investment, Transmission Related Accumulated Deferred Income Taxes associated with

Post-2003 PTF Investment shall equal the PTO’s balance of total property-related

accumulated deferred income taxes as recorded in FERC accounts 281 and 282,

multiplied by the ratio of Total Investment in Transmission Plant, excluding Phase I/II

HVDC-TF Leases, to Total Plant in Service excluding Phase I/II HVDC-TF Leases,

further multiplied by the ratio of Post-2003 PTF Transmission Plant to Total Investment

in Transmission Plant, excluding Phase I/II HVDC-TF Leases.

(f) Transmission Related Loss on Reacquired Debt shall equal the PTO’s electric balance of

Total Loss on Reacquired Debt multiplied by the Plant Allocation Factor, further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

(g) Other Regulatory Assets/Liabilities shall equal the PTO’s electric balance of any deferred

rate recovery of FAS 106 expenses multiplied by the Transmission Wages and Salaries

Allocation Factor, plus the PTO’s electric balance of FAS 109 multiplied by the Plant

Allocation Factor. This sum shall be multiplied by the PTF/HTF Transmission Plant

Allocation Factor.

(h) Transmission Prepayments shall equal the PTO's electric balance of prepayments

multiplied by the Transmission Wages and Salaries Allocation Factor and further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

(i) Transmission Materials and Supplies shall equal the PTO's electric balance of

Transmission Plant Materials and Supplies, multiplied by the PTF/HTF Transmission

Plant Allocation Factor.

(j) Transmission Related Cash Working Capital shall be a 12.5% allowance (45 days/360

days) of the PTO's Transmission Operation and Maintenance Expense, Transmission

Related Administrative and General Expense and Transmission Support Expense, to the

extent that Transmission Support Expense exceeds Transmission Support Revenue

included in Paragraph J of the formula.

(k) MPRP CWIP shall equal CMP's balance as recorded in FERC Account No. 107 for the

MPRP as authorized by Commission order and in accordance with CMP's Accounting

Procedures for MPRP CWIP. In order to calculate the Incremental Return and Associated

Income Taxes for MPRP CWIP, MPRP CWIP shall be separately identified.

(l) NEEWS CWIP shall equal CL&P, WMECO and NEP’s balances as recorded in FERC

Account No. 107 for the NEEWS as authorized by Commission order and in accordance

with the companies’ respective Accounting Procedures for NEEWS CWIP. In order to

calculate the Incremental Return and Associated Income Taxes for NEEWS CWIP,

NEEWS CWIP shall be separately identified.

2. Cost of Capital Rate

The Cost of Capital Rate will equal (a) the PTO's Weighted Cost of Capital, plus (b)

Federal Income Tax plus (e) State Income Tax.

(a) The Weighted Cost of Capital will be calculated based upon the capital structure at the

end of each year and will equal the sum of (i), (ii), and (iii) below. The Cost of Capital

Rate to be used in calculating the Incremental Return and Associated Income Taxes for

Post-2003 PTF Investment and for MPRP CWIP and NEEWS CWIP, shall only reflect

item (iii) below and shall apply in the manner indicated below.

(i) the long-term debt component, which equals the product of the actual weighted average

embedded cost to maturity of the PTO's long-term debt then outstanding and the ratio that

long-term debt is to the PTO's total capital.

(ii) the preferred stock component, which equals the product of the actual weighted average

embedded cost to maturity of the PTO's preferred stock then outstanding and the ratio

that preferred stock is to the PTO's total capital.

(iii) the return on equity component, shall be the product of the allowed ROE of the PTO's

common equity and the ratio that common equity is to the PTO's total capital. For pre-

1997 and post-1996 assets, the ROE is 11.07%. In order to calculate the Incremental

Return and Associated Income Taxes for Post-2003 PTF Investment and for MPRP

CWIP and NEEWS CWIP, the incremental return on equity shall be the product of: (1)

the PTO's incremental return on equity of 1.0% for plant investments associated with

projects included in the RSP and placed in service by December 31, 2008 or otherwise

permitted in Docket Nos. ER04-157, et al.; (2) any ROE incentive approved by the FERC

under Order No. 679 for other plant investments (however; the 125 basis point ROE

incentive adder granted to NEEWS under Order No. 679 in Docket No. ER08-1548 and

the 50 basis point ROE incentive adder for RTO participation shall not apply to the costs

related to the Central Connecticut Reliability Project, consistent with FERC’s order) and

MPRP CWIP and NEEWS CWIP, provided that the total ROE for any project, including

any such ROE incentives, shall be capped by the top of the applicable zone of

reasonableness determined by FERC for the relevant period, and (3) the ratio that

common equity is to the PTO's total capital) 1

(b) Federal Income Tax shall equal

(A+[(C+B)/D])(FT)

I-FT

where FT is the Federal Income Tax Rate and A is the sum of the preferred stock

component and the return on equity component, as determined in Sections ll.A.2.(a)(ii)

and (iii) above, B is Transmission Related Amortization of Investment Tax Credits, as

determined in Section II.D., below, C is the Equity AFUDC component of Transmission

Depreciation Expense, as defined in Section ll.B., and D is Transmission Investment

Base, as determined in Section II.A.1., above. In order to calculate the Incremental

Return and Associated Income Taxes for Post-2003 PTF Investment and for MPRP

CWIP and NEEWS CWIP, the incremental Federal Income Tax shall equal

(A’ * FT)

(1 -FT)

where FT is the Federal Income Tax Rate and A' is the incremental return on equity

component, as determined in Section II.A.2.(a)(iii) above.

(c) State Income Tax shall equal

(A+[(C+B)/D] + Federal Income Tax)(ST)

1 -ST

where ST is the State Income Tax Rate, A is the sum of the preferred stock component

and return on equity component determined in Sections II.A.2.(a)(ii) and (iii) above, B is

the Amortization of Investment Tax Credits as determined in Section ll.D.below, C is the

equity AFUDC component of Transmission Depreciation Expense, as defined in Section

1 FERC Form-730 contains a list of transmission projects for which FERC has granted incentives under Order No.

679.

II.B.. D is the Transmission Investment Base, as determined in II.A.1., above and Federal

Income Tax is the rate determined in Section II.A.2.(b) above. In order to calculate the

Incremental Return and Associated Income Taxes for Post-2003 PTF Investment and for

MPRP CWIP and NEEWS CWIP, the incremental State Income Tax shall equal

(A’ + Federal Income Tax)(ST)

(1 – ST)

where ST is the State Income Tax Rate, A’ is the incremental return on equity component

determined in Section II.A.2.(a)(iii) above, and Federal Income Tax is the rate

determined in Section II.A.2.(b) above.

B. Transmission Depreciation and Amortization Expense shall equal the PTF/HTF Transmission

Plant Allocation Factor, multiplied by the sum of (i) the PTO’s Depreciation Expense for

Transmission Plant, plus (ii) an allocation of Intangible Plant Amortization Expense and (iii)

General Plant Depreciation and Amortization Expense calculated by multiplying the sum of (a)

Intangible Plant Amortization Expense and (b) General Plant Depreciation and Amortization

Expense by the Transmission Wages and Salaries Allocation Factor.

C. Transmission Related Amortization of Loss on Reacquired Debt shall equal the PTO’s electric

Amortization of Loss on Reacquired Debt multiplied by the Plant Allocation Factor, and further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

D. Transmission Related Amortization of Investment Tax Credits shall equal the PTO’s electric

Amortization of Investment Tax Credits multiplied by the Plant Allocation Factor, and further

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

E. Transmission Related Municipal Tax Expense shall equal the PTO’s total electric municipal tax

expense multiplied by the Plant Allocation Factor, and further multiplied by the PTF/HTF

Transmission Plant Allocation Factor.

F. Transmission Related Payroll Tax Expense shall equal the PTO’s total electric payroll tax

expense, multiplied by the Transmission Wages and Salaries Allocation Factor, further multiplied

by the PTF/HTF Transmission Plant Allocation Factor.

G. Transmission Operation and Maintenance Expense shall equal the PTO’s Transmission Operation

and Maintenance Expenses multiplied by the PTF/HTF Transmission Plant Allocation Factor.

H. Transmission Related Administrative and General Expenses shall equal the sum of the PTO’s (1)

Administrative and General Expenses multiplied by the Transmission Wages and Salaries

Allocation Factor, (2) Property Insurance multiplied by the Transmission Plant Allocation Factor,

and (3) Expenses included in Account 928 related to FERC Assessments multiplied by Plant

Allocation Factor, plus any other Federal and State transmission related expenses or assessments,

plus specific transmission related expenses included in Account 930.1. This sum shall be

multiplied by the PTF/HTF Transmission Plant Allocation Factor.

I. Transmission Related Integrated Facilities Charges shall equal the PTO’s transmission payments

to Affiliates for use of the PTF and HTF integrated transmission facilities of those Affiliates.

J. Transmission Support Revenues shall equal the PTO’s revenue received for PTF and HTF

transmission support but excluding the support payments to PTOs or their designee pursuant to

Schedule 11 and excluding the support payments to PTOs or their designee pursuant to Schedule

12 Part 1(a) and Part B.2, and excluding support payments, if any, made to PTOs or their

respective designee pursuant to Part II.C of this OATT.

K. Transmission Support Expense shall equal the expense paid by (1) PTOs, (2) Transmission

Customers or (3) Related Persons pursuant to Section II.49 of the Tariff for PTF and HTF

transmission support other than expenses for payments made for congestion rights or for

transmission facilities or facility upgrades placed in service on or after January 1, 1997, where the

support obligation is required to be borne by particular PTOs or other entities in accordance with

the OATT. Transmission Support Expenses by any entity other than a PTO, included in this

provision, shall be capped at that entity’s annual payment for Regional Network Service or its

Point To Point Service for each individual Point To Point transaction from the resource with

which the support payment is associated.

L. Transmission-Related Expense from Generators shall equal the expenses from generators that

both (1) the PTO Administrative Committee determines should be included as transmission

expense as a result of the impact of such generators on reducing transmission costs that would

otherwise be required to be paid by Transmission Customers and (2) are reflected in a filing made

by the PTOs with the Commission under Section 205 of the Federal Power Act and accepted by

the Commission for recovery under the OATT.

M. Transmission Related Taxes and Fees Charge shall include any fee or assessment imposed by any

governmental authority on service provided under this Section which is not specifically identified

under any other section of this rule.

N. Revenues for Short-Term service under the OATT shall be revenues distributed to each PTO for

short term service provided under the OATT, received after March 1, 1999. These revenues will

be credited pro-rata between pre-1997 and post-1996 PTF revenue requirements in proportion to

pre-1997 and post-1996 PTF Transmission Plant.

O. Transmission Rents Received from Electric Property shall equal any Account 454 Rents from

electric property, associated with PTF and HTF Transmission Plant as defined in Section

II.A.1.(a) above but not reflected as a credit in Transmission Support Revenues in paragraph K of

this Attachment.

P. Transmission Revenues from MGTSAs shall equal any MGTSA revenues recorded in Account

456.

APPENDIX A TO ATTACHMENT F

IMPLEMENTATION RULE RULES FOR DETERMINING

INVESTMENT TO BE INCLUDED IN PTF

Section A – Transmission Lines*

Section B – Terminal Facilities*

Section C – Right of Way*

Effective June 1, 1998

*The following provision shall apply to Sections A, B and C below:

Of those transmission facilities that are upgrades, modifications or additions to the New England

Transmission System on and after January 1, 2004, only those that: (i) are rated 115kV or above, and (ii)

otherwise meet the non-voltage criteria specified in Section II.49 of this OATT shall be classified as PTF.

Those transmission facilities that were PTF on December 31, 2003, and any upgrades to such facilities

that meet the definition of PTF specified in this OATT, shall remain classified as PTF for all purposes

under the Transmission, Markets and Services Tariff.

Section A: Rules for Determining Transmission Line Investment to be Included in PTF

Pool Transmission Facilities (PTF) are the transmission facilities owned by PTO rated 69 kV or above

required to allow energy from significant power sources to move freely on the New England transmission

network, and include:

1. All transmission lines and associated facilities owned by the PTOs rated 69 kV and above,

except:

a. those which are required to serve local load only, thereby contributing little or no parallel

capability to the transmission network,

b. generator leads, which are defined as the radial transmission from a generator bus to the

nearest point on the transmission network,

c. lines that are normally operated open.

d. those that are classified as MTF.

2. Terminal facilities (including substation facilities such as transformers, circuit breakers, and

associated equipment) required to interconnect the lines which constitute PTF (see Section B).

3. If a PTO with significant generation in its system (initially 25 MW) is connected to the New

England Transmission System and none of the transmission facilities owned by the PTO qualify

to be included in PTF as defined in “1” and “2” above, then such PTO’s connection to PTF will

constitute PTF if both of the following requirements are met for this connection:

a. The connection is rated 69 kV or above.

b. The connection is the principal transmission link between the PTO and the remainder of

the ISO PTF network.

The PTF facilities covered by this provision shall consist of a single line from the point of connection on

the transmission network to the first bus within the PTO’s system.

4. R/W and land required for the installation of PTF facilities listed in “1”, “2”, or “3” (see Section

C).

The following examples indicate the intent of the above definitions:

a. Radial tap lines to local load are excluded.

b. Lines which loop, from two geographically separate points on the transmission network,

the supply to the load bus from the transmission network are included.

c. Lines which loop, from two geographically separate points on the transmission network,

the connections between a generator bus, and the transmission network are included.

d. Radial connection or connections from a generating station to a single substation or

switching station on the transmission network are excluded unless the requirements of

paragraph 3 above are met.

e. The cost of a PTF line will include only those costs associated with that line. When other

facilities require rebuilding or undergrounding to permit the construction of a PTF

facility, the investment costs in the relocated or undergrounded facility will not be

included.

f. Where multiple circuit structures support a mixture of PTF and Non-PTF circuits, the

total cost of the multiple circuit structures will be allocated between the circuits in

accordance with the ratio of costs of comparable individual structures.

The PTOs shall review at least annually the status of transmission lines and related facilities and

determine whether such facilities constitute PTF and shall prepare and keep current a schedule or catalog

of PTF facilities.

All new facilities being installed should be properly classified at the time the facilities are approved under

Section I.3.9 of the Transmission, Markets and Services Tariff.

Transmission facilities owned or supported by a Related Person of a PTO which are rated 69 kV or above

and are required to allow Energy from significant power sources to move freely on the New England

Transmission System shall also constitute PTF provided (i) such Related Person files with the ISO its

consent to such treatment; and (ii) the ISO determines in consultation with the PTO Administrative

Committee determines that treatment of the facility as PTF will facilitate accomplishment of the ISO’s

objectives. If such facilities constitute PTF pursuant to this paragraph, they shall be treated as “owned” or

“supported,” as applicable, by a PTO for purposes of the OATT and the other provisions of the TOA,

including the ability to include the cost associated with such PTF and any Transmission Support Expenses

for support of PTF made by its Related Person in that PTO’s Annual Transmission Revenue

Requirements pursuant to Attachment F of the OATT.

Section B: Rules for Determining Terminal Investment to be Included in PTF

Terminal Investment is investment associated with the terminal facilities of electrical lines, including

substation facilities such as transformers, circuit breakers, disconnects and airbreaks, bus conductor,

related protection equipment and other related facilities (see paragraph 7).

1. The investment in terminal facilities shall be included where these facilities are identifiable and

serve directly for terminating and/or switching PTF lines.

2. In cases where a line terminal is used in conjunction with both PTF and Non-PTF lines and/or

facilities, it will be considered a PTF facility providing the terminal facility is at 69 kV or above

and carries any power flow at 69 kV or above through parallel paths within the interconnected

network under normal operation. PTF equipment is any element of the transmission system in

those parallel paths. Any equipment not in these parallel paths is Non-PTF.

3. Where line terminals are installed solely for Non-PTF facilities, and do not carry any power flow

at 69 kV or above through parallel paths within the interconnected network under normal

operation, such terminal cost shall not be included in PTF.

4. A two-winding transformer which connects PTF facilities at both terminals along with any

switcher which can be identified as pertaining solely to the transformer, will be included in their

entirety as PTF.

5. An autotransformer or three winding transformer which connects PTF facilities at two (2) or more

terminals, along with any switchgear which can be identified as pertaining solely to the PTF-

connected terminals of the transformer, will be included in their entirety as PTF. An

autotransformer or three winding transformer which is connected to PTF at only one terminal will

not be PTF.

