Public Meeting #3Peoria/Riverside Transit Study

January 8, 2013

South Brooke Church of Christ

Agenda

1. Background

2. Bus Rapid Transit

3. Goals/Needs

4. Definitions of Alternatives

5. Evaluation Criteria

6. Evaluation Results

7. Preferred Alternative

8. Next Steps

1/9/2013 2

Current Transit System

1/9/2013 3

• 18 fixed routes

• 300,000 annual revenue hours

• 65 fixed route vehicles

• 52 Paratransit vehicles

• 10,000-12,000 boardings/day

• $18M annual operating budget

Tulsa Transit Ridership by Route

1/9/2013 4

47,542

48,808

80,434

86,605

89,823

113,795

126,842

130,593

130,885

134,342

161,348

166,885

171,187

190,378

260,717

315,269

458,559

306

471

118

318

117

215

203

251

111

114

100

221

210

112

101

222

105

FY12 Ridership Route 105: Peoria

Adopted 10/13/2011

Adopted Regional Transit System Plan

Adopted 10/13/2011

Adopted Regional Transit System Plan

20.2 Miles

Residents: 56,000 (1 in 7)

Jobs: 52,000 (1 in 5)

5,700 TOTAL daily trips to/from downtown (13%)

Peoria/Riverside Corridor

Major Activity Centers

1/9/2013 7

Tulsa Tech

Blair Property Park

Cherry Street

Mabee Center/ORU Brookside

Downtown

Utica Square

St. John & Hillcrest

PlaniTulsa Comprehensive Plan

1/9/2013 8

Ride Check Survey

1/9/2013 9

• April 24-26, 2012

(Tuesday – Thursday)

• 9 Routes surveyed

• 9 routes accounted for 64% of total ridership, of which 25% was on Route 105 (Peoria)

• 20% flag stops (5% of riders)

• Major stops at Pine, DAS, 41st

Street, 61st Street, and 81st

Street

• 4,000+ benefitting riders

Grouping On Board + Boardings

N Peoria + S Peoria 1,681

N Peoria + Downtown 2,819

S Peoria + Downtown 3,728

All Segments 4,114

Public Involvement

1/9/2013 11

Steering Committee Initial Meeting (June)

Initial round of public meetings July 16th & 17th

Targeted Neighborhood Outreach

Public Involvement

1/9/2013 12

Public Comments Big Ideas

• We need to ensure service for North Tulsa

• Be conscious of where bus stops are placed

• Better frequencies

• Outreach to North Tulsa churches

Scenario Comparison

1/9/2013 13

Scenario A Scenario C Scenario D Scenario EScenario B

4,050 4,050 3,950 3,950 3,690

Existing Transit Riders

Based on technical analysis and public input, move forward with Scenario B(66th St. North to 81st & Lewis)

Bus Rapid Transit

1/9/2013 14

Branded Buses Off-Board Fare Collection

Passenger InformationEnhanced Boarding Platforms

The Spur – Ft. Worth, TX

1/9/2013 15

The Spur Line – Ft. Worth, TX

1/9/2013 16

1/9/2013 17

The Spur Line – Ft. Worth, TX

Shelters & Passenger Information

1/9/2013 18

Stop Types

1/9/2013 19

Station Concept Examples

1/9/2013 20

• 20 ft Concrete platform

•Station canopy and structural framing support

•LED lighting beneath station canopy

•Benches and / or leaning rails, bicycle racks, trash cans

•Branded, BRT signage and passenger information

•Allowance for public art incorporated into amenities

Station Concept Examples

1/9/2013 21

•35 ft Concrete platform

•Station canopy and structural framing support

•LED lighting beneath station canopy

•Benches and / or leaning rails, bicycle racks, trash cans

•Branded, BRT signage and passenger information

•Allowance for public art incorporated into amenities

San Antonio Primo

1/9/2013 22

Study Goals

• Goal 1: Improve Transit Access and Regional Mobility

• Goal 2: Support Economic Development

• Goal 3: Invest in Low-Cost, High-Impact Transit Infrastructure

• Goal 4: Build Community Support for the Value of Transit

Peoria-Riverside Transit Study Goals

1/9/2013 23

Description of Alternatives

• Bus Rapid Transit- BRT (MAP-21 req)

• Fast Bus

• Tulsa Enhanced

• Tulsa (+) Plus

• “No Build”

1/9/2013 24

BRT

1/9/2013 25

• Bus Rapid Transit (BRT) 50 min. Trip Time

BRT stops at approx. ½ mi. intervals (36 stations at 19 locations)

10-15 minute headways

5:30am-8:30pm

Monday-Sunday

DEDICATED LANES

TRAFFIC PRIORITY AT SIGNAL

TICKET VENDING MACHINES

NEXT BUS ARRIVAL

PEDESTRIAN CROSSINGS

SIDEWALKS

ILLUMINATION

Fast Bus

1/9/2013 26

• FAST BUS 50 min. Trip Time

Fast Bus stops at approx. ½ mi. intervals (36 stations at 19 locations)

30 minute headways (15 min w/rte 105)

5:30am-10:30pm

Monday-Saturday

Local Rt. 105 remains unchanged

X DEDICATED LANES

TRAFFIC PRIORITY AT SIGNAL

TICKET VENDING MACHINES

NEXT BUS ARRIVAL

PEDESTRIAN CROSSINGS

SIDEWALKS

ILLUMINATION

Tulsa Enhanced

1/9/2013 27

• TULSA ENHANCED 60 min. Trip Time

Stops every 2-3 Blocks (approx. 120 stops at 60 locations)

20 minute headways

5:30am-10:30pm

Monday-Saturday

Circulator 66th St. N. to 38th St. N.

