Page 1: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

PROJECT UPDATE

SEPTEMBER 2015

GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

Page 2: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

2

Background

Page 3: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT
Page 4: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

4

Progress over the last 12 months

• Development Consent Order granted (12 September 2014)

• Andy Mitchell appointed Chief Executive Officer (January 2014)

• Main Works preferred tenderers announced (February 2015)

• Licence award granted by Ofwat (August 2015)

• Investors appointed for Bazalgette Tunnel Limited (August 2015)

• Main Works Contractors appointed (August 2015)

Page 5: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

5

PLANNING AND CONSULTATION

Page 6: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

6

Consultation and Community Engagement

30Months

development

9,400Responses

during consultation

Over 200meetings attended

114 days of public

exhibitions held

Page 7: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

7

Route to Development Consent

• Over six years of project development, planningand extensive consultation

• Planning Act 2008

• Public consultation

• DCO application

- 50 separate documents

- 50,000 pages in total, including a 25,000 page Environmental Statement.

- Development Consent granted 12 September 2014

Page 8: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

8

Received Support for the project

Page 9: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

9

DELIVERING THE PROJECT

Page 10: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

10

Delivery model

• Thames Water worked with the Government and Ofwat to consider a range of models to ensure a value for money solution

• A new regulated Infrastructure Provider, Bazalgette Tunnel Limited (BTL), has been formed under the Flood and Water Management Act 2010

• Regulated by Ofwat

• Tendered through a competitive process and will build, manage and maintain the tunnel. Thames Water will operate it

• £1.1bn of investment is from Thames Water, £3.1bn is from BTL

• Licence awarded 24 August 2015.

• Flat bills for Thames Water customers

Page 11: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

11

Page 12: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

12

Bazalgette Tunnel Limited

The new Infrastructure Provider is the first Wastewater only company in the UK. It is made up of the following shareholders:

Page 13: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

13

About Tideway

• Bazalgette Tunnel Limited- New, independent regulated water company- First one created in 20 years, 6th largest in the country- Only waste-water-only water company in the country- UK tax based company- Invested funds representing 1.7 million UK pensioners

- Ambition is long-term modest returns- Keen to see

•Highest standards of Health Safety and Wellbeing

•Delivered at demonstrable value for money

•Earning a positive reputation

•As soon as possible

Page 14: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

14

Main Works Contractors

West Central East System Integrator

All contracts awarded 24 August 2015

Page 15: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

15

Main Construction Works

WESTLondon Clay

CENTRALLondon Clay/Lambeth Group/Thanets

EASTChalk

Page 16: PROJECT UPDATE SEPTEMBER 2015 GEOFF LOADER, HEAD OF STAKEHOLDER ENGAGEMENT

16

Timetable

2016

Main works preliminary constructionbegins

2017

Tunnelling begins

2021

Tunnelling ends

2022

System commissioning begins

2015

• BTL granted licence by Ofwat

• Main Works contracts awarded

2023

Project completion