6. When a transformer supplies only Non-PTF facilities, the entire transformer installation,

including the high side disconnect switch or circuit breaker and associated structures or tap lines

shall be excluded from PTF except for the portion of line terminal facilities covered by paragraph

2.

7. Other facilities – the investment in that portion of a multi-use substation or switching station

which is identifiable as serving a PTF function shall be included in PTF, while the investment in

such facilities which are identifiable as serving a Non-PTF function shall be excluded. The

investment in land, structures, ground mats, fences, ducts, lighting, etc., can often be identified

and thus allocated. The investment in other facilities in the substation or switching station,

excluding transformers, which are not identifiable as serving either a PTF or a Non-PTF function

and general overheads shall be allocated to PTF on the basis of the ratio of the investment in

those facilities identified as PTF to the sum of the investments in the facilities which are

identified as serving PTF and Non-PTF functions; the equipment cost of power transformers shall

not be included in this calculation for determining the division of investment, since this would

produce a distorted balance.

8. Alternate method of allocating the cost of terminal facilities – In those cases where the major

portion of the investment has been lumped and utility plant records do not permit the accurate

assignment of costs to specific terminals, the total investment may be prorated to PTF and Non-

PTF according to the number of terminals serving PTF and Non-PTF facilities.

9. In cases where microwave facilities are used in whole or part for PTF purposes, a prorated

portion of such investment shall be included in PTF based on the PTF and Non-PTF functions

served by the microwave facilities except where these facilities are otherwise supported under the

Microwave Sharing Agreement dated June 1, 1970 among some of the New England utilities.

10. Generator unit transformers and generator circuit breakers shall be excluded from PTF, unless

otherwise included by paragraphs 1 or 5.

11. In cases where remote control (Supervisory Control) and telemetering facilities are used in whole

or in part for PTF purposes, a prorated portion of such investment shall be included in PTF based

on the PTF and Non-PTF functions served by these facilities.

12. The PTO Administrative Committee may designate appropriate facilities as PTF.

Section C: Rules for Determining PTF R/W Costs

1. If a R/W has only PTF lines and no Non-PTF lines are expected to be added, the entire cost of the

R/W is to be included as PTF.

2. If the R/W has only PTF lines but includes additional unused R/W which was purchased for

future use by Non-PTF lines, the cost of the additional R/W is not to be included as PTF.

3. If the R/W contains both PTF and Non-PTF lines, the R/W cost to be assigned to PTF is to be

determined as follows:

a. Where new or additional R/W is required to permit the construction of PTF line(s) and

the added R/W is adequate to contain the new PTF, the cost of the new R/W is to be

assigned to the PTF line(s), (even if the PTF line is located on the old R/W).

b. Where an existing R/W is used (without additional R/W), the amount allocated to PTF

will be determined in accordance with paragraph 4.

c. Where a R/W is widened, but the new facilities, either PTF or Non-PTF, require partial

use of the existing R/W, the incremental cost of the new R/W will be assigned to the new

facilities. The width of the original R/W will be added to the width of the new R/W and

the combined width will be allocated between PTF and Non-PTF as in paragraph 4. The

cost of the old R/W and the combined width will be allocated between PTF and Non-PTF

as in paragraph 4. The cost of the old R/W will be allocated to the new facilities in

proportion to the width of the old R/W assigned to the new facilities. Thus, the R/W for

the new facilities will be the additional R/W plus a share of the old R/W.

4. In allocating R/W between PTF and Non-PTF lines, each shall bear a share of the R/W in

accordance with the following formulae.

a. Determine the R/W width required for each facility if constructed independently using

appropriate type structures.

b. Allocate the actual R/W width to each facility in the proportion its independent R/W

requirement would be to the sum of the independent R/W requirements.

5. R/W and land held for future PTF facilities may be included in PTF facilities only if specifically

approved by the PTO Administrative Committee included under paragraph 1.

ATTACHMENT 1 TO APPENDIX A TO

ATTACHMENT F IMPLEMENTATION RULE

Examples of the Methods for Distinguishing PTF

from Non-PTF Terminal Facilities

in a Number of Typical Substation Configurations

APPENDIX B TO ATTACHMENT F IMPLEMENTATION RULE

HTF TRANSITION SCHEDULE

The inclusion of HTF Annual Transmission Revenue Requirements in Attachment F (and the calculation

of the Pool PTF Rate) to this OATT will be limited by the provisions of this schedule.

VELCO, as a PTO and acting as agent for the HTF owners, may include the HTF Annual Transmission

revenue Requirements (i.e., HTF Transmission Plant) within the Attachment F calculations. Additionally,

the total HTF Annual Transmission Revenue Requirements included shall be limited to the following:

Year 1: A maximum of $1.2M in Year 1. For the sole purpose of this Schedule, “Year 1” shall be

defined as the first full year after the Operations Date:

Year 2: A maximum of $2.0M in Year 2. For the sole purpose of this Schedule, “Year 2” shall be

defined as the second full year after the Operations Date;

Year 3: A maximum of $2.8M in Year 3. For the sole purpose of this Schedule, “Year 3” shall be

defined as the third full year after the Operations Date;

Year 4: A maximum of $3.5M in Year 4. For the sole purpose of this Schedule, “Year 4” shall be

defined as the fourth full year after the Operations Date;

and

Year 5 and thereafter: All HTF Annual Transmission Revenue Requirements shall be included in

Attachment F.

ATTACHMENT F IMPLEMENTATION RULE

APPENDIX C

I. DEFINITIONS

(i) Annual True-up – Pre-1997 (ATU): shall be the difference between the actual Pre-1997 Annual

Transmission Revenue Requirements and the as-billed Pre-1997 Annual Transmission Revenue

Requirements, adjusted to include interest pursuant to Part II below. The actual Pre-1997 Annual

Transmission Revenue Requirements shall be an after-the-fact calculation and shall be

determined at the conclusion of each rate-effective period, i.e. June 1 through May 31 of each

year, by application of the Attachment F formula rate and each PTO’s relevant Pre-1997 PTF cost

data for the most recently concluded calendar year. The as-billed Pre-1997 Annual Transmission

Revenue Requirements shall be those Pre-1997 Annual Transmission Revenue Requirements

used to establish the RNS rates that were made effective on June 1 of the most recently concluded

calendar year.

(ii) Annual True-up – Post-1996 (ATU’): shall be the difference between the actual Post-1996

Annual Transmission Revenue Requirements and the as-billed Post-1996 Annual Transmission

Revenue Requirements, adjusted to include interest pursuant to Part II below. The actual Post-

1996 Annual Transmission Revenue Requirements shall be an after-the-fact calculation and shall

be determined at the conclusion of each rate-effective period, i.e. June 1 through May 31 of each

year, by application of the Attachment F formula rate and each PTO's relevant Post-1996 PTF

cost data for the most recently concluded calendar year.The as-billed Post-1996 Annual

Transmission Revenue Requirements shall be those Post-1996 Annual Transmission Revenue

Requirements used to establish the RNS rates that were made effective on June 1 of the most

recently concluded calendar year and which included the sum of the Post-1996 Transmission

Revenue Requirements for the year prior to the most recently concluded calendar year plus the

Forecasted Transmission Revenue Requirements for the most recently concluded calendar year.

(iii) Forecast Period: The calendar year immediately following the calendar year for which the most

recent FERC Form 1 data is available.

(iv) Forecasted Transmission Plant Additions (FTPA): shall equal an estimate of the PTO's Post-1996

PTF plant additions for the Forecast Period.

(v) Forecasted MPRP CWIP (FCWIP): shall equal CMP's estimated incremental change in

MPRPCWIP for the Forecast Period.

(vi) Carrying Charge Factor (CCF): shall reflect the most recent calendar year data used in determining

Post-1996 Annual Transmission Revenue Requirements and shall equal the sum of Attachment F

Sections II.A, excluding MPRP CWIP and NEEWS CWIP, through II.H divided by Attachment F

Section II.A.1.a.

(vii) MPRP Cost of Capital Rate (MCOC): shall be determined in accordance with Attachment F

Section II.A.2.

(viii) Forecasted Transmission Revenue Requirement (FTRR): shall equal FTPA multiplied by the

CCF plus FCWIP multiplied by the MCOC, plus FCCWIP multiplied by CCOC, plus FWCWIP

multiplied by WCOC, plus FNCWIP multiplied by NCOC, as shown:

FTRR = FTPA * CCF + (FCWIP * MCOC) + (FCCWIP * CCOC) + (FWCWIP * WCOC) +

(FNCWIP * NCOC)

(ix) Forecasted CL&P NEEWS CWIP (FCCWIP): shall equal CL&P’s estimated incremental change

in NEEWS CWIP for the Forecast Period.

(x) Forecasted WMECO NEEWS CWIP (FWCWIP): shall equal WMECO’s estimated incremental

change in NEEWS CWIP for the Forecast Period.

(xi) NEEWS CL&P Cost of Capital Rate (CCOC): shall be determined in accordance with

Attachment F Section II.A.2.

(xii) NEEWS WMECO Cost of Capital Rate (WCOC): shall be determined in accordance with

Attachment F Section II.A.2.

(xiii) Forecasted NEP NEEWS CWIP (FNCWIP): shall equal NEP’s estimated incremental change in

NEEWS CWIP for the Forecast Period.

(xiv) NEEWS NEP Cost of Capital Rate (NCOC): shall be determined in accordance with Attachment

F Section II.A.2.

II. INTEREST ON ANNUAL TRUE-UPS

Interest on the Annual True-up amounts (i.e., interest applicable to any over or under collection) shall be

calculated in accordance with the methodology specified in the Commission’s regulations at 18 C.F.R. §

35.19a (a) (2) (iii).

III. INFORMATIONAL FILINGS

The PTOs’ annual informational filing shall include supporting documentation for their estimated capital

additions to be placed in service during the current calendar year as well as supporting documentation

pertaining to any annual true-up and interest calculations.

APPENDIX A

FORM OF PROTECTIVE AGREEMENT

FORM OF PROTECTIVE AGREEMENT

UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION

Eversource Energy Service Company ) Docket No. ER16-116-000

PROTECTIVE AGREEMENT 1. This Protective Agreement shall govern the use of all Protected Materials produced by, or on behalf of, any Participant. Notwithstanding any order terminating this proceeding, this Protective Agreement shall remain in effect until specifically modified or terminated by the Federal Energy Regulatory Commission (“Commission”). 2. This Protective Agreement applies to the following two categories of materials: (A) A Participant may designate as protected those materials which customarily are treated by that Participant as sensitive or proprietary, which are not available to the public, and which, if disclosed freely, would subject that Participant or its customers to risk of competitive disadvantage or other business injury; and (B) A Participant shall designate as protected those materials which contain critical energy infrastructure information, as defined in 18 C.F.R. § 388.113(c)(1) (“Critical Energy Infrastructure Information”). 3. Definitions — For purposes of this Protective Agreement. (a) The term “Participant” shall mean a Participant as defined in 18 C.F.R. §385.102(b). (b) (1) The term “Protected Materials” means (A) materials provided by a Participant and designated by such Participant as protected; (B) any information contained in or obtained from such designated materials; (C) any other materials which are made subject to this Protective Agreement by the Commission, by any court or other body having appropriate authority, or by agreement of the Participants; (D) notes of Protected Materials; and (E) copies of Protected Materials. The Participant producing the Protected Materials shall physically mark them, at least on the first page of each document, as “PROTECTED MATERIALS” or with words of similar import as long as the term “Protected Materials” is included in that designation to indicate that they are Protected Materials. If the Protected Materials contain Critical Energy Infrastructure Information, the Participant producing such information shall additionally mark on each page containing such information the words “Contains Critical Energy Infrastructure Information - Do Not Release.” (2) The term “Notes of Protected Materials” means memoranda, handwritten notes, or any other form of information (including electronic form) which copies or discloses materials described in Paragraph 5. Notes of Protected Materials are subject to the same

- - - 3 -

restrictions provided in this order for Protected Materials except as specifically provided in this Protective Agreement. (3) Protected Materials shall not include (A) any information or document contained in the files of the Commission, or any other federal or state agency, or any federal or state court, unless the information or document has been determined to be protected by such agency or court, or (B) information that is public knowledge, or which becomes public knowledge, other than through disclosure in violation of this Protective Agreement, or (C) any information or document labeled as “Non-Internet Public” by a Participant, in accordance with Paragraph 30 of FERC Order No. 630, FERC Stat. & Reg. ¶ 31,140. Protected Materials do include any information or document contained in the files of the Commission that has been designated as Critical Energy Infrastructure Information. (c) By signing this Protective Agreement, a Participant that has been granted access to Protected Materials certifies its understanding that such access to Protected Materials is provided pursuant to the terms and restrictions of this Protective Agreement, and that such Participants have read the Protective Agreement and agree to be bound by it. (d) The term “Reviewing Representative” shall mean a person who has executed this Protective Agreement, except that members of the Commission’s Staff need not execute, and who is: (1) Commission Staff; (2) an attorney who has made an appearance in this proceeding for a Participant; (3) attorneys, paralegals, and other employees associated for purposes of this case with an attorney described in Paragraph (2); (4) an expert or an employee of an expert retained by a Participant for the purpose of advising, preparing for or testifying in this proceeding; (5) a person designated as a Reviewing Representative by order of the Commission; or (6) employees or other representatives of Participants appearing in this proceeding with significant responsibility for this docket. 4. Protected Materials shall be made available under the terms of this Protective Agreement only to Participants and only through their Reviewing Representatives as provided in Paragraphs 7-9. 5. Protected Materials shall remain available to Participants until the later of the date that an order terminating this proceeding becomes no longer subject to judicial review, or the date that any other Commission proceeding relating to the Protected Material is concluded and no longer subject to judicial review. If requested to do so in writing after that date, the Participants shall,

- - - 4 -

within fifteen days of such request, return the Protected Materials (excluding Notes of Protected Materials) to the Participant that produced them, or shall destroy the materials, except that copies of filings, official transcripts and exhibits in this proceeding that contain Protected Materials, and Notes of Protected Material may be retained, if they are maintained in accordance with Paragraph 6, below. Within such time period each Participant, if requested to do so, shall also submit to the producing Participant an affidavit stating that, to the best of its knowledge, all Protected Materials and all Notes of Protected Materials have been returned or have been destroyed or will be maintained in accordance with Paragraph 6. To the extent Protected Materials are not returned or destroyed, they shall remain subject to the Protective Agreement. 6. All Protected Materials shall be maintained by the Participant in a secure place. Access to those materials shall be limited to those Reviewing Representatives specifically authorized pursuant to Paragraphs 8-9. The Secretary shall place any Protected Materials filed with the Commission in a non-public file. By placing such documents in a non-public file, the Commission is not making a determination of any claim of privilege. The Commission retains the right to make determinations regarding any claim of privilege and the discretion to release information necessary to carry out its jurisdictional responsibilities. For documents submitted to Commission Staff (“Staff”), Staff shall follow the notification procedures of 18 C.F.R. § 388.112 before making public any Protected Materials. 7. Protected Materials shall be treated as confidential by each Participant and by the Reviewing Representative in accordance with this Protective Agreement executed pursuant to Paragraph 9. Reviewing Representatives that are Commission Staff are required to comply with the requirements of this Protective Agreement but need not execute this Protective Agreement. Protected Materials shall not be used except as necessary for the conduct of this proceeding, nor shall they be disclosed in any manner to any person except a Reviewing Representative who is engaged in the conduct of this proceeding and who needs to know the information in order to carry out that person’s responsibilities in this proceeding. Reviewing Representatives may make copies of Protected Materials, but such copies become Protected Materials. Reviewing Representatives may make notes of Protected Materials, which shall be treated as Notes of Protected Materials if they disclose the contents of Protected Materials. 8. (a) If a Reviewing Representative’s scope of employment includes the marketing of energy or the buying or selling of fossil generating assets, the direct supervision of any employee or employees whose duties include the marketing of energy or the buying or selling of fossil generating assets, the provision of consulting services to any person whose duties include the marketing of energy or the buying or selling of fossil generating assets, or the direct supervision of any employee or employees whose duties include the marketing of energy or the buying or selling of fossil generating assets, such Reviewing Representative may not use information contained in any Protected Materials obtained through this proceeding to give any Participant or any competitor of any Participant, including its own employees or the employees of the party it represents, a commercial advantage or any non-public information regarding operation of fossil generating assets. (b) In the event that a Participant wishes to designate as a Reviewing Representative a person not described in Paragraph 3(d) above, the Participant shall seek agreement from the

