(pmbok guide ) sixth edition - 3fold education centre · pdf fileproject management institute,...

27
Abu Dhabi : 02-6670660 Dubai: 04-3574622 www.3foldtraining.com www.pmexamstudy.com [email protected] ©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 1 ©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 1 A Guide to the PROJECT MANAGEMENT BODY OF KNOWLEDGE (PMBOK ® GUIDE ) Sixth edition Chapter 7 – Project Cost Management PMBOK is a registered mark of the Project Management Institute, Inc ©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 2 © 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 2 Project Cost Management. *Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.

Upload: lynguyet

Post on 23-Mar-2018

245 views

Category:

Documents


8 download

TRANSCRIPT

Page 1: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 1©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 1

A Guide to the

PROJECT MANAGEMENT

BODY OF KNOWLEDGE

(PMBOK ® GUIDE ) – Sixth edition

Chapter 7 – Project Cost Management

PMBOK is a registered mark of the Project Management Institute, Inc

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 2© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 2

Project Cost Management. *Project Cost Management includes the processes involved in planning, estimating, budgeting, financing, funding, managing, and controlling costs so the project can be completed within the approved budget.

Page 2: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 3©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 3

Topic

A cost that does not change with an increase or decrease in the amount of goods or services produced.

Fixed Cost

Ge

ne

ral C

on

cep

ts

Description

Costs that vary depending on a company's production volume; they rise as production increases and fall as production decreases

Variable Cost

A price that can be completely attributed to the production of specific goods or services.

Direct Cost

Costs that are not directly accountable to a cost object (such as a particular project, facility, function or product).

Indirect Cost

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 4©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 4

Topic

In economics and business decision-making, a sunk cost is a cost that has already been incurred and cannot be recovered.

Sunk Cost

Ge

ne

ral C

on

cep

ts

Description

The process of identifying and documenting all the costs involved over the life of an asset is known as Life Cycle Costing (LCC).

Lifecycle Cost

The loss of other (highest) alternatives when one alternative is chosen.Opportunity Cost

Page 3: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 5©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 5

Topic

Value engineering (VE) is a systematic method to improve the "value" of goods or products and services by using an examination of function. Value, as defined, is the ratio of function to cost. Value can therefore be increased by either improving the function or reducing the cost.

Value Engineering

Ge

ne

ral C

on

cep

ts

Description

Cost escalation is defined as changes in the cost or price of specific goods or services in a given economy over a period.

Cost Escalation

In economics, inflation is a sustained increase in the general price level of goods and services in an economy over a period of time.

Inflation

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 6©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 6

Chapter 7

7.1 Plan Cost Management

7.2 Estimate Costs

7.3 Determine Budget

7.4 Control Costs

Project Cost Management

Page 4: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 7© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 7

7.1 Plan Cost Management. *The process of defining how the project costs will be estimated, budgeted, managed, monitored, and controlled.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 8©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 8

7.1 Plan Cost Management (ITTO)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-2, Page 235.

Page 5: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 9© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 9

7.2 Estimate Costs. The process of developing an approximation of the monetary resources needed to complete project work.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 10©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 10

7.2 Estimate Costs (ITTO)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-4, Page 240.

Page 6: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 11© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 11

7.3 Determine Budget. *The process of aggregating the estimated costs of individual activities or work packages to establish an authorized cost baseline.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 12©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 12

7.3 Determine Budget (ITTO)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-6, Page 248.

Page 7: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 13© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 13

In bottom-up cost aggregation, individual activities are added up, or aggregated.

Example: Cost Aggregation

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 14© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 14

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-8, Page 255.

Page 8: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 15© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 15

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-9, Page 255.

Cost Baseline, Expenditures, and Funding Requirements

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 16© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 16

7.4 Control Costs. *The process of monitoring the status of the project to update the project costs and manage changes to the cost baseline.

Page 9: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 17©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 17

Process 7.4 Topics covered in this process

7.4 Control Costs

5.6.1 Control Costs: Inputs

5.6.2 Control Costs: Tools and Techniques

5.6.3 Control Costs: Outputs

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 18©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 18

7.4 Control Costs (ITTO)

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 10: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 19©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 19

Inputs

Cost management plan, cost baseline and performance measurement baseline are inputs to this process.Project

Management Plan

7.3

Co

ntr

ol C

ost

s -

Inp

uts

Relevance

Lessons learned register.Project

Documents

1

2

The project funding requirements are an important input into the Control Costs process because they enable you to determine when expenditures will be incurred and when funding for the project will be available and to therefore assess actual versus planned project funding requirements and control any changes to these elements.

Project Funding Requirements

3

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 20©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 20

Inputs

The types of organizational process assets that will be useful as inputs into the Control Costs process are any existing organizational policies, procedures, templates, or any other element relating to how costs will be monitored and reported on in your project.

