project report (transient analysis)
TRANSCRIPT
-
8/11/2019 Project Report (Transient Analysis)
1/86
FINAL REPORT
PRESSURE TRANSIENT
ANALYSIS PROJECT
July 05
th
, 2011 - Noveme! 05
th
,2011
LE"#A$A PEN$A#%IAN
"ASYARA&AT
-
8/11/2019 Project Report (Transient Analysis)
2/86
UNI'ERSITAS ISLA" RIAU
(LP"-UIR)
PREFACE
Pressure transient Analysis project has completed study of
Area 456, well testing data based on contract number C88008,
between !embaga Pengabdian "asyara#at $ %ni&ersitas 'slam
(iau )!P"*%'(+ and P- Che&ron Paci.c 'ndonesia )P- CP'+- he
wor# was conducted since /uly 6th, 0 until 1o&ember 5th,
0-
he project team would li#e to than# to P CP', which
pro&ides an opportunity to carry out this project- his .nal report
consists of hard copy and soft copy that is presented as part of
the contract-
Pe#anbaru, 1o&ember
0
#u!h*+u+, SE, ".S
%!e/to! LP"-UIR
-
8/11/2019 Project Report (Transient Analysis)
3/86
CONTENTS
P(23AC2----------------------------------------------------------------------------------------ii
C121------------------------------------------------------------------------------------iii
!' 3 3'%(2-----------------------------------------------------------------------------&
!' 3 A7!2-----------------------------------------------------------------------------&iii
22C%'92 %""A(:-------------------------------------------------------------------;
C
-
8/11/2019 Project Report (Transient Analysis)
4/86
>- "ethodology PA of 3all o est-----------------------------------------
.2.1 P'T *+ Pet!o4hy/ %*t*..............................................15
.2.1 6ell Tet+7 %*t*...................................................................16
.2. o!+e! Plot A+*ly U+7 E/!+ v3.12.08
(S*4h!).....................................................................................................19
.2.3 %*7+ot/ A+*ly...............................................................20
.2.5 Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC")..................21
>-> "ethodology PA of Pressure 7uild %p )P7%+ est-------------
..1 P'T *+ Pet!o4hy/ %*t*..............................................23
..2 6ell Tet+7 %*t*...................................................................23
..2 "*+u*l o!+e! Plot A+*ly...........................................25
.. o!+e! Plot A+*ly U+7 E/!+ v3.12.08
(S*4h!).....................................................................................................26
..3 %*7+ot/ A+*ly...............................................................28
..5 Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC")..................30
>-4 tatic 7ore -5
C5
4- 3all* est------------------------------------------------------------------------>5
4- Pressure 7uild %p est--------------------------------------------------------4
4-> tatic 7ore
-
8/11/2019 Project Report (Transient Analysis)
5/86
3.3.3 Shut + Tme Re/omme+*to+......................................65
C
-
8/11/2019 Project Report (Transient Analysis)
6/86
3igure 4-4 =irect "easurement Pressure =ata at A*and----------46
3igure 4-5 =irect "easurement Pressure =ata at 7*and----------46
3igure 4-6 =irect "easurement Pressure =ata at 7*and----------4@
3igure 4-@ =irect "easurement Pressure =ata at =*and-----------4@
3igure 4-8 abulation #in of A*and-----------------------------------------5>
3igure 4-D abulation #in of A*and-----------------------------------------5>
3igure 4-0 abulation #in of 7*and---------------------------------------54
3igure 4- abulation #in of 7*and---------------------------------------54
3igure 4- abulation #in of =*and-----------------------------------------55
3igure 4-> abulation #in of *and-----------------------------------------56
3igure 4-4 abulation #in of All and---------------------------------------56
3igure 4-5
-
8/11/2019 Project Report (Transient Analysis)
7/86
LIST OF TA#LE
able >- the =etails 'n&alid of ?C 3---------------------------------------6
able >- the =etails 9alid of ?C 3------------------------------------------@
able >-> the =etails 'n&alid of ?C P7%---------------------------------------@
able >-4 the =etails 9alid of ?C P7%------------------------------------------@
able >-5 !ist Eell 'n&alid of ?C P7%-------------------------------------------8
able >-6 the (esult of ?C 7-@ the (esult of ?C -8 the =etails of 'n&alid -D Petrophysics =ata of >=*6> )area 05+, A*and-----------
able >-0 P9 =ata of >=*6> )area 05+, =*and------------------------
able >- /ob !og perator of >=*6> )area 05+, =*and------------4able >- =*6> )area 05+, =*and
---------------------------------------------------------------------------------------------5
able >-> =*6>
)area 05+-------------------------------------------------------------------------------@
able >-4 =iagnostic Analysis (esult of >=*6> )area 05+, =*and
---------------------------------------------------------------------------------------------8
-
8/11/2019 Project Report (Transient Analysis)
8/86
able >-5 elected Analytical "odels in aphir of >=*6> )area
05+, =*and---------------------------------------------------------------------------D
able >-6 Automatic ype Cur&e "atching )AC"+ (esult of >=*
6> )area 05+--------------------------------------------------------------------------D
able >-@ Petro physics =ata of 4A*6D )Area 06+ 7*and--------->0
able >-8 Eell est
able >-0 5
able >- =iagnostic Analysis (esult of 4A*6D )Area 06+ 7*and
--------------------------------------------------------------------------------------------->6
able >- Automatic ype Cur&e "atching )AC"+ (esult of 4A*
6D )area 06+-------------------------------------------------------------------------->8
able >-> !ist well of
able 4- (esult 3 at A*and-------------------------------------------------44
able 4-> (esult 3 at 7*and-------------------------------------------------45
able 4-4 (esult 3 at 7*and-------------------------------------------------46
able 4-5 (esult 3 at =*and---------------------------------------------------4@
able 4-6 (esult 3 at *and---------------------------------------------------4@
able 4-@ (esult P7% at A*and-------------------------------------------------48
able 4-8 (esult P7% at A*and-------------------------------------------------4D
able 4-D (esult P7% at 7*and-------------------------------------------------50
able 4-0 (esult P7% at 7*and-----------------------------------------------5
able 4- (esult P7% at =*and-------------------------------------------------5
able 4- =etail of 3 and P7% est----------------------------------------55
able 4-> =etail Con.dence of 3 and P7% est----------------------5@
able 4-4 Complete Eell------------------------------------------------------------56
-
8/11/2019 Project Report (Transient Analysis)
9/86
able 4-5 Complete est =istribution-----------------------------------------56
able 4-6 hut in time 3 and P7%------------------------------------------@
Appendi; "iddle Con.dence of 3----------------------------------------@@
