project scheduling
TRANSCRIPT
How to schedule our project
Work Breakdown Structure
Visually breaks down project scopeo Projecto Subprojectso Work packageso Activities / Tasks
Work Breakdown Structure
Work Breakdown StructureStartup project
Procurement HR Shipping Maintenance Providing service Final report
Dependencies
Dependencies will gives up the
logical flow of the project and
ultimately they allow us to find out
the duration of our project
Dependencies structure matrix
Procurement HR Shipping Maintenance Providing service Final report
Procurement
HR
Shipping
Maintenance
Providing service
Final report
activity Description Predecessors
1 Procurement -
2 HR -
3 Shipping 1
4 Maintenance 3
5 Providing service 2,4
6 Final report 5
Startup
HR
Procurement
Shipping
Maintenance
Providing service
Final report
End
Type of Dependencies
Finish Start Finish Finish
Start Start
Start Finish
Duration activity Description Predecessors Estimated
Duration (weeks)
1 Procurement - 6
2 HR - 4
3 Shipping 1 1
4 Maintenance 3 1
5 Providing service 2,4 16
6 Final report 5 2
Duration obstacles
• Parkinson’s Law• Student’s Syndrome• Overconfidence• Biases
AnchoringConfirmation
Overconfidence
Startup
HR
Procurement
Shipping
Maintenance
Providing service
Final report
End
Duration diagram
Longest path 26 weeks
Critical path
• The critical path is the longest chain, the longest path of activities in our network :
• The project duration, defined by the length of the critical path, is also known as makespan.
• A delay in any activity along the critical path will cause a delay in the project.
• The method was developed by Engineers at DuPont Corporation in the 1950s.
Startup
HR
Procurement
Shipping
Maintenance
Providing service
Final report
End
0
0 6
87
2426 2624
8
76
0 4
Early start – Early Finish
Startup
HR
Procurement
Shipping
Maintenance
Providing service
Final report
End
262624248
8776
84
60
0
Late finish – Late start
Startup
HR
Procurement
Shipping
Maintenance
Providing service
Final report
End
0
0 6
87
2426 2624
8
76
0 4
262624248
8776
84
60
0
ASAP & ALAP
TIME COST
As Soon As Possible
As late As Possible
Gantt Chart One of tools that used to schedule the project by using MS Project
Project Crashing• Project duration can be reduced only by shortening critical activities.
• It may be worth spending money to reduce the length of a project: Select the
least expensive to crash
• New critical paths may emerge: reduce all critical paths!
As a Result of Project Crashing• Critical path
o Shortero May changeo More activities may become critical
• Higher risk?
• WBSAvailable? Complete? Communicated? Agreed-upon?
• Network DiagramOne start and one finish? All activities with predecessors or successors?
• MilestonesOne start milestone and one project completion milestone?
Intermediate milestones? Each one has a critical path?
• Gantt-chartNo missing dependencies between activities in correct sequence?
No summary task links? Tasks with excessive durations?
Check generalized dependencies (overlaps, time lags), Check critical path: from project start to finish?
Scheduling Checklist
Thank you