New Ringgold Middle School
Project SlideshowAugust 5, 2017
Aerial Photo – Overall Site from the South
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo – Overall Site from the East
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo – Overall Site from the North
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo from West
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo from Southwest
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo from South
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo from Northeast
Provided by Hudson Group – Taken 7.29.2017
Aerial Photo from North
Provided by Hudson Group – Taken 7.29.2017
Building Areas
Provided by Hudson Group – Taken 7.29.2017
1st Floor - Area A
Storefront Installation – Cafeteria Entrance - Area A
Storefront Installation – Admin & Auditorium Entance
Metal Door Installation – 1st Floor – Area A
Wood Door Installation – 1st Floor – Area A
Glazing – 1st Floor – Area A
Window Sill Installation – 1st Floor – Area A
Toilet Partition Installation – 1st Floor – Area A
VCT Installation – 1st Floor – Area A
Carpet Installation – Admin – 1st Floor - Area A
Rubber Base Installation – 1st Floor – Area A
Admin Area
Cafeteria
Reception Desk Installation – Admin Area - 1st Floor – Area A
Unit Cabinet Heater – Cafeteria Vestibule - Area A
Diffuser Installation – Cafeteria - Area A
Light Fixture Installation – Cafeteria - Area A
Progress Cleaning - Food Service Equipment – Kitchen - Area A
Interior Work Progress – 1st Floor - Area A
Work Completed• HVAC Ductwork• HVAC Piping • HVAC Insulation • HVAC Controls• GRD Installation• Electrical Rough In• Light Fixture Installation• Electrical Device Installation• Cable Tray Installation• Telecommunication Wiring• Data Rack Installation• Cafeteria Sound System Installation• Clock Installation• Plumbing Rough In• Plumbing Insulation Installation• Plumbing Fixture Installation• Sprinkler Piping InstallationWork in Progress• Casework Installation• VCT Installation• Elevator Installation• Toilet Accessory Installation
• Sprinkler Head Installation• Interior Door Frame Installation• Drywall Finishing• Block Filler & Painting• Ceramic Tile Installation• Rolling Grille Installation• Kitchen Walk-In Installation• Kitchen Hood Installation • Window Installation • Ceiling Grid Installation• Locker Installation• Carpet Installation• Exterior Door Installation• Metal & Wood Door Installation• Marker & Tack Board Installation• Toilet Partition Installation• Signage Installation
• Food Service Equip. Installation• Storefront Installation• Glazing• Rubber Base Installation
2nd Floor – Area A
Countertop Installation – 2nd Floor - Area A
Countertop Installation – 2nd Floor - Area A
Rubber Base Installation – 2nd Floor - Area A
Window Sill Installation – 2nd Floor - Area A
Circulation Desk Installation – 2nd Floor - Area A
Media Center
Ceiling Tile Installation – 2nd Floor - Area A
Classroom
Corridor
Ceiling Grid & Tile Installation – Stair 4 - Area A
Handrail Painted – Stair 4 - Area A
GRD Installation – 2nd Floor - Area A
Extension Cord Reel Installation – 2nd Floor - Area A
STEM Assembly Classroom
Telecommunications Final Connections – 2nd Floor - Area A
Interior Work Progress – 2nd Floor - Area A
Work Completed• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Clock Installation• Wire Molding Installation• Plumbing Rough In• Plumbing Insulation Installation• Restroom Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls• GRD Installation• Spiral Duct Installation• Sprinkler Head Installation• Interior Door Frame Installation• Window Installation
Work in Progress• Countertop Sink Installation• Elevator Installation
• Block Filler & Painting• Stud Framing • Drywall Finishing• Ceiling Grid Installation• Ceiling Tile Installation• Carpet Installation• Cement Board Installation• Ceramic Tile Installation• Column Cover Installation• VCT Installation• Rubber Base Installation• Casework Installation• Metal & Wood Door Installation• Window Sill Installation• Glazing• Marker & Tack Board Installation• Signage Installation
• Toilet Accessory Installation
1st Floor - Area B
Window Installation – 1st Floor – Area B
Classroom Corridor
Painting – Stair 2 – Area B