- - - 5 -

Participant providing the Protected Materials. If an agreement is reached that person shall be a Reviewing Representative pursuant to Paragraphs 3(d) above with respect to those materials. If no agreement is reached, the Participant shall submit the disputed designation to the Commission for resolution. 9. (a) A Reviewing Representative shall not be permitted to inspect, participate in discussions regarding, or otherwise be permitted access to Protected Materials pursuant to this Protective Agreement unless that Reviewing Representative has first executed this Protective Agreement provided that if an attorney qualified as a Reviewing Representative has executed such agreement, the paralegals, secretarial and clerical personnel under the attorney’s instruction, supervision or control need not do so. A copy of each Protective Agreement shall be provided to counsel for the Participant asserting confidentiality prior to disclosure of any Protected Material to that Reviewing Representative. (b) Attorneys qualified as Reviewing Representatives are responsible for ensuring that persons under their supervision or control comply with this Protective Agreement. 10. Any Reviewing Representative may disclose Protected Materials to any other Reviewing Representative as long as the disclosing Reviewing Representative and the receiving Reviewing Representative both have executed a Protective Agreement. In the event that any Reviewing Representative to whom the Protected Materials are disclosed ceases to be engaged in these proceedings, or is employed or retained for a position whose occupant is not qualified to be a Reviewing Representative under Paragraph 3(d), access to Protected Materials by that person shall be terminated. Even if no longer engaged in this proceeding, every person who has executed a Protective Agreement shall continue to be bound by the provisions of this Protective Agreement. 11. Subject to Paragraph 17, the Commission shall resolve any disputes arising under this Protective Agreement. Prior to presenting any dispute under this Protective Agreement to the Commission, the parties to the dispute shall use their best efforts to resolve it. Any Participant that contests the designation of materials as protected shall notify the party that provided the protected materials by specifying in writing the materials whose designation is contested. This Protective Agreement shall automatically cease to apply to such materials five (5) business days after the notification is made unless the designator, within said 5-day period, files a motion with the Commission, with supporting affidavits, demonstrating that the materials should continue to be protected. In any challenge to the designation of materials as protected, the burden of proof shall be on the participant seeking protection. If the Commission finds that the materials at issue are not entitled to protection, the procedures of Paragraph 17 shall apply. The procedures described above shall not apply to protected materials designated by a Participant as Critical Energy Infrastructure Information. Materials so designated shall remain protected and subject to the provisions of this Protective Agreement, unless a Participant requests and obtains a determination from the Commission’s Critical Energy Infrastructure Information Coordinator that such materials need not remain protected. 12. All copies of all documents reflecting Protected Materials, including the portion of the hearing testimony, exhibits, transcripts, briefs and other documents which refer to Protected

- - - 6 -

Materials, shall be filed and served in sealed envelopes or other appropriate containers endorsed to the effect that they are sealed pursuant to this Protective Agreement. Such documents shall be marked “PROTECTED MATERIALS” and shall be filed under seal and served under seal upon the Commission and all Reviewing Representatives who are on the service list. Such documents containing Critical Energy Infrastructure Information shall be additionally marked “Contains Critical Energy Infrastructure Information - Do Not Release.” For anything filed under seal, redacted versions or, where an entire document is protected, a letter indicating such, will also be filed with the Commission and served on all parties on the service list. Counsel for the producing Participant shall provide to all Participants who request the same, a list of Reviewing Representatives who are entitled to receive such material. Counsel shall take all reasonable precautions necessary to assure that Protected Materials are not distributed to unauthorized persons. If any Participant desires to include, utilize or refer to any Protected Materials or information derived therefrom in testimony or exhibits during these proceedings in such a manner that might require disclosure of such material to persons other than reviewing representatives, such Participant shall first notify both counsel for the disclosing participant and the Commission of such desire, identifying with particularity each of the Protected Materials. Thereafter, use of such Protected Material will be governed by procedures determined by the Commission. 13. Nothing in this Protective Agreement shall be construed as precluding any Participant from objecting to the use of Protected Materials on any legal grounds. 14. Nothing in this Protective Agreement shall preclude any Participant from requesting the Commission, or any other body having appropriate authority, to find that this Protective Agreement should not apply to all or any materials previously designated as Protected Materials pursuant to this Protective Agreement. The Commission may alter or amend this Protective Agreement as circumstances warrant at any time during the course of this proceeding. 15. Each party governed by this Protective Agreement has the right to seek changes in it as appropriate from the Commission. 16. All Protected Materials filed with the Commission, or any other judicial or administrative body, in support of, or as a part of, a motion, other pleading, brief, or other document, shall be filed and served in sealed envelopes or other appropriate containers bearing prominent markings indicating that the contents include Protected Materials subject to this Protective Agreement. Such documents containing Critical Energy Infrastructure Information shall be additionally marked Contains Critical Energy Infrastructure Information — Do Not Release.” 17. If the Commission finds at any time in the course of this proceeding that all or part of the Protected Materials need not be protected, those materials shall, nevertheless, be subject to the protection afforded by this Protective Agreement for three (3) business days from the date of issuance of the Commission’s decision. None of the Participants waives its rights to seek additional administrative or judicial remedies after the Commission’s decision respecting Protected Materials or Reviewing Representatives, or the Commission’s denial of any appeal

- - - 7 -

thereof. The provisions of 18 C.F.R. §§ 388.112 and 388.113 shall apply to any requests for Protected Materials in the files of the Commission under the Freedom of Information Act. (5 U.S.C. § 552). 18. Nothing in this Protective Agreement shall be deemed to preclude any Participant from independently seeking through discovery in any other administrative or judicial proceeding information or materials produced in this proceeding under this Protective Agreement. 19. None of the Participants waives the right to pursue any other legal or equitable remedies that may be available in the event of actual or anticipated disclosure of Protected Materials. 20. The contents of Protected Materials or any other form of information that copies or discloses Protected Materials shall not be disclosed to anyone other than in accordance with this Protective Agreement and shall be used only in connection with this (these) proceeding(s). Any violation of this Protective Agreement executed hereunder shall constitute a violation of an order of the Commission.

[The next page is the signature page]

- - - 8 -

IN WITNESS WHEREOF, Eversource Energy Service Company and [the undersigned Recipient] each has caused this Protective Agreement to be signed by its duly authorized representative as of the date set forth below. By (Recipient):_________________________ Title:_________________________________ Representing:__________________________ Date:_________________________________ By:__________________________________ Title:_________________________________ Representing: Eversource Energy Service Company Date:_________________________________

Attachment 1

CCRP CWIP Balances and AFUDC

(April 2007 through May 2011)

Docket No. ER16-116Attachment 1

Page 1 of 2

Ln MonthCumulative CWIP

Balance AFUDC - Debt AFUDC - Equity Total AFUDC1 March 2007 (a) 180,216.00$ 2 April 2007 229,080.20$ 628.46$ 452.31$ 1,080.77$ 3 May 2007 278,561.54$ 593.44$ 1,087.97$ 1,681.41$ 4 June 2007 327,981.06$ 755.85$ 1,257.47$ 2,013.32$ 5 July 2007 460,484.50$ 937.92$ 1,522.70$ 2,460.62$ 6 August 2007 655,076.75$ 1,167.23$ 1,774.88$ 2,942.11$ 7 September 2007 816,409.08$ 1,542.93$ 2,001.06$ 3,543.99$ 8 October 2007 1,050,004.08$ 1,791.95$ 2,531.65$ 4,323.60$ 9 November 2007 1,294,448.88$ 2,171.66$ 3,734.45$ 5,906.11$

10 December 2007 1,616,169.62$ 2,852.00$ 4,642.18$ 7,494.18$ 11 2007 Total (Sum of Lines 1 through 10) 12,441.44$ 19,004.67$ 31,446.11$

12 January 2008 1,734,963.06$ 3,412.40$ 4,758.85$ 8,171.25$ 13 February 2008 1,916,956.47$ 3,333.06$ 7,122.70$ 10,455.76$ 14 March 2008 2,107,465.31$ 3,731.37$ 7,713.18$ 11,444.55$ 15 April 2008 2,295,528.44$ 4,086.61$ 7,767.27$ 11,853.88$ 16 May 2008 2,373,102.68$ 4,580.46$ 8,128.07$ 12,708.53$ 17 June 2008 2,578,908.72$ 5,037.13$ 8,933.16$ 13,970.29$ 18 July 2008 2,648,469.86$ 5,269.09$ 11,476.51$ 16,745.60$ 19 August 2008 2,751,368.99$ 5,632.75$ 12,268.59$ 17,901.34$ 20 September 2008 2,845,773.08$ 6,204.49$ 11,638.49$ 17,842.98$ 21 October 2008 2,989,798.54$ 7,182.58$ 10,699.27$ 17,881.85$ 22 November 2008 3,221,207.61$ 7,574.11$ 11,494.83$ 19,068.94$ 23 December 2008 3,335,703.55$ 7,397.91$ 10,073.25$ 17,471.16$ 24 2008 Total (Sum of Lines 12 through 23) 63,441.96$ 112,074.17$ 175,516.13$

25 January 2009 3,643,900.30$ 7,582.03$ -$ 7,582.03$ 26 February 2009 3,228,260.79$ 7,568.79$ -$ 7,568.79$ 27 March 2009 4,735,422.43$ 11,227.54$ 5,830.24$ 17,057.78$ 28 April 2009 5,203,343.49$ 12,439.10$ 17,869.26$ 30,308.36$ 29 May 2009 6,095,981.16$ 9,684.51$ 22,698.95$ 32,383.46$ 30 June 2009 6,738,321.30$ 10,927.57$ 25,612.37$ 36,539.94$

Eversource Energy Service CompanyCWIP Balance & AFUDC for April 2007 through May 2011

Central Connecticut Reliability Project

Docket No. ER16-116Attachment 1

Page 2 of 2

Ln MonthCumulative CWIP

Balance AFUDC - Debt AFUDC - Equity Total AFUDC31 July 2009 7,719,558.52$ 12,428.92$ 29,131.31$ 41,560.23$ 32 August 2009 8,551,468.23$ 14,786.99$ 34,658.16$ 49,445.15$ 33 September 2009 9,296,169.36$ 16,816.32$ 39,414.51$ 56,230.83$ 34 October 2009 9,787,223.96$ 18,936.45$ 44,383.68$ 63,320.13$ 35 November 2009 10,646,664.17$ 21,636.32$ 50,711.63$ 72,347.95$ 36 December 2009 12,007,611.01$ 23,303.11$ 54,618.30$ 77,921.41$ 37 2009 Total (Sum of Lines 25 through 36) 167,337.65$ 324,928.41$ 492,266.06$

38 January 2010 12,377,484.96$ 26,273.44$ 60,026.48$ 86,299.92$ 39 February 2010 12,670,442.73$ 27,665.11$ 63,205.99$ 90,871.10$ 40 March 2010 12,960,459.19$ 28,458.31$ 65,018.15$ 93,476.46$ 41 April 2010 13,198,400.96$ 28,974.41$ 66,197.29$ 95,171.70$ 42 May 2010 13,504,669.86$ 29,432.53$ 67,245.15$ 96,677.68$ 43 June 2010 13,462,461.71$ 29,715.36$ 67,891.35$ 97,606.71$ 44 July 2010 14,341,833.38$ 32,010.80$ 73,135.79$ 105,146.59$ 45 August 2010 14,559,155.33$ 33,086.32$ 75,593.04$ 108,679.36$ 46 September 2010 14,495,958.39$ 33,019.64$ 75,440.71$ 108,460.35$ 47 October 2010 14,700,543.38$ 32,940.66$ 75,260.26$ 108,200.92$ 48 November 2010 14,830,645.26$ 33,150.40$ 75,739.47$ 108,889.87$ 49 December 2010 14,981,744.12$ 33,283.88$ 76,044.41$ 109,328.29$ 50 2010 Total (Sum of Lines 38 through 49) 368,010.86$ 840,798.09$ 1,208,808.95$

51 January 2011 15,030,969.34$ -$ -$ -$ 52 February 2011 15,267,279.60$ 68,794.95$ 158,757.57$ 227,552.52$ 53 March 2011 15,395,902.19$ 35,331.34$ 81,533.85$ 116,865.19$ 54 April 2011 15,548,535.72$ 35,822.58$ 82,667.49$ 118,490.07$ 55 May 2011 15,653,524.55$ 35,865.11$ 82,765.64$ 118,630.75$ 56 2011 Total (Sum of Lines 51 through 55) 175,813.98$ 405,724.55$ 581,538.53$

57 Grand Total (Lines 11 + 24 + 37 + 50 + 56) 787,045.89$ 1,702,529.89$ 2,489,575.78$

Note:(a) - The cumulative CWIP balance represents the first months costs on the project. No AFUDC was calculated.

Central Connecticut Reliability Project

Eversource Energy Service CompanyCWIP Balance & AFUDC for April 2007 through May 2011

Attachment 2

Siting and Permitting Charges – Eversource’s Internal Labor

(including Public Outreach and Education Costs)

Docket No. ER16-116Attachment 2

Page 1 of 2

Line No. Year Month Total Siting and Permitting Amounts Notes

1 2007 Mar 5,045$ 2 2007 Apr 6,486$ 3 2007 May 5,540$ 4 2007 Jun 3,870$ 5 2007 Jul 2,501$ 6 2007 Aug 5,888$ 7 2007 Sep 5,571$ 8 2007 Oct 8,727$ 9 2007 Nov 6,441$

10 2007 Dec 7,049$ 11 2008 Jan 6,962$ 12 2008 Feb 3,517$ 13 2008 Mar 1,347$ 14 2008 Apr 2,177$ 15 2008 May 9,729$ 16 2008 Jun 3,485$ 17 2008 Jul 2,577$ 18 2008 Aug 1,233$ 19 2008 Sep 1,700$ 20 2008 Oct 2,150$ 21 2008 Nov 4,568$ 22 2008 Dec (146)$ (a)23 2009 Jan 8,769$ 24 2009 Feb (2,013)$ (a)25 2009 Mar 18,669$ 26 2009 Apr 10,323$ 27 2009 May 14,539$ 28 2009 Jun 10,627$ 29 2009 Jul 15,304$ 30 2009 Aug 16,452$ 31 2009 Sep 20,039$ 32 2009 Oct 22,878$ 33 2009 Nov 17,317$ 34 2009 Dec 31,871$

Eversource Energy Service CompanyInternal Labor Including Overheads and Indirect Charges

Siting and Permitting - Including Public Outreach and Education ChargesCentral Connecticut Reliability Project

Docket No. ER16-116Attachment 2

Page 2 of 2

Line No. Year Month Total Siting and Permitting Amounts Notes

35 2010 Jan 8,479$ 36 2010 Feb 7,435$ 37 2010 Mar 6,452$ 38 2010 Apr 7,380$ 39 2010 May 10,091$ 40 2010 Jun 7,006$ 41 2010 Jul 142,662$ 42 2010 Aug 6,746$ 43 2010 Sep (54,985)$ (b)44 2010 Oct 8,464$ 45 2010 Nov 4,221$ 46 2010 Dec 2,064$ 47 2011 Jan 3,015$ 48 2011 Feb 888$ 49 2011 Mar 688$ 50 2011 Apr 2,561$ 51 2011 May (784)$ (a)52 2011 Jun 1,529$

53 445,104$

54 Total S&P55 2007 57,118$ 56 2008 39,300$ 57 2009 184,774$ 58 2010 156,015$ 59 2011 7,896$

Note:

(b) This adjustment is associated with a year-to-date true up of the clearing account

Totals By Year Summary

(a) Negative amounts are typically associated with adjustments to labor and overheads

Attachment 3

Siting and Permitting –

(including Public Outreach and Education Costs)

Docket No. ER16-116Attachment 3

Page 1 of 3

Line No. Transaction

Date

General Ledger Year and Month

Charge Amount Charge Type Total Charges

in Month

Allocated Siting and Permitting

Amounts (c)

Invoice # Invoice Date Invoice Amount

1 7/31/2007 2007 - 07 57,943$ Unvouchered Liability (a) 57,943$ 30,618$ 2 8/7/2007 2007 - 08 (57,943)$ Unvouchered Liability 114,770$ 53,749$ 3 8/31/2007 2007 - 08 172,713$ Unvouchered Liability4 9/7/2007 2007 - 09 (172,713)$ Unvouchered Liability 94,382$ 37,199$ 5 9/9/2007 2007 - 09 1,285$ tax (b)6 9/7/2007 2007 - 09 1,861$ tax7 9/9/2007 2007 - 09 32,943$ invoice 44409-1 7/31/2007 32,943$ 8 9/7/2007 2007 - 09 47,723$ invoice 44409-2 8/31/2007 47,723$ 9 10/1/2007 2007 - 09 183,283$ Unvouchered Liability

