Project Development Academy Project Development Academy (PDA) (PDA) “Project Funding” “Project Funding” September 19, 2007 Ron Rigney, P.E. & P.L.S. Director Division of Program Management

Upload: oro

Post on 09-Jan-2016

21 views

Category:

Documents


0 download

DESCRIPTION

Project Development Academy (PDA) “Project Funding”. September 19, 2007. Ron Rigney, P.E. & P.L.S. Director Division of Program Management. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Project Development Academy (PDA) “Project Funding”

Project Development Academy Project Development Academy (PDA)(PDA)

“Project Funding”“Project Funding”

September 19, 2007

Ron Rigney, P.E. & P.L.S.Director

Division of Program Management

Page 2: Project Development Academy (PDA) “Project Funding”

The Division of Program Management is responsible for preparing the programming documents for authorization of state and federal funding for the Preliminary Engineering (PE) and Environmental, Design, Right-of-Way, Utility, and Construction phases of KYTC projects.

Page 3: Project Development Academy (PDA) “Project Funding”

Programming documents are required for authorization of the initial funding to begin the corresponding phase activities and the modifications to previously authorized funding. Modifications add or reduce funds to correspond with the projected amount of required funding to complete the remaining work of the corresponding project phase.

Page 4: Project Development Academy (PDA) “Project Funding”

The majority of the funding for transportation projects is either state funding or federal funding. However, a project may include both state and federal funding and may even include partial funding from a local city or county agency.

Page 5: Project Development Academy (PDA) “Project Funding”

Various transportation funding programs are available for transportation projects within KYTC. Each of these funding programs has state/federal regulations which must be followed throughout the entire project process. The regulations outline the type of project activities that are eligible for the designated funding and the required processes that must be followed throughout the entire project.

Page 6: Project Development Academy (PDA) “Project Funding”

Funding for KYTC projects include transportation projects funded through the Rural Secondary Program with funds allocated to each of the 120 Kentucky counties for construction, reconstruction, and maintenance of secondary and rural roads in each county. The program is funded by 22.2 percent of the motor fuels taxes and distributed by formula to each of the 120 counties. The projected annual amount of funding through the Rural Secondary Program is approximately $110 million per year.

Page 7: Project Development Academy (PDA) “Project Funding”

Also, funding for KYTC projects include transportation projects funded through the County Road Aid Co-op Program allocated to each of the 120 Kentucky counties for construction, reconstruction, and maintenance of secondary and rural roads in each county. The program is funded by 18.3 percent of the motor fuels taxes and distributed by formula to each of the 120 counties, but the funding is expended by the fiscal court in each county. The projected amount of funding through the County Road Aid Co-op Program is approximately $92 million per year.

Page 8: Project Development Academy (PDA) “Project Funding”

In addition, funding for KYTC projects include transportation projects funded through the Municipal Aid Co-op Program for construction, reconstruction, and maintenance of urban roads and streets within 421 incorporated cities and 46 unincorporated urban places throughout Kentucky. The funding is 7.7 percent of the motor fuels taxes and is distributed by formula and expended by the fiscal court within each of the urban areas. The projected amount of funding through the Municipal Aid Co-op Program is approximately $38 million per year.

Page 9: Project Development Academy (PDA) “Project Funding”

The Rural Secondary Program, the County Road Aid Co-op Program and the Municipal Aid Co-op Program are administered through the Department of Governmental Relations, Office of Rural and Secondary Roads.

Page 10: Project Development Academy (PDA) “Project Funding”

Also, state funding provided through the Division of Maintenance and the Division of Traffic Operations are provided for normal maintenance and operations of existing roadways throughout the entire Commonwealth of Kentucky. The projects include bridge maintenance, pavement resurfacing, guardrail, slide repairs, drainage, pavement markers, pavement striping, roadway signing and lighting, and other traffic operations projects. The projected amount of funding through the maintenance and operations programs is approximately $280 million per year.

Page 11: Project Development Academy (PDA) “Project Funding”

In addition to these KYTC programs, KYTC has projects funded through the state road fund (FD04) and through the federal transportation funding (FD52) programs. The projects funded through the FD04 and FD52 programs must come through the Six-Year Highway Plan (SYP) process and must be approved by the Kentucky General Assembly. Each fiscal year, the projected amount of funding available for the FD04 program is approximately $200 million and approximately $600 million through the FD52 federal program.

Page 12: Project Development Academy (PDA) “Project Funding”

In addition to the FD04 and FD52 programs, the 2005 General Assembly approved the sale of $300 million in state bonds and $150 million in federal GARVEE bonds.

Page 13: Project Development Academy (PDA) “Project Funding”

The 2006 General Assembly approved the sale of $350 million in state bonds and an additional $290 million in federal GARVEE bonds.

Page 14: Project Development Academy (PDA) “Project Funding”

The combined bond programs provided $650 million in state bonds and $440 million in GARVEE bonds for funding construction phases of KYTC roadway projects.

Page 15: Project Development Academy (PDA) “Project Funding”

Kentucky Six-Year Highway Plan (SYP)

Page 16: Project Development Academy (PDA) “Project Funding”

KYTC projects that are funded through the state road fund (FD04) program, through the federal transportation funding (FD52) program, through the 2005 and 2006 state bond programs, and through the 2005 and 2006 GARVEE bond programs must come through an “Enacted Six-Year Highway Plan (SYP)” approved by the Kentucky General Assembly.