Appendi; 4 Con.dence f P7%---------------------------------------------------@8
SU""ARY
Pressure ransient Analysis is one of methods to obtain
reser&oir parameters surrounding wellbore, such asG
permeability, s#in, coeHcient of wellbore storage, reser&oir
pressure and reser&oir boundary- 7est e&aluation can be obtained
if it is supported by complete data- his study includes 3all*
est )3+, Pressure 7uild up est )P7%+, tatic 7ottom
-
8/11/2019 Project Report (Transient Analysis)
10/86
pecially for the analysis of 3 and P7%, the project team
used 2crin software 4--06 &ersion- Assumptions used in this
analysis are homogeneous, radial Jow, and in.nite acting
reser&oir-And the result of 3 and P7% test, the a&erage of
pressure, s#in, permeability, and wellbore storage can be seen in
the tables- he permeability and s#in at 7*and is highest and
*sand is lowest- Project time recommends the a&erage of shut*in
time is > hours fot 3 and @ hours for P7% test
7
-
8/11/2019 Project Report (Transient Analysis)
11/86
measuring the pressure change &ersus time in one or more wells
in the reser&oir-
1.1#*/97!ou+
'n&estment in Petroleum industry reBuires a high technology,
high ris# as well as high cost- herefore in order to ha&e right
decision, it is &ery important to use good planning and supported
by accurate data- therwise, the in&estment will be useless
without signi.cant result- 3or e;ample, the accurate data is
necessary for well stimulation or determine of injection &olume-
3irst, the project team needs to #now well characteristics such as
permeability, s#in, Jow eHciency, radius in&estigation, boundary,
fault presence in around of wellbore and bottom hole pressure-
7ased on that case, the project team needs a method to get
mentioned parameters, such as pressure build up, fall o test,
hall plot and static bottom hole pressure- 2ach method will gi&e
same parameters such as abo&e, e;cept
-
8/11/2019 Project Report (Transient Analysis)
12/86
of science technology- 3inally, this cooperation carried out at the
ne;t time, and the human resources de&elopment at the
uni&ersity will be better in the future-
1.2O:e/tve
As an e&aluation of A456 3 and P7% data
As a reference in the current design of 3 and P7% test for
the ne;t job
o optimiIe of 3 and P7% job in area 456 in the future
o get of update reser&oir pressure database with most recent
direct measurement points
o &isualiIe historical trend of each producti&e layer
)historical chart and contour map+
CAPTER II $ENERAL
INFOR"ATION
$ENERAL INFOR"ATION
2.1 U+ve!t* Il*m R*u (UIR)
he College is better #nown as %'(, founded by :!P' (iau
eptember 4th, D6 and inaugurated by "inister of (eligious
-
8/11/2019 Project Report (Transient Analysis)
13/86
Aairs as outlined in the charter which was signed on April 8th,
D6>-
9ision of the 'slamic %ni&ersity f (iau
'slamic %ni&ersity f (iau Making a superior Riau Islamic
University and Leading In Southeast Asia In 2020
"ission of the 'slamic %ni&ersity f (iau
a- Pro&ide education and Buality research to support national
de&elopment
b- Community ser&ice that is consistent with the philosophy of
the uni&ersity
c- row and de&elop a healthy academic life and to build
de&elopment of science, technology, and humanities with an
insight into the islamitation and the 'ndonesian
d- Play an acti&e role in creating ci&il campus by optimiIing
e;isting resources
he goal of 'slamic %ni&ersity of (iau is to build a human being
&irtuous and sincere throughout the teachings of 'slam, a capable
and ha&e the con&iction, is responsible for the welfare of the
'ndonesian people, especially the world generally in the practice
of science, technology and art and too# oHce in order to remain
faithful to Allah and
-
8/11/2019 Project Report (Transient Analysis)
14/86
and mission of the %'( as its parent institution that has made %'(
9ision 00-
As stated in the statutes of the %'( 9ision 00 isG !eing a
superior Islamic University and leading in Southeast
Asia"
'n connection with the !P" %'( formulate 9''1 00 as followsG
"L#M $ecomes a$sor$er as relia$le science and
technology %or rural communities o% Southeast Asia in2020"
his &ision is e;pressed with the sloganG
"Science in the service and devolution to science"
o achie&e that &ision !P" %'( has mission as followsG
a- =e&elop a more resilient institutional !P"
b- 7eing a facilitator for the de&elopment of academic %'(
application of science and technology-
c- =irecting, implement, coordinate, monitor and access the
implementation of community ser&ice acti&ities by academics
%'(-
d- o de&elop programs for the utiliIation of science and
technology, religion and socio*cultural for humans and the
en&ironment-
As an element of academic e;ecutor has the tas# of !P"G
a- upport the &ision and mission in the 00 %'( aspects of
de&olution to community-
b- Assist the (ector in planning, implementing and controlling the
acti&ities of community ser&ice
-
8/11/2019 Project Report (Transient Analysis)
15/86
c-
-
8/11/2019 Project Report (Transient Analysis)
16/86
CAPTER III TRANSIENT ANALYSIS TEORY
P!eu!e T!*+e+t A+*ly Stuy
ransient well testing is a reser&oir description and e&aluation
method used to obtain dynamic reser&oir properties- 't is a
&aluable tool that, li#e all other indirect determination methods,
should be used with understanding of the physical concepts
behind well testing and succeeds non uniBueness of the
solutions- ransient well testing should be used with complete
understanding of the geological and operational aspects of the
.eld- 't is often necessary to run se&eral types of transient tests
and integrate their result with other characteriIation methods to
obtain a &alid description of the reser&oir- 'nterpretation of well
test relies on identifying &arious Jow regimes, calculating initial
reser&oir system properties from these Jow regimes and history
matching the entire test using an appropriate reser&oir model,
the initial estimates and regression analysis- "ost of the models
currently in use are analytical but the technology is mo&ing
towards the use of numerical modeling-
ransient testing is the general case that encompasses
measurement of Jow rates and pressure under &arious
conditions- Assume a well is producing oil at a constant rate of B7= for a period of tphours- 'f the well is shut*in, the bottom
hole pressure of the well will be decrease )draws down+ as
production begins and will increase )build up+ when the well is
shut*in-
-
8/11/2019 Project Report (Transient Analysis)
17/86
a noisy e;periment that may be run to indirectly determine the
dynamic reser&oir properties->
.1 u*lty Co+t!ol %*t*
=ata from user )P CP'+ must be passed ?C process before it
can be analyIed- his data is categoriIed based on type of the
test, i-e- P7% analysis, 3 analysis, 7
-
8/11/2019 Project Report (Transient Analysis)
18/86
7h u*lty%*t*
Re4o!t P!eu!eT!*+e+t A+*ly
St*!t P!eu!eT!*+e+t A+*ly
Co+;!m to CPITo 7et /om4lete*t* e to!y P
? T 4lot, P!eu!e
%e!v*tve Ch*!t,
o!+e!
