proton source vacuum plan

21
Proton Source Vacuum Plan By David B. Augustine Ben Ogert Jr. August 30, 2011

Upload: calla

Post on 16-Feb-2016

42 views

Category:

Documents


0 download

DESCRIPTION

Proton Source Vacuum Plan. By David B. Augustine Ben Ogert Jr. August 30, 2011. Linac and Booster. The vacuum system in the Proton Source is mostly original. Ie . Vacuum valves, Ion pumps, mechanical pumps, Ion pumps, etc In several cases Vacuum valves are worn beyond repair - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Proton Source Vacuum Plan

Proton Source Vacuum Plan

ByDavid B. Augustine

Ben Ogert Jr.August 30, 2011

Page 2: Proton Source Vacuum Plan

2

Linac and Booster

• The vacuum system in the Proton Source is mostly original. Ie. Vacuum valves, Ion pumps, mechanical pumps, Ion pumps, etc

• In several cases– Vacuum valves are worn beyond repair– Will not lock closed with out air pressure– Mechanical pumps are obsolete– N2 gas systems in need of repair– Ion pump bodies worn

Page 3: Proton Source Vacuum Plan

3

Linac and Booster

• About a year ago• A detailed cost estimate created for– PreAcc– Linac– Booster– This estimate just shy of 800K in FY10 dollars

Page 4: Proton Source Vacuum Plan

4

Linac

• MSD funds used to purchase newer equipment in FY11 to mitigate operational liability– New gate valves were purchased for the old Linac

RF ~ 5K not installed– One LN2 dewar was repaired at A-0 ~40K,

completed in May 2011– One left to repair

Page 5: Proton Source Vacuum Plan

5

Linac Low EnergyThis is a example of on of the four gate valves that will be replaced during a long shutdown or a large failure.

Page 6: Proton Source Vacuum Plan

6

Linac400 MeV Area

Four of these each or 48K

Page 7: Proton Source Vacuum Plan

7

Linac Low EnergyExisting high capacity Roots Blower station on tanks one and two in the Linac tunnel. Used to pump out the low energy Linac ~50K

Page 8: Proton Source Vacuum Plan

8

Linac Low EnergyExisting high capacity Roots Blower station on tanks three and four in the Linac tunnel. Used to pump out the low energy Linac ~40KThis is a floater station

Page 9: Proton Source Vacuum Plan

9

Linac Low EnergyExisting high capacity Roots Blower station on tank five in the Linac tunnel. Used to pump out the low energy Linac ~40KThis is a floater station

Page 10: Proton Source Vacuum Plan

10

Linac

The o-rings used in the Linac low energy tanks are custom. We do have some minor amount of spares. It is assumed that these are beyond there shelf life. A manufacturer should be investigated and these o-ring made. I have no cost estimate. They would be a custom extrusion

Page 11: Proton Source Vacuum Plan

11

Linac High Energy

• The Linac High Energy does not need extensive work– Spare vacuum equipment should be understood

i.e valves, ion pumps, solenoids, etc

Page 12: Proton Source Vacuum Plan

12

Liquid Nitrogen Dewars

Dewar Before Repair Dewar After Repair

Page 13: Proton Source Vacuum Plan

13

Booster

• MSD funds used to mitigate operational liability– Purchased two Roots blower stations.– Purchased some replacement vacuum valves at

these stations.

Page 14: Proton Source Vacuum Plan

14

BoosterVacuum Valves in the ring are mostly the non-locking type when closed. They all will open upon loss of gas pressure. There are approximately 8 of these, 3K each ~ 24K. This does not include flange changes in the tunnel, seals, welding, etc

Page 15: Proton Source Vacuum Plan

15

Booster

The Mechanical pumps in the tunnel are obselete. MSD funds in the past two years have replaced 4 turbo pumps out of the 24. These are ~8K each or 160K

Page 16: Proton Source Vacuum Plan

16

BoosterThe Roots Blower stations in the fan rooms are obsolete. Two have been replaced by MSD funds. One is dead and the last is a cobbled spare. Two will need to be purchased ~25K

Page 17: Proton Source Vacuum Plan

17

Booster

Example of cobbled together Roots blower station ~ 13K

Page 18: Proton Source Vacuum Plan

18

Booster

This is the last 40 year old station in Booster ~13 K to replace

Page 19: Proton Source Vacuum Plan

19

2012 Purchases In Priority Order

No funding from MSDInstallation by Linac Booster Mechanical Group

Purchase Cost in $ K Labor Installation Time Access time needed271

Large Roots blower station in Linac 50 Purchased product 1 Day 3 techs yesSmall Roots blower station in Linac 30 Purchased product 1 Day 3 techs yesSmall Roots blower station in Linac 30 Purchased product 1 Day 3 techs yesRepair Dewar 01 A-0 South 40 Purchased Service 20 Days 1tech 1 Eng no Replace Roots blowers in Booster fan rooms 2 25 Purchased product 4 Days 3 techs noReplace non locking valves in 400 MeV area 24 Purchased product 4 Days 3 techs yesReplace turbo and roughers 400 MeV area 62 Purchased product 4 Days 3 techs yesElectrical work needed for turbo pumps 10 Purchased Service 2 Electricians 2 weeks yes

Page 20: Proton Source Vacuum Plan

20

Booster

• In many cases over the years vacuum leaks were patched over with glyptol, and vacuum epoxy. There is currently a three page list of these. They should all be fixed correctly before the tunnel gets too hot. I cannot estimate the cost of this.

Page 21: Proton Source Vacuum Plan

21

Thank you for your attention