project brie vogtle nuclear power plant units 3 & 4 nuclear power plant...vogtle nuclear power...

1
Project Brief geocomp.com Vogtle Nuclear Power Plant Units 3 & 4 Background & Project Challenges The Vogtle Electric Generating Plant is southeast of Augusta, Georgia. Units 1 and 2 have been in operation for 20 years and produce approximately 2,400 megawatts of electric energy by nuclear power. Units 3 and 4 will more than double the electrical generating capacity of the facility. These will be the first nuclear- powered generating units to be built in the United States in the past 30 years. Each unit requires 90 feet of unacceptable soil to be removed and replaced with 50 feet of compacted structural fill. Approximately 2 million cubic yards of soil must be removed for each unit. Materials below the bottom of the excavation consist of hundreds of feet of alternating layers of clay, silt and sand. The Nuclear Regulatory Commission (NRC) requires field verification of the effective stiffness of these materials to improve the reliability of predictions of settlement of the reactor facilities. Geocomp Role & Accomplishments Geocomp assisted the general contractor, in selecting a method to monitor heave of the foundation soils continuously during the removal of the 90 feet of unacceptable soils. The monitoring points would be within the footprint of the excavation and exposed to the intense excavation activities. Requirements for the system were to minimize interference with the excavation activities, monitor heave (from a relative and absolute basis) and settlement continuously during this activity, and provide repeatability of at least ±1.5 mm. Geocomp recommended a monitoring system consisting of Borros anchors with rods to the surface, and displacement transducers at the top to monitor movement of the anchors relative to the top head for the anchors. The movement of the head would be monitored with a Leica automated total station located outside the excavation footprint. Movement of the total station would be measured by siting to reference prisms located outside the zone of influence of the excavation. In addition, three anchors at different elevations at each of five locations within each unit were installed. Vibrating wire piezometers were installed at each location to monitor pore pressure over time. Geocomp was responsible for procurement, installation and operations of the systems. PD11015 Client: Shaw Constructors, Inc. Location: Augusta, GA Services Provided: • Monitoring system recommendations for foundation soils • Procurement, installation, and operation of monitoring systems Value Provided: • Monitoring system recommendations alerted and minimized interference of construction activities

Upload: vuduong

Post on 24-Apr-2018

216 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Project Brie Vogtle Nuclear Power Plant Units 3 & 4 Nuclear Power Plant...Vogtle Nuclear Power Plant Units 3 & 4 ... the electrical generating capacity of the facility. ... Geocomp

Pro jec t B r ie f

g e o c o m p . c o m

Vogtle Nuclear Power Plant Units 3 & 4

B a c kg ro u n d &

P ro j e c t C h a l l e n g e s

The Vogtle Electric Generating

Plant is southeast of Augusta,

Georgia. Units 1 and 2 have been in

operation for 20 years and produce

approximately 2,400 megawatts of

electric energy by nuclear power.

Units 3 and 4 will more than double

the electrical generating capacity of the facility. These will be the first nuclear-

powered generating units to be built in the United States in the past 30 years. Each

unit requires 90 feet of unacceptable soil to be removed and replaced with 50 feet

of compacted structural fill. Approximately 2 million cubic yards of soil must be

removed for each unit. Materials below the bottom of the excavation consist of

hundreds of feet of alternating layers of clay, silt and sand. The Nuclear Regulatory

Commission (NRC) requires field verification of the effective stiffness of these

materials to improve the reliability of predictions of settlement of the reactor

facilities.

G e o c o m p R o l e & A c c o m p l i s h m e n t s

Geocomp assisted the general contractor, in selecting a method to monitor

heave of the foundation soils continuously during the removal of the 90 feet of

unacceptable soils. The monitoring points would be within the footprint of the

excavation and exposed to the intense excavation activities. Requirements for

the system were to minimize interference with the excavation activities, monitor

heave (from a relative and absolute basis) and settlement continuously during this

activity, and provide repeatability of at least ±1.5 mm.

Geocomp recommended a monitoring system consisting of Borros anchors

with rods to the surface, and displacement transducers at the top to monitor

movement of the anchors relative to the top head for the anchors. The movement

of the head would be monitored with a Leica automated total station located

outside the excavation footprint. Movement of the total station would be

measured by siting to reference prisms located outside the zone of influence of

the excavation. In addition, three anchors at different elevations at each of five

locations within each unit were installed. Vibrating wire piezometers were installed

at each location to monitor pore pressure over time. Geocomp was responsible

for procurement, installation and operations of the systems.

PD11015

Cl ient :

Shaw Constructors, Inc.

Locat ion :

Augusta, GA

Serv ices Prov ided:

• Monitoring system recommendations for foundation soils

• Procurement, installation, and operation of monitoring systems

Va lue Prov ided:

• Monitoring system recommendations alerted and minimized interference of construction activities