pre-feasibility reportenvironmentclearance.nic.in/writereaddata/online/tor/0_0_13_nov... ·...
TRANSCRIPT
Pre-Feasibility Report (As per MOEF&CC circular dated 30th Dec 2010)
Proposed Industrial Park at
Gandrajupalle Village, Gangavaram Mandal,
Chittoor District, Andhra Pradesh
Submitted to:
The Director (IA-III)
Ministry of Environment & Forest & Climate Change, Indira Paryavaran Bhawan, 3rd floor, Vayu Wing, JorBagh,
New Delhi-110003
Submitted by:
Andhra Pradesh Industrial Infrastructure Corporation
(APIIC) APIIC, 4th floor, Fateh Maidan Road,
Hyderabad-500 004.
Consultant
Ramky Enviro Engineers Limited. 2nd floor, Ramky Grandiose, Ramky Towers
Gachibowli, Hyderabad (QCI/NABET Approved - Certificate No. NABET/EIA/1013/016)
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram
Mandal, Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad, i
TABLE OF CONTENTS
Section No Description Page No.
Chapter 1 – Pre-Feasibility Report
1.1 Preamble 1
1.2 Project Rationale 2
1.3 Need for the Project 4
1.4 Feasibility of the Project 6
1.4.1 Land Break-up of the Project 7
1.4.2 Industrial Area – Processing Area 8
1.4.3 Road Network 9
1.4.4 Road Design Criteria 9
1.4.5 Landscaping 9
1.4.6 Storm Water Drainage System 10
1.4.7 Drainage 10
1.4.8 Water Supply Network 11
1.4.9 Raw Water Sourcing And Storage 11
1.4.10 Water Demand 11
1.4.11 Power Supply and Control System 11
1.4.12 Street Lighting 11
1.4.13 Fire Hydrant 12
1.4.14 Manpower Requirement 12
1.4.15 Wastewater Generation 13
1.4.16 Solid Waste Generation 13
1.5 Techniques of Cleaner Production - Energy Efficiency (CP-EE) 13
1.6 Financial Analysis of the Project 15
1.7 Rehabilitation and Resettlement Plan (R & R) 15
1.8 Financial and Social Benefits 15
1.9 Employment Potential 16
1.10 Benefits to the Region 16
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram
Mandal, Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad, ii
LIST OF TABLES
Table No. Contents Page No.
1.1 Location Coordinates of Site Boundaries Falling In Respective
Villages 1
1.2 Land use Area Break-up 7
1.3 Proposed Industries in Industrial Park 8
1.4 Category of Industries with No of Plots 8
1.5 Power Requirement Details 11
1.6 Technical Details of Street Lighting System 12
1.7 Man Power Requirement Details 12
1.8 Project Cost Break-up Details 17
LIST OF FIGURES
Figure No. Contents Page No.
1.1 Location Map of the Project Site 2
1.2 Topographical Map of the Project Site 3
1.3 Layout of the Proposed Project Site (Tentative) on Google Earth 5
1.4 Common Infrastructure 6
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 1
PRE-FEASIBILITY REPORT
1.1 Preamble
Andhra Pradesh Industrial Infrastructure Corporation Ltd (APIIC) is the premier organization in
the state of Andhra Pradesh, vested with the objective of providing industrial infrastructure
through the development of industrial areas. The corporation has so far developed over 320
industrial parks spreading over an extent of about 1,30,000 acres. This includes IT, Bio-Tech,
Automotive, Apparel, Pharma, Leather, SEZs with its expertise in providing Industrial
infrastructure. The Corporation is also developing sector focused parks like Edible oil units,
Auto Parks, Textiles processing parks, Leather parks in the state of Andhra Pradesh.
With the advent of economic liberalization the Corporation has reoriented itself to the changing
needs of economy and assumed the role of facilitator. To its credit the Corporation has developed
Hi-Tech city with a private promoter. The corporation is the principle facilitator in Mega
Projects like Special Economic Zone, Visakha Industrial Water Supply, Gangavaram Port,
Convention Centre, Mega Industrial Parks at Parawada, Pashamylaram, Financial District, and
Hardware Park at Hyderabad.