10 10/4/2007 2007 - 10 (183,283)$ Unvouchered Liability 145,919$ 59,037$ 11 10/15/2007 2007 - 10 2,088$ tax12 10/10/2007 2007 - 10 53,531$ invoice 44409-3 9/27/2007 53,531$ 13 11/1/2007 2007 - 10 273,584$ Unvouchered Liability14 11/4/2007 2007 - 11 (273,584)$ Unvouchered Liability 120,322$ 48,837$ 15 11/4/2007 2007 - 11 7,049$ tax16 11/4/2007 2007 - 11 180,754$ invoice 44409-4 10/25/2007 180,754$ 17 12/4/2007 2007 - 11 206,103$ Unvouchered Liability18 12/6/2007 2007 - 12 (206,103)$ Unvouchered Liability 246,522$ 89,863$ 19 12/9/2007 2007 - 12 4,701$ tax20 12/9/2007 2007 - 12 120,531$ invoice 44409A 11/29/2007 120,531$ 21 1/3/2008 2007 - 12 327,393$ Unvouchered Liability22 1/5/2008 2008 - 01 (327,393)$ Unvouchered Liability 87,660$ 30,587$ 23 1/5/2008 2008 - 01 2,773$ tax24 1/5/2008 2008 - 01 71,114$ invoice 44409-6 12/21/2007 71,114$ 25 2/4/2008 2008 - 01 341,166$ Unvouchered Liability26 2/6/2008 2008 - 02 (341,166)$ Unvouchered Liability 96,523$ 27,083$ 27 2/8/2008 2008 - 02 3,104$ tax28 2/8/2008 2008 - 02 79,588$ invoice 44409-7 1/30/2008 79,588$ 29 3/3/2008 2008 - 02 354,997$ Unvouchered Liability30 3/6/2008 2008 - 03 (354,997)$ Unvouchered Liability 103,816$ 23,086$ 31 3/6/2008 2008 - 03 2,530$ tax32 3/6/2008 2008 - 03 64,867$ invoice 44409-8 2/27/2008 64,867$ 33 4/1/2008 2008 - 03 391,416$ Unvouchered Liability34 4/3/2008 2008 - 04 (391,416)$ Unvouchered Liability 35,465$ 9,237$ 35 4/8/2008 2008 - 04 1,562$ tax36 4/8/2008 2008 - 04 40,055$ invoice 444099 3/31/2008 40,055$ 37 5/2/2008 2008 - 04 385,264$ Unvouchered Liability38 5/4/2008 2008 - 05 (385,264)$ Unvouchered Liability 56,748$ 10,761$ 39 5/8/2008 2008 - 05 3,075$ tax40 5/8/2008 2008 - 05 78,838$ invoice 44409-10 4/30/2008 78,838$ 41 6/2/2008 2008 - 05 360,100$ Unvouchered Liability42 6/5/2008 2008 - 06 (360,100)$ Unvouchered Liability 54,750$ 9,332$ 43 6/5/2008 2008 - 06 2,733$ tax44 6/5/2008 2008 - 06 70,073$ invoice 44409-11 5/29/2008 70,073$ 45 7/2/2008 2008 - 06 342,045$ Unvouchered Liability46 7/4/2008 2008 - 07 (342,045)$ Unvouchered Liability 62,829$ 16,786$ 47 7/4/2008 2008 - 07 3,680$ tax48 7/4/2008 2008 - 07 94,363$ invoice 44409-12 6/27/2008 94,363$ 49 8/1/2008 2008 - 07 306,831$ Unvouchered Liability50 8/6/2008 2008 - 08 (306,831)$ Unvouchered Liability 19,962$ 7,103$ 51 8/6/2008 2008 - 08 2,738$ tax52 8/6/2008 2008 - 08 70,207$ invoice 44409-13 7/30/2008 70,207$ 53 9/3/2008 2008 - 08 253,848$ Unvouchered Liability54 9/5/2008 2008 - 09 (253,848)$ Unvouchered Liability 11,595$ 7,605$ 55 9/5/2008 2008 - 09 1,724$ tax56 9/5/2008 2008 - 09 44,217$ invoice 44409-14 8/27/2008 44,217$ 57 10/2/2008 2008 - 09 219,501$ Unvouchered Liability58 10/4/2008 2008 - 10 (219,501)$ Unvouchered Liability 53,382$ 22,356$ 59 10/9/2008 2008 - 10 1,166$ tax60 10/9/2008 2008 - 10 29,909$ invoice 44409-15 9/29/2008 29,909$ 61 10/31/2008 2008 - 10 241,807$ Unvouchered Liability62 11/5/2008 2008 - 11 (241,807)$ Unvouchered Liability 109,289$ 56,921$ 63 11/5/2008 2008 - 11 510$ tax64 11/5/2008 2008 - 11 13,073$ invoice 44409-16 10/27/2008 13,073$ 65 12/2/2008 2008 - 11 337,513$ Unvouchered Liability

Eversource Energy Service CompanySiting and Permitting (including Public Outreach and Education Costs)

Central Connecticut Reliabity Project

Docket No. ER16-116Attachment 3

Page 2 of 3

Line No. Transaction

Date

General Ledger Year and Month

Charge Amount Charge Type Total Charges

in Month

Allocated Siting and Permitting

Amounts (c)

Invoice # Invoice Date Invoice Amount

66 12/3/2008 2008 - 12 (337,513)$ Unvouchered Liability (35,465)$ (14,367)$ 67 12/26/2008 2008 - 12 1,247$ tax68 12/3/2008 2008 - 12 2,604$ tax69 12/26/2008 2008 - 12 31,983$ invoice 44409-18 12/23/2008 31,983$ 70 12/3/2008 2008 - 12 66,781$ invoice 44409-17 11/24/2008 66,781$ 71 1/5/2009 2008 - 12 199,433$ Unvouchered Liability72 1/6/2009 2009 - 01 (199,433)$ Unvouchered Liability 149,150$ 58,242$ 73 2/3/2009 2009 - 01 348,583$ Unvouchered Liability74 2/4/2009 2009 - 02 (348,583)$ Unvouchered Liability (286,982)$ (111,135)$ 75 2/4/2009 2009 - 02 2,312$ tax76 2/4/2009 2009 - 02 59,289$ invoice 44409-19 1/30/2009 59,289$ 77 4/1/2009 2009 - 03 7,809$ tax (d) 1,080,154$ 315,662$ 78 4/1/2009 2009 - 03 200,243$ Invoice (d) 44409-21 3/30/2009 205,137$ 79 4/2/2009 2009 - 03 872,102$ Unvouchered Liability80 4/3/2009 2009 - 04 (872,102)$ Unvouchered Liability 384,757$ 44,999$ 81 4/5/2009 2009 - 04 4,769$ tax82 4/5/2009 2009 - 04 122,292$ invoice 44409-20 2/27/2009 122,292$ 83 5/1/2009 2009 - 04 1,129,798$ Unvouchered Liability84 5/5/2009 2009 - 05 (1,129,798)$ Unvouchered Liability 668,378$ 117,319$ 85 5/5/2009 2009 - 05 12,061$ tax86 5/5/2009 2009 - 05 309,255$ invoice 44409-22 4/30/2009 309,255$ 87 6/2/2009 2009 - 05 1,476,860$ Unvouchered Liability88 6/3/2009 2009 - 06 (1,476,860)$ Unvouchered Liability 557,846$ 107,735$ 89 6/3/2009 2009 - 06 17,637$ tax90 6/3/2009 2009 - 06 452,237$ invoice 44409-23 5/28/2009 452,237$ 91 7/1/2009 2009 - 06 1,564,832$ Unvouchered Liability92 7/5/2009 2009 - 07 (1,564,832)$ Unvouchered Liability 800,280$ 203,949$ 93 7/5/2009 2009 - 07 9,639$ tax94 7/5/2009 2009 - 07 247,153$ invoice 44409-24 6/26/2009 247,153$ 95 8/4/2009 2009 - 07 2,108,321$ Unvouchered Liability96 8/5/2009 2009 - 08 (2,108,321)$ Unvouchered Liability 718,894$ 249,392$ 97 8/6/2009 2009 - 08 16,873$ tax98 8/25/2009 2009 - 08 38,646$ tax99 8/6/2009 2009 - 08 432,646$ invoice 44409-25 7/31/2009 432,646$

100 8/25/2009 2009 - 08 990,926$ invoice 44409-26 8/21/2009 990,926$ 101 9/2/2009 2009 - 08 1,348,124$ Unvouchered Liability102 9/3/2009 2009 - 09 (1,348,124)$ Unvouchered Liability 606,355$ 235,839$ 103 10/2/2009 2009 - 09 1,954,479$ Unvouchered Liability104 10/4/2009 2009 - 10 (1,954,479)$ Unvouchered Liability 261,824$ 92,471$ 105 10/30/2009 2009 - 10 21,930$ tax106 10/4/2009 2009 - 10 36,135$ tax107 10/30/2009 2009 - 10 562,300$ invoice 44409-28 10/14/2009 562,300$ 108 11/3/2009 2009 - 10 669,408$ Unvouchered Liability109 10/4/2009 2009 - 10 926,531$ invoice 44409-27 9/25/2009 926,531$ 110 11/4/2009 2009 - 11 (669,408)$ Unvouchered Liability 718,214$ 217,670$ 111 11/15/2009 2009 - 11 18,974$ tax112 11/15/2009 2009 - 11 486,501$ invoice 44409-29 11/12/2009 486,501$ 113 12/2/2009 2009 - 11 882,147$ Unvouchered Liability114 12/3/2009 2009 - 12 (882,147)$ Unvouchered Liability 1,143,451$ 349,326$ 115 12/17/2009 2009 - 12 24,425$ tax116 12/17/2009 2009 - 12 626,271$ invoice 44409-30 12/14/2009 626,271$ 117 1/6/2010 2009 - 12 1,374,903$ Unvouchered Liability118 1/6/2010 2010 - 01 (1,374,903)$ Unvouchered Liability 199,642$ 44,344$ 119 1/20/2010 2010 - 01 24,559$ tax120 1/20/2010 2010 - 01 629,709$ invoice 44409-31 1/18/2010 629,709$ 121 2/3/2010 2010 - 01 920,278$ Unvouchered Liability122 2/3/2010 2010 - 02 (920,278)$ Unvouchered Liability 134,562$ 15,507$ 123 2/12/2010 2010 - 02 11,792$ tax124 2/12/2010 2010 - 02 302,367$ invoice 44409-32 2/10/2010 302,367$ 125 3/2/2010 2010 - 02 740,680$ Unvouchered Liability126 3/3/2010 2010 - 03 (740,680)$ Unvouchered Liability 136,578$ 12,561$ 127 3/14/2010 2010 - 03 6,919$ tax128 3/14/2010 2010 - 03 177,419$ invoice 44409-33 3/10/2010 177,419$ 129 4/1/2010 2010 - 03 692,919$ Unvouchered Liability130 4/6/2010 2010 - 04 (692,919)$ Unvouchered Liability 81,579$ 2,292$ 131 4/14/2010 2010 - 04 4,940$ tax132 4/14/2010 2010 - 04 126,669$ invoice 44409-34 4/12/2010 126,669$ 133 5/3/2010 2010 - 04 642,889$ Unvouchered Liability

Docket No. ER16-116Attachment 3

Page 3 of 3

Line No. Transaction

Date

General Ledger Year and Month

Charge Amount Charge Type Total Charges

in Month

Allocated Siting and Permitting

Amounts (c)

Invoice # Invoice Date Invoice Amount

134 5/5/2010 2010 - 05 (642,889)$ Unvouchered Liability 109,351$ 20,779$ 135 5/17/2010 2010 - 05 3,607$ tax136 5/17/2010 2010 - 05 92,484$ invoice 44409-35 5/13/2010 92,484$ 137 6/2/2010 2010 - 05 656,149$ Unvouchered Liability138 6/3/2010 2010 - 06 (656,149)$ Unvouchered Liability (76,439)$ (10,805)$ 139 6/11/2010 2010 - 06 3,065$ tax140 6/11/2010 2010 - 06 78,594$ invoice 44409-36 6/9/2010 78,594$ 141 7/2/2010 2010 - 06 498,051$ Unvouchered Liability142 7/6/2010 2010 - 07 (498,051)$ Unvouchered Liability 80,059$ 10,504$ 143 7/16/2010 2010 - 07 2,990$ tax144 7/16/2010 2010 - 07 76,661$ invoice 44409-37 7/14/2010 76,661$ 145 8/3/2010 2010 - 07 498,459$ Unvouchered Liability146 8/4/2010 2010 - 08 (498,459)$ Unvouchered Liability 63,826$ 8,856$ 147 8/11/2010 2010 - 08 2,882$ tax148 8/11/2010 2010 - 08 73,908$ invoice 44409-38 8/9/2010 73,908$ 149 9/2/2010 2010 - 08 485,495$ Unvouchered Liability150 9/3/2010 2010 - 09 (485,495)$ Unvouchered Liability 75,251$ 9,942$ 151 9/14/2010 2010 - 09 2,624$ tax152 9/14/2010 2010 - 09 67,286$ invoice 44409-39 9/13/2010 67,286$ 153 10/4/2010 2010 - 09 490,836$ Unvouchered Liability154 10/6/2010 2010 - 10 (490,836)$ Unvouchered Liability 41,249$ 10,958$ 155 10/13/2010 2010 - 10 2,056$ tax156 10/13/2010 2010 - 10 52,709$ invoice 44409-40 10/8/2010 52,709$ 157 11/1/2010 2010 - 10 477,321$ Unvouchered Liability158 11/3/2010 2010 - 11 (477,321)$ Unvouchered Liability (8,569)$ (1,605)$ 159 11/21/2010 2010 - 11 22$ tax160 11/21/2010 2010 - 11 1,272$ tax161 11/12/2010 2010 - 11 33,169$ invoice 44409-41 11/9/2010 33,169$ 162 12/1/2010 2010 - 11 434,289$ Unvouchered Liability163 12/3/2010 2010 - 12 (434,289)$ Unvouchered Liability 15,731$ 3,771$ 164 12/19/2010 2010 - 12 747$ tax165 12/19/2010 2010 - 12 19,158$ invoice 44409-42 12/15/2010 19,158$ 166 1/4/2011 2010 - 12 430,114$ Unvouchered Liability167 1/5/2011 2011 - 01 (430,114)$ Unvouchered Liability 20,257$ 16,840$ 168 1/23/2011 2011 - 01 731$ tax169 1/14/2011 2011 - 01 18,754$ invoice 44409-43 1/12/2011 18,754$ 170 2/2/2011 2011 - 01 430,885$ Unvouchered Liability171 2/3/2011 2011 - 02 (430,885)$ Unvouchered Liability (16,044)$ (13,589)$ 172 2/15/2011 2011 - 02 517$ tax173 2/15/2011 2011 - 02 13,264$ invoice 44409-44 2/10/2011 13,264$ 174 3/2/2011 2011 - 02 401,060$ Unvouchered Liability175 3/3/2011 2011 - 03 (401,060)$ Unvouchered Liability 13,600$ 12,008$ 176 3/15/2011 2011 - 03 559$ tax177 3/3/2011 2011 - 03 13,455$ tax178 3/15/2011 2011 - 03 14,345$ invoice 44409-45C1 3/10/2011 14,345$ 179 4/4/2011 2011 - 03 41,301$ Unvouchered Liability180 3/3/2011 2011 - 03 345,000$ invoice 44409-44A 2/28/2011 345,000$ 181 4/5/2011 2011 - 04 (41,301)$ Unvouchered Liability 5,679$ 5,456$ 182 4/13/2011 2011 - 04 461$ tax183 4/13/2011 2011 - 04 11,819$ invoice 44409-46 4/11/2011 11,819$ 184 5/3/2011 2011 - 04 34,700$ Unvouchered Liability185 5/4/2011 2011 - 05 (34,700)$ Unvouchered Liability (26,219)$ (26,219)$ 186 6/1/2011 2011 - 05 187$ tax187 6/2/2011 2011 - 05 3,507$ Unvouchered Liability188 5/12/2011 2011 - 05 4,788$ invoice 44409-47 5/10/2011 4,788$ 189 6/4/2011 2011 - 06 (3,507)$ Unvouchered Liability (635)$ 190 7/5/2011 2011 - 06 1$ Unvouchered Liability191 6/14/2011 2011 - 06 108$ tax192 6/14/2011 2011 - 06 2,763$ invoice 44409-48 6/10/2011 2,763$ 193 7/6/2011 2011 - 07 (1)$ Unvouchered Liability (1)$

Totals 9,088,193 9,088,193 2,528,863 8,751,952

Notes(a)

(b) The tax entries are the tax amounts associated with each invoice. (c)

(d) The Invoice on line 78 was adjusted and only paid at $200,243 instead of the listed amount of $205,137. This also decreased the associated tax payment.

Eversource maintains its accounting records on an accrual basis in accordance with generally accepted accounting principles. Transactions with vendors for the acquisition of services are recorded on Eversource s books in the month in which services have been performed. Eversource meets this requirement by recording an invoice (vouchering), or by recording a journal entry to set up a liability (an unvouchered liability or UVL). A UVL is the term used by Eversource to identify transactions for the performance of services where an invoice has not been processed as an actual charge against a charge cost center (CCC) budget.

To calculate the "Allocated Siting and Permitting Amounts" ES worked with to identify the specific employees who worked on siting and permitting efforts. Eversource calculated the amount allocated to siting and permitting based on the ratio of actual hours charged by these specific employees to the total hours that were charged to Eversource monthly by The resulting ratio was multiplied by the amount in "Total Charges in Month" to derive the amount specifically attributable to siting and permitting for the month.

Attachment 4

Siting and Permitting - Charges

Docket No. ER16-116Attachment 4

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 03/11/2007 SALES TAXES 480$ 2 03/11/2007 SALES TAXES 1,397$ 3 03/11/2007 10/16/2006 361021 10,429$ 4 03/11/2007 10/16/2006 362984 30,379$ 5 Total 42,685$

Eversource Energy Service CompanyIndividual Charges by Date

Central Connecticut Reliabity Project

Attachment 5

Siting and Permitting – Charges

Docket No. ER16-116Attachment 5

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 12/31/2009 SALES TAXES 184$ 2 12/31/2009 12/03/2009 09-0337 4,725$ 3 Total 4,909$

Eversource Energy Service Companyndividual Charges by Date

Central Connecticut Reliabity Project

Attachment 6

Siting and Permitting –

Docket No. ER16-116Attachment 6

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 05/10/2009 04/30/2009 APRIL 2009 3,688$ 2 05/10/2009 SALES TAXES 144$ 3 06/18/2009 05/31/2009 MAY 2009 413$ 4 06/18/2009 SALES TAXES 16$ 5 08/14/2009 07/31/2009 JULY 2009 2,719$ 6 08/14/2009 SALES TAXES 106$ 7 09/24/2009 09/01/2009 AUGUST 2009 4,256$ 8 09/24/2009 SALES TAXES 166$ 9 11/08/2009 10/31/2009 OCTOBER 2009 1,188$

10 11/08/2009 SALES TAXES 46$ 11 12/17/2009 11/30/2009 NOVEMBER 2009 6,311$ 12 12/17/2009 SALES TAXES 246$ 13 02/19/2010 01/31/2010 JANUARY 2010 2,563$ 14 02/19/2010 SALES TAXES 100$ 15 Total 21,960$

Eversource Energy Service CompanyIndividual Charges by Date

Central Connecticut Reliabity Project

Attachment 7

Siting and Permitting – Charges

Docket No. ER16-116Attachment 7

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 01/14/2010 SALES TAXES 88$ 2 01/14/2010 SALES TAXES 31$ 3 01/14/2010 12/02/2009 180055 2,260$ 4 01/14/2010 12/15/2009 180062 805$ 5 Total 3,185$

Eversource Energy Service CompanyIndividual Charges by Date

Central Connecticut Reliabity Project

Attachment 8

Siting and Permitting – Charges

Docket No. ER16-116Attachment 8

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 06/24/2008 SALES TAXES 25$ 2 06/24/2008 05/23/2008 08-159 693$ 3 Total 718$

Eversource Energy Service CompanyIndividual Charges by Date

Central Connecticut Reliabity Project

Attachment 9

Siting and Permitting – Charges

Docket No. ER16-116Attachment 9

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 04/29/2008 SALES TAXES 7$ 2 04/29/2008 04/01/2008 001 197$ 3 07/10/2008 SALES TAXES 19$ 4 07/10/2008 07/01/2008 002 525$ 5 10/16/2008 SALES TAXES 13$ 6 10/16/2008 10/01/2008 003 356$ 7 01/26/2009 SALES TAXES 20$ 8 01/26/2009 01/01/2009 004 563$ 9 03/11/2009 SALES TAXES 7$

10 03/11/2009 03/01/2009 005 225$ 11 Total 1,932$

Eversource Energy Service Company Individual Charges by Date

Central Connecticut Reliabity Project

Attachment 10

Siting and Permitting – Charges

Docket No. ER16-116Attachment 10

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 11/06/2008 08/14/2008 80820 149$ 2 11/06/2008 SALES TAXES 6$ 3 01/26/2009 12/23/2008 120827 120$ 4 01/26/2009 SALES TAXES 5$ 5 03/18/2009 02/26/2009 20932 211$ 6 03/18/2009 SALES TAXES 8$ 7 04/08/2009 03/20/2009 30927 320$ 8 04/08/2009 SALES TAXES 12$ 9 04/14/2009 03/31/2009 30945 145$

10 04/14/2009 SALES TAXES 6$ 11 06/04/2009 05/20/2009 50921 107$ 12 06/04/2009 SALES TAXES 4$ 13 06/21/2009 06/09/2009 60911 90$ 14 06/21/2009 SALES TAXES 4$ 15 09/27/2009 09/18/2009 90907 317$ 16 09/27/2009 SALES TAXES 12$ 17 10/07/2009 09/29/2009 90924 40$ 18 10/07/2009 09/29/2009 90925 40$ 19 10/07/2009 SALES TAXES 2$ 20 10/07/2009 SALES TAXES 2$ 21 10/18/2009 09/30/2009 90937 166$ 22 10/18/2009 SALES TAXES 6$ 23 Total 1,771$

Eversource Energy Service CompanyIndividual Charges by Date

Central Connecticut Reliabity Project

Attachment 11

Siting and Permitting –Charges

Docket No. ER16-116Attachment 11

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 03/11/2008 SALES TAX 0$ 2 03/11/2008 SALES TAX 21$ 3 03/11/2008 01/01/2008 124216 583$ 4 04/06/2008 SALES TAX 9$ 5 02/03/2010 SALES TAX 76$ 6 02/03/2010 01/01/2010 127242 2,371$ 7 05/05/2010 SALES TAX 76$ 8 05/05/2010 04/01/2010 127609 2,371$ 9 Total 5,507$

Eversource Energy Service Company Individual Charges by Date

Central Connecticut Reliabity Project

Attachment 12

Siting and Permitting –

Charges

Docket No. ER16-116Attachment 12

Page 1 of 3

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 04/05/2007 02/07/2007 10609 3,200$ 2 04/05/2007 SALES TAXES 115$ 3 05/04/2007 04/13/2007 10642 3,200$ 4 05/04/2007 SALES TAXES 115$ 5 06/06/2007 05/17/2007 10668 3,200$ 6 06/06/2007 SALES TAXES 115$ 7 07/20/2007 07/17/2007 10716 3,200$ 8 07/20/2007 SALES TAXES 115$ 9 09/07/2007 08/16/2007 10735 3,200$

10 09/07/2007 SALES TAXES 115$ 11 10/25/2007 10/15/2007 10766 3,200$ 12 10/25/2007 SALES TAXES 115$ 13 12/18/2007 11/06/2007 10781 2,560$ 14 12/18/2007 12/03/2007 10805 1,000$ 15 12/18/2007 SALES TAXES 92$ 16 12/18/2007 SALES TAXES 36$ 17 12/19/2007 01/15/2008 10782 2,560$ 18 12/19/2007 SALES TAXES 92$ 19 02/06/2008 11/15/2007 10802 3,320$ 20 02/06/2008 SALES TAXES 120$ 21 04/01/2008 01/15/2008 10815 4,667$ 22 04/01/2008 SALES TAXES 168$ 23 04/18/2008 02/11/2008 10826 4,667$ 24 04/18/2008 03/18/2008 10838 4,667$ 25 04/18/2008 SALES TAXES 168$ 26 04/18/2008 SALES TAXES 168$ 27 04/24/2008 04/14/2008 10854 4,667$ 28 04/24/2008 SALES TAXES 168$ 29 05/13/2008 05/08/2008 10871 4,667$ 30 05/13/2008 SALES TAXES 168$ 31 07/04/2008 06/25/2008 10888 4,667$ 32 07/04/2008 SALES TAXES 168$ 33 07/11/2008 07/07/2008 10897 4,667$ 34 07/11/2008 SALES TAXES 168$ 35 07/23/2008 12/31/2007 10808 277$ 36 07/23/2008 SALES TAXES 10$ 37 08/18/2008 08/07/2008 10907 4,667$ 38 08/18/2008 SALES TAXES 168$ 39 08/20/2008 08/14/2008 10914 362$ 40 08/20/2008 SALES TAXES 13$ 41 09/30/2008 09/09/2008 10917 4,667$ 42 09/30/2008 SALES TAXES 168$

Eversource Energy Service CompanyIndividual Charges by Date

Central Connecticut Reliabity Project

Docket No. ER16-116Attachment 12

Page 2 of 3

43 10/16/2008 10/10/2008 10927 8,750$ 44 10/16/2008 SALES TAXES 315$ 45 12/03/2008 11/03/2008 10929 8,750$ 46 12/03/2008 SALES TAXES 315$ 47 12/10/2008 12/03/2008 10940 8,750$ 48 12/10/2008 SALES TAXES 315$ 49 01/28/2009 01/12/2009 10954 8,750$ 50 01/28/2009 SALES TAXES 341$ 51 02/15/2009 02/02/2009 10964 8,750$ 52 02/15/2009 SALES TAXES 341$ 53 03/25/2009 03/05/2009 10980 8,750$ 54 03/25/2009 SALES TAXES 341$ 55 04/21/2009 04/01/2009 10990 8,750$ 56 04/21/2009 SALES TAXES 341$ 57 05/08/2009 04/17/2009 11001 8,750$ 58 05/08/2009 SALES TAXES 341$ 59 05/22/2009 05/18/2009 11009 8,750$ 60 05/22/2009 SALES TAXES 341$ 61 06/18/2009 06/10/2009 11024 8,750$ 62 06/18/2009 SALES TAXES 341$ 63 06/26/2009 06/19/2009 11031 8,750$ 64 06/26/2009 SALES TAXES 341$ 65 08/21/2009 08/05/2009 11049 8,750$ 66 08/21/2009 SALES TAXES 341$ 67 10/08/2009 09/16/2009 11059 8,750$ 68 10/08/2009 SALES TAXES 341$ 69 10/08/2009 09/16/2009 11064 225$ 70 10/08/2009 SALES TAXES 9$ 71 11/08/2009 11/01/2009 11069 8,750$ 72 11/08/2009 SALES TAXES 341$ 73 12/13/2009 12/01/2009 11092 8,750$ 74 12/13/2009 SALES TAXES 341$ 75 01/19/2010 01/07/2010 11105 8,750$ 76 01/19/2010 SALES TAXES 280$ 77 02/14/2010 02/03/2010 11119 8,750$ 78 02/14/2010 SALES TAXES 280$ 79 03/12/2010 03/04/2010 11133 8,750$ 80 03/12/2010 SALES TAXES 280$ 81 04/11/2010 04/01/2010 11143 8,750$ 82 04/11/2010 SALES TAXES 280$ 83 05/11/2010 05/01/2010 11155 8,750$ 84 05/11/2010 SALES TAXES 280$ 85 06/11/2010 06/01/2010 11176 8,750$ 86 06/11/2010 SALES TAXES 280$ 87 07/11/2010 07/01/2010 11185 8,750$ 88 07/11/2010 SALES TAXES 280$

Docket No. ER16-116Attachment 12

Page 3 of 3

89 08/10/2010 08/04/2010 11207 8,750$ 90 08/10/2010 SALES TAXES 280$ 91 09/09/2010 09/02/2010 11218 8,750$ 92 09/09/2010 SALES TAXES 280$ 93 10/10/2010 10/05/2010 11233 8,750$ 94 10/10/2010 SALES TAXES 280$ 95 11/09/2010 11/01/2010 11248 8,750$ 96 11/09/2010 SALES TAXES 280$ 97 12/14/2010 12/01/2010 11266 8,750$ 98 12/14/2010 SALES TAXES 280$

Total 318,729$

Attachment 13

Siting and Permitting – Charges

Docket No. ER16-116Attachment 13

Page 1 of 1

Line No. Transaction Date Vendor ID Invoice Date Invoice Number Amount1 11/19/2010 Voucher 24$ 2 Total 24$

Eversource Energy Service Company Individual Charges by Date

Central Connecticut Reliabity Project

Attachment 14

Public Outreach and Education – Eversource’s Internal Labor

Public Outreach and EducationEversource Internal Labor Charges ‐ CCRPCharges Incurred per month , By Title

Job Title 2007 2008 2009 2010 2011 Grand Total

DIRECTOR ‐$                     ‐$                     10,614$               47,120$               ‐$                    57,734$             MANAGER 4,931$                 18,873$               16,829$               24,051$               631$                   65,315$             

COORDINATOR ‐$                     4,279$                 11,268$               18,393$               4,759$                38,699$             EXECUTIVE 5,815$                 ‐$                     ‐$                     ‐$                    ‐$                    5,815$               DIRECTOR ‐$                     ‐$                     1,422$                 ‐$                    ‐$                    1,422$               EXECUTIVE 4,667$                 ‐$                     ‐$                     ‐$                    ‐$                    4,667$               DIRECTOR 186$                    11,007$               6,624$                 ‐$                    ‐$                    17,817$             DIRECTOR 684$                    2,245$                 10,221$               798$                    ‐$                    13,948$             SPECIALIST ‐$                     ‐$                     9,469$                 16,017$               1,558$                27,043$             ASSISTANT 1,941$                 ‐$                     7,469$                 8,283$                 ‐$                    17,693$             

Subtotal 18,224$               36,404$               73,916$               114,661$             6,948$                250,153$           

Job Title jan feb mar apr may jun jul aug sep oct nov dec

DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   MANAGER ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     2,392$                 1,293$                1,246$               

COORDINATOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     ‐$                     3,293$                 2,522$                ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     412$                    485$                    582$                   1,060$                458$                   698$                   628$                    343$                   ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    186$                  DIRECTOR ‐$                     ‐$                     364$                    320$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   SPECIALIST ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   ASSISTANT ‐$                     ‐$                     416$                    546$                    531$                   448$                   ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   

Subtotal 1,192$                 4,643$                 3,635$                1,508$                458$                   698$                   628$                    2,735$                 1,293$                1,433$               

Job Title jan feb mar apr may jun jul aug sep oct nov dec

DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   MANAGER 1,090$                 1,222$                 734$                    1,269$                 1,423$                1,249$                1,692$                1,103$                1,461$                 434$                   1,819$                5,376$               

COORDINATOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    1,148$                3,130$               EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR 1,985$                 ‐$                     1,451$                 841$                    4,925$                1,804$                ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     108$                   300$                   1,838$               SPECIALIST ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   ASSISTANT ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   

Subtotal 3,076$                 1,222$                 2,185$                 2,110$                 6,348$                3,053$                1,692$                1,103$                1,461$                 542$                   3,267$                10,344$             

Job Title jan feb mar apr may jun jul aug sep oct nov dec

DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    872$                    4,219$                 2,030$                3,493$               MANAGER 1,592$                 1,319$                 1,296$                 1,309$                 1,626$                1,495$                1,164$                1,216$                1,582$                 1,963$                 1,099$                1,169$               

COORDINATOR 1,050$                 817$                    904$                    880$                    1,049$                887$                   756$                   1,521$                841$                    1,325$                 661$                   577$                  EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    872$                    550$                   ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     669$                    1,384$                 1,130$                 2,107$                877$                   457$                   ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     1,428$                 1,198$                 1,119$                 1,486$                ‐$                    253$                   1,003$                964$                    1,153$                 753$                   863$                  SPECIALIST ‐$                     ‐$                     ‐$                     ‐$                    674$                   813$                   1,041$                834$                   2,843$                 2,659$                 376$                   228$                  ASSISTANT 501$                    591$                    644$                    618$                    901$                   670$                   590$                   1,067$                764$                    643$                   281$                   199$                  

