PMI Art CommissionConcept Designs
Research & ConsultationProcess of TranslationSchedules & Budgets
Heather BarnettFebruary 2011
Research Groups
Cancer Control
Medical Engineering
Clinical Simulation Lab
Reconstructive Surgery
Burns Research
Mental Health
Investigations
Aims of researchIntended outputsLong term goalsProcesses involved
(mechanisms, procedures)Visualisation of research
(communication within and outside expertise)Links between what happens in the lab and its
potential real world impact
Research & Consultation
• initial meetings
• email correspondence
• research papers & web resources
• creative consultation activities
Research Groups
Cancer Control
Medical Engineering
Clinical Simulation Lab
Reconstructive Surgery
Burns Research
Mental Health
?
Concept DesignsPoints of Connection :
Transformational Research & Predictive Calculations •
Individualised Medicine in Diagnosis & Treatment •
Relationship between molecular/cellular & whole person •
Link between laboratory research & clinical setting •
Concept DesignsThe whole is greater than the sum of its parts
Transformation of Scale (enlarging/reducing) •
Interior – Exterior (in body and building) •
Parts and the whole (shifting focus) •
Audience engagement (devices for interactivity) •
External siteDirectly outside PMI
• potential for single point perspective• design changes as you change position
Single point perspectiveExample with molecular structure of Cortisol
• 3D design in metal or glass• Design changes depending on viewing position
Transformation of scaleExample with enlarged fragment of knee cartilage
• cement material to resemble bone• potential for interactivity: furniture / balance
ScheduleTimescale for different artworks proposed
2D/3D external artwork6-15 weeks
Depending on complexity of design, materials used, site prep needed, installation requirements
2D internal artwork3-5 weeks
Depending on material, sample tests, site prep needed and installation requirements
Schedule breakdown
Activity Dates
Work up designs March
Open Presentation/Consultation? 15 March
Present designs 15 April
Production April-May
Installation of 2D artwork/s May (21-27)
Installation of 3D artwork/s May onwards…