Page 1: Provo-Orem Bus Rapid Transit Project Update July 2013

Provo-Orem Bus Rapid Transit

Project Update

July 2013

Page 2: Provo-Orem Bus Rapid Transit Project Update July 2013

Agenda

• Introduction

• BRT ComponentsJanelle Ericson, UTA

• Roadway ComponentsJohn Higgins, UDOT

Page 3: Provo-Orem Bus Rapid Transit Project Update July 2013

Project Description

BRT• 11 miles

• 17 stations

• 53% exclusive BRT lanes

General Purpose Lanes

Innovative Intersections

Page 4: Provo-Orem Bus Rapid Transit Project Update July 2013

Project Description

Page 5: Provo-Orem Bus Rapid Transit Project Update July 2013

Project Description

Page 6: Provo-Orem Bus Rapid Transit Project Update July 2013

Roadway Components

Intersection improvements

Page 7: Provo-Orem Bus Rapid Transit Project Update July 2013

Innovative Intersections Superstreet

Page 8: Provo-Orem Bus Rapid Transit Project Update July 2013

Innovative Intersections Through-U

Page 9: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Examples - Eugene

Page 10: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Examples - Eugene

Page 11: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Examples - Cleveland

Page 12: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Visualizations

Page 13: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Visualizations

Page 14: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Visualizations

Page 15: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Visualizations

Page 16: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Benefits

Current Bus Route 830

Opening Day BRT

Ridership 3,600 / day 12,900 / day

Frequency 15 minutes 5 minutes

Corridor Travel Time

SLC to BYU

45 min

1 hr 20 min

34 min (37 car)

1 hr 7 min

Reliability 84% Est. at 95%

Auto Trips Saved 4,200 / day

Parking saved BYU/UVU 7 acres

Corridor Person Throughput 10-25% increase

Page 17: Provo-Orem Bus Rapid Transit Project Update July 2013

BRT Ridership

0

500

1000

1500

2000

2500

3000

Opening Day

Provo-Orem BRTOpending Day Daily Boardings by Station

2015 Boardings by Station

Page 18: Provo-Orem Bus Rapid Transit Project Update July 2013

Next Steps

• Determine construction scheduling

• Update to TAC in Fall 2013

Janelle Ericson, [email protected]