proton plan expectations eric prebys ad/proton source

22
Proton Plan Expectations Eric Prebys AD/Proton Source

Upload: emil-alexander

Post on 18-Jan-2018

242 views

Category:

Documents


0 download

DESCRIPTION

Proton Plan Expectations – SNuMI Review – E. Prebys SNuMI Director’s Preliminary Review November 2006 Eric Prebys 3 Proton Plan The Proton Plan is the current campaign to maximize proton delivery to NuMI and MiniBooNE during the collider era: –Hardware projects complete in 2008 shutdown –Plan complete in 2009 –SNuMI assumes success of Proton Plan The Main Goals of the Proton Plan are: –Increase overall reliability of Linac/Booster –Increase Booster efficiency to reduce uncontrolled beam loss in Booster tunnel (currently the limiting factor in beam delivery) Total beam throughput limit 18E16 protons per hour –Achieve Booster beam quality necessary for slip stacking in the Main Injector Longitudinal emittance=.08 eV-s,  p = ±8 MeV –Increase average Booster repetition rate to at least 9 Hz If the first three goals are met, they will satisfy the needs of SNuMI Repetition rate remains an issue –This is the only scope currently in SNuMI!

TRANSCRIPT

Page 1: Proton Plan Expectations Eric Prebys AD/Proton Source

Proton Plan Expectations

Eric PrebysAD/Proton Source

Page 2: Proton Plan Expectations Eric Prebys AD/Proton Source

2Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Overview

• Overview of Proton Plan• Status• Remaining Projects• Projections• Conclusions

Page 3: Proton Plan Expectations Eric Prebys AD/Proton Source

3Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Proton Plan

• The Proton Plan is the current campaign to maximize proton delivery to NuMI and MiniBooNE during the collider era:– Hardware projects complete in 2008 shutdown– Plan complete in 2009– SNuMI assumes success of Proton Plan

• The Main Goals of the Proton Plan are:– Increase overall reliability of Linac/Booster– Increase Booster efficiency to reduce uncontrolled beam loss in Booster

tunnel (currently the limiting factor in beam delivery)• Total beam throughput limit 18E16 protons per hour

– Achieve Booster beam quality necessary for slip stacking in the Main Injector

• Longitudinal emittance=.08 eV-s, p = ±8 MeV– Increase average Booster repetition rate to at least 9 Hz

• If the first three goals are met, they will satisfy the needs of SNuMI• Repetition rate remains an issue

– This is the only scope currently in SNuMI!

Page 4: Proton Plan Expectations Eric Prebys AD/Proton Source

4Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Limits to Proton Intensity

• Total proton rate from Proton Source (Linac+Booster):– Booster batch size

• ~4-5E12 protons/batch– Booster repetition rate

• 15 Hz instantaneous• Prior to 2006 shutdown: 7.5Hz average (injection bump+RF)• Now: 9 Hz (including conditioning pre-pulses)

– Beam loss• Damage and/or activation of Booster components• Above ground radiation

• Total protons accelerated in Main Injector:– Maximum main injector load

• Six “slots” for booster batches (3E13)• Up to ~11 with slip stacking (4-5E13)• Some RF issues (see Kourbanis talk)

– Cycle time:• 1.4s + loading time (1/15s per booster batch)

Historically our biggest worry

Page 5: Proton Plan Expectations Eric Prebys AD/Proton Source

5Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Goals of Proton Plan

• 120 GeV (NuMI)– Accelerate 4-5E13 protons per 2.2s cycle– This alone is within demonstrated performance of the Booster (at least

in terms of total protons):• 7.5Hz adequate• Total proton rate ~OK

– Most of the necessary work is in Main Injector– Maintaining acceptable longitudinal quality from Booster for slip stacking

presents an operational challenge• 8 GeV (BNB)

– Maintain ~2e20 p/year to maintain 8 GeV neutrino program– Requires ~50% increase in total protons– Requires Booster to go to ~9Hz

• Future– Pave the way for increased beam throughput needed by SNuMI and

beyond• e.g. Booster corrector upgrade

Page 6: Proton Plan Expectations Eric Prebys AD/Proton Source

6Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Context: Staged Approach to Neutrino Program

• NuMI era (concurrent with Run II)– Ramp up to deliver slip stacked protons to both NuMI and antiproton production– Continue to deliver protons to the 8 GeV line at some level– Goal:

• ~380 kW to NuMI• 1-2E20 protons to 8 GeV line

• S(uper)NuMI era (after collider program)– Use Recycler as a pre-loader to the Main Injector to eliminate loading time– Becoming a formal plan.– Goal

• ~700 kW to NuMI line• SNuMI 2 (tentative)

– Use Antiproton Accumulator Ring to momentum stack protons– Boxcar stack these protons into Recycler– Load into Main Injector– Goal

• ~1.2 MW to NuMI line• HINS (formerly known as “Proton Driver”)?

