pmbok® guide 5th edition - 47 project management...

1
PLANNING Based on the PMBOK® Guide 5 th Edition (English Version) Copyright: Project Management Institute, A Guide to the Project Management Body of Knowledge - Fifth Edition (PMBOK® Guide), Project Management Institute, Inc., (2013). Copyright and all rights reserved. The material from this publication has been reproduced with the permission of PMI. Explanatory Note: The represented process flow is based on figures of the PMBOK® Guide. Only a few connections are depicted in the flow. To see the detailed relationships, please recall the process data flow diagrams in the PMBOK® Guide. This flow does not replace the need for reading the PMBOK® Guide. The PMBOK® Guide contains a deep explanation of all processes including Inputs, Tools & Techniques and Outputs that are not listed in this flow. Adaptation: Ricardo Viana Vargas, MSc, CSM, PRINCE2® Practitioner, PMI-RMP, PMI-SP, PMP Review: Wagner Maxsen, Kaplan-Norton BSC Certified Graduate, PMP, PRINCE2 Practitioner, PMI-RMP Graphic Design: Sérgio Jardim, PMP Become a member of PMI and download the PMBOK Guide 5 th Edition and all other PMI Standards at www.pmi.org PMBOK® GUIDE 5 TH EDITION - 47 PROJECT MANAGEMENT PROCESSES www.ricardo-vargas.com PMBOK® GUIDE 5 TH EDITION - 47 PROJECT MANAGEMENT PROCESSES PROCUREMENT 12.1 Plan Procurement Management INTEGRATION 4.2 Develop Project Management Plan TIME 6.1 Plan Schedule Management TIME 6.2 Define Activities TIME 6.3 Sequence Activities TIME 6.4 Estimate Activity Resources TIME 6.5 Estimate Activity Durations TIME 6.6 Develop Schedule COST 7.1 Plan Cost Management COST 7.2 Estimate Costs COST 7.3 Determine Budget QUALITY 8.1 Plan Quality Management COMMUNICATIONS 10.1 Plan Communications Management STAKEHOLDER 13.2 Plan Stakeholder Management RISK 11.1 Plan Risk Management RISK 11.2 Identify Risks RISK 11.3 Perform Qualitative Risk Analysis RISK 11.4 Perform Quantitative Risk Analysis RISK 11.5 Plan Risk Responses SCOPE 5.3 Define Scope SCOPE 5.1 Plan Scope Management SCOPE 5.2 Collect Requirements SCOPE 5.4 Create WBS HUMAN RESOURCE 9.1 Plan Human Resource Management EXECUTING INTEGRATION 4.3 Direct and Manage Project Work HUMAN RESOURCE 9.2 Acquire Project Team HUMAN RESOURCE 9.3 Develop Project Team HUMAN RESOURCE 9.4 Manage Project Team QUALITY 8.2 Perform Quality Assurance COMMUNICATIONS 10.2 Manage Communications PROCUREMENT 12.2 Conduct Procurements STAKEHOLDER 13.3 Manage Stakeholder Engagement CLOSING PROCUREMENT 12.4 Close Procurements INTEGRATION 4.6 Close Project or Phase INITIATING INTEGRATION 4.1 Develop Project Charter STAKEHOLDER 13.1 Identify Stakeholders MONITORING & CONTROLLING RISK 11.6 Control Risks INTEGRATION 4.4 Monitor and Control Project Work INTEGRATION 4.5 Perform Integrated Change Control TIME 6.7 Control Schedule COST 7.4 Control Costs QUALITY 8.3 Control Quality COMMUNICATIONS 10.3 Control Communications PROCUREMENT 12.3 Control Procurements STAKEHOLDER 13.4 Control Stakeholder Engagement SCOPE 5.5 Validate Scope SCOPE 5.6 Control Scope

Upload: dinhdieu

Post on 07-Jul-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: PMBOK® GUIDE 5TH EDITION - 47 PROJECT MANAGEMENT PROCESSESsartori.orgfree.com/docs/ricardo_vargas_simplified_pmbok_flow_5ed... · Based on the PMBOK® Guide 5th Edition ... please