The Corporation has to its credit the execution of civil works for various Government
Departments. It has executed works covering Referral Hospitals, Navodaya Schools Polytechnic
Buildings Court Complex, Building and Hostel for Indian Institute of Information Technology.
Government entrusted the responsibility of constructing Games Stadium and Games Village for
the National Games on Project Management Basis. The Corporation is the Nodal Agency for
Government Sponsored scheme like Growth Centres, Export Promotion Industrial Parks, and
Integrated Infrastructure Development Centers.
The Industrial Areas are equipped with approved layouts, internal roads, water supply and power
supply. In continuation with above said works, APIIC is planning to establish an Industrial Park
in an area of 482.51 Acres (195.2 ha.) in the village Gandrajupalle of Gangavaram Mandal,
Chittoor District. The location coordinates covering the proposed Project Site boundary are given
in Table 1.1.
Table 1.1: Location Coordinates of Site Boundaries Falling In Respective Villages
S.No Village Name Latitude Longitude
1 Gandrajupalle
13040’ 36.5”N 78º56’06.9” E
13040’ 33.0”N 78º56’05.0” E
13039’ 52.0”N 78º53’28.0” E
13039’ 44.0”N 78º55’20.9” E
13039’ 19.5”N 78º56’43.7” E
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 2
Location Analysis
Availability of commercial and social infrastructure
Ample availability of cost effective land.
Availability of skilled man power.
1.2 Project Rationale
Industrial Parks have a tremendous socio-economic impact on Indian economy. Industrial Parks
have contributed to the growth and development of the Indian Economy in terms of exports,
employment and investments. It is the key growth driver of Nation's economy and has made the
country globally competitive.
The location map of the proposed project site is shown in Figure 1.1 & Topographical map is
shown in Figure 1.2.
Figure 1.1: Location Map of the Project Site
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 3
Figure 1.2: Topographical Map of the Project Site
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 4
1.3 Need for the Project
The main reasons for establishing the Industrial Park near Gandrajupalle village, Gangavaram
mandal is:
To improve the Industrial Infrastructural facilities in Chittoor district of A.P
Availability of World class Business groups at the nearest cities like Bengaluru (around
92 km) ) & Chennai (around 169km).
Good infrastructure availability at short distance less than 55 km (Chittoor, District
Head Quarters)
Availability of skilled manpower at short distance less than 60 km
Government's positive attitude towards the industrialization
Concept of Development for Industrial Park
Indian economy has witnessed tremendous growth in the last decade primarily due to the
contributions made by the exports. In order to augment the growth of the exports the
Government has set up Special Industrial Parks which would provide a hassle free and
internationally competitive environment for companies. The exports have been facilitated by
the growth in a number of industries such as chemicals and pharmaceuticals, readymade
garments, iron ore, machinery and equipment etc.
Southern India houses the majority of Industrial Parks. With a view to facilitate large scale
development of a number of industries APIIC proposes to establish an Industrial Park in the
State. The Industrial Park would provide infrastructure support and other incentives for the
growth of most lucrative businesses in the State. The APIIC would provide infrastructure
support for the proposed Industrial Park. The Industrial Park would encompass firms from
different industries such as textiles, automotive industry, engineering industry, Glass&
ceramic, Electric & electronics and leather appliances etc.
The proposed Industrial Park is 18 km away from Gangavaram Mandal having head quarters
in Chittoor. The district head quarters Chittoor is about 55 kms from the area and the nearest
big city having all communication and marketing facilities is Bengaluru at a distance of
92km. The area is well connected with BT roads from Gandrajupalle. The BT road from
Palmaner town which is 16 k.m from Project Site to Mulbagal of Kolar District in Karnataka
passes near to the Industrial Park area. Chittoor railway station is around 52 k.m from the
Project Site. The road and railway connections have lent very high prominence to the area
under consideration.
The role of the APIIC for the proposed Industrial Park will consists of developing common
infrastructural facilities - roads, water, power, drainage, street lightening and green belt etc.
