Page 1: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

New Ringgold Middle School

Project SlideshowAugust 5, 2017

Page 2: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo – Overall Site from the South

Provided by Hudson Group – Taken 7.29.2017

Page 3: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo – Overall Site from the East

Provided by Hudson Group – Taken 7.29.2017

Page 4: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo – Overall Site from the North

Provided by Hudson Group – Taken 7.29.2017

Page 5: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo from West

Provided by Hudson Group – Taken 7.29.2017

Page 6: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo from Southwest

Provided by Hudson Group – Taken 7.29.2017

Page 7: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo from South

Provided by Hudson Group – Taken 7.29.2017

Page 8: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo from Northeast

Provided by Hudson Group – Taken 7.29.2017

Page 9: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Aerial Photo from North

Provided by Hudson Group – Taken 7.29.2017

Page 10: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Building Areas

Provided by Hudson Group – Taken 7.29.2017

Page 11: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

1st Floor - Area A

Page 12: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Storefront Installation – Cafeteria Entrance - Area A

Page 13: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Storefront Installation – Admin & Auditorium Entance

Page 14: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Metal Door Installation – 1st Floor – Area A

Page 15: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Wood Door Installation – 1st Floor – Area A

Page 16: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Glazing – 1st Floor – Area A

Page 17: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Window Sill Installation – 1st Floor – Area A

Page 18: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Toilet Partition Installation – 1st Floor – Area A

Page 19: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

VCT Installation – 1st Floor – Area A

Page 20: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Carpet Installation – Admin – 1st Floor - Area A

Page 21: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Rubber Base Installation – 1st Floor – Area A

Admin Area

Cafeteria

Page 22: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Reception Desk Installation – Admin Area - 1st Floor – Area A

Page 23: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Unit Cabinet Heater – Cafeteria Vestibule - Area A

Page 24: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Diffuser Installation – Cafeteria - Area A

Page 25: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Light Fixture Installation – Cafeteria - Area A

Page 26: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Progress Cleaning - Food Service Equipment – Kitchen - Area A

Page 27: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 1st Floor - Area A

Work Completed• HVAC Ductwork• HVAC Piping • HVAC Insulation • HVAC Controls• GRD Installation• Electrical Rough In• Light Fixture Installation• Electrical Device Installation• Cable Tray Installation• Telecommunication Wiring• Data Rack Installation• Cafeteria Sound System Installation• Clock Installation• Plumbing Rough In• Plumbing Insulation Installation• Plumbing Fixture Installation• Sprinkler Piping InstallationWork in Progress• Casework Installation• VCT Installation• Elevator Installation• Toilet Accessory Installation

• Sprinkler Head Installation• Interior Door Frame Installation• Drywall Finishing• Block Filler & Painting• Ceramic Tile Installation• Rolling Grille Installation• Kitchen Walk-In Installation• Kitchen Hood Installation • Window Installation • Ceiling Grid Installation• Locker Installation• Carpet Installation• Exterior Door Installation• Metal & Wood Door Installation• Marker & Tack Board Installation• Toilet Partition Installation• Signage Installation

• Food Service Equip. Installation• Storefront Installation• Glazing• Rubber Base Installation

Page 28: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

2nd Floor – Area A

Page 29: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Countertop Installation – 2nd Floor - Area A

Page 30: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Countertop Installation – 2nd Floor - Area A

Page 31: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Rubber Base Installation – 2nd Floor - Area A

Page 32: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Window Sill Installation – 2nd Floor - Area A

Page 33: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Circulation Desk Installation – 2nd Floor - Area A

Media Center

Page 34: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Tile Installation – 2nd Floor - Area A

Classroom

Corridor

Page 35: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Grid & Tile Installation – Stair 4 - Area A

Page 36: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Handrail Painted – Stair 4 - Area A

Page 37: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

GRD Installation – 2nd Floor - Area A

Page 38: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Extension Cord Reel Installation – 2nd Floor - Area A

STEM Assembly Classroom

Page 39: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Telecommunications Final Connections – 2nd Floor - Area A

Page 40: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 2nd Floor - Area A

Work Completed• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Clock Installation• Wire Molding Installation• Plumbing Rough In• Plumbing Insulation Installation• Restroom Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls• GRD Installation• Spiral Duct Installation• Sprinkler Head Installation• Interior Door Frame Installation• Window Installation

Work in Progress• Countertop Sink Installation• Elevator Installation

• Block Filler & Painting• Stud Framing • Drywall Finishing• Ceiling Grid Installation• Ceiling Tile Installation• Carpet Installation• Cement Board Installation• Ceramic Tile Installation• Column Cover Installation• VCT Installation• Rubber Base Installation• Casework Installation• Metal & Wood Door Installation• Window Sill Installation• Glazing• Marker & Tack Board Installation• Signage Installation

• Toilet Accessory Installation

Page 41: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

1st Floor - Area B

Page 42: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Window Installation – 1st Floor – Area B

Classroom Corridor

Page 43: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Painting – Stair 2 – Area B

