Installation of Pipeline End Manifold (PLEM)
and Subsea Tie-In of Expansion Spools
Zamri B Ahmad Petroleum Management (PMU),
PETRONAS
2011 PETROLIAM NASIONAL BERHAD (PETRONAS) All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.
PETRONAS-PETRAD-INTSOK-CCOP
Deepwater Subsea Tie-Back Workshop 25 26th January 2011
-
INTRODUCTION
Background Information
Scope of Presentation
INSTALLATION PRELIMINARIES
Pipeline End Manifold (PLEM)
Expansion Spools
Installation Barge
Final Assembly
INSTALLATION PROCEDURE
Pipeline End Manifold (PLEM)
Expansion Spools
Final Assembly
CONCLUSION
OUTLINE
1
Introduction Installation Preliminaries Installation Procedure Conclusion
-
2 2
Pipeline End Manifold (PLEM):
commonly used for subsea manifold to tie-in of underwater pipelines. used to comingle 2 or more pipelines together and eliminate the
need for additional risers.
INTRODUCTION:
Background Information Introduction Installation Procedure Installation Preliminaries Conclusion
-
3
Introduction Installation Procedure Installation Preliminaries Conclusion
INTRODUCTION:
Background Information
-
4
Introduction Installation Procedure Installation Preliminaries Conclusion
INTRODUCTION:
Background Information
-
5 5
Installation of PLEM and expansion spools:
require great precision sensitive to weather conditions high installation cost
INTRODUCTION:
Background Information Introduction Installation Procedure Installation Preliminaries Conclusion
-
1. Installation of PLEM.
2. Installation of 2 expansion spools.
6
INTRODUCTION:
Scope of Presentation
CPP
PLEM
MOPU 1
MOPU 2
10 6km
16 25km
Introduction Installation Procedure Installation Preliminaries Conclusion
-
Designed Weight: ~ 70 MT Dimension: 14m x 6m Water Depth: 114ft (43.9m)
7
INSTALLATION PRELIMINARIES:
Pipeline End Manifold (PLEM) Introduction Installation Procedure Installation Preliminaries Conclusion
-
8
INSTALLATION PRELIMINARIES:
Pipeline End Manifold (PLEM) Introduction Installation Procedure Installation Preliminaries Conclusion
-
Expansion Spool at Pipeline / PLEM Expansion Spool at PLEM / MOPU
16 diameter Full Well Stream (FWS)
9
INSTALLATION PRELIMINARIES:
Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion
-
10
INSTALLATION PRELIMINARIES:
Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion
-
DP DLB Lewek Champion
358 person accommodation 1 x 800MT main crane 2 x 30MT secondary crane Dynamic Positioning with 6 Azimuth thrusters (max thrust 378.7kN)
11
INSTALLATION PRELIMINARIES:
Installation Barge Introduction Installation Procedure Installation Preliminaries Conclusion
-
PLEM
Expansion
spool
Pipeline to CPP
MOPU Leg
Footing
Expansion
spool
12
For future
expansion
INSTALLATION PRELIMINARIES:
Final Assembly Introduction Installation Procedure Installation Preliminaries Conclusion
-
13
INSTALLATION PROCEDURE:
Pipeline End Manifold (PLEM)
PLEM
Pre-installation:
USBL
beacons
Introduction Installation Procedure Installation Preliminaries Conclusion
-
14
INSTALLATION PROCEDURE:
Pipeline End Manifold (PLEM)
Barge setup for PLEM installation
Introduction Installation Procedure Installation Preliminaries Conclusion
-
15
INSTALLATION PROCEDURE:
Pipeline End Manifold (PLEM)
PLEM footprint and debris survey.
Introduction Installation Procedure Installation Preliminaries Conclusion
-
Stage 2 Stage 1 Stage 3 16
INSTALLATION PROCEDURE:
Pipeline End Manifold (PLEM) Introduction Installation Procedure Installation Preliminaries Conclusion
-
Barge Set-Up for Pipeline /
PLEM Spool Installation
17
INSTALLATION PROCEDURE:
Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion
-
Pipeline on an A Frame
18
INSTALLATION PROCEDURE:
Expansion Spools
Lifting Riggings on Expansion Spool
Introduction Installation Procedure Installation Preliminaries Conclusion
-
INSTALLATION PROCEDURE:
Expansion Spools
Stage 2 Stage 1 Stage 3 19
Introduction Installation Procedure Installation Preliminaries Conclusion
-
20
INSTALLATION PROCEDURE:
Expansion Spools
Expansion spool tie-in to PLEM
Introduction Installation Procedure Installation Preliminaries Conclusion
-
SPOOL PLEM
21 +/- 300mm
INSTALLATION PROCEDURE:
Expansion Spools
2
Introduction Installation Procedure
1
Installation Preliminaries Conclusion
-
22
INSTALLATION PROCEDURE:
Expansion Spools
Expansion spool tie-in to pipeline
Introduction Installation Procedure Installation Preliminaries Conclusion
-
Flange Protector Drawings
23
INSTALLATION PROCEDURE:
Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion
-
Barge Set-Up for PLEM / MOPU
Spool Installation
24
INSTALLATION PROCEDURE:
Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion
-
25
INSTALLATION PROCEDURE:
Final Assembly Introduction Installation Procedure
PLEM
Expansion
spool
Pipeline to CPP
MOPU Leg
Footing
Expansion
spool
Installation Preliminaries Conclusion
-
26
Similar approach is used for deepwater installation.
However, the challenges are greater. Due to the depth;
human divers are out of bound. Thus extensive use of ROVs
high-accuracy beacons are needed for positioning.
DP vessel are required as apposed to anchor handling.
CONCLUSION: