1 | Page The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4 th Edition. The PMBOK 4 th Edition is applicable to PMP exams up to the 31 st of July 2013. Key: PG Process Groups, KA Knowledge Area Prepared by: Meegan Scott PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs No Process &Process Group Input Output Tools & Techniques 1 Develop Project Charter 1. Project Statement of Work 1. Project Charter 1. Expert judgment PG: Initiating 2. Business Case KA: Project Integration Management 3. Contract 4. Enterprise Environmental Factors 5. Organizational Process Assets 2 Identify Stakeholders 1. Project Charter 1. Stakeholder Register 1. Expert judgment PG: Initiating 2. Procurement Documents 2. Stakeholder Management Strategy 2. Stakeholder analysis KA: Project Communications Management 3. Enterprise Environmental Factors 4. Organizational Process Assets 3 Develop Project Management Plan 1. Project Charter 1. Project Management Plan 1. Expert judgment PG: Planning 2. Outputs from Planning Processes KA: Project Integration Management 3. Enterprise Environmental Factors 4. Organizational Process Assets

Upload: trankhue

Post on 06-Mar-2018

218 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

1 Develop Project Charter 1. Project Statement of Work 1. Project Charter 1. Expert judgment

PG: Initiating 2. Business Case

KA: Project Integration

Management 3. Contract

4. Enterprise Environmental Factors

5. Organizational Process Assets

2 Identify Stakeholders 1. Project Charter 1. Stakeholder Register 1. Expert judgment

PG: Initiating 2. Procurement Documents

2. Stakeholder Management

Strategy 2. Stakeholder analysis

KA: Project Communications

Management 3. Enterprise Environmental Factors

4. Organizational Process Assets

3

Develop Project Management

Plan 1. Project Charter 1. Project Management Plan 1. Expert judgment

PG: Planning 2. Outputs from Planning Processes

KA: Project Integration

Management 3. Enterprise Environmental Factors

4. Organizational Process Assets

Page 2: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

2 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

4 Collect Requirements 1. Project Charter 1. Requirements Documentation 1. Interviews

PG: Planning 2. Stakeholder Register

2. Requirements Management

Plan 2. Focus groups

KA: Project Scope Management

3. Requirements Traceability

Matrix 3. Facilitated Workshops

4. Group Creativity

Techniques

5. Group Decision Making

Techniques

6. Questionnaires & Surveys

7. Observations

8. Prototypes

5 Define Scope 1. Project Charter 1. Project Scope Statement 1. Expert judgment

PG: Planning 2. Requirements Documentation 2. Project Document Updates 2. Product Analysis

KA: Project Scope Management 3. Organizational Process Assets 3. Facilitated Workshops

4. Alternatives Identification

Page 3: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

3 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

6 Create WBS 1. Project Scope Statement 1. WBS 1. Decomposition

PG: Planning 2. Requirements Documentation 2. WBS Dictionary

KA: Project Scope Management 3. Organizational Process Assets 3. Scope Baseline

4. Project Document

Updates

7 Define Activities 1. Scope Baseline 1. Activity List 1. Rolling Wave Planning

PG: Planning 2. Enterprise Environmental Factors 2. Activity Attributes 2. Decomposition

KA: Project Time Management 3. Organizational Process Assets 3. Milestone List 3. Templates

4. Expert Judgment

8 Sequence Activities 1. Activity List

PG: Planning 2. Activity Attributes

1. Project Schedule

Network Diagram

1.Precedence Diagramming

Method (PDM)

KA: Project Time Management 3. Milestone List

2. Project Document

Updates 2. Dependency Determination

4. Project Scope Statement 3. Applying Leads & Lags

5. Organizational Process Assets 4. Schedule Network

Templates

Page 4: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

4 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

9 Estimate Activity Resources 1. Activity List

1. Activity Resource

Requirements 1. Expert Judgment

PG: Planning 2. Activity Attributes

2. Resource Breakdown

Structure 2. Alternatives Analysis

KA: Project Time Management 3. Resource Calendars

3. Project Document

Updates 3. Published Estimating Data

4. Enterprise Environmental Factors 4. Bottom-up Estimating

5. Organizational Process Assets

5. Project Management

Software

10 Estimate Activity Durations 1. Activity List

1. Activity Durations

Estimate 1. Expert Judgment

PG: Planning 2. Activity Attributes

2. Project Document

Updates 2. Analogous Estimating

KA: Project Time Management 3. Activity Resource Requirements 3. Parametric Estimating