Social Infrastructure - Banks, Post Office, canteens, primary health centre, etc. The Industrial
Park will also have an Industrial Area Local Authority for maintenance of the Industrial Park,
approval of building plans etc. the layout of the proposed Industrial Park is shown in the
Figure 1.3.
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 5
Figure 1.3: Layout of the Proposed Project Site (Tentative) on Google Earth
Establishment of an Industrial Park promises to change the existing scenario and cluster the
scattered community in and around the region. The setting up of the Industrial Park is
expected to provide a major boost to the state's multiproduct sector by ensuring a fair share of
export revenues and also by raising the living standard of workers. The setting up of the
Industrial Park is also expected to bring about a marked improvement in the operational
efficiency of the units in the state and reduce the monopoly of merchant exporters.
The proposed Industrial Park will develop all amenities required for environmental friendly
operation of units, and other units which can be occupied by the industrialists without any
administrative hassles associated with setting up of an industry. The following are the
highlights of the project.
The proposed Industrial Park is having sufficient area to house good number of
multiproduct industries.
The entire Industrial Park will come up in a planned manner with an approved layout
taking into consideration all the statutory requirements.
The park will have well-planned uniform and common infrastructure facilities like
roads, storm water drains, rain water harvesting pits and greenbelt.
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 6
The Industrial Park will have uninterrupted power supply.
The Industrial Park will have a well-planned water supply system.
The sample photos regarding facilities to be provided in the proposed Industrial Park are
shown in the Figure 1.4
Figure 1.4: Common Infrastructure Sample Photos
Water Storage and Supply Power Supply
Storm water drainage system Roads Network, Street Lighting & Greenbelt
1.4 Feasibility of the Project
Detailed feasibility studies were carried for the proposed Industrial Park. The results of the
study are very encouraging and instilled confidence in the project proponents about the
success of the project.
The study was carried out in a systematic way starting with site suitability studies to the
financial feasibility of the project by assessing the demand through personal interviews with
some of the industrialists.
The demand assessment summary based projections were also carried during the study.
The basic infrastructure covers the main requirements like
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 7
Water - Water treatment facility
Power
Roads
Street lights
The environment infrastructure covers:
Green Belt
Storm Water drains
Waste water treatment facilities
Solid waste collection and disposal facilities
Other Infrastructure - Industry specific
Fire fighting facilities
Security etc.
First aid facilities
Canteen
Inline to the above the social infrastructure or Common Facility Centers (C.F.C) would be
provided by the APIIC in order to make the facility ready for occupation by the industries as
early as possible. The following facilities will be provided as part of the social infrastructure
development:
Buses. Bust stand
Post offices, Banks
Parks and open spaces
Restaurants, etc
1.4.1 Land Break-up of the Project
The details of the land allotted for various purposes viz. industrial activity, common facilities
and green belt, etc as per the master plan and presented in the Table 1.2. The Project Layout
is enclosed as Appendix-I.
Table 1.2: Land use Area Break-up
S.No Land use Type Area
(in Acres)
Area
(in Hectares)
Allocation
(In %)
1 Plotted area 314.37 127.22 65.10
2 Green Belt and Open Space for Green
Belt 76.62 31.00 15.86
3 Road Network 73.97 29.93 15.32
4 Common facilities Area 17.55 7.10 3.63
Total 482.51 195.25 100
Note: 1. over all 33% of the total area will be maintained as green belt at park level
15.86% at industrial park level i.e. 76.62 acres (31ha)
In addition to this, greenbelt will be maintained by individual plot owners as per norms.
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 8
1.4.2 Industrial Area – Processing Area
The proposed Industrial Park is designed based on the market value potential and demand
assessment study for sector of industries to be established in the Industrial Park. The type of
industries proposed for Industrial Park is given in Table 1.3 & category of Industries with no.
of plots are given in Table 1.4.
