plem and spool installation

28
Installation of Pipeline End Manifold (PLEM) and Subsea Tie-In of Expansion Spools Zamri B Ahmad Petroleum Management (PMU), PETRONAS © 2011 PETROLIAM NASIONAL BERHAD (PETRONAS) All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner. PETRONAS-PETRAD-INTSOK-CCOP Deepwater Subsea Tie-Back Workshop 25 26 th January 2011

Upload: sumnerting

Post on 22-Nov-2015

156 views

Category:

Documents


15 download

DESCRIPTION

PLEM and Spool Installation

TRANSCRIPT

  • Installation of Pipeline End Manifold (PLEM)

    and Subsea Tie-In of Expansion Spools

    Zamri B Ahmad Petroleum Management (PMU),

    PETRONAS

    2011 PETROLIAM NASIONAL BERHAD (PETRONAS) All rights reserved. No part of this document may be reproduced, stored in a retrieval system or transmitted in any form or by any means (electronic, mechanical, photocopying, recording or otherwise) without the permission of the copyright owner.

    PETRONAS-PETRAD-INTSOK-CCOP

    Deepwater Subsea Tie-Back Workshop 25 26th January 2011

  • INTRODUCTION

    Background Information

    Scope of Presentation

    INSTALLATION PRELIMINARIES

    Pipeline End Manifold (PLEM)

    Expansion Spools

    Installation Barge

    Final Assembly

    INSTALLATION PROCEDURE

    Pipeline End Manifold (PLEM)

    Expansion Spools

    Final Assembly

    CONCLUSION

    OUTLINE

    1

    Introduction Installation Preliminaries Installation Procedure Conclusion

  • 2 2

    Pipeline End Manifold (PLEM):

    commonly used for subsea manifold to tie-in of underwater pipelines. used to comingle 2 or more pipelines together and eliminate the

    need for additional risers.

    INTRODUCTION:

    Background Information Introduction Installation Procedure Installation Preliminaries Conclusion

  • 3

    Introduction Installation Procedure Installation Preliminaries Conclusion

    INTRODUCTION:

    Background Information

  • 4

    Introduction Installation Procedure Installation Preliminaries Conclusion

    INTRODUCTION:

    Background Information

  • 5 5

    Installation of PLEM and expansion spools:

    require great precision sensitive to weather conditions high installation cost

    INTRODUCTION:

    Background Information Introduction Installation Procedure Installation Preliminaries Conclusion

  • 1. Installation of PLEM.

    2. Installation of 2 expansion spools.

    6

    INTRODUCTION:

    Scope of Presentation

    CPP

    PLEM

    MOPU 1

    MOPU 2

    10 6km

    16 25km

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • Designed Weight: ~ 70 MT Dimension: 14m x 6m Water Depth: 114ft (43.9m)

    7

    INSTALLATION PRELIMINARIES:

    Pipeline End Manifold (PLEM) Introduction Installation Procedure Installation Preliminaries Conclusion

  • 8

    INSTALLATION PRELIMINARIES:

    Pipeline End Manifold (PLEM) Introduction Installation Procedure Installation Preliminaries Conclusion

  • Expansion Spool at Pipeline / PLEM Expansion Spool at PLEM / MOPU

    16 diameter Full Well Stream (FWS)

    9

    INSTALLATION PRELIMINARIES:

    Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion

  • 10

    INSTALLATION PRELIMINARIES:

    Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion

  • DP DLB Lewek Champion

    358 person accommodation 1 x 800MT main crane 2 x 30MT secondary crane Dynamic Positioning with 6 Azimuth thrusters (max thrust 378.7kN)

    11

    INSTALLATION PRELIMINARIES:

    Installation Barge Introduction Installation Procedure Installation Preliminaries Conclusion

  • PLEM

    Expansion

    spool

    Pipeline to CPP

    MOPU Leg

    Footing

    Expansion

    spool

    12

    For future

    expansion

    INSTALLATION PRELIMINARIES:

    Final Assembly Introduction Installation Procedure Installation Preliminaries Conclusion

  • 13

    INSTALLATION PROCEDURE:

    Pipeline End Manifold (PLEM)

    PLEM

    Pre-installation:

    USBL

    beacons

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • 14

    INSTALLATION PROCEDURE:

    Pipeline End Manifold (PLEM)

    Barge setup for PLEM installation

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • 15

    INSTALLATION PROCEDURE:

    Pipeline End Manifold (PLEM)

    PLEM footprint and debris survey.

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • Stage 2 Stage 1 Stage 3 16

    INSTALLATION PROCEDURE:

    Pipeline End Manifold (PLEM) Introduction Installation Procedure Installation Preliminaries Conclusion

  • Barge Set-Up for Pipeline /

    PLEM Spool Installation

    17

    INSTALLATION PROCEDURE:

    Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion

  • Pipeline on an A Frame

    18

    INSTALLATION PROCEDURE:

    Expansion Spools

    Lifting Riggings on Expansion Spool

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • INSTALLATION PROCEDURE:

    Expansion Spools

    Stage 2 Stage 1 Stage 3 19

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • 20

    INSTALLATION PROCEDURE:

    Expansion Spools

    Expansion spool tie-in to PLEM

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • SPOOL PLEM

    21 +/- 300mm

    INSTALLATION PROCEDURE:

    Expansion Spools

    2

    Introduction Installation Procedure

    1

    Installation Preliminaries Conclusion

  • 22

    INSTALLATION PROCEDURE:

    Expansion Spools

    Expansion spool tie-in to pipeline

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • Flange Protector Drawings

    23

    INSTALLATION PROCEDURE:

    Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion

  • Barge Set-Up for PLEM / MOPU

    Spool Installation

    24

    INSTALLATION PROCEDURE:

    Expansion Spools Introduction Installation Procedure Installation Preliminaries Conclusion

  • 25

    INSTALLATION PROCEDURE:

    Final Assembly Introduction Installation Procedure

    PLEM

    Expansion

    spool

    Pipeline to CPP

    MOPU Leg

    Footing

    Expansion

    spool

    Installation Preliminaries Conclusion

  • 26

    Similar approach is used for deepwater installation.

    However, the challenges are greater. Due to the depth;

    human divers are out of bound. Thus extensive use of ROVs

    high-accuracy beacons are needed for positioning.

    DP vessel are required as apposed to anchor handling.

    CONCLUSION:

    Introduction Installation Procedure Installation Preliminaries Conclusion

  • 27

    THANK YOU

    Introduction Installation Procedure Installation Preliminaries Conclusion