$*the!+7%*t*
-
8/11/2019 Project Report (Transient Analysis)
19/86
F7u!e .1 u*lty Co+t!ol %*t* Flo= Ch*!t
T*le .1 the %et*l I+v*l o< C FOT
3rom the table abo&e, has 84 data, total in&alid >@ data-
'n&alid or couldnLt analyIe becauseG
* > case duplicate* @ case *and, dropped by user* @ two layer* >6 cases 1o (ow data, presence dierent data between job log
and as .le-* 8 case Eellbore =ynamic, if occur change pressure because
of presence wellbore dynamic, so this is associated with
wellbore pressure, not reser&oir pressure-* cases 3 too early, if test too early process-* 5 incomplete job or failure 3P7% test- Problem when
running the test, such as memory gauge canLt go down-
he ne;t analyIed the project teams found out some of wells in
two or three areas- 't caused by G* Erong copy data to area )from original data+* 1othing information at job log* Change status sand area ) layer be multi*layer+* After the ne;t analyIed, the project team found if the original
data has dierent row data, and ne;t learn, the project team
got if data actually was not &alid or wellbore dynamic- o total
in&alid data became 4@, and remaining >@ is &alid data- Ee
will see at the table >- for the &alid data-
-
8/11/2019 Project Report (Transient Analysis)
20/86
T*le .2 the %et*l '*l o< C FOT
.1.2 C P#U
3or P7% data, the project team recei&ed .rst data as muchas > set data, and the second data as much as 5 set data, so
total all of them are >@ set data- he project team analyIed, and
found out 6 in&alid data at st data, two of them is elisa*sand
and in&alid data at the second data- he project team can see
at table >->, table >-4, and table >-5 to more details-
T*le . the %et*l I+v*l o< C P#U
T*le .3 the %et*l '*l o< C P#U
-
8/11/2019 Project Report (Transient Analysis)
21/86
T*le .5 Lt 6ell I+v*l o< C P#U
.1. C S#P
?C 7
-6- 3rom the table, the project team get information
total Eell is 4, total set data is 46, which could analyIed is >6
data and couldnLt AnalyIed is 6 data
T*le .8 the Reult o< C S#P
.1.3 C *ll Plot
3or
-
8/11/2019 Project Report (Transient Analysis)
22/86
According to this article, the e;amination of the -8
T*le .@ the Reult o< C *ll Plot
T*le . the %et*l o< I+v*l *ll Plot
.2 "ethoolo7y PTA o< F*ll oB Tet
A fall o test is meassuring the pressure decline subseBuentto the closure of an injection- 't is conceptually identical to a
build up test- As with injection test, fall o test interpretation is
more diHcult if the injected Juid is dierent from the original
reser&oir Juid-4
bjecti&e 3all o estG determine Permeability, s#in around
injection well, Jow eHciency and static reser&oir pressure- 'n the
operation of a waterJood program, it becomes necessary to
4"odern Eell est Analysis
-
8/11/2019 Project Report (Transient Analysis)
23/86
determine injection capacity through the e&aluation of indi&idual
injection well performance- Eith the occurrence of a decrease in
a particular wellLs injection, and need arises for a direct
calculation of capacity loss or wellbore damaged-
(eser&oir undergoing water Jooding for a long period of time
ha&e a larger area around the injection wells at the residual oil
saturation )i-e-, only water is Jowing+- 3all o test in these wells
are &ery similar to buildup tests which were discussed earlier
e;cept that water is the single Jowing phase and we usually
ha&e a constant pressure outer boundary around these wells
)since they are usually surrounded by producers+-
'n the course of normal operations then, a pressure fall*o
test is usually run on the problem well to determine the e;istence
and e;tent of damage- hese test are lengthy, time consuming
and costly- he proposed method of e&aluation can yield
indications of the e;tent and nature of injection loss without the
use of fall*o tests- he method presented in&ol&es the
interpretation of routine monthly injection data for all reBuired
calculations and eecti&ely eliminates con&entional testing
procedures in a normal water Jooding program-
3igure >-> is methodology of P7% and 3- Commonly, the
project team begin from MstartN and plot data using manual
calculation with e;cel- hen e&aluate manual result by
-
8/11/2019 Project Report (Transient Analysis)
24/86
F+*l
Reult
Ev*lu*te Tet y
E/!+ v3.12.08
Co+/luo+Re/omme+*t
o+
START
Plot %*t* U+7m*+u*l /*l/ul*to+
=th E/el
Ev*lu*te "*+u*lReult
y o!+e! Plot
I+4ut %*t* to E/!+v3.12.08
"*9e C*!te*+ PlotReult D &, S, !, C,
P, et/
Com4*!e "*+u*lReult *+ E/!+
Reult
END
-
8/11/2019 Project Report (Transient Analysis)
25/86
F7u!e .2 "ethoolo7e o< P#U *+ FOT Flo= Ch*!t
o clearly, the project team ta#e one case at =ell %-8 (*!e*
05), %-S*+
.2.1 P'T *+ Pet!o4hy/ %*t*
his section discusses basic data pro&ided by CP' that used
in the well test interpretation- he data was gi&en by CP' and
used in the well test interpretation- he petrophysics data was
also pro&ided by CP' where the &alue of the reser&oir thic#ness
based on the oil net pay of sand- he petrophysics data isshown in table >-D
T*le . Pet!o4hy/ %*t* o< %-8 (*!e* 05), A1-S*+
he summary of the P9 data is listed intable >-8
T*le .10 P'T %*t* o< %-8 (*!e* 05), %-S*+
-
8/11/2019 Project Report (Transient Analysis)
26/86
.2.1 6ell Tet+7 %*t*
he well test operation in >=*6> Area 05 of =*and is
conducted o&er the and with the perforation inter&al
>0*>4 ft 9= at @ in (7P Pac#ers hangO00 ft- he total
length of perforation inter&al was 4 ft in 9=- he fall o
period lasted for > hours- he details seBuence of e&ents of the
well testing operation can be seen in able >-- he well test
history plot and operator job log is shown in the .gure >-4
-
8/11/2019 Project Report (Transient Analysis)
27/86
F7u!e . to!y Plot P!eu!e (P), Lu R*te (ST#G%) v Tme
(h!)