Table 1.3: Proposed Industries in Industrial Park
S.No Type of Industry (with Sub Segments)
1 Light Engg.Industries (like Bearing Industry process Control Sys, Steel Forging)
2 Textiles & apparels
3 MSME(Micro, small & Medium Enterprises)
4 Agro & Food allied Industries, Dairy based
5 Leather & foot wear Mfg.
6 Spun Pipes
7 Glass & ceramic
8 Green house for Sericulture
9 Paper products
10 Electrical & Electronics
11 Any other
Table 1.4: Category of Industries with No. of Plots
S.No Sector Type of Industries Classification
as per SPCB
Area
(acres)
No.of
Plots
Proposed
1 Sector-1 MSME - 53.87 39
2 Sector-2 Light Engineering Industries Green 60.09 35
3 Sector-3 Agro & Food Allied Industries orange 44.75 17
4 Sector-3 Green House For Sericulture Green 10.46 2
5 Sector-4 Glass & Ceramic Green 12.77 6
6 Sector-5 Paper Products Orange/Green 10.46 5
7 Sector-6 Spun Pipes
20.96 7
8 Sector-7 Electrical & Electronics Green 7.34 3
9 Sector-8 Leather & Foot Ware
Manufactures Green 34.30 6
10 Sector-9 Textile Orange/Red 59.41 12
Total: 314.41 132
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 9
1.4.3 Road Network
The proposed site is well connected to the Gangavaram Mandal Head quarters. The proposed
internal road network in the Industrial Park has been planned as Type I: Road with median
having 2-lane carriage-way on both the sides. After placing the road the utility requires a
minimum space of 3 to 4 m. on either side to accommodate water supply lines, sewage
conveyance lines, storm water drains, overhead electrical lines etc. So, the minimum Right
of Way (RoW) planned is 24 /30 m. main corridor and 15/18 m. for inner roads.
Area allotted for Roads is 73.97 acres. (15.32% of overall site area). In order to maximize
the land values and minimize the land taken by major and minor roads, hierarchy of roads is
proposed to ensure a smooth traffic movement inside the Industrial Park Site planning
intentions have been guided by the desire to minimize on expensive road works by utilizing
100% of all existing roads. The road pattern in the Industrial Park is in a grid system with
major axis leading from main entrance. The widths of the roads proposed in the Industrial
Park are designed to cater heavy goods vehicle and container specific. The main spine road
will be a major traffic collector into and out of Proposed Industrial Park.
1.4.3 Road Design Criteria
Roads of this Industrial Park are generally catering for:
Movement of goods/machinery/finished products through heavy vehicles.
Movement of persons through light vehicles including cyclist/pedestrian. Other roads
around parking area shall be considered for aesthetic and pleasing lighting systems.
Basic requirement of road lighting shall be as follows:
Adequate level of illuminations for heavy vehicles/light vehicles/cyclist
Uniform illumination level over the carriage way with minimum glare.
Safety of movement
Minimum disturbance during dust conditions.
Use of high efficiency lighting fixtures with high lumen output and low power
consumption.
Power supply to road lighting system shall be fed through underground PVC insulated
armored, aluminum conductor cables.
1.4.5 Landscaping
The landscape concept would be to create a ‘park like’ environment within the proposed Industrial Park. Lush greenery with extensively landscaped areas is set aside within the site
such as entrance plaza and perimeter fringes to ensure that forested landscape areas are
achieved. These areas shall not be used for any use other than the prescribed use. However,
these areas may be used to have natural drains, which are not cemented but lined with
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 10
interlocking blocks to ensure percolation of rain water and such drains will be used to convey
rain water runoff.
While linear planting is to be carried out along the roads, informal and mass plantings are
proposed for landscape areas. About approximately 15.86 %( 76.62 acres) of the land within
the Industrial Park has been allotted for green belt. These are maintained by the Nodal
developer and comprise of:
Linear Green Stripes
Defined landscape areas at the entrance gateway and pocket parks within the
Industrial Park.
The following guidelines are followed to achieve the nature of landscape envisaged.
To complement the network of roads, the road side trees are very important. Large
shade trees are planted at 10 m. center to center to achieve a canopy environment in
the shortest possible time.
The buffer zone would be densely planted with quick growing trees to have the forest
effect. Here, function screening is the main priority, thus heavy foliage and low
branching trees are preferred. To create identity, different areas will have different
varieties planted-one area for colour, one area for form, one area for fragrance and
one area for shade.