4. Resource Calendars 4. Three-Point Estimates

5. Project Scope Statement 5. Reserve Analysis

6. Enterprise Environmental Factors

7. Organizational Process Assets

Page 5: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

5 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

11 Develop Schedule 1. Activity List 1. Project Schedule 1. Schedule Network Analysis

PG: Planning 2. Activity Attributes 2. Schedule Baseline 2. Critical Path Method

KA: Project Time Management

3. Project Schedule Network

Diagram 3. Schedule Data 3. Critical Chain Method

4. Activity Resource Requirements 4. Project Document Updates 4. Resource Leveling

5. Resource Calendars 5. What-If Scenario Analysis

6. Activity Duration Estimates 6. Applying Leads & Lags

7. Project Scope Statement 7. Schedule Compression

8. Enterprise Environmental Factors 8. Scheduling Tool

9. Organizational Process Assets

12 Estimate Costs 1. Scope Baseline 1. Activity Cost Estimates 1. Expert Judgment

PG: Planning 2. Project Schedule 2. Basis of Estimates 2. Analogous Estimating

KA: Project Cost Management 3. Human Resource Plan 3. Project Document Updates 3. Parametric Estimating

4. Risk Register 4. Three-Point Estimates

5. Enterprise Environmental Factors 5. Reserve Analysis

6. Organizational Process Assets 6. Bottom-up Estimating

7. Cost of Quality (COQ)

8. Project Management

Estimating Software

9. Vendor Bid Analysis

Page 6: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

6 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

13 Determine Budget 1. Activity Cost Estimates 1. Cost Performance Baseline 1. Cost Aggregation

PG: Planning 2. Basis of Estimates

2. Project Funding

Requirements 2. Reserve Analysis

KA: Project Cost Management 3. Scope Baseline 3. Project Document Updates 3. Expert Judgment

4. Project Schedule 4.Historical Relationships

5. Resource Calendars

5. Funding Limit

Reconciliation

6. Contracts

7. Organizational Process Assets

14 Plan Quality 1. Scope Baseline 1. Quality Management Plan 1. Cost-Benefit Analysis

PG: Planning 2. Stakeholder Register 2. Quality Metrics 2. Cost of Quality

KA: Project Quality Management 3. Cost Performance Baseline 3. Quality Checklists 3. Control Charts

