agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015 Better Portfolio Prioritization with the Lean Canvas Brad Swanson, CSC, CST® [email protected] @bradswanson Mike Caspar, CSP, Senior Agile Coach [email protected] @mikecaspar http://www.agile42.com/en/blog/

Upload: mike-caspar

Post on 09-Aug-2015

190 views

Category:

Leadership & Management


2 download

TRANSCRIPT

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015

Better Portfolio Prioritization with the Lean Canvas

Brad Swanson, CSC, CST® [email protected] @bradswanson

Mike Caspar, CSP, Senior Agile Coach [email protected] @mikecaspar

http://www.agile42.com/en/blog/

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

agile42  The  Agile  Coaching  Company.  agile42 is a market leader in providing agile transformation services to companies looking to adopt a more efficient and adaptive way of working.By continually refining our approach, agile42 has developed a unique and proven framework for supporting organizations in realizing the benefits of a agile & lean practices. We provide assessment, strategic consulting, training, and coaching to get you results. Our customers regularly confirm that they achieve:• Accelerated revenue generation

• Faster Return-on-Investment

• Improved technical quality

• Rapid delivery to market

• Increased team motivation

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Photo: Rory Mizen

Highest Paid Person’s Opinion

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

1.  Problem  

top  3  problems  

Exis2ng  alterna2ves

4.  Solu2on  top  3  features

8.  Key  metrics  e.g.  AARRR

3.  Unique  value  

proposi2on  Clear  compelling  message.  Why  makes  you  different?  

2.  Customer  segments  

Target  customers  

Early  adopters?

9.  Unfair  advantage  Not  easily  copied  

or  bought

5.  Channels  Path  to  customers

7.  Cost  Structure  Customer  acquisi2on,  distribu2on,  people,  

etc.

6.  Revenue  streams  Revenue  model,  life  2me  value,  revenue,  

gross  margin

Lean Canvas: Ash Maurya

Lean  Canvas,  from  Ash  Maurya:  Running  Lean.  Licensed  under  Crea2ve  Commons-­‐AVribu2on-­‐Share  Alike  3.0

Product Market

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Problem  Top  3  problems  

Exis2ng  /alterna2ve  solu2ons

Customer  segments  Early  adopters?

Success  metrics  

Leading  and  lagging  indicators

Possible  solu2ons  Key  features  &  benefits  for  customers  &  business

Business  readiness  What  is  needed  to  deploy  and  support  the  solu2on?  

(Staff,  budget,  training,  systems,  support,  opera2ons  dependencies  on  projects/

vendors)

Channels  Path  to  

customers  

Costs  People,  training,  capital,  marke2ng,  etc.  +  Objec2ve  jus2fica2on

Business  value  1.  User  &  business  value  2.  Cost  of  Delay  (urgency)  3.  risk  reduc2on/opportunity  enablement  +  Objec2ve  jus2fica2on

Lean Project Canvas

ProductMarket

Cost  of  delay  

time

linear

dela

y co

st

1,2,3,5,8,13,21 1,2,3,5,8,13,21

<Title  /  headline>

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

time

linear

dela

y co

st

time

must do now

dela

y co

st

time

logarithmic

dela

y co

st

time

intangible

dela

y co

st

Cost of Delay is the cost we incur by delaying delivery of a product, due to lost revenue or unrealized cost savings.

Cost of Delay profiles

time

fixed date

dela

y co

st

Kenny Rubin: Essential Scrum

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

42 Investment Group: building a luxury resort hotel

Goals: • Luxury

amenities & activities

• Destination hotel

• Repeat customers

• Profitable in 1st year

https://www.flickr.com/photos/28685147@N04/

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Portfolio of Projects / Features

• 18 hole golf course• Jacuzzi tubs in guest rooms• Valet Parking• Free internet access • On-site tailor shop• Child care centre• Pet spa• Mini golf

• Bungee jumping tower • Full service spa• Healing mud baths• Swim with dolphins• Concierge service• Live music nightly• Amusement park & roller

coaster• Themed guest rooms

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Activity 1: Build a Lean Project Canvas

• Choose 2 projects from this list at each table

• Write a lean canvas for each, working in groups of 3-4 • Problem/opportunity & existing alternatives • customer segments • possible solution • business value • cost of delay profile

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Estimate the relative value of projects in a portfolio

100 200 500 800 1200 2000 3000

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Activity 2: Business Value Game•Play the Business Value Game: your 2 Canvases + 4 samples •Arrange blue cards from smallest to largest value •Arrange canvases as shown in the sample here •Write the business value number on each Canvas

100 200 800 1200 2000 3000

1200

1200 2000200

200

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

ROI calculation & project sequencing

Project Relative Value Relative Effort (cost) Relative R.O.I. Sequence?

A 1200 3 400

B 800 3 267

C 2000 8 250

D 3000 40 75

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Activity 3: Determine how to sequence projects

• Write the Cost number on each canvas (handout) • Calculate Relative ROI for each canvas. Write it on

each canvas • ROI = Value / Cost

• Sequence projects based on ROI (high to low) • Consider Cost of Delay profile: does this change

the sequence?

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

ROI calculation & project sequencing

Project Relative Value

Relative Effort (cost)

Relative R.O.I. CoD Sequence?

A 1200 3 400

B 800 3 267

C 2000 8 250

D 3000 40 75

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Finally

1agile42 2Innovation Games® 3Dean Leffingwell: Agile Software Requirements

Whatever works best for your situation!

Not….

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Photo: Rory Mizen

Highest Paid Person’s Opinion

No

HiPPOs

allowed !

http://www.agile42.com/en/blog/2015/04/30/scrum-gathering-phoenix-2015-sessions/

Brad Swanson, CSC, Senior Agile Coach [email protected] @bradswanson

Mike Caspar, CSP, Senior Agile Coach [email protected] @mikecaspar

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2012.

Reference Section: The process steps for sequencing projects

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Process for Sequencing Projects

1. Stakeholders and Product Owners prepare canvases. Optional: limit number per stakeholder

2. Review & validate canvases for completeness & understanding - ahead of time

3. Select appropriate group of voting stakeholders and a neutral facilitator

4. Brief “sales pitch” for each project, based on the canvas

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Process for Sequencing Projects (2)

6. Choose a baseline project/canvas, assign it a mid-range point value. Can shift up/down later if necessary.

7. Business Value GameTM,1; assign the relative value of each project, without considering cost/effort

1agile42 2Innovation Games®

Alternative to Biz Value Game: Buy a Feature / Prune the Product Tree 2

agile42 | The Agile Coaching Company www.agile42.com | All rights reserved. Copyright © 2007 - 2015.

Process for Sequencing Projects (3)

8. Delivery teams estimate cost/effort.

9. Calculate relative ROI: value / cost

10.Sequence projects, and/or allocate investments:

1. ROI

2. cost of delay

3. people and/or resource constraints