Page 17: Project Development Academy (PDA) “Project Funding”

KYTC submits to the General Assembly in February of even number years a “Recommended Six-Year Highway Plan” containing a listing of proposed projects including the scheduled project phases, proposed type of funding, scheduled fiscal year, and the estimated cost of the corresponding project phase.

Page 18: Project Development Academy (PDA) “Project Funding”

The General Assembly reviews the projects identified in the Recommended SYP, and they may make revisions to projects, they may add projects, and they may even remove projects before they approve the SYP. Approval of the SYP normally is in April of even number years and also depends upon approval of the state budget by the General Assembly.

Page 19: Project Development Academy (PDA) “Project Funding”

The Enacted SYP is the state document that by law as outlined within KRS, the Transportation Cabinet can proceed with the identified project phases scheduled within the next biennium depending upon the availability of identified funding for each project.

Page 20: Project Development Academy (PDA) “Project Funding”

Federal-Aid Highway Program Funding

Page 21: Project Development Academy (PDA) “Project Funding”

The Enacted SYP contains the listing of projects scheduled to utilize state roadway funding (FD04) and federal-aid highway program funding (FD52).

Page 22: Project Development Academy (PDA) “Project Funding”

The federal-aid highway program funding is in accordance with the current federal transportation act, “Safe, Accountable, Flexible, Efficient Transportation Equity Act: A Legacy for Users (SAFETEA-LU).”

Page 23: Project Development Academy (PDA) “Project Funding”

Legislative approval by Congress for SAFETEA-LU was signed into law by President Bush on August 10, 2005.

Page 24: Project Development Academy (PDA) “Project Funding”

Normally, a transportation act covers a period of six years, but SAFETEA-LU only covers five years – FY 2005 through FY 2009.

Page 25: Project Development Academy (PDA) “Project Funding”

With SAFETEA-LU scheduled to expire at the end of FY 2009 (October 1, 2009), preliminary work has already begun on the next transportation act.

Page 26: Project Development Academy (PDA) “Project Funding”

House of Representatives Senate

Any Differences?

President

Start Over

Conference Committee

Conference Bill

Floor Action

Surface Transportation

Act

Public Hearings

Subcommittee Bill

Committee Bill

House Bill

Public Hearings

Subcommittee Bill

Committee Bill

Senate Bill

Override Veto?

No Yes

Veto Approval

Yes No

CongressionalProcedures

Page 27: Project Development Academy (PDA) “Project Funding”

To better understand the federal-aid highway program the following terms are provided:

Page 28: Project Development Academy (PDA) “Project Funding”

Authorization Act: This is the current transportation act (SAFETEA-LU) which establishes or continues federal transportation programs or agencies and establishes an upper limit on the amount of funds for the program(s).

Page 29: Project Development Academy (PDA) “Project Funding”

Appropriations Act: Yearly action by Congress that makes funds available for expenditures with specific limitations as to amount, purpose, and duration. It permits funding previously identified in the authorization act to be obligated and payments made.

Page 30: Project Development Academy (PDA) “Project Funding”

Apportionment: The distribution of funds as prescribed by a statutory formula.

Page 31: Project Development Academy (PDA) “Project Funding”

Allocation: An administrative distribution of funds for programs that do not have statutory distribution formulas.

Page 32: Project Development Academy (PDA) “Project Funding”

Obligation Limitation: A restriction, or “ceiling,” on the amount of federal funding that may be obligated during a specified time period.

Page 33: Project Development Academy (PDA) “Project Funding”

Obligation: The federal government’s legal commitment to pay or reimburse the states for the federal share of a project’s eligible costs.

Page 34: Project Development Academy (PDA) “Project Funding”

The obligation limitation of federal funds do not affect the apportionment or allocation of federal funds. It controls the rate or the amount of which funds may be used.

Page 35: Project Development Academy (PDA) “Project Funding”

Thus, the amount of apportionments and allocating of federal funds made available in each fiscal year that is actually available to obligate is controlled by the amount of obligation limitation for each program.

Page 36: Project Development Academy (PDA) “Project Funding”

The obligation limitation received each year normally ranges between 85 to 95 percent of apportionments, with some allocation programs receiving 100 percent obligation limitation.

Page 37: Project Development Academy (PDA) “Project Funding”

The federal-aid highway program is not a grant program.

The federal-aid highway program is a reimbursement program, which means project expenditures must be paid first with state funds, and then the state sends requests to FHWA for reimbursement of eligible costs.

Page 38: Project Development Academy (PDA) “Project Funding”

KYTC submits a weekly federal billing to FHWA requesting reimbursement of federal funds, and the turn-around time to receive reimbursement runs 6 to 10 days.

Page 39: Project Development Academy (PDA) “Project Funding”

Multi-year authorization act

(e.g., SAFETEA-LU)

Annual distribution (apportionment or

allocation)

Total Federal aid available for a

fiscal year

Obligation (Federal government’s

promise to pay)

Reimbursement (Federal government

pays its share)

Unobligated balances of prior years’ distributions

Limitation on

obligations

Annual Appropriations

act

Liquidating cash to reimburse states

(Highway Trust Fund)

Contract Authority Programs

Page 40: Project Development Academy (PDA) “Project Funding”

Kentucky Statewide Transportation Improvement Program

(STIP)

and

Federal Discretionary Funding Programs

Page 41: Project Development Academy (PDA) “Project Funding”

As noted, the Enacted SYP is the state document required by KRS, however, federal regulations require that KYTC prepare and submit to FHWA and FTA a Statewide Transportation Improvement Program (STIP).