– Always a possibility, but not part of our baseline thinking at the moment.

Proton Plan

This Review

Page 7: Proton Plan Expectations Eric Prebys AD/Proton Source

7Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Total ProtonsTotal Booster Output

0.E+00

2.E+20

4.E+20

6.E+20

8.E+20

1.E+21

1.E+21

BeforeNeutrino

Program (30year average)

Now (pBar +NuMI +

MiniBooNE)

Proton Plangoal (2009)

SNuMI I goal(NuMI only)

SnuMI II goal(NuMI only)

Ann

ual P

roto

ns

(.17E20)

Present

Page 8: Proton Plan Expectations Eric Prebys AD/Proton Source

8Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Significant Elements of Plan

• Linac– Stockpile two year supply of spare 200 MHz power amplifier tubes (7835’s),

in the event of an interruption in supply– Characterize and improve Low Energy Linac Low Level RF

• Booster:– Replace and reconfigure injection bump (ORBUMP) system.– Relocate 8 GeV dump from Booster tunnel to MI-8 transfer line– Make Booster robust to 9 Hz, and understand requirements to go to 15 Hz– Design, build, and install new corrector system

• Main Injector:– Replace seven quadrupoles with increased aperture versions, to reduce

injection and extraction losses.– Operationally develop multi-batch and multi-batch slip stacked operation– Design and install collimation system, both in the MI-8 line and in the MI ring– Modify injection kicker to allow multi-batch slip stacked operation– Characterize and make improvements to RF system to support high intensity

operation.Red =

completed

Major achievement!!!!

Page 9: Proton Plan Expectations Eric Prebys AD/Proton Source

9Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric PrebysStatus Summary

= Task completed

= Significant element(s) completed

New 13.8 kV transformers and switch gear for Booster RF

MI-8 Collimation Complete

MI-10 kicker upgrade

= Task descoped

Page 10: Proton Plan Expectations Eric Prebys AD/Proton Source

10Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Success of Plan

Proton Totals

0.0E+00

5.0E+19

1.0E+20

1.5E+20

2.0E+20

2.5E+20

3.0E+20

3.5E+20

4.0E+20

4.5E+20

5.0E+20

2000 2001 2002 2003 2004 2005 2006

Fiscal Year

Tota

l Pro

tons

MiniBooNE

NuMI

MiniBooNE

NuMI

Average Booster Activation

Factor of 15 increase in protons

Total Protons Delivered

Page 11: Proton Plan Expectations Eric Prebys AD/Proton Source

11Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Future

• A significant part of the Proton Plan was completed (or descoped) by the end of the last shutdown.

• This will free up some badly needed expertise to focus on optimizing the system to take advantage of the improvements that have been made.

• The most significant remaining tasks are:– Linac LLRF (1.1.4)– Booster Corrector System (1.2.3)

• This would be a major project all by itself• Last (?) major Booster project

– Main Injector Ring Collimation (1.3.2.1.3)– Main Injector RF Upgrade (1.3.4)

• Series tube modulator power dissipation• Anode power supply rectifier transformer• Solid State Driver power supplies See Kourbanis Talk

Page 12: Proton Plan Expectations Eric Prebys AD/Proton Source

12Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Booster Corrector System

• Replace all 48 (original) Booster corrector packages.

– Unique new design• Six independent multipoles

– Stronger H and V dipoles• ±1cm beam motion throughout cycle

– Stronger quad• Arbitrary tune working point throughout cycle

– Skew quad• Coupling, same strength as before.

– Sextupole and skew sextupole at every period.

• Less emittance blowup• More control of harmonic resonances.

• Integrated BPM– Saves space

• Total Cost– $3.6M M&S– $2.6M SWF

~16”

Page 13: Proton Plan Expectations Eric Prebys AD/Proton Source

13Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Correctors: Status

• Testing first prototype– Looks good

• Just passed internal technical review– New corrector system “badly

overdue”• Aggressive schedule• Half of correctors in stalled in 2007

shutdown.• Second half in 2008 shutdown.• Done with Booster?

Page 14: Proton Plan Expectations Eric Prebys AD/Proton Source

14Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Proton Plan Timeline

• Now– Proton Plan ~half complete (in terms of total $)

• 2007 Shutdown (June 2007)– Install half of Booster correctors– Complete Main Injector collimation and RF projects

• Main Injector “done”, in terms of hardware projects• 2008 Shutdown (June 2008)

– Install remaining Booster correctors– All Proton Plan hardware projects complete

• Mid-2009– All tuning and commissioning complete– End of Proton Plan

Page 15: Proton Plan Expectations Eric Prebys AD/Proton Source

15Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Proton Plan Projections

• Proton Plan represents the first ever attempt to accurately predict total proton output from Booster.