Toilet Partition Installation – 1st Floor – Area B
Mirror Installation – 1st Floor – Area B
Wood Door Glazing – 1st Floor – Area B
Ceiling Tile Installation – 1st Floor – Area B
Classroom
Corridor
HVAC Insulation – 1st Floor – Area B
Interior Work Progress – 1st Floor - Area B
Work Completed• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Cable Tray Installation• Telecommunication Wiring• Clock Installation• Wire Molding Installation• Data Rack Installation• Plumbing Rough In• Plumbing Insulation Installation• Restroom Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork • HVAC Insulation Installation• HVAC Controls• GRD Installation• Sprinkler Piping Installation• Sprinkler Head InstallationWork in Progress• Countertop Sink Installation• Casework Installation• Toilet Accessory Installation
• Interior Door Frame Installation• Stair Installation• Drywall Installation• Block Filler• Window Installation• Locker Bases• Ceramic Tile Installation• Handrail Installation – Stairs 1&2• Locker Installation• Marker & Tack Board Installation• Window Sill Installation• Drywall in Stairs 1 & 2• Exterior Door Installation• Wood & Metal Door Installation• Painting• Ceiling Grid Installation• VCT Installation• Toilet Partition Installation• Signage Installation
• Glazing• Ceiling Tile Installation
2nd Floor - Area B
Ceiling Tile Installation – 2nd Floor – Area B
Classroom
Corridor
Ceiling Grid & Tile Installation – Stairs 1 & 2 – Area B
Stair 1
Stair 2
Toilet Partition Installation – 2nd Floor – Area B
Mirror & Hand Dryer Installation – 2nd Floor – Area B
VCT Installation – 2nd Floor – Area B
Mini Blind Installation – 2nd Floor – Area B
Countertop Installation – 2nd Floor – Area B
Handrails Painted – Stair 2 – Area B
Locker Lock Installation – 2nd Floor – Area B
HVAC Insulation – 2nd Floor – Area B
Light Fixture Installation – Stair 2 – Area B
Final Cleaning of Classrooms – 2nd Floor – Area B
Interior Work Progress – 2nd Floor - Area B
Work Completed• Plumbing Rough In• Plumbing Insulation Installation• Restroom Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls • GRD Installation• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Clock Installation • Telecommunication Wiring• Wire Molding Installation• Sprinkler Piping Installation• Sprinkler Head Installation• Interior Door Frame Installation• Drywall Installation
Work in Progress• Countertop Sink Installation• Classroom Final Cleaning
• Block Filler• Cement Board Installation• Window Installation• Wood & Metal Door Installation• Locker Bases• Ceramic Tile Installation• Painting• Drywall in Stairs 1 & 2• Ceiling Grid Installation• Casework Installation• Marker & Tack Board Installation• VCT Installation• Rubber Base Installation• Locker Installation• Window Sill Installation• Mini Blind Installation• Glazing• Toilet Partition Installation• Signage Installation
• Ceiling Tile Installation• Toilet Accessory Installation
1st Floor - Area C
VCT Installation – 1st Floor - Area C
Classroom Corridor
Ceiling Tile Installation – 1st Floor - Area C
GRD Installation – 1st Floor - Area C
Interior Work Progress – 1st Floor - Area C
Work Completed• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Cable Tray Installation• Telecommunication Wiring• Wire Molding Installation• Clock Installation• Plumbing Rough In• Plumbing Insulation Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls• GRD Installation • Sprinkler Piping Installation• Sprinkler Head Installation
• Casework Installation• Glazing
• Interior Door Frame Installation• Stair Installation• Handrailing Installation – Stair 3• Drywall Installation• Block Filler• Window Installation • Ceiling Grid Installation• Locker Bases• Locker Installation• Marker & Tack Board Installation• Window Sill Installation• Metal & Wood Door Installation• VCT Installation• Painting• Signage Installation
Work in Progress• Rubber Base Installation• Ceiling Tile Installation
2nd Floor - Area C
Locker Lock Installation – 2nd Floor – Area C
Handrail Painted – Stair 3 – Area C
Countertop Installation – 2nd Floor - Area C
Ceiling Tile Installation – 2nd Floor - Area C
Ceiling Grid & Tile Installation – Stair 3 - Area C
Light Fixture Installation – Stair 3 - Area C
Interior Work Progress – 2nd Floor - Area C