Page 42: Project Development Academy (PDA) “Project Funding”

The STIP identifies the transportation programs and projects within Kentucky that will utilize federal funding. The STIP is prepared in the summer of even number years and includes highway, public transit, aviation, transportation enhancement, Safe Routes to School and recreational trail projects. Each of the programs contains a listing of scheduled projects and scheduled costs for the next four Federal Fiscal Years. The scheduled costs of the projects listed in the STIP must be fiscally constrained.

Page 43: Project Development Academy (PDA) “Project Funding”

The Division of Program Management is also responsible for preparing applications and documents for FHWA federal discretionary funding programs.

Page 44: Project Development Academy (PDA) “Project Funding”

The FHWA federal discretionary programs represent special funding categories where FHWA solicits for project candidates and selects projects for funding based on applications received for each of the different discretionary programs. Each of the federal discretionary programs has its own eligibility and selection criteria that are established by federal regulations.

Page 45: Project Development Academy (PDA) “Project Funding”

Since 2000, the projects receiving federal discretionary program funding have been identified through Congressional earmarks. However, the FY 2007 discretionary program will be selected through applications submitted to FHWA from KYTC.

Page 46: Project Development Academy (PDA) “Project Funding”

The Division of Program Management is responsible for monitoring the approved STIP and verifying that funding requests for proposed projects are identified within the STIP.

Page 47: Project Development Academy (PDA) “Project Funding”

In addition to the STIP requirements, federal funded projects located within the nine Metropolitan Planning Organizations (MPO) areas must be identified within their MPO Transportation Improvement Program (TIP) before project funding can be authorized. If a project is not identified within the MPO TIP, KYTC must request the MPO to amend their TIP to include the project, and this process may take several months to complete.

•KIPDA Jefferson, Bullitt, Oldham Counties, KY Clark, Floyd Counties, IN

•OKI Boone, Kenton, Campbell Counties, KY Butler, Clermont, Hamilton, Warren Counties, OH Deerborn County, IN

•FIVCO Boyd and Greenup Counties, KY

•EUTS Henderson County, KY

•GRADD Daviess County, KY

•BRADD Warren County, KY

•LTADD Hardin County, KY

•CMCRPC Christian County, KY

•LFUCG Fayette and Jessamine Counties, KY

MPO Areas

Page 48: Project Development Academy (PDA) “Project Funding”

EUTSEvansville Urban

Transportation Study

GRADDGreen River

Area Development District

LTADDLincoln Trail

Area Development District

KIPDAKentuckiana Regional Planning

and Development Agency

OKIOhio-Kentucky-Indiana

Regional Council of GovernmentsLFUCG

Lexington-FayetteUrban County Government

FIVCOFive Counties

Area DevelopmentDistrict

CMCRPCClarksville-Montgomery CountyRegional Planning Commission

BRADDBowling Green

Area Development District

MPO AREAS

Page 49: Project Development Academy (PDA) “Project Funding”

KYTC“Cash Management Balance Process”

& Processing Project Funding Requests

Page 50: Project Development Academy (PDA) “Project Funding”

The Division of Program Management is also responsible for tracking the availability of state and federal funds for projects identified within the Enacted SYP and STIP. We are in close communication with each of the Districts, each of the Central Office Divisions, Office of Budget and Fiscal Management, Executive Directors, the State Highway Engineer, the Commissioner of Highways, and the Secretary of Transportation.

Page 51: Project Development Academy (PDA) “Project Funding”

The 2000 General Assembly changed the funding authorization process to allow the Cabinet to authorize funding based on projected expenditures. Going from an authorization base to an expenditure base required the Cabinet to develop a “Cash Management Balance” process and model. The Cash Management Balance process and model is used to determine the bottom line cash balance to cover current fixed cost items, current expenditures of currently authorized projects, current modifications to existing projects, and proposed new funding requests.

Page 52: Project Development Academy (PDA) “Project Funding”

STA

TE“F

I XED

COST”

BUD

GETIT

EM

S

STATEROA

D

FUNDREVEN

UE

$$

$$

6

YP

“S

P”

PR

OJ

EC

TS

FOR FEDE R

ALP

RO

JECT

S

STATE MATCH

ING

FU

NDS F

ED

ER

AL

HI G

HW

AYT

RUS T

FU

ND

E

RV

EN

UE

ST

OK Y

T C

$$

$$

$

FHHES

APD

IM

STP

NH TE

CM

AQ

BR ID

GE

KYD

HPP

RRS

RRP

6YP

NON 6YRBUDGET

FEDERALPROGRAMS

SLO,SLX,SNK

STATE FUNDS

“FIXED COST” ITEMS:* DEBT SERVICE

* MAINTENANCE

* RESURFACING

* VEHICLE REGULATION

* HIGHWAY OPERATION

* CAPITAL CONSTRUCTION

* JUDGEMENTS & OTHER

* SECRETARY’S CONTINGENCY

* STATE POLICE & OTHER AGENCIES

* GENERAL ADMIN. & SUPPORT

* REVENUE SHARING

Page 53: Project Development Academy (PDA) “Project Funding”