Page 44: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Toilet Partition Installation – 1st Floor – Area B

Page 45: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Mirror Installation – 1st Floor – Area B

Page 46: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Wood Door Glazing – 1st Floor – Area B

Page 47: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Tile Installation – 1st Floor – Area B

Classroom

Corridor

Page 48: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

HVAC Insulation – 1st Floor – Area B

Page 49: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 1st Floor - Area B

Work Completed• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Cable Tray Installation• Telecommunication Wiring• Clock Installation• Wire Molding Installation• Data Rack Installation• Plumbing Rough In• Plumbing Insulation Installation• Restroom Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork • HVAC Insulation Installation• HVAC Controls• GRD Installation• Sprinkler Piping Installation• Sprinkler Head InstallationWork in Progress• Countertop Sink Installation• Casework Installation• Toilet Accessory Installation

• Interior Door Frame Installation• Stair Installation• Drywall Installation• Block Filler• Window Installation• Locker Bases• Ceramic Tile Installation• Handrail Installation – Stairs 1&2• Locker Installation• Marker & Tack Board Installation• Window Sill Installation• Drywall in Stairs 1 & 2• Exterior Door Installation• Wood & Metal Door Installation• Painting• Ceiling Grid Installation• VCT Installation• Toilet Partition Installation• Signage Installation

• Glazing• Ceiling Tile Installation

Page 50: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

2nd Floor - Area B

Page 51: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Tile Installation – 2nd Floor – Area B

Classroom

Corridor

Page 52: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Grid & Tile Installation – Stairs 1 & 2 – Area B

Stair 1

Stair 2

Page 53: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Toilet Partition Installation – 2nd Floor – Area B

Page 54: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Mirror & Hand Dryer Installation – 2nd Floor – Area B

Page 55: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

VCT Installation – 2nd Floor – Area B

Page 56: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Mini Blind Installation – 2nd Floor – Area B

Page 57: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Countertop Installation – 2nd Floor – Area B

Page 58: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Handrails Painted – Stair 2 – Area B

Page 59: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Locker Lock Installation – 2nd Floor – Area B

Page 60: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

HVAC Insulation – 2nd Floor – Area B

Page 61: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Light Fixture Installation – Stair 2 – Area B

Page 62: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Final Cleaning of Classrooms – 2nd Floor – Area B

Page 63: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 2nd Floor - Area B

Work Completed• Plumbing Rough In• Plumbing Insulation Installation• Restroom Plumbing Fixture Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls • GRD Installation• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Clock Installation • Telecommunication Wiring• Wire Molding Installation• Sprinkler Piping Installation• Sprinkler Head Installation• Interior Door Frame Installation• Drywall Installation

Work in Progress• Countertop Sink Installation• Classroom Final Cleaning

• Block Filler• Cement Board Installation• Window Installation• Wood & Metal Door Installation• Locker Bases• Ceramic Tile Installation• Painting• Drywall in Stairs 1 & 2• Ceiling Grid Installation• Casework Installation• Marker & Tack Board Installation• VCT Installation• Rubber Base Installation• Locker Installation• Window Sill Installation• Mini Blind Installation• Glazing• Toilet Partition Installation• Signage Installation

• Ceiling Tile Installation• Toilet Accessory Installation

Page 64: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

1st Floor - Area C

Page 65: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

VCT Installation – 1st Floor - Area C

Classroom Corridor

Page 66: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Tile Installation – 1st Floor - Area C

Page 67: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

GRD Installation – 1st Floor - Area C

Page 68: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 1st Floor - Area C

Work Completed• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Cable Tray Installation• Telecommunication Wiring• Wire Molding Installation• Clock Installation• Plumbing Rough In• Plumbing Insulation Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls• GRD Installation • Sprinkler Piping Installation• Sprinkler Head Installation

• Casework Installation• Glazing

• Interior Door Frame Installation• Stair Installation• Handrailing Installation – Stair 3• Drywall Installation• Block Filler• Window Installation • Ceiling Grid Installation• Locker Bases• Locker Installation• Marker & Tack Board Installation• Window Sill Installation• Metal & Wood Door Installation• VCT Installation• Painting• Signage Installation

Work in Progress• Rubber Base Installation• Ceiling Tile Installation

Page 69: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

2nd Floor - Area C

Page 70: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Locker Lock Installation – 2nd Floor – Area C

Page 71: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Handrail Painted – Stair 3 – Area C

Page 72: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Countertop Installation – 2nd Floor - Area C

Page 73: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Tile Installation – 2nd Floor - Area C

Page 74: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Grid & Tile Installation – Stair 3 - Area C

Page 75: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Light Fixture Installation – Stair 3 - Area C

Page 76: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 2nd Floor - Area C

Work Completed• Plumbing Rough In• Plumbing Insulation Installation• HVAC Piping Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls • GRD Installation• Electrical Rough In• Electrical Device Installation• Light Fixture Installation• Clock Installation • Telecommunication Wiring• Wire Molding Installation• Sprinkler Piping Installation• Sprinkler Head Installation• Interior Door Frame Installation• Drywall Installation