Work Completed• Plumbing Rough In• Plumbing Insulation Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls • GRD Installation• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Clock Installation • Telecommunication Wiring• Wire Molding Installation• Sprinkler Piping Installation• Sprinkler Head Installation• Interior Door Frame Installation• Drywall Installation
Work in Progress• Countertop Sink Installation• Classroom Final Cleaning
• Block Filler• Window Installation• Wood & Metal Door Installation• Locker Bases• Ceramic Tile Installation• Painting• Drywall in Stair 3• Ceiling Grid Installation• Casework Installation• Marker & Tack Board Installation• VCT Installation• Rubber Base Installation• Locker Installation• Window Sill Installation• Mini Blind Installation• Glazing• Signage Installation
• Ceiling Tile Installation
1st Floor - Area D
Metal Door Installation – Area D
Ceiling Grid Installation – Area D
Painting – Corridor A128
Epoxy Painting of Auditorium Floor - Area D
Wood Panel Installation - Auditorium – Area D
Acoustical Panel Installation - Auditorium – Area D
Auditorium Chair Installation – Area D
Glass Railing Installation - Auditorium - Area D
Display Case Installation – Area D
At Gym
At Auditorium
Locker Number Installation – Locker Rooms – Area D
Toilet Partition Installation – Area D
Toilet Accessory Installation – Area D
Gym Equipment Installation – Area D
Light Fixture Installation – Auditorium – Area D
Light Fixture Installation – Area D
Gym Sound System Installation – Area D
Electrical Connections for Gym Equipment Controls – Gym – Area D
Ductwork Installation – Gym - Area D
Ductwork Painted – Gym - Area D
Ductwork Insulation – Area D
HVAC Piping Insulation – Area D
Plumbing Fixture Installation – Locker Rooms – Area D
Interior Work Progress – 1st Floor - Area DWork Completed• Electrical Rough In• Gym Speaker Installation• Gym Sound System Installation• Plumbing Rough In• Plumbing Piping Insulation• Plumbing Fixture Installation• HVAC Piping Installation• Sprinkler Piping Installation• Rolling Grille Installation• Locker Bases• Locker Installation• Translucent Panel Installation
Work in Progress• Light Fixture Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls• Sprinkler Head Installation• Painting• Stage Equipment Installation• Exterior Door Installation
• Window Installation• Cement Board Installation• Support for Acoustical Panels• Auditorium Acoustical Panel Installation• Auditorium Chair Installation• Locker Installation• Bulkhead Installation• Interior Door Frame Installation• Block Filler• Drywall Installation• Toilet Partition Installation• Display Case Installation
• Wood & Metal Door Installation• Ceiling Grid Installation• Auditorium Wood Panel Installation• Ceramic Tile Installation• Gym Equipment Installation• Toilet Accessory Installation• Signage Installation
Signage Through Building
Electrical Devices Through Building
Metal Panel Installation – Around Building
Signage Around Building
Generator Set & Startup
Concrete Sidewalks – East & South of High School
Concrete Steps at Fitness Center
Retaining Walls 4A & 4B Installation
Concrete Curb Installation
Sitework – Ram Drive
Milling Asphalt – East Side of Ram Drive
Asphalt Binder Course – East of Middle & High Schools
Asphalt Binder Course – Ram Drive
Asphalt Binder Course – Tennis Court
Stormwater Piping – Ram Drive
Light Pole Installation along Ram Drive
• Continue Exterior Door Installation• Complete HVAC Ductwork Installation• Countertop Sink Installation • Complete Food Service Equip. Installation• Finish Ceiling Grid Installation – Area D• Touch Up Painting• Flooring Installation – Area D• Complete Ceiling Tile Installation – Areas
A, B, & C• Continue EIFS Installation at Entrances• Finish Gym Equipment Installation• Gym Wood Floor Installation• Stage Floor Installation
Scheduled Work for Next Few Weeks
• Continue Metal Door Installation• Continue Wood Door Installation• Continue Countertop Installation• Continue GRD Installation• Complete Window Sill Installation• Finish Toilet Partition Installation• Continue Toilet Accessory Installation• Continue Site Concrete• Complete Ram Drive Work• Asphalt Paving • Continue Installing Topsoil• Site Landscaping
The End