X DEDICATED LANES

TRAFFIC PRIORITY AT SIGNAL

X TICKET VENDING MACHINES

NEXT BUS ARRIVAL

PEDESTRIAN CROSSINGS

SIDEWALKS

X ILLUMINATION

Tulsa (+) Plus

1/9/2013 28

• TULSA (+) PLUS 65 min. Trip Time

Local and Flag Stops (196 stops in 98 locations)

30 minute headways

5:30am-10:30pm

Monday-Saturday

X DEDICATED LANES

TRAFFIC PRIORITY AT SIGNAL

X TICKET VENDING MACHINES

X NEXT BUS ARRIVAL

X PEDESTRIAN CROSSINGS

X SIDEWALKS

X ILLUMINATION

No Build

1/9/2013 29

NO BUILD 70 min. Trip Time

Local and Flag Stops (196 stops in 98 locations)

30-45 minute headways

5:30am-8:30pm

Monday-Saturday

X DEDICATED LANES

X TRAFFIC PRIORITY AT SIGNAL

X TICKET VENDING MACHINES

X NEXT BUS ARRIVAL

X PEDESTRIAN CROSSINGS

X SIDEWALKS

X ILLUMINATION

Evaluation Criteria

• Alternatives are evaluated based on their ability to improve transit service within the PRC by:

– Travel Time

– Transit Visibility and Perception

– Comfort/Reliability

– Safety

– Capital Cost

– Operating Cost

1/9/2013 30

Travel time

• Shorter Travel Time

• Dedicated Bus Travel Lane

• Fewer Stops

• Traffic Signal Priority

1/9/2013 31

• Longer Travel Time

• Mixed Traffic

• Frequent Stops

Perception and Visibility

• Branded Service

• Landmark Stations

• Prompt Service

• Multi-Media Technology

1/9/2013 32

• Few Amenities

• Variable Wait Times

• Minimal Passenger Information

Comfort and Reliability

• Branded Service

• Landmark Stations & Passenger Amenities

• Prompt Service

• Enhanced Trip Planning

• Multi-Media Technology

1/9/2013 33

• Few Amenities

• Variable Wait Times

• Minimal Passenger Information

Safety

• Sidewalk Enhancements

• Pedestrian Street Crossings

• Lighting at Stations

1/9/2013 34

• Limited Pedestrian Improvements

Evaluation Results

1/9/2013 35

Item Description BRT FAST BUSTULSA

ENHANCEDTULSA PLUS

EXISTING

ROUTE 105

TRAVEL TIME

VISIBILTY AND

PERCEPTION

COMFORT AND

RELIABILITY

SAFETY

CAPITAL COST

OPERATING COST

(change from

existing)

FEASIBILITY - Percent

of Tulsa Transit Annual

Operating Budget*

SUMMARY SCORE= 1 = 2 = 3 = 4 = 5

$ 20.9M $15.9M $ 16.7M $ 9.2M $0

$ 3.4M $ 2.5M $ 2.2M $1.5M $1.3M

($ 2.2M) ($1.2M) ($ .9M) ($ .2M) (No Change from

Existing)

19% 14% 12% 8% 7%

*Based on Tulsa Transit Annual Operating Budget of

$18 M

Evaluation Results

1/9/2013 36

Item Description BRT FAST BUSTULSA

ENHANCEDTULSA PLUS

EXISTING ROUTE

105

TRAVEL TIME

VISIBILTY AND

PERCEPTION

COMFORT AND

RELIABILITY

SAFETY

CAPITAL COST

OPERATIONS &

MAINTENANCE COST

(change from existing)

FEASIBILITY - Percent of

Tulsa Transit Annual

Operating Budget*

SUMMARY SCORE

= 1 = 2 = 3 = 4 = 5

22 24 21 20 18

Preferred Alternative -Fast Bus

1/9/2013 37

• FAST BUS 50 min. Trip Time, Stops @ 1/2 –mi spacing

30 minute headways (15 min w/Rt. 105)

5:30am-10:30pm, Monday-Saturday

X DEDICATED LANES

TRAFFIC PRIORITY AT SIGNAL

TICKET VENDING MACHINES

NEXT BUS ARRIVAL

PEDESTRIAN CROSSINGS

SIDEWALKS

ILLUMINATION

CAPITAL COST $15.9 M

OPERATING COST

(change from existing)

$2.5 M

($ 1.2 M)

FEASIBILITY - Percent of

Annual Operating Budget14%

Next Steps

• Feedback on preferred alternative

• Steering Committee approval

• Tulsa Transit Board concurrence

• Funding Commitments

• Design

• Implementation

1/9/2013 38

Comments & Contact Info

Send email comments to [email protected]

-OR-

Use comment card at the registration table

Contact for Questions:

James Wagner, AICP

(918) 584-7526

[email protected]