Organizational Process Assets

7.3

Co

ntr

ol C

ost

s -

Inp

uts

Relevance

5

Work performance data contains data on project status such as which activities have started, their progress (e.g., actual duration, remaining duration, and physical percent complete), and which activities have finished.

Work Performance

Data

4

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 11: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 21©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 21

T & T

Examples of expert judgment during the Control Costs process include but are not limited to:

1. Variance analysis2. Earned value analysis3. Forecasting, and4. Financial analysis

Expert Judgment

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

1

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 22©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 22

T & T

Earned Value Management. *A methodology that combines scope, schedule, and resource measurements to assess project performance and progress.

EVM develops and monitors three key dimensions for each work package and control account:

1. Planned Value2. Actual Cost3. Earned Value

Data Analysis

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

2

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 12: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 23©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 23

T & T

Actual Cost (AC). *The realized cost incurred for the work performed on an activity during a specific time period.

Planned Value (PV). *The authorized budget assigned to scheduled work.

Earned Value (EV). *The measure of work performed expressed in terms of the budget authorized for that work.

Data Analysis

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

2

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Earned Value is calculated using the formula.

EV = % Completed x Budget

Percent Completed is the progress of the work package or control account for which the progress is measured using different measurement techniques.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 24©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 24

T & T

Each work package has its own unique characteristics; therefore, there is not one single best way to measure progress. To accommodate the different types of work, there are several accepted methods to measure work performance. There are three classes of work, as follows:

1. Discrete effort

2. Apportioned effort

3. Level of effort

Progress Measurement

Techniques

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 13: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 25©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 25

T & T

Discrete Effort. * An activity that can be planned and measured and that yields a specific output.

Discrete effort is directly related to specific end products or services with distinct and measurable points, and outputs that result directly from the discrete effort.

The four discrete effort measurement methods are:

1. Fixed formula

2. Weighted milestone

3. Percent complete

4. Physical measurement

Progress Measurement

Techniques

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 26© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 26

1. Fixed Formula Methods

Fixed formula assigns a specified percentage of the budget value of the work package to the start milestone of the work packages. The remaining budget value percentage is assigned when the work package is completed.

Another important point is to note is that this method is only used on smaller work packages that are planned to start and end within two reporting time periods.

Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-2, Page 37.

Page 14: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 27© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 27

2. Weighted Milestone

The weighted milestone method divides the work package into measurable segments, each ending with an observable milestone; it then assigns a weighted value to the achievement of each milestone.

The weighted milestone method ismore suitable for longer duration work packages (i.e., those longer than two time periods) that haveintermediate and tangible results, or milestones.

Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-3, Page 38.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 28© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 28

3. Percent Complete

The percent complete method shows an estimate of the percentage of work that is complete at the end of each measurement period. This method should be based on objective and quantifiable work completion.

The planned value is determined by the time-phased resources required to accomplish the work package. The earned value (EV) is determined by multiplying the work package BAC by the percent complete.

Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-4, Page 39.

Page 15: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 29© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 29

4. Physical Measurement

The physical measurement, unlike the weighted milestone and the percent complete, can be related more explicitly to the completion of the work.

Measurement can include any units that can be explicitly related to the completion of the work.

Examples may include the length of cable laid, the area and quantity of concrete poured, and the quantity of spokes in the case of the bicycle’s wheel. The method of measurement and specific measurement with the cost or efforts spent should be defined and agreed upon in advance.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 30©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 30

T & T

Apportioned Effort. Apportioned effort is used for work with a direct, supportive relationship to discrete work. The value for the support task is determined based on the earned value of the referenced base activity.

Apportioned effort can include such work as quality assurance, inspection, and testing activities. An apportioned work effort is estimated as a percentage of the referenced discrete work effort.

The percent allocation to discrete effort is used when there are sufficient performance records and knowledge of the interrelationship between the apportioned effort and the discrete effort.

Progress Measurement

Techniques

6.6

Co

ntr

ol S

che

du

le:

T &

T

What is it?

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 16: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 31© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 31

Apportioned Effort

In this figure, the discrete effort at the second measurement point is 5,200. The apportioned effortis 10% of the discrete effort. Therefore the apportioned value at the second measurement point is 10% of 5,200 or 520.

In actuality, the actual discrete effort accomplished at the end of the second period was 7,800; therefore the apportioned earned value at the second measurement point is 10% of 7,800 or 780.

Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-5, Page 40.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 32©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 32

T & T

Level-of-effort (LOE) activities do not directly produce definitive end products that can be delivered or measured objectively.

LOE work, such as project or program management and contract management, consume project resources and should be included in the EVM Planning, Executing, and Monitoring and Controlling Process Groups.