Subtotal 3,143$                 4,824$                 5,426$                 5,056$                 7,843$                4,742$                4,263$                5,641$                8,738$                 12,512$               5,199$                6,530$               

Job Title jan feb mar apr may jun jul aug sep oct nov dec

DIRECTOR 1,636$                 3,603$                 3,094$                 2,692$                 4,952$                3,315$                37,352$              3,524$                (20,721)$              5,048$                 2,721$                (97)$                   MANAGER 1,036$                 1,308$                 1,410$                 1,335$                 1,662$                1,230$                18,806$              1,073$                (4,271)$                461$                   ‐$                    ‐$                   

COORDINATOR 723$                    904$                    778$                    905$                    1,303$                592$                   12,632$              1,048$                (4,297)$                1,512$                 1,009$                1,284$               EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR 798$                    ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   SPECIALIST 289$                    229$                    ‐$                     1,854$                 857$                   1,697$                9,475$                379$                   (494)$                   570$                   621$                   541$                  ASSISTANT 302$                    299$                    270$                    404$                    531$                   360$                   6,007$                110$                   ‐$                     ‐$                    ‐$                    ‐$                   

Subtotal 4,783$                 6,343$                 5,551$                 7,190$                 9,306$                7,194$                84,272$              6,134$                (29,783)$             7,591$                 4,351$                1,728$               

Job Title jan feb mar apr may jun jul aug sep oct nov dec

DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   MANAGER ‐$                     ‐$                     (11)$                     357$                    214$                   71$                      ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   

COORDINATOR 1,006$                 1,516$                 (136)$                   1,103$                 841$                   429$                   ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   EXECUTIVE ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   DIRECTOR ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   SPECIALIST 412$                    350$                    (26)$                     704$                    118$                   ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   ASSISTANT ‐$                     ‐$                     ‐$                     ‐$                    ‐$                    ‐$                    ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   

Subtotal 1,418$                 1,866$                 (174)$                   2,164$                 1,173$                500$                   ‐$                    ‐$                    ‐$                     ‐$                    ‐$                    ‐$                   

2008

2009

2010

2011

2007

Summary By Year

NU Labor‐WORK DOC 1 of 1

Attachment 15

Public Outreach and Education –

Docket No. ER16-116Attachment 15

Page 1 of 1

Line No.

Year MonthPublic Outreach and Education

Lead (Hours)Invoice No.

1 2009 Jan 2 44409-202 2009 Feb 14.5 44409-213 2009 Mar 50 44409-224 2009 Apr 13 44409-235 2009 May 16 44409-246 2009 Jun 21 44409-257 2009 Jul 17 44409-268 2009 Aug 18 44409-279 2009 Sep 13 44409-28

10 2009 Oct 16 44409-2911 2009 Nov 25 44409-3012 2009 Dec 13 44409-3113 2010 Jan 15 44409-3214 2010 Feb 13 44409-3315 2010 Mar 8 44409-3416 2010 Apr 14 44409-3517 2010 May 12 44409-3618 2010 Jun 22 44409-3719 2010 Jul 2 44409-3820 2010 Aug 10 44409-3922 2010 Oct 7 44409-4123 2010 Nov 2 44409-4224 2010 Dec 1 44409-4325 2011 Jan 2 44409-4426 2011 Feb 4 44409-44A27 2011 Mar 6 44409-45C128 2011 Apr 1 44409-46

Totals By Year Public Outreach and Education

Lead (Hours)

29 2009 219

30 2010 10631 2011 13

32 338

33 80,035$ (a)

Notes:

Eversource Energy Service CompanySiting and Permitting - Public Outreach and Education Summary

ChargesCentral Connecticut Reliability Project

(a) To calculate the $80,035 attributable to public outreach and education costs Eversource worked with to identify the specific employee(s) who worked on public outreach and education, which in this case was Using the the ratio of actual hours charged to the total hours that were charged to Eversource monthly by

, and multiplying it by the total charges to Eversource from for each month, Eversource was able to derive the amount specifically attributable to public outreach and education.

Attachment 16

Public Outreach and Education – Invoices

Privileged Invoices Omitted

Attachment 17

Public Outreach and Education –

Privileged Invoices Omitted

Attachment 18

Public Outreach and Education – Charges/Invoices

Privileged Invoices Omitted

Attachment 19

Public Outreach and Education – October 8, 2009 PowerPoint Presentation to Town of

Watertown

Central Connecticut Reliability Project

Town Manager, Charles FrigonTown of Watertown

October 8, 2009

Agenda

• Central Connecticut Reliability Project Overview• What We Propose To Build• Typical Construction Activities• Project Timeline • Connecticut Siting Council Process

2

Regional Transmission System Problems

New England1. East-West power flows are limited across

New England.Connecticut2. Interstate transfer capacity is limited,

affecting Connecticut reliability in the near-term and regional reliability over the longer term.

3. East-West power flows within Connecticutstress the existing system.

Massachusetts4. The Springfield, MA area experiences

thermal overloads and voltage problems under numerous contingencies.

Rhode Island5. Rhode Island’s reliability is overly

dependent upon limited access to the 345-kV system. Rhode Island experiences overloads and voltage violations under certain conditions. Imports are limited now and more so in the near future.

The Independent System Operator for New England (ISO-NE) identified a number of system weaknesses that have been summarized as five basic, interdependent problems:

3

Four Closely Related Projects Were Identified to Solve the Problems

New England Increase New England‘s East-West

transfer capability Strengthen interconnections among

Connecticut, Massachusetts and Rhode Island

Improve competitive markets

Connecticut Solve targeted Connecticut reliability

problems Create a new source of supply for

Connecticut Relieve East-West constraints

Massachusetts Solve Springfield reliability problems Provide a loop in eastern

MassachusettsRhode Island Solve targeted Rhode Island reliability

concerns Create a new source of supply for

Rhode Island

Together, these projects are called the New England East-West Solution (NEEWS).

4

Central Connecticut Reliability Project Overview

Current Preferred Project Scope• Construct approximately 36 miles of new 345-kV overhead

transmission lines on existing rights-of-way from Frost Bridge Substation in Watertown to North Bloomfield Substation in Bloomfield

• Substation upgrade at Frost Bridge Substation in Watertown

• NOTE: As analysis of the Preferred Route continues, the project scope may change

Municipalities• Towns (based on the Current Preferred Route):

Watertown, Thomaston, Litchfield, Harwinton, New Hartford, Canton, Simsbury, Bloomfield

• Towns within 2,500 ft: Waterbury, Plymouth, Torrington, East Granby

Watertown Portion of Current Preferred Route• Approximately 5 miles of 345-kV transmission line• Typical right-of-way width is 250-400 feet• Estimated 44 new structures, with typical heights of 90 to

130 feet with delta or H-frame structur

5

Typical Overhead Transmission Structures

Looking south from Watertown town line to Purgatory Junction

Town of Watertown6

Typical Overhead Transmission Structures

Looking east from Purgatory Junction to Frost Bridge Substation

Town of Watertown7

Typical Overhead Transmission Structures

8

Existing Proposed

(For Illustration purposes only)

Looking Northwest from Park Road

Town of Watertown

Frost Bridge Substation

Proposed Scope at Frost Bridge 345/115-kV Substation:

• Fence line expansion 27 feet to the North, 13 feet to the East and 13 feet to the West

• Install new 345-kV GIS switchyard

• Install new 345/115-kV auto-transformer

• Install two new 345-kV line terminal structures

• Re-alignment of existing transmission lines

• Construction duration 20-24 months

Frost Bridge SubstationLocation Approval ProcessElectric substation facilities are under the jurisdiction of the Connecticut Siting Council (CSC)• As part of the CSC's review, State law provides for limited input as to location from zoning and wetlands commissions

– Context is location and suitability of the land

• Town commissions act as an agency of the State not as a local agency

– Public utility framework

– Required to consider broader public interests in increased reliability and creation of additional capacity

– Local regulations are not controlling

• First Step for CL&P & the Town

– Additional opportunities for Town/public input include:

– Municipal Consultation Filing

– Open Houses

11

Geotechnical SurveysRight-of-way mowing

Typical Pre-Construction Activities

Stage 1: Right-of-Way Clearing and Access Road Construction

Stage 2: Drilling of Foundations

12

Stage 3: Installation of Structures

Typical Construction Activities

Stage 4: Conductor Installation

Stage 5: Right-of-Way Restoration

13

Typical Construction Activities

14

2009 Activities

Through the remainder of 2009, survey work will take place on the right-of-way. This work will include:• Wetland and Vernal Pool

Identification

• Threatened & Endangered Plant and Animal Species Surveys

• Archaeological Assessment Surveys

• Topographic, Land and Encroachment Surveys

Landowners and municipalities will be kept informed of activities by mail and if necessary, direct contact.

Environmental Considerations

15

• Identify Wetlands, Watercourses & Natural Resource Features • Conduct Wildlife Surveys• Avoid/Minimize Potential Impacts

• Utilize Existing Access• Relocate Poles• Relocate Access Roads• Environmental Monitoring• Construction Best Management Practices

• Mitigate Impacts• Restoration• Preservation • Compensatory Mitigation

(Image shown for illustration purposes only)

Project Timeline

Planning and Design

Siting and Permitting

Construction

Municipal Consultation Filing (Expected Early 2010)

Open Houses (Mid 2010)

Siting Application filed with Connecticut Siting Council ( 2010)

CSC’s Decision & Order (2011)If Approved,

Begin Construction (2011)

2006 2007 20102008 2009 2011 2012 2013

16

Quarterly Postcards

Municipal Updates

Residential Meetings (Upon Request)

First Step: The Municipal Consultation Filing• Provide to town CEOs technical reports concerning:

Public Need Site Selection Process Environmental Effects

• Seek municipal recommendations to share with the Siting Council

Second Step: File an Application to be Examined in Hearings• 1 year or longer• Application, including route variations, initiates “contested case”• Public comment hearings precede evidentiary hearings• Parties and Intervenors may:

Address written pre-hearing questions to applicant Cross-examine applicant’s witnesses Present sworn testimony and legal briefs

Third Step: Decision and Order• The Siting Council can approve or deny• If approved, the Siting Council may require modifications and impose conditions• If approved with conditions, applicant must meet conditions, including an

approved “Development & Management Plan”

Additional Opportunities for Public to Participate

Connecticut Siting Council Process

Public Participation Begins Here

17

How Your Town Can Participate In the Siting Process

• Municipalities can submit comments to CL&P as part of the Municipal Consultation Filing process

• Residents can attend an Open House for more information

• Participate in Connecticut Siting Council hearings (see www.ct.gov/csc for public participation guidelines)

18

Municipalities: Jeff Martin, Project [email protected]

General Public: 1-866-99NEEWSwww.NEEWSprojects.com

Contact Us

19

Attachment 20

Public Outreach and Education – Excerpts from 2009 NEEWS Project Execution Plan

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.1

1.1 EXECUTIVE SUMMARY

The purpose of the Project Execution Plan (PEP) is to assist all contracting parties and other

stakeholders in the efficient and successful execution of the New England East-West Solution

Project hereby referred to as “Project”, in a manner that is consistent with Northeast Utilities

Service Company’s (NUSCO) cost, schedule, quality, and performance objectives.

The contractual relationships among the stakeholders define the commercial terms, risk

allocation, scope deliverables, and standards of performance agreed to by the parties. The

information found in the PEP supplements these contracts by further describing the Project’s

organization, player roles, duties and activities, responsibilities and deliverables.

The PEP will be distributed to key individuals on the Project and will be reviewed on a semi-

annual basis to verify the manual contents are still valid. If revisions to the PEP are required,

updated document sections will be distributed to the holders-of-record.

The PEP is intended to be a working document (i.e. never in final form) and outlines the

standards, responsibilities and procedures to be followed in the execution of the Project. It is

not intended to supersede any contractual requirements of any existing contracts. If there is any

conflict between the PEP and a contractual responsibility, the contract shall take precedence.

At any time, NUSCO can request changes/deletions to any section of the PEP.

The PEP is divided into two volumes, Volume 1 containing information applicable to all parts

of the Project, and Volume 2 containing information specific to just one portion of the Project.

The individual sections in each volume are briefly described below:

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.2

VOLUME 1.0

1.1 Executive Summary (updated for 08/26/08 submission)

This section discusses the plan purpose and basic organization.

1.2 Program Management Office & Staffing

This section includes the project organization chart and details regarding

Connecticut-based Program Management Office (PMO).

1.3 Project Budget(updated for 08/26/08 submission)

This section defines the project budget philosophy, including a discussion of the initial

establishment of the budget and cash flow, as well as methods of tracking the budget

and project expenditures as the project progresses. Volume 2 includes project-specific

cost estimate information.

1.4 Project Schedule

This section defines the projects schedule philosophy. Criteria for evaluating schedule

progress versus the baseline and recovery plans are discussed. Volume 2 includes

project-specific schedule information.

1.5 Risk Management Plan

This section discusses the process by which the Project Management Team (PMT) will

identify and evaluate risks. It includes a to date listing of potential project risks and will

be revised as the Project ensues to provide a relative weighting of those risks and

measures on how the PMT expects to take to mitigate those risks.

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.3

1.6 Project Contracting Plans

This section discusses potential contracting strategies that have been developed for the

project including strategies for transmission line and substation material and

construction contracting.

1.7 Project Procurement (updated for 08/26/08 submission)

This section contains the project procurement plan and outlines the processes and

procedures to be followed throughout the project relating to procurement of professional

services, construction services, and equipment & materials. This section establishes

criteria for: identifying qualified bidders, ranking bids, bid evaluation; and defines how

Procurement Team will interface with NUSCO’s established procurement

procedures.

1.8 Change Management Plan

The PMT will be using Expedition to track and manage changes on the Project. This

section establishes criteria for accepting and rejecting scope changes and provides

details regarding how the Project will use and track allowances, authorizations to

proceed, change orders, work change directives, RFI’s, and submittals.

1.9 Project Reporting & Control System

This section describes the cost management and reporting processes to be used

throughout the project. Included in this section are the processes to be used for tracking

and reporting cost by categories, making comparisons of cost versus budget

performance, tracking the status of individual contracts and purchase orders, managing

change orders, calculating progress estimates, estimating “cost-to-complete” each

activity, handling of invoices and control of documents.

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.4

1.10 QA/QC Plans

This section covers the QA/QC requirements for the permitting, siting, and preliminary

design of the project.

1.11 Permitting and Environmental Planning

Numerous Federal, State, and local permits will be required for the Project. This section

identifies the permitting process as well as outlines the environmental compliance

monitoring process that will be used during construction activities.

1.12 Siting

The proposed project is expected to require approval by the Connecticut Siting Council

(CSC), Department of Telecommunications and Energy (DTE) and the Energy Facility

Siting Board (EFSB), depending on the specifics of the project. The Siting approach

used will focus on submittal requirements for both of these State agencies and will be

based on continued consultation with NUSCO legal counsel and previous projects of a

similar type that have been proposed in Connecticut/Massachusetts.

1.13 Community Relations Plan

This section outlines the overall community relations plan and provides guidance and

insight to the PMT relative to community impacts and mitigation approaches. Also

included is a description of the implementation approaches that will be used at various

phases of the project and the methods of communications and protocols that will be

used for specific types of project communications.

1.14 Material Handling Guideline

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.5

This section identifies the general location and release scenarios associated with

potential sources of impacts located on or near the project. The Material Handling

Guideline documents field observations and analytical results obtained from soil and

groundwater samples and provides requirements for the proper identification, handling,

storage, testing, and disposal of Excess Materials.

1.15 Project Safety and Health Program

This section outlines the safety management plan and processes that were developed to

integrate the needs of both NUSCO and and shall be implemented by the

project’s contractors and sub-tier contractors for the duration of the project construction

activities.

1.16 Real Estate Acquisition Management Plan

The purpose of this section is to outline the real estate acquisition process and present

approaches that will be used by to support the real estate acquisition functions.

The objectives of the Real Estate Acquisition Management Plan are to provide the roles,

responsibilities, and overall approach for identifying easement requirements, defining

the process, controlling costs, maintaining good relationships with property owners and

municipalities and securing properties on schedule.