1.4.6 Storm Water Drainage System
Surface drains with trapezoidal section will be provided along the roads for storm water flow
utilizing the natural slopes to design an economical system. The entire storm water drainage
system for the proposed Industrial Park will be planned utilizing the natural slopes to design
an economical system. The area forms part of plain with gentle sloping topography. The
general slope is towards East. The highest contour in the area is 750 m (spot height) which is
lying South from the Project Site area. The general elevation ranges between 232 to 750 m.
msl. Separate Provision of funds will be provided for developing storm water management
and rain water harvesting works.
1.4.7 Drainage
The area is having good drainage density with sub-articulate to sub-parallel drainage pattern.
All the drainage in and around the Project Site area flows towards the North direction and
drains into Mudi Cheruvu and finally it flows though small river and finally reaches to the
Kaundanya River which the river is flowing from North to South-East and is around 11.2 k.m
towards East from the Project Site. There are many water tanks outside the Project Site which
are being fed by local drains and streamlets originating in their vicinity. The general slope of
the area is towards East and is less than 3%.
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 11
1.4.8 Water Supply Network
Water is one of the major resources for industries coming up in the proposed Industrial Park.
It is directly used in the process and also other uses like floor washings, domestic purposes,
utilities and green belt development etc.
1.4.9 Raw Water Sourcing and Storage
As part of the Industrial Park, a storage reservoir has been proposed. The reservoir shall be
fed with the water supply and will be the ultimate source of water for the proposed Industrial
Park. The water for the proposed multi product Industrial Park is sourced from nearby
Kowndinya River which is 11.2 km. from the Project Site. A total of 3.5 MLD water is
required which is allotted by the State Government.
1.4.10 Water Demand
The water demand includes all forms of water use such as water required for production
units, workers, commercial use and landscape irrigation. In addition, the Industrial Park
would also require adequate provision of water for fire fighting. The primary source of water
is from Kowndinya River.
1.4.11 Power Supply and Control System
The proposed Industrial Park will house different sized plots accordingly the load demand
has been worked out to be 50 KW/acre has the total power requirement for been considered
for the load calculation of the Industrial Park. The proposed Industrial Park is 16.5592 MW
for the total units proposed in the multi Sector Industrial Park. A substation of 220/130 KV
and 33/11 KV capacity sub-station has been proposed. The power requirement details are
given in the Table 1.5 below:
Table 1.5: Power Requirement Details
S.No Details Land Assumed
KW/Acre
Power Required
KW MW
1 Industrial Area 314.37 50 15718.5 15.7185
2 Common Area, GB and Roads 168.14 5 840.7 0.8407
Total: 482.51 55 16559.2 16.5592
For plotted area 50 KW/acre has been considered.
For Common area 5 KW/acre has been considered
The total power estimated for the proposed Industrial Park approximately 16.55 MW
1.4.12 Street Lighting
Street lighting is proposed to be provided on either side of the road all along the length on
stepped tubular poles each provided with 1 x 250 W HPSV lamps in a staggered manner.
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 12
Power for the street lights shall be drawn from AP TRANSCO and shall be distributed
through underground cabling network. Power supply to road lighting system shall be fed
through aluminum conductor cables. The technical details of street lighting system are shown
in Table.16.
Table 1.6: Technical Details of Street Lighting System
S.No Description 30m RoW 24m RoW 18M RoW
1 Pole arrangement Twin arm pole on
center verge
Single arm pole
on one side of the
road.
Single arm pole
on one side of the
road.
2 Type of lighting
fixtures
250W, HPSV
lamp
150W, HPSV
lamp
150W, HPSV
lamp
3 Tilt of fixture 10o 10o 10o
4 Lamp lux 25,000 lumens 13,500 lumens 13,500 lumens
5 Mounting height 9.5 m 9.5 m 8 m
6 Spacing 25M-30 m 25M-30 m 25M-30 m
1.4.13 Fire Hydrant
External fire hydrant double outlet, stand post type, as per IS: 908 are proposed on main
water supply distribution lines as per requirement. Fire brigade inlet connections and draw off
connections will be provided into the distribution system at water works site.
