New Ringgold Middle School
Project SlideshowMay 27, 2016
Continued Keyway Construction
Installation of Drain
Installation of Gravel Over Drain
Keyway Construction
Keyway Construction
Compaction of Material
Keyway – from West
Keyway – from East
Removal of Unsuitable Soil from Site
Removal of Topsoil from Site
Removal of Demo Materials from Gearing Rd. Residence Complete
Before
After
Began Removing Tennis Court Asphalt
• Finish Keyway Construction.• Finish Removal of Topsoil from Site.• Finish Removal of Tennis Court Asphalt• Start Sitework for Building.• Start Retaining Walls• Move Construction Trailers• Establish New Construction Area with
Moving Fencing After Last Day of School.
Scheduled Work for Next Few Weeks
The End