1.17 Development & Management (D&M) Plan Execution

This section defines the level and type of information to be included in the individual

D&M plans that will be submitted to the towns and Connecticut Siting Council.

1.18 Lessons Learned from previous NUSCO / Projects

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.6

This section will address lessons learned from previous NUSCO team projects

such as Subjects to be covered include:

Engineering, Contract Administration, Budget, Schedule, Community Relations, Siting,

Permitting, Open Houses, Construction, Outages, Testing and Commissioning, and

Project Closeout.

1.19 Decision Documentation Process

This section defines how the NEEWS Project Team will document what constitutes a

reasonable decision,. how a decision will be reviewed, and how to demonstrate the

reasonableness of the decision.

This section also includes an outline of what is recommended for sufficient

documentation of key process decisions, actions, events, and potential or actual claims

such that it is demonstrated that the NEEWS Project Team made a reasonable decision.

1.20 Program Deliverables

This section includes a comprehensive list of deliverables cited in the Master Service

Agreement (MSA) and Project Specific Agreement (PSA-5), as well additional

deliverables which will be provided to NUSCO.

VOLUME 2.0

2.1 Project Scope

This section defines the scope of the project.

2.2 Project-Specific Budget

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.7

This section includes the project-specific cost estimates The cost estimates provided in

this section are expected to be updated as the project progresses to support the

establishment of the baseline project budget.

2.3 Project-Specific Schedule

This section includes project-specific schedules. These schedules define and identify

activities related to: permitting; preliminary design; equipment & material procurement;

detailed design; construction; and commissioning. Project schedules will be updated on

a monthly basis and included with the monthly report.

2.4 Project-Specific Phasing Plan

Paul Williams to complete pending further direction from Jeff Towle.

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.8

1.1 TERMS AND DEFINITIONS: Authorization to Proceed ATP

Change Order CO

Change Order Request COR

Connecticut Siting Council CSC

Contract Qualification Statement CQS

CSX Transportation Company CSX

Department of Telecommunications and Energy DTE

Department of Environmental Protection DEP

Emergency Response Coordinator ERC

Energy Facility Siting Board EFSB

Excess Material EM

Geographic Information System GIS

Massachusetts Environmental Policy Act MEPA

Master Service Agreement MSA

Material Handling Guideline MFG

Material Request MR

NEEWS and Springfield 115kV Projects Project

Northeast Utilities Service Company NUSCO

Procurement Sourcing Manager PSM

Program Management Office PMO

Program Management Team PMT

Project Execution Plan PEP

Project Manager PM

NUSCO New England East-West Solution Execution Plan, Rev 08/26/08 Page 1.1.9

Project Procurement Manager PPM

Project Procurement Plan PPP

Project Specific Agreement PSA

Proposed Change Order PCO

Purchase Order PO

Quality Assurance/Quality Control QA/QC

Request for Proposal RFP

Rights of Way ROW

Safety Manager SM

Transmission Contract Administration TCA

Western Massachusetts Electric Company WMECO

Weekly Telephone Conferences WTC

Work Breakdown Structure WBS

Work Change Directive WCD

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.1

1.13 COMMUNITY RELATIONS PLAN

1.13.1 EXECUTIVE SUMMARY

The Project is part of an initiative designed to help serve southern New England’s growing

demand for electricity, improve reliability of service and bring the transmission system up to

regional and national standards. The Project will occur in both Connecticut (CL&P) and

Massachusetts (WMECO).

1.13.2 PURPOSE OF PLAN

Public opposition is a major risk to construction of a large, highly visible infrastructure project,

such as transmission lines. understands that if sufficient momentum to this

opposition were to develop, it could suspend the project and result in significant delays and cost.

A comprehensive community relations plan providing for open lines of communication with all

affected stakeholders is essential to the success of the project. This plan will target stakeholders

groups, such as municipalities, residents, businesses, community-based organizations and special

interest groups, in order to mitigate this risk.

1.13.3 CONTACTS

will work

in coordination with project staff, the NUSCO NEEWS Campaign Team (Appendix A)

and contractors to implement this plan. All media inquiries will be directed to NUSCO

Corporate Communications.

1.13.4 OBJECTIVES / DESIRED OUTCOMES

1.13.4.1 Build a two-way relationship between CL&P/WMECO and stakeholders by

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.2

fostering stakeholder participation in the regulatory process.

1.13.4.2 Generate a positive image for the Project and its agents so that

CL&P/WMECO is perceived as a credible source of information and a

cooperative community partner.

1.13.4.3 Develop the image of CL&P/WMECO as a leader in electric reliability and

conservation to correctly foster perception that CL&P/WMECO is working in

the public’s best interest.

1.13.5 CRITERIA FOR SUCCESSFUL COMMUNITY RELATIONS

1.13.5.1 Proactive – Anticipate stakeholders’ questions and concerns and provide

appropriate information.

1.13.5.2 Interactive -- Provide mechanisms for stakeholders to contact us. A toll-free

number (1-866-99NEEWS) and project email, [email protected], have

been established for this purpose.

1.13.5.3 Consistent – Ensure consistent messages across all audience and Project

segments. A Stakeholder Inquiry Protocol (Appendix B) has been developed

to ensure that communications are handled in a consistent manner, using

standard, pre-approved messaging, in accordance with NU’s corporate

communication standards.

1.13.5.4 Timely – Communicate quickly and accurately in a responsive manner – In

accordance with the Stakeholder Inquiry Protocol (Appendix B), inquiries are

to be quickly acknowledged, generally within 24 hours or by the next business

day.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.3

1.13.5.5 Clear & Concise – Provide simple, user-friendly communications tailored to

each stakeholder group, while avoiding the use of jargon or acronyms that

may alienate particular audiences.

1.13.5.6 Empathic – Recognize that the Project has a significant impact on the daily

lives of stakeholders. Respect and understand these impacts and be sensitive

to them in discussions with those affected.

1.13.5.7 Courtesy - Always demonstrate patience and good manners, treating the

public with respect when providing information they need.

1.13.6 KEY MESSAGES

Project-Specific Messages

1.13.6.1 Safety is of utmost importance – First and foremost, construction will be

performed in a manner that ensures the safety of workers and the public.

Additionally, construction will not interfere with the access and egress of

emergency vehicles (police, fire, ambulance, etc.)

1.13.6.2 Minimizing Impact - We care about how the Project affects the towns and its

residents. Together, we will identify these impacts and ensure that

construction is performed in a manner that is as non-intrusive as possible.

Property restoration will be completed in a timely manner.

1.13.6.3 Open Communications - We welcome questions and comments from the

public. We encourage towns and residents to be active participants in the

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.4

regulatory process.

1.13.6.4 Environmentally Sensitive – We have taken great care in the design of the

Project to identify environmental resources such as soils, water resources,

wetlands and water quality, vegetation and wildlife, threatened or endangered

species, and noise and visual impacts. We will construct in an

environmentally responsible manner that will not result in any significant

long-term adverse impacts.

Overarching Messages

Background

The organization responsible for making sure there is a reliable flow of power available in Connecticut and New England, ISO New England (ISO-NE), identified certain system problems in the southern New England area that must be addressed in order for the transmission network to meet regional and national reliability standards. Through the ISO-NE planning process, four major transmission projects were identified to meet these reliability needs. Together, these projects are called the New England East-West Solution (NEEWS). The four individual projects are:

o Greater Springfield Reliability Project (GSRP) o Interstate Reliability Project (Interstate) o Central Connecticut Reliability Project (CCRP) o Rhode Island Reliability Project (RIRP)

Of the four projects, NU’s operating companies will build the GSRP, approximately half of the Interstate Project, and CCRP. National Grid, an electric utility serving part of Massachusetts and Rhode Island, will complete the rest of Interstate and build RIRP. These projects, consisting of new 345-kV transmission lines, some 115-kV line upgrades and associated substation work, are designed to improve the reliability of the transmission system, reduce bulk power system constraints, and provide business and residents with enhanced access to cleaner, competitively priced power.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.5

1.13.6.5 Demand for Electricity has Increased – Today’s lifestyles are driving energy

demands to levels never before seen. Since 1980, peak electricity use in New

England has increased 87%.

1.13.6.6 Maintaining Reliability is Imperative – CL&P/WMECO’s continued

investment in infrastructure upgrades is imperative to keep power flowing to

customers. In the last five years alone, CL&P/WMECO has spent nearly $200

million to maintain system reliability. However, it is recognized that more needs

to be done to improve reliability.

1.13.6.7 Modernizing the System – The Project will improve the southern New England

area’s electrical infrastructure to keep pace with the growing demand and

minimize the risk of power outages. The system will be continuously monitored

to identify future opportunities to improve and modernize the electric service.

1.13.6.8 Economics of Upgrading – A major electrical outage would have a serious

negative or even catastrophic effect on businesses. In addition, adding additional

transmission capacity will eliminate millions of dollars in potential penalties that

otherwise would be imposed upon ratepayers each year as congestion charges.

1.13.6.9 Positive Environmental Impacts – Having the capability to connect customers

to cleaner sources of electric power in our region will reduce the need to run

older, less efficient power plants.

1.13.6.10 Local Tax Benefits – Adding new and enhanced transmission lines and facilities

increases local tax revenues, thereby reducing the tax burden for residents and

businesses.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.6

1.13.6.11 Employment Opportunities – Over the project’s duration, the construction of

the Project is expected to create new jobs for area workers.

1.13.7 STAKEHOLDERS

There are three categories of stakeholder groups addressed by this plan: 1) primary; 2)

secondary; and 3) general.

1.13.7.1 Primary Stakeholders include, but are not limited to:

Municipalities - Chief elected municipal officials; public works; building

officials; planning/zoning officials; police and fire departments; emergency

response.

Public Services – Public and private schools, recreation, churches, libraries,

transportation (bus, rail, taxi), commuters.

Residential: Adjacent landowners (abutters), non-adjacent nearby landowners

and residents at-large.

Community Organizations: Churches, schools, hospitals and nursing homes,

daycare centers and other civic organizations.

Commercial: Property owners, tenants (business owners).

Business/Civic Organizations: Chambers of Commerce, Rotary Clubs, etc.

Relationships with Primary Stakeholders will be managed by the NUSCO NEEWS Campaign

Team during the Siting & Permitting phase and by during the construction phase.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.7

1.13.7.2 Secondary stakeholders include, but are not limited to:

Regional – ISO New England.

State (CT) - Connecticut Siting Council (CSC), Connecticut Department of

Transportation (CDOT), Connecticut Department of Environmental Protection

(DEP), CT Legislators.

State (MA) – Massachusetts Department of Telecommunications and Energy

(DTE), Massachusetts Energy Facilities Board (EFSB), Massachusetts

Highway Department (MHD), Massachusetts Environmental Policy Act

(MEPA) Office, MA Legislators.

Federal - Army Corps of Engineers (ACOE).

Relationships with Secondary Stakeholders are primarily managed by the NUSCO NEEWS

Campaign Team. However, the may be asked to draft or review communications to

these agencies.

1.13.7.3 General stakeholders include, but are not limited to:

Media (local, state): TV, Radio, Newsprint.

Client: NUSCO Project Team (leads and staff), NUSCO/CL&P/WMECO

Communications leads, NUSCO/CL&P/WMECO employees.

management and employees.

Relationships with General Stakeholders will be managed by the (with the

exception of the media which will be managed by the NUSCO Corporate Communications

Department).

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.8

1.13.8 PHASES OF IMPLEMENTATION

This plan will be implemented in two phases: 1) Siting & Permitting; and 2) Construction.

The NUSCO NEEWS Campagin Team (Appendix A) will lead the community outreach

efforts through the Siting & Permitting phase. Under the oversight of the NUSCO NEEWS

Campaign Team, the will implement this plan during the Construction phase.

During the construction phase, a streamlined decision and approval process will be needed to

ensure that construction is not delayed or redirected unnecessarily, resulting in additional costs

to the projects.

1.13.8.1 Siting & Permitting Phase Communications

During the Siting & Permitting phase (pre-construction), communications will be tailored

to each stakeholder group – specifically stakeholders most directly affected by the project

(abutters), the general public and municipal officials in the cities or towns where the

route will be located.

1.13.8.1.1 Communications with Abutters and the General Public

During the Siting & Permitting Phase, abutters and the general public (and

possibly other stakeholders as well) will be offered information regarding the

need for the Project. Primary tactics may include: a project web site, news

releases, direct mail, media outreach program, articles and letters in publications,

fact sheets, and briefings to the public at community meetings.

Concurrently, stakeholder and public input is gathered to determine the best

Project route (i.e., resulting in the least amount of impact). Open houses will be

held to help educate the public and to obtain their input. Additionally, toll-free

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.9

project hotlines (1-866-99NEEWS and 888-773-5384, a Spanish version) and a

project email, [email protected] have been established to facilitate stakeholder

questions and input.

If a public meeting is requested, it will typically begin with a presentation by

CL&P/WMECO officials including an overview of the Project; a Powerpoint

presentation, graphics of the route, maps, a Project timeline and a discussion of

Project benefits. The presentation is followed by an interactive session where

stakeholders’ input (questions, comments) will be encouraged. Stakeholder

questions/comments may include, but are not limited to, design changes,

construction activities, structure height, structure finish, movement of structures

along the right of way, vegetation, restoration, traffic, property values, liability,

electric and magnetic fields (EMFs), environmental impact and noise. Preliminary

drawings and handouts will be available to facilitate discussion regarding specific

scenarios. Written requests and comments may be submitted to CL&P/WMECO

after these public meetings as well. Residents may request copies of the

presentation or project drawings. Where appropriate, correspondence conveying

CL&P/WMECO’s resolution of requests will be provided.

1.13.8.1.2 Communications with Municipalities

To support ongoing efforts to site and permit the Project, face-to-face

consultations will be held with municipalities affected by the Project.

Additionally, when appropriate, conference calls with municipal officials will

occur to establish open channels of communication for upcoming construction

activities.

1.13.8.1.3 Communications During Pre-Construction Studies

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.10

Studies will be needed for pre-construction design work, including engineering

surveys, environmental surveys, archeological surveys, and subsurface and

geotechnical investigations along the right-of-way. Town officials will be

notified of these activities via email updates and/or phone calls. Adjacent

property owners to this work will be contacted via mail, phone calls, email, face-

to-face meetings or a door hanger to inform them of the work to be performed

along the right-of-way.

1.13.8.2 Construction Phase Communications

The focus during the construction phase will be on providing current information on the Project’s

progress and maintaining an open dialogue with the municipalities, community organizations and

residents along the route. Monthly conference calls will be a primary communication vehicle for

municipal officials, and construction briefings will be held to keep officials and residents up-to-

date on construction progress. Through local advertising and news releases, residents will

continue to be directed to the project website and hotlines for questions and concerns. Direct

mail will be sent to residents along and in the vicinity of Project construction area to notify them

of major milestones and changes in the construction schedule. Customized communications will

be developed by neighborhood and delivered door-to-door to notify adjacent property owners that

construction will occur on the right-of-way on their property shortly. Follow-up phone calls or

field visits will be made to properties heavily impacted by construction.

1.13.9 COMMUNICATION TACTICS

A variety of tactics will be used, tailored to each stakeholder audience and their particular

communication style and preference (See Appendix C for a matrix of the following

communication tactics and their intended use.) For example, some audiences may be most

effectively reached through mass media, while others in an individualized manner, such as a

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.11

phone call or face-to-face meeting. Messages will be communicated in English and Spanish,

where appropriate. Our strategy is to provide multiple and concurrent communications methods

to reach and inform a variety of audiences and knowledge levels. Flexibility in these

communications tactics will be observed, allowing for changes or the creation of new tactics, as

warranted.

Each of these tactics will be reviewed and approved the the NUSCO NEEWS Campaign Team

prior to their initial use. Once approved, the organizations or positions stated below will be

responsible for implementing these tactics.

1.13.9.1 Conference Calls – Primarily aimed at keeping municipal officials up-to-date

on the status of the Project. Chief elected officials or their designees are invited to these

calls. Calls may be held monthly, however, the frequency may increase or decrease as

appropriate.

Responsibility: Coordination by with support from Project and

Construction Managers; Calls hosted by NUSCO Project Management or their designee.

1.13.9.2 Face-to-Face Briefings – Pre-Construction – Proactive pre-construction

briefings may be scheduled, as needed, with municipalities (chief elected official, public

works, police, fire, traffic control, etc.), hospitals, ambulance services, emergency

services, transportation services and sensitive businesses along the project route to

outline the construction process, major milestones and expected timelines. It is also a

way to identify issues or events unique to each entity that have not yet been considered.

