India’s plan is for 8-9% of GDP growth; which would require corresponding growth in electricity generation
Coal based electricity generation capacity is 54.8% by March 2011 (99,503 MW out of total of 181,558 MW)
By 2030,it may reach around 450,000 MW
This would lead to
Huge Investment needs
Depletion of natural resources (coal & water)
Higher emissions to environment
EE R&M: Present National Scenario
Renewable Sources of Power Generation
New Capacity Addition
Renovation & Modernization (R&M)of old plants(>25
years)
Energy Conservation
Supply Side and Demand Side Management
EE R&M: Power Generation Options - Feasible Alternatives
Grid Access/Switchyard.Cooling water Availability.Access to Infrastructure.Permission for Power generation and evacuation.Fuel Supply agreements.Trained Operation and Maintenance Personnel.Administrative facilities and residential
accommodation
EE R&M of old PS: Comparative Edge owing to existing facilities
EE R&M of old PS: Improvement required in 25 years old units
Due to continuous operation, many of the plant equipment and system have undergone ageing process, resulting in:- Reduced output. Technological Obsolescence.
Large number of smaller capacity, very old units like 50 / 62.5/100/210/500 MW are operating with poor efficiency, which may become techno-economically viable after RLA and Energy Audit study.
The concept in R&M has recently shifted from primarily generation maximization & remaining life extension, to performance enhancement at the same time that is Energy Efficiency, Net heat rate (NHR) Improvement.
Coal is an exhaustible natural resource. Hence, its saving by way of increasing old plants efficiency is desirable. EE-R&M helps in lowering specific coal consumption, increased plant availability hence it’s cost effective .
Present day R&M concept: Energy efficiency Enhancement
Old plants can be renovated and Modernized at lower costs and optimum life extension is achieved.
R&M implementation is carried out during longer / annual shut down, there by assuring sustained power to users.
Availability and efficiency can be improved. Energy Conservation, reduction in Aux. power consumption &
performance improvement is achieved, new tech. adopted. No R&R problems. For new plants Limited availability of new site, land, water and road etc.
and power evacuation. High initial cost, longer gestation period of new plant. To comply to Stringent Environmental and safety norms. Coal, Water Linkages and Land Litigation becoming hurdles in
Green/Brown Field Plants
EE R&M of old plants Vs new plants: Comparative Edge
The benefits accrued from EE-R&M in a typical 200/210 MW (LMZ) steam turbine unit include:
• Restoration / Increased output by about 3 to 5 % of the design rating.
• Improved unit heat rate by 2 to 2.5 % of design value resulting in fuel saving .
• Extending Plant Life by about 15-20 years with very low outages
• Additional economical power generation from old units becomes available in short duration.
Present day R&M concept: Energy efficiency Enhancement
Performance evaluation and conductance of energy audit of the old units is most desirable in addition to RLA study of complete plant for designing the scope of work for EE R&M.
Present day R&M concept: Energy efficiency Enhancement
To enhance Life of Units by 15-20 years.
Improve PLF above 85%,
Increase availability above 90%,
Up-gradation/Restoration of Rated Load considering the present worst coal GCV.
Reduction in Auxiliary consumption
Ensure emission level (SPM) sustained below 50-70 mg/Nm3 at full load.
To evaluate the different option of up-rating the unit.
To improve unit net heat rate as compared to design.
Key objectives of the EE-R&M study
Go through QCBS procedure of selection and select the best agency Selection may be in 70:30 weight ratio for selection of key
design specialist of Boiler, Turbine, C&I, Generator , BOP etc. and Price.
Mere selection on L1 basis may not meet your objectives of study Judge the technical capability also, based on(not only QR):-
ask for Procedure/methodology to be followed and grade accordingly
ask for manpower available presently and to be deployed, can one keep provision to ensure at site?
ask to submit list of calibrated instruments to be used for measurements of the Parameters
Right Selection process Selection of Right agency Right Study and evaluation Meeting the objectives
Selection of EE R&M Design Consultant
Preliminary Survey Carrying out RLA & Report preparation
Conducting Energy Audit & Report preparation
Preparation of Technical Audit Report
Step- I
Step- IIPreparation of DPR , techno-economic viability of various options
Step- IIITenderization process up to order finalization and handing over the job to ISC Step – IVProviding support to owner during execution of job (optional)
Plant may take guidance from R&M Design Consultant
Services offered by a design consultant:
1. Review previous studies carried out on the unit
2. Carrying out technical audit of the various equipment and related BoP
3. Undertake energy audit for baseline assessment of the entire unit
4. Undertake RLA/LE study of Boiler, Turbine including steam path audit , Generator & electrical equipment & Civil structures and foundations of unit.
5. Prepare an exhaustive list of Run/Repair/Replace decision Matrix for various equipment including Valves, Hangers and Supports, Expansion Joints, Ducts, Insulation, Motors, Cables, Pumps, Fans, C&I equipment, Impulse lines , etc
6. Assess techno-economically various R&M options
Steps of activities of design consultancy
7. Prepare the detailed Scope of Works with cost estimate and assess the cost effectiveness of alternative rehabilitation options including new Units and suggest the optimum solution
8. Prepare a DPR giving the various options (including scope of work in each option), techno-economic financial analysis of various options and recommend the best option for Energy Efficient rehabilitation project including strategy for dealing with surprises.
9. Prepare the Bidding documents both Technical and Commercial.
10. Assist the owner through the bidding process
11. Assist in Post bid discussions and award.
Steps of activities of design consultancy
Presently working on four(4) EE-R&M assignments as Design Consultant Awarded through QCBS(Quality & Cost Basis Selection)of the World Bank. 1. Panipat Thermal Power Station (2x110 MW),HPGCL Draft DPR
submitted
2. Chandrapur Super Thermal Power Station(2x210 ,MSPGCL Energy Audit and RLA for both units completed and reports submitted except that for Unit#1 RLA
3. Bhusawal Thermal Power Station (1x210 MW),unit no.2, MSPGCL
RLA is completed on boiler, turbine, generator, elctrical, civil structures & steam path audit. Energy Audit also completed.
4. Parli Thermal Power Station (1x210 MW),unit no.3, MSPGCL Energy Audit is in progress
Energy Efficient Renovation & Modernization (EE R&M)