ENACTED FY 2007-2008 BIENNIAL HIGHWAY PROGRAM AND

IDENTIFIED PRECONSTRUCTION PROGRAM PLAN FOR FY 2009 - FY 2012 ANTICIPATED FUNDING LEVELS

FED-AID INTERSTATE MAINTENANCE

FEDERAL SAFETY PROGRAM FUNDS

FED-AID SURFACE TRANSPORTATION

PROGRAM (Includes Trans. Enhancement

and Metro-specific funding categories)

FED-AID NATIONAL HIGHWAY SYSTEM

FEDERAL HIGH PRIORITY PROJECTS

FED-AID BRIDGE REPLACEMENT

FEDERAL FOREST HIGHWAY FUNDS

STATE CONSTRUCTION FUNDS EXPECTED

TO BE AVAILABLE FOR OBLIGATION ("SP")

FEDERAL APPALACHIAN HIGHWAYS FUNDS

FED-AID CONGESTION MITIGATION

$708,200,000

$158,200,000

$1,000,200,000

$785,200,000

$168,600,000

$406,100,000

$3,000,000

$1,528,600,000

$514,200,000$73,000,000

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)(10)

(1)

(2)

(3)

(4)

(5)

(6)

(7)

(8)

(9)

(10)

Page 54: Project Development Academy (PDA) “Project Funding”

FEDERAL AND STATE HIGHWAY SIX-YEAR HIGHWAY PLAN FUNDING LEVELSFROM 2007 THRU 2012

(as estimated by the Kentucky Transportation Cabinet)M

illio

ns

$625

$381

$647

$348

$653

$200

$596

$200

$597

$200

$597

$200

$0

$200

$400

$600

$800

$1,000

$1,200

2007 2008 2009 2010 2011 2012

Federal State & Local Match State Projects "SP"

$40 $40 $40

$40 $40 $40

Page 55: Project Development Academy (PDA) “Project Funding”

KYTC project managers are responsible for submittal of funding requests for their projects. All funding requests for projects identified within the Enacted SYP and STIP are submitted to the Division of Program Management.

Page 56: Project Development Academy (PDA) “Project Funding”

County

Initial

Initial

No. of Parcels

Grave Relocation

Initial

Amount

Yes No R/W Plans submitted to Program Management Yes No Environmental Cleared

PercentOverrun/(Underrun)Amount Overrun/(Underrun)

Phase Cost Total EstimatedPhase Cost

Project Manager

Type of Request

Project Phase and Responsibility:

FUNDING FOR PHASES INDICATED

Right of Way PE

Date Request Submitted by:

Six-Year Plan

Utilities

Amount Requestingand

Additional

PLANNING AND DESIGN

OwnerParcel No

Other

PE & Environmental

Name of Utilities or Railroad Company

Railroad Protective Devices Construction

UTILITIES

Utility Adjustment Railroad Adjustment

Construction Title Deeded To Other

REQUEST FOR FUNDING AUTHORIZATION

Local State FHWA

Design Right of Way

DIVISION OF PROGRAM MANAGEMENT

TRANSPORTATION CABINETDEPARTMENT OF HIGHWAYS

Funding: Other

Road Name

Authorization No.

Additional

RIGHT OF WAYRelocation Assistance

Phase II Design Special Agreement Scoping Study

Six Year Item No

Planning

Previous Amount Authorized

Mars No.

Additional

Comments/Remarks:

Applicable when requesting Authorization of Funding:

Hardship Corridor Preservation

Residences Acquisition Cost Relocation Cost

BusinessesMiscellaneous

Page 57: Project Development Academy (PDA) “Project Funding”

TC 90-123

7/2007

County

Justification for Increase:

The scope of services for the increase in design phase funding is within the original RFP.

C) Other (List)

Justification for Increase: B) Increase for State Forces Charges

C) Increase for Other Charges (LIST)

Justification for Increase:

SECTION 2:

Date of Request for Proposals (RFP) NA - Design to be Conducted with State Forces

Modification Funding Requested Amount

A) Increase for Consultant Fees

A) Estimated Consultant Fees

B) Estimated State Forces Charges

Modification Funding Request (GO TO SECTION 2)

SECTION 1: Initial Funding Requested Amount

$0

DirectorDate

FHWA

TOTAL (Should match the modification funding request) $0

TOTAL (Should match initial funding request)

Funding: Other

Road Name

Initial Funding Request (GO TO SECTION 1)

State Local

RFP Before Dec. 1, 2005

RFP After Dec. 1, 2005

Mars No.

TRANSPORTATION CABINETDEPARTMENT OF HIGHWAYS

Six Year Item No Federal Project No. (if applicable)

Project Manager

DIVISION OF PROGRAM MANAGEMENTDESIGN PHASE FUNDING CERTIFICATION

Comments:

Use the Comments box below if necessary.

Page 58: Project Development Academy (PDA) “Project Funding”

The request for project funding identifies the SYP Item Number, the Phase that funding is required, outlines if the funding is initial or additional funding, the estimated amount of required funding, and includes an area for the Project Manager to provides details on funding request.

Page 59: Project Development Academy (PDA) “Project Funding”

The Division of Program Management reviews the request for funding and determines:

1) If the request is for the initial funding to start a project phase, the project phase and scheduled funding must be identified within the biennium of the current SYP and if federal funds it must be identified within the STIP.

2) If the request is for additional funding for a previously authorized funded phase, a detailed explanation of the additional funding is required for submittal along with the unsigned TC10 for approval signatures.

