opportunities and challenges
DESCRIPTION
Opportunities and Challenges. A Soundararajan L&T Metro. Hyderabad. City of pearls Hub of IT, ITES and Biopharmaceutical 4 th largest city in terms of Area 6 th most populous city (90 + Lakh ) Infrastructure Development - struggling to keep pace with the economic growth. - PowerPoint PPT PresentationTRANSCRIPT
Opportunities and Challenges
A Soundararajan L&T Metro
Hyderabad
- City of pearls
- Hub of IT, ITES and Biopharmaceutical
- 4th largest city in terms of Area
- 6th most populous city (90 + Lakh )
- Infrastructure Development -
struggling to keep pace with the
economic growth
“ Economic Development of any city is linked to its Transportation infrastructure - Positive Multiplier effect - Additional investments, more employment “
2
Hyderabad Traffic Scenario
Traffic is growing 4 times faster
than the population
Heavy traffic volumes in major corridors
3
MIXED TRAFFIC
Heterogeneous traffic- Average
speed as low as 12 kmph in peak hrs.
Avg. 750-1000 new vehicles
added every day
TRAFFIC GRID LOCK- OLIPHANTA, SECUNDERABAD
Hyderabad Traffic Scenario
Overcrowding of Public Transport
Public Transportation Scenario
• 9 million people travel daily by Public Transport (about 60% by PT)• Suburban rail traffic increased by 6 times while the capacity increased by
only 2.3 times.• 2 - 3 times passengers travel per train against the carrying capacity resulting
in unbearable overcrowding.4
Metro Rail in Hyderabad
“A significant step towards Transportation developmentIn Hyderabad ” 5
GOVT
Concessionaire (SPV)
Financial Institutions
Commuters
EPC + System contracts
Owner(s) + Golden share for
Government
Operating sub-contractors
Grant/PremiumLong term
Concession contractDebt (Senior/
/Mezzanine/Subordinate) Ticket and Parking
Fee
EquityEPC Contracts
O&M contract
Financing Agreements
Share holders Agreement
Other users
Rentals, advertising fee etc.
- Hyderabad Metro Project being executed on PPP basis- Risk Sharing between
- GoAP (Land, ROW, Utilities, Viability grant)- Concessionaire (Design, Build, Finance, operate and Maintain)
Typical Framework for PPP Projects
Hyderabad Metro project under PPP model
6
Concession Design Build Finance Operate Transfer Model
Lowest Viability Gap Funding – Evaluation Parameter Concession Period - 35 Years + extendable by 25 years Construction Period - 5 Years for all lines
Golden Share to be given to Govt. & one Board Membership
Concessionaire L&T Metro Rail (Hyderabad ) Limited L&T Group company
Concessioning Authority
Government of Andhra Pradesh through - Hyderabad Metro Rail Limited
Project Structure
Issue of LOI(06.08.10)
Signing of Concession Agreement (04.09.10)
Appointed Date(CP Completion date)
COD for all lines – 5 years
End of Concession Period
30 days
Concession period : 35 years + 25 years
Construction period Operation PeriodDevelopment Period
7
7
Nagole – Shilparamam (27.51km)
JBS – Falaknuma (14.78 km)
Miyapur – LB Nagar (28.87) km
Double Elevated Stretches
LB Nagar
Nagole
JBS
Falaknuma
Miyapur
Shilparamam
Panjgutta
Malakpet
Narayanguda
Mettuguda
Intra-Modal Interchange
Inter-Modal Interchange - MMTS / Bus Station
To Bangalore
To Pune
To Nagpur
To Vijaywada
Ameerpet
MG Bus Stand
Parade Ground
• Line 1: Miyapur – LB Nagar (28.87) km
• Connects the outskirts of Hyderabad to the upcoming development in Miyapur- 27 stations
• Line 2 : JBS – Falaknuma (14.78) km
• Passes through the old & congested city of Hyderabad – 16 stations• Line 3:Nagole –
Shilparamam(27.51 km)• Connects undeveloped outskirts of
Hyderabad to the important areas of Banjara Hills, Jubilee Hills, HITEC City – 23 stations
Hitec City
1
2
3
Length of Viaduct – 71.6 kmNo.of Stations – 66
No.of Depots - 3
Transit Oriented Development- Depot Land: 212 acres - Parking and Circulation area: 57 acres in 25 land parcels around the stations
Area to be developed:18.5 M Sft
Within Station: commercial development - 20% of floor area of station building
- Advertisement, Parking, Carbon credits
Snapshot of the Project
8
Civil – Viaduct
Viaduct (71.16 Km)
Stations and Real Estate Dev.