3igure >-> is recorded pressure data plot- 't is will be used to
e;amine wellbore dynamic- Eellbore dynamic is anything that
happened in or near the wellbore that will aect the recorder
pressure- "any, but not all, o these MwellboreN transients occur
at &ery early time- heir detection and documentation has been
facilitated by the ad&ent of electronic pressure recorders- hese
recorders are so accurate that they will detect these wellbore
eects &ery clearly, and can easily be misinterpreted as
Mreser&oirN eect- 'ndeed, the whole thrust of our .eld of
engineering is to interpret the Mreser&oirN, by using pressures
recorded in a MwellboreN- his often places the reser&oir and the
wellbore in a tug*of*war, and the project team .nd that, &ery
often, MwellboreN transients will distort, or e&en, dominate our
Mreser&oirN transient- his is not surprising in &iew of the fact that
in this tug*of*war, the wellbore has a distinct ad&antage o&er the
-
8/11/2019 Project Report (Transient Analysis)
28/86
reser&oir because this highly sensiti&e recorder is sitting in the
wellbore and not in the reser&oir-Eellbore dynamic can be caused by many factor, such as
!iBuid 'nJu; 2u;, phase (edistribution, Eellbore )and near
wellbore+ Clean*%p, dierences between drawdown and build up,
plugging, recorder eects and mysterious eects- he .rst thing
we should do when analyIe fall o test is e;amining this wellbore
dynamic phenomena-
T*le .11 Jo Lo7 O4e!*to! o< %-8 (*!e* 05), %-S*+
.2.2 "*+u*l o!+e! Plot A+*ly
3irst of step, determine s#in &alue, permeability, and other
parameters, using manual -4 and table >-
-
8/11/2019 Project Report (Transient Analysis)
29/86
T*le .12 o!+e! Plot A+*ly Reult o< %-8 (*!e* 05), %-S*+
F7u!e .3 "*+u*l o!+e! Plot A+*ly o< %-8 (*!e* 05), %-S*+
-
8/11/2019 Project Report (Transient Analysis)
30/86
.2. o!+e! Plot A+*ly U+7 E/!+ v3.12.08 (S*4h!)
econd of step, determine s#in &alue, permeability, and
other parameters, using -5 and able >->
F7u!e .5 o!+e! Plot A+*ly =th So
-
8/11/2019 Project Report (Transient Analysis)
31/86
.2.3 %*7+ot/ A+*ly
1e;t of step, determine s#in &alue, permeability, and other
parameters, using =iagnostic Analysis with 2crin &4--06
)aphir+, it can be seen in 3igure >-6 and table >-4 below
1E-4 1E-3 0.01 0.1 1,ime QhrR
1
10
100
Pressure
F7u!e .8 %*7+ot/ A+*ly o< %-8 (*!e* 05), %-S*+
T*le .13 %*7+ot/ A+*ly Reult o< %-8 (*!e* 05), %-S*+
-
8/11/2019 Project Report (Transient Analysis)
32/86
.2.5 Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC")
7ased on 3low (egime 'denti.cation analysis, below table is
Analytical "odel that selected in FAPPA aphir"oftware- !ast of
step, determine s#in &alue, permeability, and other parameters,
using Automatic ype Cur&e "atching with 2crin &4--06
)aphir+, it can be seen in 3igure and able below-
F7u!e .@ Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC") o< %-8 (*!e* 05)
T*le .15 Sele/te A+*lyt/*l "oel + S*4h! o< %-8 (*!e* 05), %-
S*+
T*le .18 Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC") Reult o< %-8
(*!e* 05)
-
8/11/2019 Project Report (Transient Analysis)
33/86
. "ethoolo7y PTA o< P!eu!e #ul U4 (P#U) Tet
'n a build up test, a well which is already Jowing ideally at
constant rate+ is shut in and the downhole pressure is measured
as the pressure build up- Analysis of build up test often reBuires
only slight modi.cation of the techniBues used to interpret
constant rate drawdown test- he practical ad&antage of a build
up test is that the constant Jow rate condition is more easily
achie&ed )since the Jow rate is Iero+- 7uild up test also ha&e
disad&antagesG
- 't may be diHcult to achie&e the constant rate production
prior to the shut in- 'n particular, it may be necessary to close
the well brieJy to run the pressure tool into the hole
- Production is lost while the well is shut in
bjecti&e analysis P7% is to determineG
Permeability absolute and permeability eecti&e roc#
formation
#in 3actor
3low 2Hciency
-
8/11/2019 Project Report (Transient Analysis)
34/86
P initial and P a&erage at reser&oir
9olume radius in&estigation
pace sector fault from well
"ethodology P7% already e;plain in .gure >->- for further, the
project team ta#e one case at=ell3A-8 (*!e* 08) #2-S*+-
..1 P'T *+ Pet!o4hy/ %*t*
his ection discusses basic data pro&ided by P- CP' that
used in the well test interpretation- he P9 data was gi&en byP- CP' and used in the well test interpretation- he summary of
the P9 data is listed in table >-0- he petro physics data also
pro&ided by P- CP', where the &alue of the reser&oir thic#ness is
based on the oil net pay of >D0 sand- he petro physics data it
shows by table >-@
T*le .1@ Pet!o 4hy/ %*t* o< 3A-8 (A!e* 08) #2-S*+
..2 6ell Tet+7 %*t*
he well test operation in 4A*6D Area 06 of 7*and is
conducted o&er the >D0 and with the perforation inter&al4@*4 ft 9= at @ in (7P Pac#ers hangO>8@-@4 ft- he
total length of perforation inter&al was 5 ft in 9=- he build
up is conducted after the cleanup processK the buildup period
lasted for 6 hours- he details seBuence of e&ents of the well
testing operation can be seen in .gure >-8 and table >-8
-
8/11/2019 Project Report (Transient Analysis)
35/86
T*le .1 6ell Tet to!y Plot o< 3A-8 (A!e* 08) #2-S*+ *t "*!/h
0, 2011
-
8/11/2019 Project Report (Transient Analysis)
36/86
F7u!e . 6ell Tet Seue+/e o< Eve+t
..2 "*+u*l o!+e! Plot A+*ly
3irst of step, determine s#in &alue, permeability, and other
parameters, using manual -0 and table >-D
-
8/11/2019 Project Report (Transient Analysis)
37/86
F7u!e . "*+u*l o!+e! Plot A+*lye
T*le .1 "*+u*l o!+e! Plot A+*ly Reult o< 3A-8 (A!e* 08) #2-
S*+
.. o!+e! Plot A+*ly U+7 E/!+ v3.12.08 (S*4h!)