• History has shown that the lab tends to overestimate the benefits of particular improvements.– Tuning and optimization take a long time– Tend to asymptotically approach the goal, then get distracted by other

things.• So we…

– Evaluate the potential of particular improvements based on effective aperture increase or uncontrolled beam loss reduction:

• For example, if something reduces uncontrolled loss by 10%, it has the potential to allow us to send 10% more beam.

– Consider the following scenarios:• “Design”: After one year of tuning, we realize half of the potential benefit.• “Fallback”: After one year of tuning, we realize one quarter of the potential

benefit.

Page 16: Proton Plan Expectations Eric Prebys AD/Proton Source

16Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Peak Booster Intensities

• These are “peak” numbers

• An “average to peak” correction is applied to get average values

• These are the numbers from loss limits

• The real peak value will be limited by the 9Hz rep rate at about 1E17, depending on batch size.

Peak Booster Beam Limit (losses only, w/o Efficiencies)

0.00E+00

2.00E+16

4.00E+16

6.00E+16

8.00E+16

1.00E+17

1.20E+17

1.40E+17

1.60E+17

1.80E+17

2.00E+17

1/1/2005 1/1/2006 1/1/2007 1/1/2008 1/1/2009 1/1/2010

Date

prot

ons/

hour

DesignFallback

Phase I

Doglegs ORBUMP New Correctors

Present

Page 17: Proton Plan Expectations Eric Prebys AD/Proton Source

17Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Factors Considered in Projections

• Linear ramp-up to see benefit of improvements• Slip stacking efficiency• Different Booster efficiency for cogged (pBar+NuMI) cycles and

uncogged (BNB) cycles.• Annual shutdowns (assume 2 mo/yr)

– Overall asymptotic ramp-up after shutdown (improved for FY06)• Uptimes: based on MiniBooNE 2004 and NuMI 2005• Peak to average corrections

– For BNB, based on MiniBooNE 2004– For NuMI, used reasonable guess

Page 18: Proton Plan Expectations Eric Prebys AD/Proton Source

18Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Proton Projections: Total

• Overall– “Good” running in line with plan– Overly optimistic on turn-on after

shutdowns– Improved for future projections

Turn on slower than

expected

Page 19: Proton Plan Expectations Eric Prebys AD/Proton Source

19Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Projections: NuMI

Water in target

Horn ground fault

Tritium in water

Special runs

Resin beads in water system

RAW Problem

Water in target

• Overall– Projections accurate when up– Lower uptime than expected– Revised for future projections

and SNuMI

Page 20: Proton Plan Expectations Eric Prebys AD/Proton Source

20Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Proton Projections: BNB

• Overall– BNB has benefitted from NuMI

problems– Total delivery pretty close to

projections

Page 21: Proton Plan Expectations Eric Prebys AD/Proton Source

21Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Long Term Cumulative Totals

• Projections as revised at last Director’s Review• Compared to first Director’s Review

BNB Totals

0.00E+00

2.00E+20

4.00E+20

6.00E+20

8.00E+20

1.00E+21

1.20E+21

1.40E+21

1.60E+21

1.80E+21

2.00E+21

1/1/2005 1/1/2006 1/1/2007 1/1/2008 1/1/2009

Date

Prot

ons

Base (2005 Review)Design (2005 Review)Base (from 8-1-06)Design (from 8-1-06)

Actual value as of 8/1/06

NuMI Totals

0.00E+00

2.00E+20

4.00E+20

6.00E+20

8.00E+20

1.00E+21

1.20E+21

1.40E+21

1/1/2005 1/1/2006 1/1/2007 1/1/2008 1/1/2009

Date

Prot

ons

Base (2005 Review)Design (2005 Review)Base (from 8-1-06)Design (from 8-1-06)

Actual value as of 8/1/06

Page 22: Proton Plan Expectations Eric Prebys AD/Proton Source

22Proton Plan Expectations – SNuMI Review – E. Prebys

SNuMISNuMI

Director’s Preliminary Review

14-16 November 2006Eric Prebys

Conclusions

• SNuMI relies on the success Proton Plan– So far, the Proton plan has done a good job of tracking major projects and

proton delivery– At the end of the Plan, the Booster should meet the SNuMI needs in terms

of beam quality and total proton rate • If the Proton Plan is successful, the only remaining projects needed for SNuMI

will involve repetition rate issues– RF cooling– Anode power supplies– Cavity bias supplies

• Important for SNuMI to keep track of Proton Plan over next several years– e.g. SNuMI milestones

• 1.1.2.1.1 – verify that Booster meets beam loss requirements• 1.1.2.2.1 – verify that Booster meets beam quality requirements