Page 60: Project Development Academy (PDA) “Project Funding”

The Division of Program Management prepares the project authorization document (TC10) outlining the project location, scope of project, the type of state or federal funding, and the required amount of funding in the Project Authorization System (PAS), and prints the unsigned TC10 to route for approval signatures.

Page 61: Project Development Academy (PDA) “Project Funding”
Page 62: Project Development Academy (PDA) “Project Funding”

In addition to the TC10, the projected expenditures and required cash flow for each funding request is entered into the KYTC “Cash Management Balance” model to determine if cash is available to cover the projected expenditures.

Page 63: Project Development Academy (PDA) “Project Funding”

The Division of Program Management routes the unsigned TC10 and “Cash Management Balance” sheet through the Preauthorization Review Team (Pre-ART) Committee for their review and recommendation to the Authorization Review Team (ART) Committee for funding approval signatures.

Page 64: Project Development Academy (PDA) “Project Funding”

Upon receiving the approved signed TC10, if the funding is state funding the Division of Program Management enters the state funding into the eMARS accounting system and the funding is ready for project expenditures.

Page 65: Project Development Academy (PDA) “Project Funding”

However, if the TC10 is for federal funding, the Division of Program Management then begins the process to prepare the federal funding programming document (PR1) to be submitted to FHWA. This process can vary from a couple of days to several weeks depending upon several factors, which include the status of the environmental document, and the status of project in the STIP or MPO TIP.

Page 66: Project Development Academy (PDA) “Project Funding”
Page 67: Project Development Academy (PDA) “Project Funding”

Upon submittal of the federal PR1 document to FHWA, normally the approval process through FHWA is completed within two to three weeks depending upon the availability of staff reviewing and approving the PR1 document.

Page 68: Project Development Academy (PDA) “Project Funding”

Upon receiving the approved federal PR1 document, the Division of Program Management enters the federal funding into the eMARS accounting system and the funding is ready for reimbursement of project expenditures.

Page 69: Project Development Academy (PDA) “Project Funding”

Please keep in mind that the federal PR1 document approved and signed by FHWA serves as the project agreement between KYTC and FHWA that the corresponding project phase activities are eligible for reimbursement of federal funds in accordance with federal funding regulations.

Page 70: Project Development Academy (PDA) “Project Funding”

The FHWA approval date is the beginning date that project expenditures are eligible for reimbursement, and any project expenditures occurring prior to the approval date on the PR1 are not eligible for reimbursement of federal funds.

Page 71: Project Development Academy (PDA) “Project Funding”

Type of Funding&

Funding Regulations

Page 72: Project Development Academy (PDA) “Project Funding”

The type of funding for a given project will determine the state and federal funding regulations that the Project Manager must meet so the project is eligible for the designated funding. These funding regulations may establish project milestones that must be met before the funding can be authorized for the project to proceed into the next phase of the project.

Page 73: Project Development Academy (PDA) “Project Funding”

The federal funding is broken down into the following core programs, and each program has defined regulations that

must be met to be eligible for federal funding:

Bridge Replacement (BR)Congestion Mitigation (CM)Interstate Maintenance (IM)

National Highway (NH)Safety Program (HES)

Surface Transportation Program (STP)Forest Highway Program (FH)

Appalachian Development (APD)

Page 74: Project Development Academy (PDA) “Project Funding”

*Includes 20% state match**Reflects 2% takedown for SPR; toll credits for match***Reflects 2% takedown for SPR; 10% set aside for TE Program

Funding Category FY-2007 FY-2008 FY-2009 FY-2010 FY-2011 FY-2012

2007-2012TOTAL

FUNDINGAppalachian Development (APD) * 85.7 85.7 85.7 85.7 85.7 85.7 514.2Bridge Replacement On-System (BRO)** 42.0 43.9 44.5 44.5 44.5 44.5 263.9Bridge Replacement On/Off (BRX)** 12.9 13.5 13.7 13.7 13.7 13.7 81.2Bridge Replacement Off (BRZ)** 9.7 10.1 10.3 10.3 10.3 10.3 61.0Congestion Mitigation (CMAQ)** 11.6 12.2 12.3 12.3 12.3 12.3 73.0Forest Highways (FH) 0.5 0.5 0.5 0.5 0.5 0.5 3.0Interstate Maintenance (IM)** 112.9 118.1 119.3 119.3 119.3 119.3 708.2National Highways (NH)** 125.1 130.9 132.3 132.3 132.3 132.3 785.2Rail Protect. Devices (RRP) 2.0 2.0 2.0 2.0 2.0 2.0 12.0Rail Separation (RRS) 2.0 2.0 2.0 2.0 2.0 2.0 12.0Hazard Elimination (HES) 21.6 22.2 22.6 22.6 22.6 22.6 134.2STP-Henderson (SHN) 0.4 0.4 0.4 0.4 0.4 0.4 2.4STP-Louisville (SLO) 11.5 11.6 11.8 11.8 11.8 11.8 70.3STP-Lexington (SLX) 3.9 4.0 4.0 4.0 4.0 4.0 23.9STP-Northern Kentucky (SNK) 4.3 4.4 4.5 4.5 4.5 4.5 26.7Surface Transportation (STP)*** 127.2 133.3 134.9 134.9 134.9 134.9 800.1Transportation Enhancement (TE) 12.8 12.8 12.8 12.8 12.8 12.8 76.8High Priority Projects (HPP) 56.2 56.2 56.2 0.0 0.0 0.0 168.6Kentucky Appropriations Earmarks (KYD) 0.0 0.0 0.0 0.0 0.0 0.0 0.0Subtotal Federal Program $642.3 $663.8 $669.8 $613.6 $613.6 $613.6 $3,816.7

Page 75: Project Development Academy (PDA) “Project Funding”

In addition to the normal state and federal funding programs, KYTC utilizes both state and federal bond programs to fund roadway projects. As previously discussed, the 2005 and 2006 General Assembly passed legislation allowing KYTC to sell $650 million in state bonds and $440 million in GARVEE bonds.