LOE is not necessarily characterized by a uniform rate of work over a period of time. A planned value is assigned to each LOE task for each measurement period, and this planned value is credited as EV at the end of the measurement period.

EV is accrued in line with PV which means LOE activities will not havea schedule variance. However cost variance can be incurred because the actual cost (AC) is usually different from EV.

Progress Measurement

Techniques

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 17: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 33© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 33

Level of Effort

Earned value equal to the planned value at all measurement points.

Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. 7-6, Page 41.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 34

Earned Value Calculation

Wall 1

Wal

l 2

Wall 3

Wal

l 4

Schedule PlanSchedule: To complete the work in 4 weeks –work is equally distributed

Budgeted CostUSD 10000 / wall

Status at the end of week 3Wall 1 – Progress 100% - AC $12000Wall 2 – Progress 100% - AC $13000Wall 3 – Progress 50% - AC $7000Wall 4 – Progress 0% - AC $0

Calculate BAC, PV, AC and EV

Page 18: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 35

Work Package Planned Value Actual Cost Progress Earned Value

Wall 1 10000 12000 100 % 10000

Wall 2 10000 13000 100 % 10000

Wall 3 10000 7000 50 % 5000

Wall 4 10000 0 0 % 0

Total 40000 32000 25000

Solution

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 36©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 36

T & T

Variance Analysis. * A technique for determining the cause and degree of difference between the baseline and actual performance.

There are 4 formula to calculate variance

1. Cost Variance2. Cost Performance Index3. Schedule Variance4. Schedule Performance Index5. Variance At Completion (VAC). * A projection of the amount of budget

deficit or surplus, expressed as the difference between the budget at completion and the estimate at completion. (Explained later)

Data Analysis

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

2

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 19: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 37

Cost Performance

Cost Variance Cost Performance Index

Earned Value – Actual Cost𝑬𝒂𝒓𝒏𝒆𝒅 𝑽𝒂𝒍𝒖𝒆

𝑨𝒄𝒕𝒖𝒂𝒍 𝑪𝒐𝒔𝒕Positive = Under planned costNeutral = On planned costNegative = Over planned cost

Greater than 1.0 = Under planned costExactly 1.0 = On planned costLess than 1.0 = Over planned cost

Schedule Performance

Schedule Variance Schedule Performance Index

Earned Value – Planned Value 𝑬𝒂𝒓𝒏𝒆𝒅 𝑽𝒂𝒍𝒖𝒆

𝑷𝒍𝒂𝒏𝒏𝒆𝒅 𝑽𝒂𝒍𝒖𝒆Positive = Ahead of ScheduleNeutral = On scheduleNegative = Behind Schedule

Greater than 1.0 = Ahead of scheduleExactly 1.0 = On scheduleLess than 1.0 = Behind schedule

Vari

ance

An

alys

is

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 38

Cost Performance

Cost Variance Cost Performance Index

25000 – 32000 = (7000) 25000 / 32000 = 0.781

Schedule Performance

Schedule Variance Schedule Performance Index

25000 – 30000 = (5000) 25000 / 30000 = 0.833

Page 20: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 39©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 39

T & T

Trend Analysis. An analytical technique that uses mathematical models to forecast future outcomes based on historical results.

Trend analysis uses Charts and Forecasting techniques to measure project performance over time to determine if performance is improving or deteriorating.

(Explained in subsequent slides)

Data Analysis

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

2

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

PMIS is often used to generate, capture and report project performance.PMIS

3

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 40© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 40

Charts

This chart uses S-curves to display EV data for a project that is performing over budget and behind the schedule.

Earned Value, Planned Value, and Actual Costs

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-12, Page 264.

Page 21: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 41

Estimate At Completion

EAC EAC

𝑩𝑨𝑪

𝑪𝑷𝑰AC + (BAC – EV)

CPI is expected to be the same for the remainder of the project

Future work will be accomplished at the planned rate

EAC EAC

AC + (𝑩𝑨𝑪 −𝑬𝑽)

(𝑪𝑷𝑰 𝒙 𝑺𝑷𝑰) AC + Bottom up ETC

CPI and SPI influence the remaining work Initial plan is no longer valid

Forecasting EAC

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 42

Estimate At Completion

EAC EAC

𝟒𝟎𝟎𝟎𝟎

𝟎.𝟕𝟖𝟏= 51216 32000 + (40000 – 25000) = 47000

CPI is expected to be the same for the remainder of the project

Future work will be accomplished at the planned rate

EAC EAC

32000 + (𝟒𝟎𝟎𝟎𝟎 −𝟐𝟓𝟎𝟎𝟎)

(𝟎.𝟕𝟖𝟏 𝒙 𝟎.𝟖𝟑𝟑)= 55055 32000 + Bottom up ETC

CPI and SPI influence the remaining work Initial plan is no longer valid

Page 22: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 43

Estimate To Complete

ETC ETC

EAC – AC Re-Estimate

Assumes work is proceeding on plan. Re-estimate the remaining work from the bottom up.