Work in Progress• Countertop Sink Installation• Classroom Final Cleaning

• Block Filler• Window Installation• Wood & Metal Door Installation• Locker Bases• Ceramic Tile Installation• Painting• Drywall in Stair 3• Ceiling Grid Installation• Casework Installation• Marker & Tack Board Installation• VCT Installation• Rubber Base Installation• Locker Installation• Window Sill Installation• Mini Blind Installation• Glazing• Signage Installation

• Ceiling Tile Installation

Page 77: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

1st Floor - Area D

Page 78: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Metal Door Installation – Area D

Page 79: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ceiling Grid Installation – Area D

Page 80: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Painting – Corridor A128

Page 81: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Epoxy Painting of Auditorium Floor - Area D

Page 82: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Wood Panel Installation - Auditorium – Area D

Page 83: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Acoustical Panel Installation - Auditorium – Area D

Page 84: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Auditorium Chair Installation – Area D

Page 85: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Glass Railing Installation - Auditorium - Area D

Page 86: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Display Case Installation – Area D

At Gym

At Auditorium

Page 87: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Locker Number Installation – Locker Rooms – Area D

Page 88: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Toilet Partition Installation – Area D

Page 89: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Toilet Accessory Installation – Area D

Page 90: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Gym Equipment Installation – Area D

Page 91: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Light Fixture Installation – Auditorium – Area D

Page 92: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Light Fixture Installation – Area D

Page 93: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Gym Sound System Installation – Area D

Page 94: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Electrical Connections for Gym Equipment Controls – Gym – Area D

Page 95: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ductwork Installation – Gym - Area D

Page 96: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ductwork Painted – Gym - Area D

Page 97: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Ductwork Insulation – Area D

Page 98: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

HVAC Piping Insulation – Area D

Page 99: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Plumbing Fixture Installation – Locker Rooms – Area D

Page 100: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Interior Work Progress – 1st Floor - Area DWork Completed• Electrical Rough In• Gym Speaker Installation• Gym Sound System Installation• Plumbing Rough In• Plumbing Piping Insulation• Plumbing Fixture Installation• HVAC Piping Installation• Sprinkler Piping Installation• Rolling Grille Installation• Locker Bases• Locker Installation• Translucent Panel Installation

Work in Progress• Light Fixture Installation• HVAC Ductwork Installation• HVAC Insulation Installation• HVAC Controls• Sprinkler Head Installation• Painting• Stage Equipment Installation• Exterior Door Installation

• Window Installation• Cement Board Installation• Support for Acoustical Panels• Auditorium Acoustical Panel Installation• Auditorium Chair Installation• Locker Installation• Bulkhead Installation• Interior Door Frame Installation• Block Filler• Drywall Installation• Toilet Partition Installation• Display Case Installation

• Wood & Metal Door Installation• Ceiling Grid Installation• Auditorium Wood Panel Installation• Ceramic Tile Installation• Gym Equipment Installation• Toilet Accessory Installation• Signage Installation

Page 101: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Signage Through Building

Page 102: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Electrical Devices Through Building

Page 103: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Metal Panel Installation – Around Building

Page 104: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Signage Around Building

Page 105: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Generator Set & Startup

Page 106: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Concrete Sidewalks – East & South of High School

Page 107: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Concrete Steps at Fitness Center

Page 108: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Retaining Walls 4A & 4B Installation

Page 109: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Concrete Curb Installation

Page 110: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Sitework – Ram Drive

Page 111: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Milling Asphalt – East Side of Ram Drive

Page 112: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Asphalt Binder Course – East of Middle & High Schools

Page 113: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Asphalt Binder Course – Ram Drive

Page 114: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Asphalt Binder Course – Tennis Court

Page 115: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Stormwater Piping – Ram Drive

Page 116: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

Light Pole Installation along Ram Drive

Page 117: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

• Continue Exterior Door Installation• Complete HVAC Ductwork Installation• Countertop Sink Installation • Complete Food Service Equip. Installation• Finish Ceiling Grid Installation – Area D• Touch Up Painting• Flooring Installation – Area D• Complete Ceiling Tile Installation – Areas

A, B, & C• Continue EIFS Installation at Entrances• Finish Gym Equipment Installation• Gym Wood Floor Installation• Stage Floor Installation

Scheduled Work for Next Few Weeks

• Continue Metal Door Installation• Continue Wood Door Installation• Continue Countertop Installation• Continue GRD Installation• Complete Window Sill Installation• Finish Toilet Partition Installation• Continue Toilet Accessory Installation• Continue Site Concrete• Complete Ram Drive Work• Asphalt Paving • Continue Installing Topsoil• Site Landscaping

Page 118: Project Slideshow August 5, 2017 - Ringgold School District · 2017-08-07 · Project Slideshow August 5, 2017. Aerial Photo – Overall Site from the South Provided by Hudson Group

The End

Provided by Hudson Group – Taken 7.29.2017