Page 76: Project Development Academy (PDA) “Project Funding”

$440 Million Grant Anticipation Revenue Vehicle (GARVEE) Bond Program

Interstate 64:

Interstate 65:

Interstate 75:

Widen to six lanes from the Snyder Freeway in Jefferson County toward Shelbyville (total cost $127 million)

Widen to six lanes from the Tennessee State line to Bowling Green (total cost $178 million)

Widen to six lanes from the end of the current six-lane section in northern Scott County to the current six-lane section south of KY 22 in Grant County (total cost $135 million)

Total Cost= $135 million

Total Cost= $127 million

Total Cost= $178 million

75

64

65

64

64

75

75

265

6524

Page 77: Project Development Academy (PDA) “Project Funding”

The funding regulations are in addition to design standards and environmental regulations, which a Project Manager must meet as he tries to keep the project on schedule and within the scheduled cost of the project. However, the programming of funding for each phase of the project is a critical element to completing the project and being able to fund other roadway projects.

Page 78: Project Development Academy (PDA) “Project Funding”

Effect of Inflation on the HighwayDollar since 1987*

*As calculated from FHWA’s “Price Trends for Federal-aid Highway Construction”YEAR

0

100 K

200 K

300 K

400 K

500 K

600 K

700 K

800 K

900 K

1 million

87 88 89 90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05

$1 million 1987buys in 2005641K

Page 79: Project Development Academy (PDA) “Project Funding”

1.1 Bi llion

390

304336

424

605

333

382

564

638

689736

792

695655

463

750

0

100

200

300

400

500

600

700

800

900

90 91 92 93 94 95 96 97 98 99 00 01 02 03 04 05 06 07 08 09 10 11 12

Historic Construction Awards ($)

Calendar Year

mill

ion

s

1 bil

(potential)1.1 bil1.1 bil

1.2 bil

Page 80: Project Development Academy (PDA) “Project Funding”

Oracle Six-YearHighway Plan

PreconstructionStatus System

Page 81: Project Development Academy (PDA) “Project Funding”

In 1996 an Oracle relational database system was developed for the Division of Program Management by the KYTC Office of Informational Technology. The Oracle Six-Year Highway Plan Preconstruction Status System, which is often referred to as the Precon Status System or the Oracle SYP system, is a real time relational database system that numerous KYTC employees within the District Offices and Central Office Divisions enter data for SYP projects.

Page 82: Project Development Academy (PDA) “Project Funding”

The Oracle SYP system is used to prepare and print the Recommended and Enacted Six-Year Highway Plan and to track the current status of each project.

Page 83: Project Development Academy (PDA) “Project Funding”

The Oracle SYP Precon Status system provides the means to track the current estimated cost of each phase of the project, the scheduled fiscal year of funding for each phase of the project, and the type of scheduled funding for each phase of the project.

Page 84: Project Development Academy (PDA) “Project Funding”

In addition, the Oracle SYP system allows the user to track current environmental information, current right-of-way information, utility relocation information, and projected letting dates. Also, the project manager can enter various project milestone data elements and dates for each project.

Page 85: Project Development Academy (PDA) “Project Funding”

Also, the means are provided to enter and save project remarks throughout the various stages of the project, along with a place to enter CAP (Communicating All Promises) data, so as the project moves from one phase to the next, the various people working on the project can review any previous promises made to other agencies, elected officials, general public, or property owners along the project route.

Page 86: Project Development Academy (PDA) “Project Funding”

These project remarks are the project “History” file that can be used to determine why and when certain project activities occurred or why certain decisions were made concerning the project.

Page 87: Project Development Academy (PDA) “Project Funding”

The Oracle SYP Precon Status system is the backbone and foundation for development of the SYP and STIP and for tracking the current status of SYP projects.

Page 88: Project Development Academy (PDA) “Project Funding”

When a SYP project is let to construction and the construction contract is awarded, the project becomes “Inactive” in the Oracle SYP Precon Status system and becomes “Active” in the Division of Construction’s Transport system.

Page 89: Project Development Academy (PDA) “Project Funding”

Federal regulations require that each state DOT have an approved financially fiscal constrained STIP, where the estimated federal-aid funding apportionments compared to the planned federal-aid funding obligations have a ratio of 1.

Page 90: Project Development Academy (PDA) “Project Funding”

The fiscal constraint calculations for the 2008 STIP must meet new federal regulations where the planned federal-aid funding obligations are based upon the estimated costs of the corresponding project phase activities for the projected fiscal year of initial funding authorization.

Page 91: Project Development Academy (PDA) “Project Funding”

In order to meet the federal regulations, a new “Cost Escalator” process is being developed within the Oracle SYP Precon Status System that Project Managers will have the ability to enter the estimated cost of each phase of a project in current year dollars and the projected year of when the funding will be required for each phase of the project.