Forecasting ETC

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 44

Estimate To Complete

ETC ETC

51216 – 32000 = 19216CPI is expected to be the same for the

remainder of the project.

Re-Estimate

Assumes work is proceeding on plan. Re-estimate the remaining work from the bottom up.

Page 23: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 45©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 45

T & T

* A measure of the cost performance that is required to be achieved with the remaining resources in order to meet a specified management goal, expressed as the ratio of the cost to finish the outstanding work to the remaining budget.

To-Complete Performance

Index

7.3

Co

ntr

ol C

ost

s –

T &

T

What is it?

3

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

To Complete Performance Index

TCPI TCPI

(BAC – EV)/(BAC – AC) (BAC – EV)/(EAC – AC)

The efficiency that must be maintained in order to complete on plan.

The efficiency that must be maintained in order to complete the current EAC.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 46

To Complete Performance Index

TCPI TCPI

(BAC – EV)/(BAC – AC)

(40000-25000) / (40000-32000)

1.875

(BAC – EV)/(EAC – AC)

(40000-25000) / (51216-32000)

0.781

The efficiency that must be maintained in order to complete on plan.

The efficiency that must be maintained in order to complete the current EAC.

TCPI

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 24: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 47

Variance At Completion

VAC

BAC – EAC

40000 – 51216 = (11216)

The estimated difference in cost at the completion of the project.

VAC

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 48©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 48

Outputs

The easiest way to display work performance information based on the work performance data is by using the earned value calculations for cost variance (CV), schedule variance (SV), cost performance index (CPI), schedule performance index (SPI), and the to-complete performance index (TCPI).

Work Performance Information

7.3

Co

ntr

ol C

ost

s –

Ou

tpu

ts

Description

1

Cost Forecasts

2EAC and ETC will be communicated to the stakeholders.

Change Request

3Change requests may include preventive or corrective actions.

PMP and PD Updates

4 & 5Project Management Plan and Project Documents will be updated.

Project Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute Inc., 2017, Fig. 7-10, Page 257.

Page 25: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 49©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 49

Emerging Concept

Chapter 7 – Project Cost Management

PMP and PMBOK are registered marks of the Project Management Institute, Inc

Earned Schedule

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 50©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 50

Topic

Earned schedule (ES), developed by Lipke in 2003, extends the graphical method of projecting EV accrued onto the PV curve.

The idea of Earned Schedule is similar to Earned Value. However, instead of using cost for measuring schedule performance, we would use time.

Earned Schedule is determined by comparing the cumulative EV earned to the performance baseline. The time associated with EV, i.e. Earned Schedule, is found from the PV S-curve. The significance of using the Earned Schedule concept is that the associated schedule indicators behave appropriately throughout the entire period of project performance.

Earned Schedule

EAR

NED

SC

HED

ULE

Description

Page 26: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 51© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 51

Earned Schedule Concept

Schedule Variance (time)SV(t)= ES - AT

Schedule Performance Index (time) SPI(t)= ES / AT

Schedule Variance (time)SV(t)= 6 – 10 = -4

Schedule Performance Index (time) SPI(t)= 6/10 = 0.60

When the ES exceeds AT, the SV(t) is positive and negative when it lags. The SPI(t) is greater than 1.0 when ES exceeds AT, and less than 1.0 when ES is less than AT. SV(t) will only revert to zero and SPI(t) to unity at project completion

when the project completes on time.

Project Management Institute, Practice Standard for Earned Value Management– Second Edition, Project Management Institute Inc., 2011, Fig. D1, Page 100.

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 52© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 52

Activity 7.2

Instruction

Cost Baseline

Calculate various component of a cost baseline (BAC, PV, AC and EV).

Format Individual Exercise

Time Limit 10 Minutes

Discussion 5 Minutes

Learning Outcome

7.2

Page 27: (PMBOK GUIDE ) Sixth edition - 3FOLD Education Centre · PDF fileProject Management Institute, A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) –Sixth Edition,

Abu Dhabi : 02-6670660Dubai: 04-3574622

www.3foldtraining.comwww.pmexamstudy.com

[email protected]

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 53© 3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 53

Activity 7.3

Instruction

Cost Control

Evaluate project performance using various cost control techniques.

Format Individual Exercise

Time Limit 10 Minutes

Discussion 5 Minutes

Learning Outcome

7.3

©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 54©3FOLD Education Centre . All rights reserved . [email protected] . www.3foldtraining.com . PMP® Exam Review Slide # 54

End of Seminar

PMP and PMBOK are registered marks of the Project Management Institute, Inc