econd of step, determine s#in &alue, permeability, and
other parameters, using - and table >-0
-
8/11/2019 Project Report (Transient Analysis)
38/86
F7u!e .10 o!+e! Plot A+*ly =th So
-
8/11/2019 Project Report (Transient Analysis)
39/86
T*le .20 o!+e! Plot A+*ly Reult =th So- and table >-
F7u!e .11 %*7+ot/ A+*ly
-
8/11/2019 Project Report (Transient Analysis)
40/86
he type cur&e at figure abo&e show the log log plot of log )Sp+
and deri&ati&e &s- log )St+- he deri&ati&e shown is the absolute
&alue of the slope of the semi log plot, but plotted on the log log
plot- here are many information that the project team can get
from this type cur&e that isG
* Ehen the data is in the straight line with slope , it is wellbore
storage- he project team #nows nothing about the reser&oir-
* Ehen the model becomes a straight line in semi log plot, the
deri&ati&e becomes a horiIontal line- 't show the in.nite acting
reser&oir
* 3rom this Jow regime, the project team can get permeability of
the reser&oir
* he separation between the two cur&es can tell us the &alue of
damage of reser&oir )s#in+
* Ehere the Jat ends and ta#e o, it show the boundary of the
reser&oir
* 'f increasing e;treme end cur&e is boundary dominated Jow
regime- his Jow regime indicates the shape of the reser&oir
boundary- 3rom this, the project team can learn about how far
is the boundary and #now the drainage area of this well-
T*le .21 %*7+ot/ A+*ly Reult o< 3A-8 (A!e* 08)
#2-S*+
-
8/11/2019 Project Report (Transient Analysis)
41/86
..5 Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC")
7ased on 3low (egime 'denti.cation analysis, the table
below is Analytical "odel that selected in FAPPA aphir"
oftware-
T*le .22 Sele/te A+*lyt/*l "oel + S*4h! o< 3A-8 (A!e* 08) #2-
S*+
!ast of step, determine s#in &alue, permeability, and other
parameters, using Automatic ype Cur&e "atching with 2crin
&4--06 )aphir+, it can be seen in .gure >-> and table >->
-
8/11/2019 Project Report (Transient Analysis)
42/86
Figure 3.12 Automatic Types Curve Matching ATCM! o< 3A-8 (A!e* 08) #2-S*+
T*le .22 Autom*t/ Ty4e Cu!ve "*t/h+7 (ATC") Reult o< 3A-8
(*!e* 08)
.3 St*t/ #o!e ole P!eu!e (S#P)
"ethodology of 7
-
8/11/2019 Project Report (Transient Analysis)
43/86
- Collect data 7, hall presented a system of analyIing the
performance of injection wells using better #nown as
-
8/11/2019 Project Report (Transient Analysis)
44/86
recogniIing any formation damage as e&ident by the
accompanying drop in injecti&ity which is seen to a rise in the
slope
-
8/11/2019 Project Report (Transient Analysis)
45/86
can be used to Bualitati&ely interpret what is happening in the
reser&oir when changes occur in the slope of the cur&e-
hat is methodological
-
8/11/2019 Project Report (Transient Analysis)
46/86
b- Area 05
* 3ill up G >0 Eell 1o .ll up G >0 Eell,
c- Area 06
* 3ill up G >0 Eell 1o .ll up G Eell,
o, otal .ll upG 84 and 1o 3ill %p @
T*le .2 Lt =ell o< *ll Plot
CAPTER I'RESULT AN%ANALYSIS
RESULT AN% ANALYSIS
-
8/11/2019 Project Report (Transient Analysis)
47/86
3.1 F*ll-OB Tet
(esult con.dence of the .nal 3 test is D wells, with >@
&alid test data- 3 acBuisition location to all data can be seen at
the .gure 4-
F7u!e 3.1 FOT A/uto+ Lo/*to+
-
8/11/2019 Project Report (Transient Analysis)
48/86
he &alid tests data can di&ide into high con.dence are 50
tests, middle con.dences are D tests and low con.dence are 68
tests- Ee can see at appendi;
A1-S*+
T*le 3.1 Reult FOT *t A1-S*+
7ased on 3 test in A*and, the project teams getG
F 9alue from 45 m= until @40 m=-
#in 9alue from *0- until >0- his formation ha&e indication
damage e;cept 5C*86 )area 04+ "arch >, 008 ha&e &alue
s#in is *0-
P reser&oir is heterogenic
Eellbore storage ha&e a&erage 0-84
'ndication Eells close by fault is 4=* )area 05+ /uly , 006
A2-S*+
-
8/11/2019 Project Report (Transient Analysis)
49/86
T*le 3.2 Reult FOT *t A2-S*+
7ased on 3 test in A*and, the project teams getG
F 9alue from m= until D6@0 m=, which at 57*5 )area 06+
/anuary 0@, 00@ has &alue F only m=, because lowest rate
as compared to other wells-
#in 9alue from *>-@4 until 88-8- his formation has indication
damage e;cept 57*5 )area 06+ "arch >, 00@ ha&e &alue
s#in is *>-@4
P reser&oir is heterogeneous
-
8/11/2019 Project Report (Transient Analysis)
50/86
Eellbore storage has a&erage 0-48
'ndication Eells close by fault are >=*86 )area 05+ "ay 5,
006 and >=*86)area 05+ /uly D, 00D
#1-S*+
T*le 3. Reult FOT *t #1-S*+
7ased on 3 test in 7*and, the project team getsG
F 9alue from >8 m= until @850 m=,