Responsibility: Coordinated by with support from Project and

Construction Managers. Meetings led by NUSCO Project Management or their

designee.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.12

1.13.9.3 Face-to-Face Meetings – During Construction – Field meetings will be

held, as appropriate, to address specific questions or concerns brought up by any

stakeholder or stakeholder group.

Responsibility: with support from appropriate Project and

Construction Managers and/or NUSCO Project Management.

1.13.9.4 Construction Updates (email) – A proactive communication, this written

update will be emailed on a weekly basis or as needed to town officials, police, fire,

ambulance, bus companies, residents, etc. which includes: 1) a description of

construction locations for the upcoming week(s), and 2) an up-to-date status report on the

overall construction progress.

Responsibility: with support from Project and Construction

Managers

1.13.9.5 Website – Part of NUSCO’s Transmission Group website, a dedicated URL

(NEEWSprojects.com) that provides an overview of the Project, project route map,

detailed construction information by town, frequently asked questions, D&M Plans,

contact information, news and other information regarding the Project.

Responsibility: Content – NUSCO NEEWS Campaign Team and Technical

– NUSCO Information Technology

1.13.9.6 Project Email – a dedicated, shared email address ([email protected]) that

directs all email inquiries to a central location.

Responsibility: responsible for inquiry response and tracking, per inquiry

protocol (Appendix B), with support from project management and appropriate subject

matter experts.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.13

1.13.9.7 Hotline – A dedicated, toll-free phone line (1-866-99NEEWS or 888-773-

5384, Spanish version) for the general public to ask questions or voice concerns about the

Project. Our commitment is to provide the first response within 24 hours or the next

business day for weekends and holidays. All phone calls and their resolution are

recorded and tracked in a central database (Expedition – “Public Contact”). During the

construction phase, the project hotline may be staffed rather than having callers leave a

message to provide the highest level of customer service.

Responsibility: responsible for inquiry response and tracking, per inquiry

protocol (Appendix B), with support from project management and appropriate subject

matter experts.

1.13.9.8 Direct Mail – Adjacent and nearby property owners/tenants to the project route

will be notified of the construction process and major milestones that will occur in close

proximity to their property. As a condition of the CSC Approved Development &

Management Plan, notifications must be sent to these stakeholders two weeks prior to the

commencement of construction. As a minimum, notification letters will be sent to all property

owners who abut the project route; however, it is the intent of this plan to expand this list to

include nearby residents and/or businesses that may also be impacted by the Project. Follow-

up mailings in letter or pamphlet form may be sent if there are major changes to the

construction schedule, if major issues arise or if a high-level status report of the project is

appropriate.

Responsibility - with support from NUSCO NEEWS Campaign Team.

1.13.9.10 Door Hangers/Construction Updates – Intended for field use as a parallel

notification to residents or businesses that construction is imminent near their property.

If a face-to-face notification is impractical, a pocket door hanger will be placed on (front)

doors, mailboxes or other prominent fixture where it will be easily observed. In the

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.14

pocket is a written update that briefly describes the project, notifies the property owner

that construction is imminent in that area and directs individuals to the project website

and/or hotline with any questions or concerns. Notification using the door hangers

should occur within seven (7) days, but in no case less than 48 hours, prior to the start of

the construction event. This process will be repeated in an area if there is more than one

major construction activity in that area separated by more than one month’s time.

Responsibility: Construction Updates developed by subject to approval by

NUSCO NEEWS Campaign Team. Outreach conducted by or their

contractors.

1.13.9.11 Written Correspondence – Used to document certain agreements,

notification of construction to municipal officials or response to an inquiry/concern to

municipalities, residents or community groups, as needed.

Responsibility: Drafted by with support from NUSCO NEEWS Campaign

Team and/or appropriate subject matter expert. Final approval and signature by NUSCO

Project Management.

1.13.9.12 Signage – Signs or electronic VMS boards may be used to provide specific

messages for targeted areas. In addition, general signage will be used throughout the

project construction area. A-frame signs showing project name, hotline telephone

number, website, etc. may be created for display at construction sites to inform the public

and vehicular traffic to identify the Project.

Responsibility: Project contractors with assistance from

1.13.9.14 Promotional Items – Create various promotional items directing individuals

to the project website and hotline to be distributed at public meetings and other events.

Items could include magnets, pens, paper pads, logos for hard hats, as needed..

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.15

Responsibility: subject to approval by NUSCO NEEWS Campaign Team.

1.13.9.15 Speaker’s Bureau – Upon request, we can provide speakers for a group

meeting (i.e., Rotary, Chambers of Commerce, Realtors, schools) to discuss the Project.

A standard presentation has been developed which includes an overview of the Project,

graphics of the route, a Powerpoint presentation, maps, a Project timeline and a

discussion of Project benefits.

Responsibility: NUSCO NEEWS Campaign Team.

1.13.9.16 Bill Inserts - If practical, develop informational pieces to be included in

NUSCO electric bills or municipal mailings.

Responsibility: NUSCO NEEWS Campaign Team.

1.13.9.17 Local Advertising – As needed, create ads for local newspapers in response

to town-specific issues. Copy would direct residents to the project website and hotline

for further information.

Responsibility: NUSCO NEEWS Campaign Team.

1.13.9.18 Letters to the Editor/Op Eds – Develop, as needed, to respond to inaccurate

information or a particular point of view regarding the Project.

Responsibility: NUSCO NEEWS Campaign Team.

1.13.9.19 Television – Where available, contact local cable television community service

channel management and request that project updates be posted regularly.

Responsibility: NUSCO NEEWS Campaign Team.

1.13.9.20 News Releases – News releases will be issued as various project announcements

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.16

are made and milestones are met. All releases will be posted on the project website. See

Appendix B for a list of weekly and bi-weekly local newspapers in the communities affected

by the Project.

Responsibility: NUSCO NEEWS Campaign Team and Corporate Communications.

1.13.9.21 Project Identification – It is important that Project workers and equipment

display proper markings to be identifiable to the public and motorists at job sites.

Identification must be worn by foreman-level and up. Vehicles should be clearly marked

and identifiable.

Responsibility: Badging - and contractors.

Appendix A – NUSCO NEEWS Campaign Team Chart (attached separately)

Appendix B – Stakeholder Protocol (attached separately – note that one of these attachments

was revised since the last version)

Appendix C – see Tactic chart below

Appendix D – Middletown/Norwalk Project Lessons Learned (Scott asked that we include this

– don’t have it finalized yet but will have it to you soon.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.17

Appendix C Summary of Community Relations Tactics

And Their Primary Use Note: All tactics will be reviewed and approved by the NUSCO NEEWS Campaign Team prior to

their initial use

INTENDED AUDIENCE

Municipali

ties

Residential Property Owner

Commercial

Property Owner/Ten

ant

Community

Groups

Business/Civic Organizations

Regional/ State/

Federal Officials

Media

TACTIC Conference Calls X X Face-to-Face Briefings - Pre- Construction

X

X

X

X

X

X

Face-to-Face Meetings – During Construction

X

X

X

X

X

X

Construction Updates (email)

X

X

X

X

X

X

Website X X X X X X X Project Email X X X Hotline X X X Direct Mail X X X Door Hangers/ Construction Updates

X X

Written Correspondence

X X X X X X

Signage X X Promotional Items X X Speaker’s Bureau X X Bill Inserts X X Local Advertising X X Letters/Ops Eds. X X X Television X X X News Releases X Project Identification X X

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.18

NEEWS Project Stakeholder Inquiry Protocol

Background: The NEEWS Projects will traverse a number of communities in Connecticut and western Massachusetts. It is expected to be a highly visible undertaking and will likely result in numerous customer and other stakeholder inquiries. Some of these inquiries may be contentious, so it is imperative that we institute an effective community relations plan that includes two-way, open lines of communication. These communications must be handled in a consistent manner, using standard, pre-approved messaging, in accordance with NU’s corporate communication standards. Inquiries are to be quickly acknowledged and fully documented in Contract Manager (formerly, Expedition). References:

1. Stakeholder Inquiry Flowchart (Attachment 1) 2. Field Incident Log (Attachment 2) 3. Issue Contact List (Attachment 3)

Sources of Inquiries: Inquiries about the Project may come from various sources including, but not limited to, the following:

NEEWS Hotline (1-866-99NEEWS or 1-888-773-5384 (for Spanish-speaking callers)) NEEWS Website (NEEWSprojects.com) Project Email ([email protected]) NU Field and other Personnel (e.g., Account Executives, Circuit Owners) Field Personnel and Subcontractors NU Customer Service Media State and local officials

The Community Relations Team ( will be the central “funnel” point for most customer and stakeholder inquiries about the NEEWS projects. All phone calls

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.19

from the NEEWS hotline, email from the NEEWS websites, and customer contact request forms from field personnel will be directed to the In addition, the NU Customer Service Center will provide customers who call with questions about NEEWS with the NEEWS toll-free number and website address. Stakeholder inquiries directed to the will be addressed in the manner described in this protocol (see Attachment 1 – Stakeholder Inquiry Flowchart) – with the exception of media and state/local official inquiries (see below). In many cases the initial inquiry may be resolved by the at the time of the initial contact using NU-approved FAQs and/or other pre-approved messages. In these cases, no additional stakeholder contact will be made unless specifically requested. Each of these contacts will be documented in Contract Manager. If the inquiry cannot be resolved utilizing these initial measures and more input is needed to resolve the issue, then additional steps will be taken by the as described in the protocols below and depicted in the flowchart. The Field Incident Log (Attachment 2) is a tool for use by NU and field staff and subcontractors to document NEEWS-related customer contacts and/or inquiries encountered during field work. Field personnel will provide the form, filled out with the appropriate information, to the for follow-up. Field personnel also have the option to contact the via the NEEWS hotline and/or email with the same level of appropriate information. All field staff inquiries directed to the will be addressed utilizing these protocols and documented in Contract Manager. While it is expected that the media and state/local officials will utilize traditional methods of contacting NU, there may be occasions when the media or state/local officials may inquire about NEEWS using the hotline or website. In these cases, the will make immediate contact with the appropriate NU personnel about the inquiry (Attachment 3). It is then the responsibility of the designated NU representative to inform the appropriate persons within NU (e.g., Corporate Communications for media inquiries) of the contact, respond to the inquiry in an accurate and timely manner, and provide the with an update of how the issue was resolved. The will enter the data into Contract Manager. This last step is critical and allows documentation of how the ‘loop’ was closed for media and/or state/local official inquiries. Any non-NEEWS, general transmission inquires should be directed to Ron DeFord. These

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.20

inquiries do not need to be entered into Contract Manager. Protocol: The process described below is depicted in the attached flowchart (Attachment 1):

Upon receipt of a inquiry, a representative will acknowledge the inquiry with the stakeholder within 24 hours or the next business day, if the inquiry is received on a holiday or weekend (Note: Most often, inquiries are addressed on the same day.)

If the inquiry is resolved on the first contact, the information will be provided to the stakeholder, contact documented in Contract Manager, and the appropriate Project Manager notified. Resolution at first contact will be based on standard, pre-approved messaging.

If further information is required, the representative will first work with the Project Manager and others at to develop or discuss an appropriate

response. Once approved by the Project Manager, the will contact the

appropriate Subject Matter Expert (SME) for consultation on how to proceed or to obtain subject matter content (see Attachment 3) if further input is required. In addition to the SME, the will also notify appropriate persons as listed in Attachment 3. These notifications are to keep key Project representatives apprised of the issue but do not require follow-up actions by them.

The SME is responsible for working with the to develop the solution, reach out to other subject matter experts as needed and help coordinate a timely response. If the SME determines that additional reviews are necessary, the SME is responsible for gathering and resolving these comments prior to sending them to the

Once an appropriate response is developed and agreed to by the Project Manager and the SME, a final response will be submitted to the NU Campaign team representatives and the NU Project Manager for comment and approval.

At times, the response may require legal review. Guidance on the need for legal review is to be provided by the NU Project Manager.

If the response is technical in nature, potentially controversial, contains sensitive information or requires legal review, then the Project Director must review and approve the final response.

NUSCO NEEWS – Project Execution Plan Revised 2/26/09 Page 1.13.21

Final approvals must be secured prior to the follow-up information being provided to the stakeholder.

If the issue cannot be resolved within 72 hours, the must then notify the Campaign Director.

Throughout this process, the will document the status/resolution in the Contract Manager database. All associated documents and information provided to the stakeholder is to be attached to the record.

Depending on the type of inquiry, the representative will notify the appropriate Project contact(s) of the status/resolution of these inquiries (see Attachment 3).

All stakeholder inquiries and resolutions must be documented in Contract Manager.

Attachment 21

Public Outreach and Education – Relevant Invoices

Privileged Invoices Omitted

Attachment 22

Public Outreach and Education – Scope of Service

OVERALL SCOPE OF NEEWS ENGAGEMENT

• Help to organize, manage, support and execute communications with key state holders in support of the overall (SNETR) NEEWS Project and each of its components: GSRP, Interstate and CCRP

OUTREACH GOAL

• To the extent practicable, allow the proposed Project(s) to win approval(s) based on merits, by proceeding through the various regulatory reviews, without unwarranted or ill-informed interferences from outside influences.

OUTREACH STRATEGY:

• Identify and proactively inform all potential Project(s) stakeholders (both potential proponents and opponents) about the Project plans so that, to the extent practicable, consistent, accurate information will form the basis of discussion or disagreement regarding the NEEWS Project and each of its component parts.

BASIC ELEMENTS OF OUTREACH PROGRAM

• Initial communications audit: Following tenure as SNETR project lead, where-in the primarily provided internal support of outreach strategies and messaging, was asked by

to assess the efficacy of the current NEEWS communications strategy and its execution. The objective was to identify issues and to make recommendations, which might improve the strategy, execution, coordination and staffing of the NEEWS communications initiatives.

• Following the completion of the audit and roll out of communications recommendations, assumed a role within the NEEWS team supporting outreach communications for all NEEWS Projects, to all internal and external audiences. Those activities included:

• Intelligence gathering o example: Following the deliberations of the Connecticut Energy Advisory Board and their

potential NTA plans for each of the NEEWS projects. o example: Tracking and reporting election results for CCRP towns, to ensure that all current

elected officials were identified to receive a briefing and/or update of the Project benefits and status

• Messaging and materials development o example: Developing talking points for Account Executives to use when initiating contact

with CCRP town CEOs o example: Developing materials for an “All hands meeting” to prepare NU field personnel

with accurate Project background for interactions with the public • Internal coordination of outreach activities:

o example: Helping to organize and participate in (semi)weekly, internal Project status meetings (aka: Muni-core meetings) and monthly/quarterly Campaign Advisory Committee meetings to review outreach strategy, status and next steps with individual project teams and senior management, respectively

• Assisting in development and execution of messaging tools and activities to help external constituencies stay informed of latest Project status and plans:

o examples:

A comprehensive project website (www.NEEWSprojects.com) A Project Hotline and email link to the website to facilitate inquiries from

stakeholders, with a response within 24 hours or the next business day Open houses for the public to learn more about the project and the opportunities to

participate in the regulator’s consideration of the project Periodic mailings to residents along the project right-of-way Project briefings with business, environmental and community-based organizations

• Organizing grass roots support for the Project(s) as a means to raise awareness of their benefits and need

o example: Built coalitions of potential Project supporters and held briefing breakfasts to educate and raise awareness of the project(s) and the need (Note: no formal organization was ever constituted:

• Coordinate and support outreach to groups with potential concerns/inclination to oppose the Project o example: Proactively briefed environmental organizations to pre-empt concerns about

potential harm to the environmentally sensitive areas o example: helped draft strategy to accommodate Native American interests regarding

potential Project impacts • Coordinate and support outreach to public officials

o example: provided logistics and materials support for Council of Government and Regional Plan Association briefings

o example: provided logistics and materials support for Municipal official briefings and follow up activities

o example: provided logistics and materials support for briefings of state and federal legislators. Briefings led by NU Government Relations, focused on: Informing legislators of Project description, benefits and status Notifying them of Project Open Houses and Public Hearings in their districts Offering to provide support and information in addressing constituent concerns or

questions regarding the Project Note: Could not locate copies of presentations for state or federal representatives in

my files. They are essentially the same presentations given to every other group (e.g. project description, benefits, map, schedule, contact information)

• Provide support for NU media relations as needed