- Stations (66 nos)- Transit Oriented Development (18.5 m sq ft)
P Way and Electrical
-Ballast less Track Traction-Substation – Traction/AuxPower Supply
Signaling, Train Control & Telecom
Signaling & Communication systems
Rolling stock
Cars / Maintenance Vehicle
Depot
Civil WorksE&M
AFC
Automatic Fare Collection
Project Scope
Transit Oriented Development, Operation and Maintenance : By SPV 9
Detailed Design Consultants
Independent Engineer: Louis Berger, USA (Jointly by HMRL+L&T MRHL)
Programme Manager
Owner’s Engineer
Consultants – World Class Experts
Line 1 Line 2 Line 3
Viaduct
Stations
Independent Safety and RAM Assessor
10
Financial Closure
Surveys ( Topographical and Geotechical)
Funds tied up within stipulated time Largest fund tie-up in Infrastructure Sector, in a
record period of 6 months
Topographical: Completed Geotechnical: Completed. Part of Line 2 - will
be done at the final pier locations
Current Status
Engineering Conceptual Design Completed Technical Specification Prepared Alignment finalized for Lines 1 & 3 Detailed Design in progress
Corporate office inaugurated at 4th Floor, Cyber Towers , Hyderabad on 11th Feb’11
3 Independent Directors inducted
Procurement L&T – Major Contractor Subcontractors for major Systems under
finalization
11
ROW and Land Status
Pre-Construction
More than 50% of the Land made available (total Land: 269 acres)
ROW : demolitions of buildings commenced
Over-ground Utilities: Identification : Completed for majority of route Diversion: In Progress
Underground Utilities Identification in progress
Current Status
Construction Works
Work on Casting yard Commenced
Depot Earth filling ON
12
Challenges – Pre Construction Utility Diversions
Underground Utilities - No readily available plans. Lot of Surprises in store ?– To wait & see
Government Machinery involvement key Proactive approach of Government required Requirement of Central Nodal Agency
Railway Approvals Long drawn process of approval:
Support of GoAP and MoR/SCR Hyderabad: 8no. crossings, proactive approach resulted in 6no. Crossings – in principle approval. Balance 2no. expected shortly. 13
Challenges - Land , ROW and Alignment finalization
Land- Private Acquisition difficult- Time consuming process- Risk for Concessionaire if it commences construction before availability of complete land parcel
ROW- Requirement of Continuous ROW- 22 mtrs of Construction ROW required (8mtrs Barricading + 2 lanes
on both sides)- ROW of desired width not available at some locations
Alignment Finalization- Limitation on sharp curves (< 130 m)- Leads to structures getting affected at Curves
- Building demolitions and R&R take time
14
Challenges – Design and System Integration• Design
- Design Reworks• Too many Stakeholders• Lack of Standardization in Metro Sector• Uncertain ground features
- Limited Design Experts
• System Integration
- Involves Complex system integration• Skill set nascent in the country• Huge Demand of Metro Experts in country
• Multiple metro project are in progress in India
15
Challenges - Construction
Traffic Management Limited width of ROW (only 8% of lands in Hyd. under Roads) RoW -8m width for barrication & 22 m wide RoW for construction Long periods of barricading(peak time 20 to 25 kms of barrication in city)• Mitigation Measures
• Predominately Precast Construction Methodology adopted• Training of Traffic marshals ON.• Working with GoAP to expand the roads along alignment
Logistics- Project will require transportation of
• Raw material(Steel, cement, sand, aggregate) to precast yard• Precast segments to site location• Transportation of various plants & machinery, rail systems to Site
In the peak period , about 3000 trips per day estimated Mitigation Measures
Appropriate routes being identified Transport network optimization being worked out
16
Challenges – Human Resource
Resource Mobilization• Direct Labor for Civil work -15000 to 20000• Staff: 1000-1200 technical executives
High demand for Skilled resources Adequate training to be provided
Ramping up of Human resources in a short period - a challenge
Multi cultural, region staff
17
Challenges – Financial
Financial Challenges
• Volatile Financial Market• Interest during the construction• Foreign Exchange exposure
• Escalation
• Viability and challenges for Metro Rail can be supported as • Concession in Real Estate• Other Source of Revenue• Viability Grant
18
Opportunities
• Accelerated city development• Faster, Safer and Economical means of transport• Economic Multiplier effect• Multi modal transport facility
• Generate Employment• High Impact on environment
• Mode of Transport % age contribution to CO2 emission Metro Rail - 2.4%
Road - 86.1%Air - 11.1%Water - 0.4% Source: UITP
Publication
• Installation Of Low GHG Emitting Rolling Stock In Metro SystemUNFCCC registration process commenced
(1) Modal Shift (2) Regenerative Braking Registration
19
• Concession Agreement • Termination due to Concessionaire’s default during Construction period• Appointed Date 6 months – too short• Construction related permits before Appointed Date: Stipulation to be removed/
modified • Shortfall between TPC of Authority & TPC of Concessionaire • Separate Escrow Provisions for Metro and Escrow Account• Tax and Duty exemption• Golden Share
• ROW and Land shall be procured before the Bid
• Railway approvals shall be in place before the Bid
• Additional revenue earners - Viability improvement• Annuity / Grant / Property Development / Other innovative supports• Additional lines for operations
WILL LEAD TO MORE INVESTMENT FROM PRIVATE SECTOR
Suggestions for Improvement (CA)
20
THANK YOU
21