#in 9alue from *4-05 until *0-08- his formation is not
damage
P reser&oir is heterogenic
Eellbore storage has a&erage 0->>
At >=*@ )area 05+ "arch , 008 ha&e F is bigger than other
well, that is @580 m=, so that con.dence this well is low
#2-S*+
7ased on 3 test in 7*and, the project teams getG
F 9alue from 45 m= until 4060 m=,
#in &alue is from *-6> until >45- his formation has
indication damage e;cept 47*>> )area 06+ "arch , 006
with s#in *-6>, 47*>> )area 06+ /anuary 08, 006 with s#in
*-84, 4C*>D )area 05+ 1o&ember @, 005 with s#in *-6, 47*
-
8/11/2019 Project Report (Transient Analysis)
51/86
>> )area 06+ "ay >0, 006 with s#in *-0D and >=*@ )area 05+
April 0, 00@ with s#in *0-0
P reser&oir is heterogeneous
Eellbore storage ha&e a&erage 0-00D
'ndication Eells close by fault are >=*8> )area 05+ ctober ,
005K >=*D8 )area 05+ "arch 6, 006K >=*8>)area 05+ "arch
@, 006K >=*D8 )area 05+ "ay 8, 006K >=*8> )area 05+ /uly
6, 006K >=*D8 )area 05+ April 0>, 00@K >=*D8 )area 05+ /uly
, 00@K >=*8> )area 05+ =ecember , 00@K 47*4 )area
06+ "arch 5, 008K >=*D8 )area 05+ "arch 8, 008K >=*D8
)area 05+ April 0>, 00D and >=*8> )area 05+ /uly , 00D
T*le 3.3 Reult FOT *t #2-S*+
-
8/11/2019 Project Report (Transient Analysis)
52/86
%-S*+
7ased on 3 test in =*and, the project teams getG F 9alue from 554 m= until 4@>0 m=,
#in 9alue from 4-> until D0- his formation ha&e indication
damage
P reser&oir is heterogenic
Eellbore storage ha&e a&erage 0-4
-
8/11/2019 Project Report (Transient Analysis)
53/86
T*le 3.5 Reult FOT *t %-S*+
S-S*+
7ased on 3 test in *and, the project teams getG
F 9alue from 406 m= until 556 m=,
#in 9alue from 0-50@ until 5-5- his formation ha&e
indication damage
P reser&oir is heterogenic
Eellbore storage has a&erage 0-4
T*le 3.8 Reult FOT *t S-S*+
3.2 P!eu!e #ul U4 Tet
(esult con.dences of P7% est are 5 wells, with >0 &alid test
data- 9alid test data can di&ide intoG high con.dences are D tests,
middle con.dences are 8 tests, and low con.dences are > tests-
P7% acBuisition location can be seen at .gure 4-
-
8/11/2019 Project Report (Transient Analysis)
54/86
F7u!e 3.2 P#U A/uto+ Lo/*to+ 0 m=-
Eells with &ery good F is 47*D5A, 5C*55, and 6=*-
#in 9alue from until - his formation tendency has
damage-
-
8/11/2019 Project Report (Transient Analysis)
55/86
P reser&oir is homogeneous-
Eellbore storage has a&erage 0-0D45-'ndication Eells close
by fault is 47*D5A )area 06+ =ecember 8, 00K 47*4
)area 06+ "arch , 0 and 3*D4 )area 05+ /une 5,
0- 'ndication Eells close by injector is 6=* )area 04+
/une 0, 0
A2-S*+
T*le 3. Reult P#U *t A2-S*+
7ased on P7% test in A*and, the project teams getG
F 9alue from 4> m= until >400 m=- Eells with &ery good F is
47*D5A, 4C*>, and 4=*@82-
#in 9alue from 0 until 64- his formation has indication
damage-
P reser&oir is homogeneous
Eellbore storage ha&e a&erage 0-080
'ndication Eells close by fault is 47*D5A )area 06+ =ecember
@, 00K 47*4 )area 06+ "arch , 0K 4C*> )area 05+
3ebruary 0>, 0 and 5C*55 )area 04+ April 0@, 0
'ndication Eells close by injector is 4=*@82 )area 04+ April 4,
0
-
8/11/2019 Project Report (Transient Analysis)
56/86
#1-S*+
T*le 3. Reult P#U *t #1-S*+
7ased on P7% test in 7*and, the project teams getG F 9alue from 55 m= until 45D0 m=- Eells with &ery good F is
47*D5A, 5C*55, and 57*DD-
#in 9alue from D-4 until >5- his formation has indication
high damage as compared to A*and and A*and-
P reser&oir is homogeneous
Eellbore storage ha&e a&erage 0-0D45
'ndication Eells close by fault is 47*D5A )area 06+ =ecember
6, 00K 47*4 )area 06+ "arch , 0K 57*DD )area 04+
April 6, 0 and 5C*55 )area 04+ April 0@, 0
'ndication Eells close by injector is 5=*D )area 04+ /une D,
0
#2-S*+
T*le 3.10 Reult P#U *t #2-S*+
-
8/11/2019 Project Report (Transient Analysis)
57/86
7ased on P7% test in 7*and, the project teams getG
F 9alue from D-@@ m= until 4D m=-
#in 9alue from *0->>6 until 80- his formation ha&e indication
damage, e;cept 4A*6D )area 06+ "arch 0>, 0 ha&e &alues#in is *0->>6-
P reser&oir is homogeneous
Eellbore storage ha&e a&erage 0-00D5
'ndication Eell close by fault is 4=*5*1P )area 05+ /uly 0@,
0
'ndication Eell close by injector is 5=*@> )area 04+ "ay 8,
0
%-S*+
T*le 3.11 Reult P#U *t %-S*+
7ased on P7% test in =*and, the project team getsG
F 9alue from 6 m= until D85 m=-
-
8/11/2019 Project Report (Transient Analysis)
58/86
#in 9alue from *-8 until @- his formation ha&e indication
damage e;cept 47*D5A )area 06+ =ecember @, 00 ha&e&alue s#in is -8
P reser&oir is homogeneous
Eellbore storage ha&e a&erage 0-04D5