PLANNING

Based on the PMBOK® Guide 5th Edition (English Version)Copyright: Project Management Institute, A Guide to the Project Management Body of Knowledge - Fifth Edition (PMBOK® Guide), Project Management Institute, Inc., (2013). Copyright and all rights reserved. The material from this publication has been reproduced with the permission of PMI. Explanatory Note: The represented process flow is based on figures of the PMBOK® Guide. Only a few connections are depicted in the flow. To see the detailed relationships, please recall the process data flow diagrams in the PMBOK® Guide. This flow does not replace the need for reading the PMBOK® Guide. The PMBOK® Guide contains a deep explanation of all processes including Inputs, Tools & Techniques and Outputs that are not listed in this flow.

Adaptation: Ricardo Viana Vargas, MSc, CSM, PRINCE2® Practitioner, PMI-RMP, PMI-SP, PMPReview: Wagner Maxsen, Kaplan-Norton BSC Certified Graduate, PMP, PRINCE2 Practitioner, PMI-RMPGraphic Design: Sérgio Jardim, PMP

Become a member of PMI and download the PMBOK Guide 5th Edition and all other PMI Standards at www.pmi.org

PMBOK® GUIDE 5TH EDITION - 47 PROJECT MANAGEMENT PROCESSES

www.ricardo-vargas.com

PMBOK® GUIDE 5TH EDITION - 47 PROJECT MANAGEMENT PROCESSES

PROCUREMENT

12.1 Plan Procurement Management

INTEGRATION

4.2 Develop Project Management Plan

TIME

6.1 Plan Schedule Management

TIME

6.2 Define Activities

TIME

6.3 Sequence Activities

TIME

6.4 Estimate Activity Resources

TIME

6.5 Estimate Activity Durations

TIME

6.6 Develop Schedule

COST

7.1 Plan Cost Management

COST

7.2 Estimate Costs

COST

7.3 Determine Budget

QUALITY

8.1 Plan Quality Management

COMMUNICATIONS

10.1 Plan Communications Management

STAKEHOLDER

13.2 Plan Stakeholder Management

RISK

11.1 Plan Risk Management

RISK

11.2 Identify Risks

RISK

11.3 Perform Qualitative Risk Analysis

RISK

11.4 Perform Quantitative Risk Analysis

RISK

11.5 Plan Risk Responses

SCOPE

5.3 Define Scope

SCOPE

5.1 Plan Scope Management

SCOPE

5.2 Collect Requirements

SCOPE

5.4 Create WBS

HUMAN RESOURCE

9.1 Plan Human Resource Management

EXECUTING

INTEGRATION

4.3 Direct and Manage Project Work

HUMAN RESOURCE

9.2 Acquire Project Team

HUMAN RESOURCE

9.3 Develop Project Team

HUMAN RESOURCE

9.4 Manage Project Team

QUALITY

8.2 Perform Quality Assurance

COMMUNICATIONS

10.2 Manage Communications

PROCUREMENT

12.2 Conduct Procurements

STAKEHOLDER

13.3 Manage Stakeholder Engagement

CLOSING

PROCUREMENT

12.4 Close Procurements

INTEGRATION

4.6 Close Project or Phase

INITIATINGINTEGRATION

4.1 Develop Project Charter

STAKEHOLDER

13.1 Identify Stakeholders

MONITORING & CONTROLLING

RISK

11.6 Control Risks

INTEGRATION

4.4 Monitor and ControlProject Work

INTEGRATION

4.5 Perform IntegratedChange Control

TIME

6.7 Control Schedule

COST

7.4 Control Costs

QUALITY

8.3 Control Quality

COMMUNICATIONS

10.3 Control Communications

PROCUREMENT

12.3 Control Procurements

STAKEHOLDER

13.4 Control Stakeholder Engagement

SCOPE

5.5 Validate Scope

SCOPE

5.6 Control Scope