4. Schedule Baseline 4. Process Improvement Plan 4. Benchmarking

5. Risk Register 5. Project Document Updates 5. Design of Experiments

6. Enterprise Environmental Factors 6. Statistical Sampling

7. Organizational Process Assets 7. Flowcharting

8. Proprietary Quality

Management

Methodologies

9. Additional Quality

Planning Tools

Page 7: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

7 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

15 Develop Human Resource Plan 1. Activity Resource Requirements 1. Human Resource Plan

1. Organizational Charts &

Position Descriptions

PG: Planning 2. Enterprise Environmental Factors 2. Networking

KA: Human Management 3. Organizational Process Assets 3.Organizational Theory

16 Plan Communications 1. Stakeholder Register

1. Communications

Management Plan

1. Communication

Requirements Analysis

PG: Planning

2. Stakeholder Management

Strategy 2. Project Document Updates

2. Communication

Technology

KA: Project Communications

Management 3. Enterprise Environmental Factors 3. Communication Models

4. Organizational Process Assets 4. Communication Methods

17 Plan Risk Management 1. Project Scope statement 1. Risk Management Plan

1.Planning Meeting &

Analysis

PG: Planning 2. Cost Management Plan

KA: Project Risk Management 3. Schedule Management Plan

4. Communications Management

Plan

5. Enterprise Environmental Factors 6. Organizational Process Assets

Page 8: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

8 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

18 Identify Risks 1. Risk Management Plan 1. Risk Register 1. Documentation Reviews

PG: Planning 2. Activity Cost Estimates

2. Information Gathering

Techniques

KA: Project Risk Management 3. Activity Duration Estimates 3. Checklist Analysis

4. Scope Baseline 4. Assumptions Analysis

5. Stakeholder Register 5. Diagramming Techniques

6. Cost Management Plan 6. SWOT Analysis

7. Schedule Management Plan 7. Expert Judgment

8. Quality Management Plan

9. Project Documents

10. Enterprise Environmental

Factors

11. Organizational Process Assets

19 Perform Qualitative Risk Analysis 1. Risk Register 1. Risk Register Updates

1. Risk Probability & Impact

Assessment

PG: Planning 2. Risk Management Plan

2. Probability & Impact

Matrix

KA: Project Risk Management 3. Project Scope Statement

3. Risk Data Quality

Assessment

4. Organizational Process Assets 4. Risk Urgency Assessment

5. Risk Categorization

6. Expert Judgment

Page 9: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

9 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

20 Perform Quantitative Risk Analysis 1. Risk Register 1. Risk Register Updates

1. Data Gathering &

Representation Techniques

PG: Planning 2. Risk Management Plan

2. Quantitative Risk Analysis

& Modeling Techniques

KA: Project Risk Management 3. Cost Management Plan 3. Expert Judgment

4. Schedule Management Plan

5. Organizational Process Assets

21 Plan Risk Responses 1. Risk Register 1. Risk Register Updates

1. Strategies for Negative

Risks or Threats

PG: Planning 2. Risk Management Plan

2. Risk-related Contract

Decisions

2. Strategies for Positive

Risks or Opportunities

KA: Project Risk Management

3. Project Management Plan

Updates

3. Contingent Response

Strategies

4. Project Document Updates 4. Expert Judgment

Page 10: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

10 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

22 Plan Procurements 1. Scope Baseline

1. Procurement Management

Plan 1. Make-or-Buy Analysis

PG: Planning 2. Requirements Documentation

2. Procurement Statements of

Work 2. Expert Judgment

KA: Project Procurement Management 3. Teaming Agreements 3. Make-or-Buy Decisions 3. Contract Types

4. Risk Register 4. Procurement Documents

5. Risk-related Contract Decisions 5. Source Selection Criteria

6. Activity Resource Requirements 6. Change Requests

7. Project Schedule

8. Activity Cost Estimates

9. Cost Performance Baseline

10. Enterprise Environmental

Factors

11. Organizational Process Assets

23 Direct & Manage Project Executions 1. Project Management Plan 1. Deliverables 1. Expert Judgment

PG: Executing 2. Approved Change Requests

2. Work Performance

Information

2. Project Management

Information System

KA: Project Integration Management 3. Enterprise Environmental Factors 3. Change Requests

4. Organizational Process Assets

4. Project Management Plan

Updates

5. Project Document Updates

Page 11: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

11 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

24 Perform Quality Assurance 1. Project Management Plan

1. Organizational Process

Assets Updates

1. Plan Quality & Perform

Quality Control Tools &

Techniques

PG: Executing 2. Quality Metrics 2. Change Requests 2.Quality Audits

KA: Project Quality Management 3. Work Performance Information

3. Project Management Plan

Updates 3. Process Analysis

4. Quality Control Measurements 4. Project Documents Updates

25 Acquire Project Team 1. Project Management Plan 1. Project Staff Assignments 1. Pre-Assignment

PG: Executing 2. Enterprise Environmental Factors 2. Resource Calendars 2. Negotiation