Page 92: Project Development Academy (PDA) “Project Funding”

The “Cost Escalator” process will have cost inflation factors assigned for each phase of the project to calculate the projected year of authorization cost based upon today’s cost and projected year of required funding authorization.

Page 93: Project Development Academy (PDA) “Project Funding”

The projected cost will be used in preparing the 2008 SYP and the 2008 STIP, so again the Oracle SYP Precon Status system is the backbone and development of the SYP and STIP.

Page 94: Project Development Academy (PDA) “Project Funding”

The Division of Program Management has developed several reports and electronic processes to assist the project manager and management staff to track the current status of projects and current status of funding for each phase of the SYP projects.

Page 95: Project Development Academy (PDA) “Project Funding”

At the beginning of each month, the Division of Program Management prepares and distributes a copy of the monthly project status report, which contains a listing of all the projects identified within the Enacted SYP. In addition, the monthly status report is available on the DOT Intranet, Division of Program Management website.

Page 96: Project Development Academy (PDA) “Project Funding”
Page 97: Project Development Academy (PDA) “Project Funding”

“Explanation of Item Number Series”

“Explanation of Item Number Series”

0 - 99 … Interstate Construction (Non-Pavement Rehab)100 - 899 … Non-Interstate Reconstruction, Construction,

New Route, etc 900 - 999 … HES Projects1000 - 1999 … Federal Bridge Replacement Program

2000 - 2999 ... Pavement Rehabilitation (Interstate, Parkways or Primary Routes)

3000 - 3999 ... Transportation Enhancement Projects4000 - 4299 ... County Bridge Replacement Program (State Funds)4300 - 4999 ... Guardrail Replacement Program (State Funds)5000 - 5999 ... Rockfall and Landslide Repairs6000 - 6999 ... Open7000 - 7999 ... 1998 SYP General Assembly Added Projects8000 - 8099 ... 2000 SYP General Assembly Added Projects

8300 - 8999 ... 2006 SYP General Assembly Added Projects

8100 - 8199 ... 2002 SYP General Assembly Added Projects

9000 - Above ... Open

8200 - 8299 ... 2004 SYP General Assembly Added Projects

Page 98: Project Development Academy (PDA) “Project Funding”
Page 99: Project Development Academy (PDA) “Project Funding”

LABEL ITEM DESCRIPTION OF ITEM

COUNTY The name of the Kentucky county where the project is located. The Status Report is sorted by county name.

YEAR OF SIX-YEAR HIGHWAY PLAN The year that the identified project first entered into the Six-Year Highway Plan.

KYTC IDENTIFICATION NUMBER The District Number and Item Number of the identified project. Please refer to Explanation of Item Number Series for further explanation.

PARENT NUMBER The year of SYP and KYTC Identification Number that the identified project was broken out of.

ROUTE The route prefix and route number where the project is located. For new routes, the route may be blank.

LENGTH Length of the project in miles, unless otherwise noted.DESCRIPTION A brief description and scope of the identified project, including

beginning and ending termini of project limits.MILEPOINTS The beginning milepoint(s) and ending milepoint(s) of the project

along the identified route(s).SCOPE Type of project work to be performed.PRECON FLAG Is identified as either "A" = Active Preconstruction Project or with an

"I" = Inactive Preconstruction projectPROJECT CONSTRUCTION NUMBER (PCN) KYTC Construction Contract Identification Number. This number

only appears for projects that have been let to construction, and is used in checking the status of current construction status of awarded construction phase.

AUTHORIZATION NUMBER KYTC project authorization identification number for MARS accounting information.

ENVIRONMENTAL REQUEST The type of the environmental activities and document underway or approved for the identified project.

ENVIRONMENTAL EXPIRATION DATE The expiration date of the approved environmental document. R/W SCHEDULED COMPLETION The scheduled completion date of right-of-way plans for the

identified project.LETTING STATUS The current letting status of the identified project. LETTING DATE The anticipated scheduled letting date, that is subject to change

depending upon numerous factors such as Environmental, Permits, Right-of-Way, Utility Relocations, Construction Plans, and available funding.

DESIGN BY The name of the Design Consultant or the KYTC Department conducting the project design activities.

KEY TO INTERPRETING INFORMATION PRESENTEDFY 2007- FY 2012 STATUS REPORT

Page 100: Project Development Academy (PDA) “Project Funding”

KEY TO INTERPRETING INFORMATION PRESENTEDFY 2007- FY 2012 STATUS REPORT

LABEL ITEM2004 HIGHWAY PLAN

FUNDING

PHASE

YEAR(Under the Label "2006 Highway Plan")

AMOUNT

PRECON DATA BASE

YEAR(Under the Label "Precon Data Base")

AMOUNT

STAGE

AUTH AMOUNT

OVERRUN/(UNDERRUN)

The current status of project funding. Estimated: The total funding for the phase has not been authorized. Authorized: The project funding has been authorized for the corresponding phase.Awarded: The corresponding construction phase has been let to construction and the construction contract awarded to contractor.Sent to FHWA: The federal programming document has been sent to FHWA requesting approval of federal participation for reimbursement to KYTC the federal share of the identified phase cost.Non-Six-Year: The corresponding phase is not scheduled in the Six-Year Highway Plan, but the corresponding amount is the estimated cost of the phase.Not Required: The corresponding phase is not required as originally anticipated.Reestimated: The identified phase and cost in the Six-Year Highway Plan has been moved or combined into another project.Pending: The request for funding has been submitted and KYTC authorization of funding is pending.

The amount of authorized funding for the corresponding phase.

The amount of authorized funding overrunning the original estimated Six-Year Highway Plan scheduled cost, or the amount underrunning the original estimated Six-Year Highway Plan scheduled cost.

DESCRIPTION OF ITEMThe identification of the current Six-Year Highway Plan.

The type of funds to be utilized for the identified project.

P = Preliminary Engineering and Early Public CoordinationD = Design phaseR = Right-of-way phaseU = Utility relocation phaseC = Construction phase

The fiscal year in which the identified phase activity is scheduled to be funded and should commence. Example: FY 2005 begins July 1, 2004 and ends June 30, 2005 for state funded projects, and for federal funded projects, FY 2005 begins October 1, 2004 and ends September 30, 2005.

The estimated cost of each identified phase and total cost of all identified phases.

The current project schedule and estimated cost.

The current fiscal year in which the identified phase activity is scheduled to be funded and should commence, based upon current status of project activities.

The current estimated cost of each identified phase and total cost of all identified phases based upon current status and requirement of project activities.

Page 101: Project Development Academy (PDA) “Project Funding”

Note: The Federal Funding Program is a reimbursement program. Thus, State Funds are used first to cover the costs, and then KYTC sends weekly invoices to FHWA for reimbursement of the federal share of the costs. The normal turn around time is approximately a 7 to ten days.

KEY TO INTERPRETING INFORMATION PRESENTEDFY 2007- FY 2012 STATUS REPORT

FUND CODE TYPE OF FUNDING

APD Federal Appalachian Development

BRA Federal Bridge Acceleration Funds (Demo)

BRO Federal Bridge Replacement on Federal System

BRX Federal Bridge Replacement on or off Federal System

BRZ Federal Bridge Replacement off Federal System

CM Federal Congestion Mitigation

FH Federal Forest Highway

GAR Garvee Bond Debt Service FD53

HES Federal Safety Hazard Elimination

HPP Federal High Priority Projects Defined by Congress

IM Federal Interstate Maintenance

JM1 Garvee Bonds I-65 Rehabilitation

JM2 Garvee Bonds I-75 Rehabilitation

JM3 Garvee Bonds I-64 Rehabilitation

KYD Kentucky Federal Discretionary Funding Defined by Congress

NH Federal National Highway System

RRP Federal Safety Railroad Protection

RRS Federal Safety Railroad Separation

SAF Federal Safety Funds

SHN Federal Surface Transportation Dedicated to Henderson

SLO Federal Surface Transportation Dedicated to Louisville

SLX Federal Surface Transportation Dedicated to Lexington

SNK Federal Surface Transportation Dedicated to Northern Kentucky

SP State Project funding

STP Federal Surface Transportation; Any Area

TE Federal Transportation Enhancement

Page 102: Project Development Academy (PDA) “Project Funding”
Page 103: Project Development Academy (PDA) “Project Funding”

The Oracle SYP Precon Status System is available for KYTC employees, upon submittal of request from the District Pre-Construction Engineer or Division Director to Ron Rigney in the Division of Program Management.

Page 104: Project Development Academy (PDA) “Project Funding”

The “Project Managers Toolbox” is available on the DOT intranet on the Division of Program Management’s home page.

Page 105: Project Development Academy (PDA) “Project Funding”

“Cookbook” Login Process to Access eMARS to Check

Available Budget & Current Expenditures

Page 106: Project Development Academy (PDA) “Project Funding”

1.Log into eMARS:

User IDs can be found on the Vender/Customer (VCUST) table within eMARS. To have a password reset, email [email protected] or call 502-564-9641 or 877-973-HELP.

Use address above to go to login screen. Or go to Kentucky Finance & Administration Cabinet homepage (http://finance.ky.gov/). Select eMARS in See Also… box on right side of screen. Under Applications, select eMARS (Financial Production).

Page 107: Project Development Academy (PDA) “Project Funding”

2. Click on Search on the left side of the screen:

Page 108: Project Development Academy (PDA) “Project Funding”

3. Select Page Search from list:

Page 109: Project Development Academy (PDA) “Project Funding”

4. Type “BQ39*” in Page Code field. Hit “Enter” key or click on “Browse”:

Page 110: Project Development Academy (PDA) “Project Funding”

5. Click on Funding Priority (BQ39LV1):

Page 111: Project Development Academy (PDA) “Project Funding”

6. A Search window will automatically pop-up when Funding Priority has been selected. Enter in search criteria (Department, Major Program, Program, etc.). Use * as a wildcard. Example: if you want to see all programs for a project enter “73701*”. If you want to see a specific program, enter “7370101C”. If the search window does not pop-up, click on “Search” to get the Search window.

Page 112: Project Development Academy (PDA) “Project Funding”

Available Balance

Date of Last Modification (07/01/2006 is the start date of eMARS)

Unfortunately, the Original Budget changes as modifications are made. Therefore, the Original Budget and Current Budget will always be the same.

If Start Date is 07/01/2006 (see below), then the Original Budget will be the available budget balance brought forward from MARS.

An ineligible line is set up for each project ($50,000 for federal projects, $25,000 for state projects). The ineligible budget should not be included in the available budget for the project.

Total Expenditures

Original Budget

Original Budget – Total Expenditures = Available Balance

Page 113: Project Development Academy (PDA) “Project Funding”