1.4.14 Manpower Requirement
The total manpower requirement for the project can be primarily divided into two categories,
manpower requirement during construction phase and manpower requirement for operations.
The manpower requirement during the construction stage is basically construction labor.
The manpower requirement during operations basically depends on the industries proposed to
be located in the park. The estimated total manpower requirement on completion of the
project work during operation of all the industrial units in the park is projected.
The total manpower requirement is estimated and is given in the Table 1.7:
Table 1.7: Man Power Requirement Details
S.No Details Permanent Temporary Total
1 Operation 6128 2043 8171
2 Construction 372 457 829
Total: 6500 2500 9000
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 13
1.4.15 Waste water Generation
The sources of wastewater from the Industrial Park are from the industrial units. Industries
would be using water for manufacturing activities and for operating utilities viz., boilers etc.
The quantification of wastewater generated from the Industrial will be measured as below:
Wastewater generation considered from Process: 80% of the water requirement
Wastewater generation considered from Domestic needs: 90% of the water requirement
At unit level, the process effluents will be segregated into high and low TDS and treated
respectively, the treated water will be reused and zero discharge will be maintained, similarly
the domestic sewage will be treated in ETP/STP or septic tank/soak pit, the treated water will
be reused for flushing, green belt and dust control measures. The treated water would be
mostly reused for greenbelt.
1.4.16 Solid Waste Generation
In Construction stage- no demolition waste will be generate due to open land for the proposed
project and In operation Stage- Required preventive measures (as per MSIHC rules) will be
considered which are hazardous to human health or the environment (flora, fauna and water
supplies and for solid waste (degradable waste) R4 Reduce reuse recycle and recover other
than this category waste will opt for landfilling or incineration method.
1.5 Techniques of Cleaner Production - Energy Efficiency (CP-EE)
The new and creative approach to enable less waste intensive production is based on different
techniques will be adopted by regular up-gradation of process technology. These techniques
are as here under.
Source Reduction Under this category, 5 techniques of CP - EE are briefly discussed
below:
Good Housekeeping: Systems to prevent leakages and spillages through preventive
maintenance schedules and routine equipment inspections. Proper working
instructions, supervision and regular training of workforce would facilitate proper
housekeeping.
Process Change: Under this head, four CP - EE techniques are covered:
Input Material Change - Substitution of input materials by eco-friendly (non-toxic
or less toxic than existing and renewable) material preferably having longer service
time.
Better Process Control Modifications of the working procedures, machine-operating
instructions and process record-keeping in order to run the processes at higher efficiency and
with lower waste generation and emissions.
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 14
Equipment Modification - Modification of existing producing equipment and
utilities, addition of measuring and controlling devices, in order to run the processes
at higher efficiency and lower waste and emission generation rates.
Technology Change - Replacement of the technology, processing sequence and/or
synthesis pathway in order to minimize waste and emission generation during
production.
Recycling
a. On-site Recovery and Reuse - Reuse of waste materials in the same process or for
another useful application within the industry.
b. Production of useful By-Product - Modification of the waste generation process in
order to transform the waste material into a material that can be reused or recycled
for another application within or outside the company.
Product Modification Characteristics of the product can be modified to minimize the
environmental impacts of its production or those of the product itself during or after
its use (disposal).
Benefits of adopting CP-EE The benefits of integrating CP and EE (CP - EE) are as
follows:
Structured approach for long-term viability of EE: EE improvement programmes
alone have often been unsustainable because they lacked well-structured CP
methodology for addressing together energy and environment issues. This has been
compounded by a lack of professionals with the multi-skills needed to integrate
energy management with other environmental issues. Incorporating EE into the well-
established and structured CP approach would help to ensure the long-term viability
of EE measures.
Global business mandates, Conventions and Protocols: Global business mandates,
conventions and protocols expressing international concern for resource conservation,
energy and environment.