KA: Project Human Resource

Management 3. Organizational Process Assets

3. Project Management Plan

Updates 3. Acquisition

4. Virtual Teams

26 Develop Project Team 1. Project Staff Assignments

1. Team Performance

Assessments 1. Interpersonal Skills

PG: Executing 2. Project Management Plan

2. Enterprise Environmental

Factors Updates 2. Training

KA: Project Human Resource

Management 3. Resource Calendars 3. Team-Building Activities

4. Ground Rules

5. Co-location 6. Recognition & Rewards

Page 12: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

12 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

27 Manage Project Team 1. Project Staff Assignments

1. Enterprise Environmental

Factors Updates

1. Observation &

Conversation

PG: Executing 2. Project Management Plan

2. Organizational Process

Assets Updates

2. Project Performance

Appraisals

KA: Project Human Resource

Management 3. Team Performance Assessments 3. Change Requests 3. Conflict Management

4. Performance Reports

4. Project Management Plan

Updates 4. Issue Log

5. Organizational Process Assets 5. Interpersonal Skills

28 Distribute Information 1. Project Management Plan

1. Organizational Process

Assets Updates 1. Communication Methods

PG: Executing 2. Performance Reports

2. Information Distribution

Tools

KA: Project Communications

Management 3. Organizational Process Assets

29 Manage Stakeholder Expectations 1. Stakeholder Register

1. Organizational Process

Assets Updates 1. Interpersonal Skills

PG: Executing

2. Stakeholder Management

Strategy 2. Change Requests 2.Communication Methods

KA: Project Communications

Management 3. Project Management Plan

3. Project Management Plan

Updates 3. Management Skills

4. Issue Log 4. Project Document Updates

5. Change Log 6. Organizational Process Assets

Page 13: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

13 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

30 Conduct Procurements 1. Project Management Plan 1. Selected Sellers 1. Bidder Conferences

PG: Executing 2. Procurement Documents 2. Procurement Contract Award

2. Proposal Evaluation

Techniques

KA: Project Procurement Management 3. Source Selection Criteria 3. Resource Calendars 3. Independent Estimate

4. Qualified Seller List 4. Change Requests 4. Expert Judgment

5. Seller Proposals

5. Project Management Plan

Updates 5. Advertising

6. Project Documents 6. Project Document Updates 6. Internet Search

7. Make-or-Buy Decisions 7. Procurement Negotiations

8. Teaming Agreements

9. Organizational Process Assets

31 Monitor & Control Project Work 1. Project Management Plan 1. Change Requests 1. Expert Judgment

PG: Monitoring & Controlling 2. Performance Reports

2. Project Management Plan

Updates

KA: Project Integration Management

3. Enterprise Environmental

Factors 3. Project Document Updates

4. Organizational Process Assets

32 Perform Integrated Change Control 1. Project Management Plan

1. Change Requests Status

Updates 1. Expert Judgment

PG: Monitoring & Controlling 2. Work Performance Information

2. Project Management Plan

Updates 2. Change Control Meetings

KA: Project Integration Management 3. Change Requests 3. Project Document Updates

4. Enterprise Environmental

Factors

5. Organizational Process Assets

Page 14: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

14 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

33 Verify Scope 1. Project Management Plan 1. Accepted Deliverables 1. Inspection

PG: Monitoring & Controlling 2. Requirements Documentation 2. Change Requests

KA: Project Scope Management 3. Requirements Traceability Matrix 3. Project Document Updates

4. Validated Deliverables

34 Control Scope 1. Project Management Plan

1. Work Performance

Measurements 1.Variance Analysis

PG: Monitoring & Controlling 2. Work Performance Information

2. Organizational Process Assets

Updates

KA: Project Scope Management 3. Requirements Documentation 3. Change Requests

4. Requirements Traceability Matrix

4. Project Management Plan

Updates

5. Organizational Process Assets 5. Project Document Updates

Page 15: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

15 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

35 Control Schedule 1. Project Management Plan

1. Work Performance

Measurements 1. Performance Reviews

PG: Monitoring & Controlling 2. Project Schedule

2. Organizational Process Assets

Updates 2. Variance Analysis

KA: Project Time Management 3. Work Performance Information 3. Change Requests

3. Project Management

Software

4. Organizational Process Assets

4. Project Management Plan

Updates 4. Resource Leveling

5. Project Document Updates 5. What-If Scenario Analysis

6. Adjusting Leads & Lags

7. Schedule Compression

8. Scheduling Tool

1. Work Performance

Measurements 1. Earned Value Management

36 Control Costs 1. Project Management Plan 2. Budget Forecasts 2. Forecasting

PG: Monitoring & Controlling 2. Project Funding Requirements

3. Organizational Process Assets

Updates

3. To-Complete Performance

Index (TCPI)