'ndication Eells close by injector is 47*D5A )area 06+
=ecember @, 00 and 5=*@ )area 04+ /anuary >, 0
3. St*t/ #o!e ole P!eu!e (S#P)
3or 7 * 4-@
F7u!e 3. %!e/t "e*u!eme+t P!eu!e %*t* *t A1-S*+
3rom the .gure abo&e, we got the &alue a&erage pressure at A*
and was 555-6@, and the low was 8>-80- we got the &alue
a&erage pressure at A*and was 5>8-@>, and the low was
0>-0- we got the &alue a&erage pressure at 7*and was
54-8@, and the low was 8-86- we got the &alue a&erage
-
8/11/2019 Project Report (Transient Analysis)
59/86
pressure at 7*and was 544-4, and the low was 6>-00- we got
the &alue a&erage pressure at =*and was 6>-0D, and the low
was 68-8D-
F7u!e 3.3 %!e/t "e*u!eme+t P!eu!e %*t* *t A2-S*+
F7u!e 3.5 %!e/t "e*u!eme+t P!eu!e %*t* *t #1-S*+
-
8/11/2019 Project Report (Transient Analysis)
60/86
-
8/11/2019 Project Report (Transient Analysis)
61/86
3.3 Summ*!y "+* A358 Reult
his chapter summariIed the distribution of this e&aluation
result- 3irstly, the project team will see the distribution of the test
and the categoriIe for each areas- times- 3rom 65 wells, not all of
them belong to complete test that the project team can be use
its reser&oir parameter-
here are only 44 wells of 6@ tests that the project team
can be using it data- tests in area 05, and wells of 58 tests in area 06- 't
is not an enough number to describe reser&oir parameter of the
whole area- o, the project team can ma#e the distribution of
-
8/11/2019 Project Report (Transient Analysis)
62/86
reser&oir parameter from this e&aluation data, (3 data and
7
-
8/11/2019 Project Report (Transient Analysis)
63/86
he table below is con.dence from the data could be analyIed-
he total test are 6@, there are 65 high con.dence data, >5
middle con.dence data and 6D low con.dence data-
T*le 3.18 %et*l Co+;e+/e o< FOT *+ P#U Tet
T*le 3.1@ Co+/luo+ FOT *+ P#U
and
A&erage of
Eellbore
torage
A&erage of
Permeability
)#+
A&erage
of #in
3actor )+
A&erage
of P
a&erage
A 0-86@ 6>@-54 >4-8> @54-
A 0->@6 85-45 -4 5@6-68
7 0-048> D6>-@8 64-@4 5D5-44
7 0-0D>5 00@- 6>-@6 55D
= 0-08D> @@@-46 4-@> @8>-@@
0-6@6> 486-5 6-> @80-5>
rand 0-5 @4-8> 40-> 6>5-48
-
8/11/2019 Project Report (Transient Analysis)
64/86
otal
able 4-0, is showing 7*and is high s#in and high permeability-
3.3.1 S9+
T*le 3.1 S9+ (Ave!*7e)
3rom this table abo&e, the project team can see which sand
on which area that the project team needs to test- he project
team gi&es dierent color for sand- And also the project team can
see the distribution of s#in &alue- 'n order to ma#e it clearer, here
is the s#in &alue for each well-
-
8/11/2019 Project Report (Transient Analysis)
65/86
T*le 3.1 S9+ y 6ell
-
8/11/2019 Project Report (Transient Analysis)
66/86
-
8/11/2019 Project Report (Transient Analysis)
67/86
3rom the table abo&e, the project team ha&e the opportunity
to increase the &alue of injection Jow rate by reduce this high
s#in- 3or e;ample, the project team can do wor# o&er, such as
reperforation, stimulation, etc- 3igure 4-8 $ 4- are tabulation
s#in of all sand-
F7u!e 3. T*ul*to+ S9+ o< A1-S*+
"inimum #in G *0-
"a;imum #in G
A&erage #in G >5-4>
F7u!e 3. T*ul*to+ S9+ o< A2-S*+
-
8/11/2019 Project Report (Transient Analysis)
68/86
"inimum #in G *4
"a;imum#in G 64
A&erage #in G
F7u!e 3.10 T*ul*to+ S9+ o< #1-S*+
"inimum #in G *4
"a;imum #in G >5
A&erage #in G 65
F7u!e 3.11 T*ul*to+ S9+ o< #2-S*+
-
8/11/2019 Project Report (Transient Analysis)
69/86
"inimum #in G *>
"a;imum#in G >45
A&erage #in G 64
F7u!e 3.12 T*ul*to+ S9+ o< %-S*+
"inimum #in G *"a;imum#in G @
A&erage #in G 4>
-
8/11/2019 Project Report (Transient Analysis)
70/86
F7u!e 3.1 T*ul*to+ S9+ o< S-S*+
"inimum #in G
"a;imum#in G 6
A&erage #in G 6
F7u!e 3.13 T*ul*to+ S9+ o< All S*+
3rom the graphic abo&e, can see the #in )V+ is 5 data
and this is gi&e information that the wellbore is damage- here
are 4 data the &alue of s#in )*+ and Iero- this is gi&e information
that the wellbore has stimulated or no damage- he minimum
&alue of s#in is *4-05 and the ma;imum &alue is >45 then the
s#in a&erage is 40 for all of sands in the area 4, 5 and 6- 3or the
decreasing s#in )*+ need stimulation job-
-
8/11/2019 Project Report (Transient Analysis)
71/86
F7u!e 3.15 to7!*m S9+ o< All S*+
3rom the graphic abo&e, the largest distribution of s#in is 0 $
D-DD with 44 data freBuency then W 0 with > data freBuency
and 50 $ DD-DD with @ data freBuency-
3.3.2 Pe!me*lty
3rom this analysis, the project team found that there is
dierence between permeability from F analysis )from P7% and