Stand-alone CP or EE measures not always attractive: CP or EE measures not
always attractive. CP solutions are not attractive, if resources are low priced or
subsidized. By combining it with energy efficiency, more attractive solutions can be
proposed. Alternately, CP-EE may enhance the attractiveness of reducing energy
consumption in cane of low energy costs.
Other benefits of CP-EE:
o Conservation of Raw Material and Energy
o Lower Costs
o Improved Environment
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 15
o Better compliance with environmental regulations
o Better working environment
o Quality improvement
o Improved efficiency/productivity
o Better access to finances
o Market requirements
o Public Image
1.6 Financial Analysis of the Project:
The proposed Industrial Park is a service industry and the major operational expenditure is
towards the power, fuel consumption, chemical consumables, repairs and maintenance,
salaries, administration costs etc. Therefore, operational skills attain a lot of significance in
this project. Initial project establishment cost is crucial in successful establishment and
operation of this project.
The Capital costs have been worked out on the basis of prices prevailing today and do not
include any provision for future escalation in costs during implementation period. As per
initial estimate, the cost of the project works out to around Rs. 96.5 Crores. After examining
the Environmental feasibility and Commercial & financial feasibility, it may be inferred that
the project will have a positive feasibility. The project cost is given in Table 1.8.
Table 1.8: Project Cost Break-up Details
S.No
. Activity Measurable Basis of Cost
Total Cost
(Lakhs)
Total Cost
(crores)
1 Land Development charges
including all amenities
482.51
acres
Rs. 20
lakhs/grass area 965020000 96.502
Total:
96.5
Likely date of start of construction work: 2017
Likely date of completion of construction work: 2019
1.7 Rehabilitation and Resettlement Plan (R&R)
The proposed Industrial Park does not envisage any disturbance to local community or the
village since the land is acquired and fully owned by the APIIC. The proposed project will
not affect the home oustees, land oustees and landless laborers hence, no requirement of R&R
Implementation in this project.
1.8 Financial and Social Benefits with emphasis on the benefit to the local people
including tribal population if any, in the area.
The proposed project is expected to bring significant socio-economic and environmental
benefits both at local level as listed below:
Pre-feasibility Report for Industrial Park at Gandrajupalle Village, Gangavaram Mandal,
Chittor District, Andhra Pradesh
M/s. Ramky Enviro Engineers Ltd, Hyderabad 16
Social Infrastructure:
Social awareness programs will be improved by the local authority such as sanitation
and hygiene, other communicable diseases &HIV Prevention Program etc.
Adult education and female education programme is planned to the illiterate adults
and backward females of the villages in the project surrounding area.
Infrastructure & connectivity facilities and other amenities will be improved in the
region which will helpful to the surrounding local people.
1.9 Employment Potential
The project is going to create some employment. Due to this project activity, some persons in
the project area will be recruited as skilled and semi-skilled workers by the company as per
its policy. Therefore, some employment and income are likely to be generated for the local
people. So, the project will contribute in a positive manner towards direct employment in the
project area.
1.10 Benefits to the Region
The company will supply its product to the domestic market which is likely to improve the
regional economy.
Peripheral Developments
APIIC intends to take up developmental work in the periphery area. The activities that have
been considered include the following:
Support existing schools for development of education in the area.
Help in imparting vocational training to local eligible youth.
Provide health facilities by way of medical checkup, by holding medical camps etc. in
the neighborhood.
Thus, the proposed project shall usher in the social and economic upliftment of the persons
living in the vicinity of the Project i.e. of society at large.
Proposed Industrial Park at Gandrajupalle Village, Gangavaram Mandal, Chittoor
District, Andhra Pradesh
Appendix-I
Project Layout map
TO
BA
NG
AL
OR
ET
O C
HIT
TO
OR
32
5
LA
ND
AL
LO
TT
ED
TO
FA
RM
G
AT
E A
GR
O.
SU
GU
NA
PO
ULT
RY
7.0
0
24
.00
5.2
50
18
.00
5.2
50
7.5
0
CLIE
NT
:
PR
OJE
CT
:
NO
TE
S
CO
NS
UL
TA
NT
:
Tow
ard
s s
usta
inab
le g
row
th