KA: Project Cost Management 3. Work Performance Information 4. Change Requests 4. Performance Reviews

4. Organizational Process Assets

5. Project Management Plan

Updates 5. Variance Analysis

6. Project Document Updates

6. Project Management

Software

Page 16: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

16 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

37 Perform Quality Control 1. Project Management Plan

1. Quality Control

Measurements 1. Cause & Effect Diagrams

PG: Monitoring & Controlling 2. Quality Metrics 2. Validated Changes 2. Control Charts

KA: Project Quality Management 3. Quality Checklists 3. Validated Deliverables 3. Flowcharting

4. Work Performance

Measurements

4. Organizational Process

Assets Updates 4. Histogram

5. Approved Change Requests 5. Change Requests 5. Pareto Chart

6. Deliverables

6. Project Management Plan

Updates 6. Run Chart

7. Organizational Process Assets 7. Project Document Updates 7. Scatter Diagram

8. Statistical Sampling

9. Inspection

10. Approved Change

Requests Reviews

38 Report Performance 1. Project Management Plan 1. Performance Reports 1. Variance Analysis

PG: Monitoring & Controlling 2. Work Performance Information

2. Organizational Process

Assets Updates 2. Forecasting Methods

KA: Project Communications

Management

3. Work Performance

Measurements 3. Change Requests 3.Communication Methods

4. Budget Forecasts 4. Reporting Systems

5. Organizational Process Assets

Page 17: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

17 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

39 Monitor & Control Risks 1. Risk Register 1. Risk Register Updates 1.Risk Assessment

PG: Monitoring & Controlling 2. Project Management Plan

2. Organizational Process Assets

Updates 2. Risk Audits

KA: Project Risk Management 3. Work Performance Information 3. Change Requests 3. Variance & Trend Analysis

4. Performance Reports

4. Project Management Plan

Updates

4.Technical Performance

Measurements

5. Project Documents Updates 5. Reserve Analysis

6. Status Meetings

40 Administer Procurements 1. Procurement Documents 1. Procurement Documentation

1. Contract Change Control

System

PG: Monitoring & Controlling 2. Project Management Plan

2. Organizational Process Assets

Updates

2.Procurement Performance

Reviews

KA: Project Procurement Management 3. Contract 3. Change Requests 3.Inspections & Audits

4. Performance Reports

4. Project Management Plan

Updates 4. Performance Reporting

5. Approved Change Requests 5. Payment Systems

6. Work Performance Information 6. Claims Administration

7. Records Management

System

Page 18: PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, · PDF file1 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK

18 | P a g e The PMP 42-9: Process Groups, Knowledge Areas, IOTTs is a compilation of the information presented in the PMBOK 4

th Edition.

The PMBOK 4th

Edition is applicable to PMP exams up to the 31st of July 2013.

Key: PG – Process Groups, KA – Knowledge Area Prepared by: Meegan Scott

PMP 42 - 9: PROCESS GROUPS, KNOWLEDGE AREAS, AND IOTTs

No Process &Process Group Input Output Tools & Techniques

41 Close Project or Phase 1. Project Management Plan

1. Final Product, Service, and

Result Transition 1.Expert Judgment

PG: Closing 2. Accepted Deliverables

2. Organizational Process

Assets Updates

KA: Project Integration Management 3. Organizational Process Assets

42 Close Procurements 1. Project Management Plan 1. Closed Procurements 1. Procurement Audits

PG: Closing 2. Procurement Documentation

2. Organizational Process

Assets Updates 2. Negotiated Settlements

KA: Project Procurement Management

3.Records Management

System