3 ests+ and F actual )3rom permeability log+-
T*le 3.20 & *+*ly (Ave!*7e)
T*le 3.21 & */tu*l (Ave!*7e)
-
8/11/2019 Project Report (Transient Analysis)
72/86
3igure 4-6 $ 4- are tabulation permeability of all sand
F7u!e 3.18 T*ul*to+ Pe!me*lty o< A1-S*+
"inimum Permeability G 56 m=
"a;imum Permeability G @4>0 m=
A&erage Permeability G 65D m=
F7u!e 3.1@ T*ul*to+ Pe!me*lty o< A2-S*+
-
8/11/2019 Project Report (Transient Analysis)
73/86
-
8/11/2019 Project Report (Transient Analysis)
74/86
"inimum Permeability G 0 m=
"a;imum Permeability G 4060 m=
A&erage Permeability G 00@ m=
F7u!e 3.20 T*ul*to+ Pe!me*lty o< %-S*+
"inimum Permeability G 6 m=
"a;imum Permeability G 4@>0 m=
A&erage Permeability G @@@ m=
F7u!e 3.21 T*ul*to+ Pe!me*lty o< S-S*+
-
8/11/2019 Project Report (Transient Analysis)
75/86
"inimum Permeability G 406 m=
"a;imum Permeability G 556 m=
A&erage Permeability G 48@ m=
F7u!e 3.22 T*ul*to+ Pe!me*lty o< All-S*+
3rom the graphic abo&e, can see the permeability minimum
is D-@ m=, the ma;imum permeability is D6@0 m=, then the
a&erage permeability is @6 for all of sands in the area 4,5 and
6-'n the 3igure below can see the data distribution based
freBuency-
-
8/11/2019 Project Report (Transient Analysis)
76/86
F7u!e 3.2 to7!*m Peeme*lty
3rom the picture abo&e, the largest distribution of
permeability is 500 $ DDD-DD with >D data freBuency then 000 $
4DD-DD with 5 data freBuency and 0 $ 500 with 8 data
freBuency-
-
8/11/2019 Project Report (Transient Analysis)
77/86
F7u!e 3.23 to7!*m o< $oo Pe!me*lty
=istribution 1ormal and Permeability ood CategoryG
3reBuencyG )0 $ 500+, )500 $ DDD,DD+, )000 $ 4DD,DD+,
)500 * DDD,DD+
)000 $ 4DD, DD+
F7u!e 3.28 The 7oo Pe!me*lty to7!*m + *ll S*+
3.3. P!eu!e
he table below is distribution reser&oir pressure- 3rom this
distribution, we can see which sand on which area that the
project team needs to test-
T*le 3.22 Ree!vo! P!eu!e (Ave!*7e)
-
8/11/2019 Project Report (Transient Analysis)
78/86
F7u!e 3.2@ %!e/t "e*u!eme+t P!eu!e %*t* y Tet Ty4e
F7u!e 3.2 %!e/t "e*u!eme+t P!eu!e %*t* y S*+
-
8/11/2019 Project Report (Transient Analysis)
79/86
3.3.3 Shut + Tme Re/omme+*to+
he project team has to optimiIe the shut*in time, to
economical- 7ecause of that, the project team recommends using
> hours of shut*in time for fall o test and @ hours of shut in time
for pressure build up- !etLs see table 4->
T*le 3.2 Shut + tme FOT *+ P#U
and
hut in
time 3
)hours+
hut in
time P7%
)hours+
A >-6 6-@
A -8 @-
7 -5 6-D
7 -D 6-@
= >-5 @-
-5 X
A&erag
e> @
CAPTER 'CONCLUSION AN%RECO""EN%ATIONS
CONCLUSION AN% RECO""EN%ATIONS
5.1 Co+/luo+
- "odel in analysis PA is homogeneous, radial Jow, in.nite
acting reser&oir and constant wellbore storage-
- he project team has to optimiIe the shut*in time, for
economical cost- 7ecause of that, the project team
recommends using > hours of shut*in time for fall o test and
@ hours of shut in time for pressure build up-
>- A&erage highest permeability at D6>-@8 m= )7*and+,
a&erage lowest permeability at 486-50 m= )*and+-
-
8/11/2019 Project Report (Transient Analysis)
80/86
4- A&erage highest s#in factor at 64-@4 )7*and+, A&erage
lowest s#in 3actor at 6->0 )*and+-
5- 'ndication closed by fault at 47*D5A A*and, A*and, 7*
andK 47*4 A*and, A*and )P7% >+, 7*andK 3*D4, 4C*
>, 5C*55 A*and, 7*andK 57*DD, 4=*5*1P, 4=* A*
and, >=*86 A*and, >=*8> 7*and, >=*D8 7*=*and and
47*4 7*and-
6- A&erage highest pressure )PX+ at =*and- he &alue is @8>-8
psi and lowest pressure at A**and, that is 5@6-@ psi
@- 7ased on deri&ati&e cur&e at P7% test, presence high
pressure at well 6=* A*and, 4=*@82 A*and, 5=*D 7*
and, 5=*@> 7*and, 47*D5A =*and, and 5=*@ =*and-
8- 7
psi , area
05 at 488-> psi, and area 06 at 5D-0
5.2 Re/omme+*to+
- 3or decrease wellbore dynamic eect, operator should follow
appropriate P, because wellbore dynamic can cause
analysis failure or canLt do it
- At PA, input data test between job log and supporting data
must be consistent-
>- 1eed support data li#e geologic, well history, and etc- to get
accurate results
4- o analysis accurate
-
8/11/2019 Project Report (Transient Analysis)
81/86
5- Ad&isable
-
8/11/2019 Project Report (Transient Analysis)
82/86
A44e+ 2 Lo= Co+;e+/e o< FOT
-
8/11/2019 Project Report (Transient Analysis)
83/86
-
8/11/2019 Project Report (Transient Analysis)
84/86
A44e+ "le Co+;e+/e o< FOT
A44e+ 3 Co+;e+/e O< P#U
-
8/11/2019 Project Report (Transient Analysis)
85/86
REFERENCE
-
8/11/2019 Project Report (Transient Analysis)
86/86
- "atthews C- and (ussell =-- G M Pressure Build-Up and Flow
Test in WellsN ,