Introduction In order to save your time, and in order provide depth and quick understanding about the last 13 years of my career, the following information will be provided for each of the professional experiences: 1. Company (Employer) brief description and background. 2. Employment location (especially that all of the employers I worked for had an international or at least national portfolio). 3. Positions held with dates of each promotion(s), not only the last position held, this is important to demonstrate my progression within each employment. 4. Whom did I reported to at each position or at each assignment. 5. List of general duties. 6. Details of each development I was involved with (as far as I can disclose information). For certain developments I will not be able to state any material information that will hinder the Employer’s interest. 7. For each project, I believe it is essential to demonstrate at what stage(s) I was involved, to achieve this, standard development life cycle (Illustrated in the section below) will be used, for each project, stages that I was involved in will be highlighted Development's standard lifecycle Development Idea Feasibility & Business Planning Structuring Design Tender and Contract Construction & Commissioning Ownership and Operation - Land due diligence - Preliminary market research - Highest and Best Use - Opportunity assessment - Market Research - Financial modeling - Preliminary Business Plan - Development Structure. - Legal and Tax Consideration - Detailed Business plan - Investment memorandum (If Applicable) - Land Acquisition. - Professionals RFP (Architect, Consultant, Engineer, Operators, Project Manager, QS, etc.) - Tender of Professionals - Design Management - Authorities’ liaising - Preparation of tender plan. - Preparation or administration of tender documents. - Administration of tender process - Award recommendatio ns - Management of PM, QS, Engineer, contractor, and or subcontractors. - Monitoring quality control - Management of closeout and handover - Asset management plan - Handover to property manager - Operation

Upload: fadi-tibi

Post on 18-Aug-2015

19 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Omniyat Experience Presentatio

Introduction

In order to save your time, and in order provide depth and quick understanding about the last13 years of my career, the following information will be provided for each of the professionalexperiences:1. Company (Employer) brief description and background.2. Employment location (especially that all of the employers I worked for had an international

or at least national portfolio).3. Positions held with dates of each promotion(s), not only the last position held, this is

important to demonstrate my progression within each employment.4. Whom did I reported to at each position or at each assignment.5. List of general duties.6. Details of each development I was involved with (as far as I can disclose information). For

certain developments I will not be able to state any material information that will hinder theEmployer’s interest.

7. For each project, I believe it is essential to demonstrate at what stage(s) I was involved, toachieve this, standard development life cycle (Illustrated in the section below) will be used,for each project, stages that I was involved in will be highlighted

Development's standard lifecycle

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

- Land due diligence

- Preliminary market research

- Highest and Best Use

- Opportunity assessment

- Market Research

- Financial modeling

- Preliminary Business Plan

- Development Structure.

- Legal and Tax Consideration

- Detailed Business plan

- Investment memorandum (If Applicable)

- Land Acquisition.

- Professionals RFP (Architect, Consultant, Engineer, Operators, Project Manager, QS, etc.)

- Tender of Professionals

- Design Management

- Authorities’ liaising

- Preparation of tender plan.

- Preparation or administration of tender documents.

- Administration of tender process

- Award recommendations

- Management of PM, QS, Engineer, contractor, and or subcontractors.

- Monitoring quality control

- Management of closeout and handover

- Asset management plan

- Handover to property manager

- Operation

Page 2: Omniyat Experience Presentatio

Omniyat real estate development Omniyat real estate development Omniyat real estate development Omniyat real estate development corporationcorporationcorporationcorporation

Assistant Development ManagerAssistant Development ManagerAssistant Development ManagerAssistant Development ManagerMay May May May 2004 2004 2004 2004 to April to April to April to April 2010201020102010

Page 3: Omniyat Experience Presentatio

Company background:Company background:Company background:Company background:Omniyat is the most company I enjoyed working for, joined them before they form their realestate division for about a year and few months in their IT business, Omniyat is created by itsChairman as a startup company. When the real estate division was created, and the name Omniyatwas chosen, I was selected to Join the new team (the tenth division joiner), as my experience withKharafi combined with my experience in IT would help mixing state of the art technology withbuildings to deliver distinguished model of real estate infused not only with the latest technologybut with the art of living and the ultimate experience. Omniyat was the place where the shift in mycareer happened, it is where I loved real estate development.

I had to leave after six years due to mainly factor of time, and because I became relaxed andneeded new challenge presented by Tanween’s offer in Qatar to Join Lusail City Team.

I cannot speak of Omniyat the way they speak about themselves, so kindly visit their website atwww.omniyat.com where they speak about their values and how they do real estate development

Employment period:Employment period:Employment period:Employment period: May 2004 till April 2010 (6 years)

Employment location:Employment location:Employment location:Employment location: City of Dubai – United Arab Emirates

Position(s) held:Position(s) held:Position(s) held:Position(s) held: 1. RMA Coordinator (Aug 2004 to Jan 2005)2. Service Manager (Jan 2005 to Jan 2006)3. Technical Services Manager (Jan 2006 to Jan 2008)4. Assistant Development Manager (position at exit)

Reported to:Reported to:Reported to:Reported to: � As an RMA Coordinator: to Business Unit Manager� As a Service Manager: to Sales Director� As a Technical Services Manager: to Development

Director� As an Assistant Development Manager: to Group

Executive Director � On special assignment reported to Group Chief

Financial officer and the Chairman.

Career Progression:Career Progression:Career Progression:Career Progression: � Aug 2004 � Jan 2005� Jan 2006

� Jul 2006� Mar2007

� Jan 2008

Salary increase 16% Promotion Promotion (The Major Career Change)Salary Increase 100%Bonus 1.4X salaryBonus 2X salarySalary increase 100%PromotionBonus 1.85X salarySalary Increase 63%

Page 4: Omniyat Experience Presentatio

Projects involved Projects involved Projects involved Projects involved 1) One - Business Bay – Dubai

Started in 2006 and completed in 2009, One is a 35-storeyskyscraper located at the northern (at Sheikh Zayed Road)entrance of Business Bay, Dubai. Designed by Germanarchitects Kling Consult GmbH, the tower have 3 basementfloors and a five floor podium with more than 1000 car park.

Each floor will be larger than the previous. It will have 774 m² on its 1stfloor and 1,420 m² on its 30th floor, while three of its upper floorsremarkably extend out of the building. There is a glass feature on topwith a sloping roof. On the roof of the podium a garden is locatedincluding trees and paving.

The building offers860,000 sqft BUA of freehold offices, tranquilityzone, car park and ground floor retail, and high-tech infrastructure.

Omniyat moved its head quarter to the building when it was completed.

Development's Lifecycle involved:

Main Duties:

� Project financing.� Business planning and financial updates.� Managed the design process including incorporation of high-tech systems.� Managed the Project management and Quantity Surveying firms� Oversight of sales and marketing.� Managed relationship with authorities (Municipal, RERA (Real Estate Regulatory Authority) , DLD

(Dubai Land Department). In regard to:� Permits� Registration of project and the units� Issuance of Title dead

� Implementation of Strata management and association requirements, being one of the firstprojects mandated under the new Dubai Strata Law.

� Preparation of handover to strata and facility management teams� Working with finance team in management of Escrow account, contractors payments and

drawdowns, while maintaining continues monitoring of the feasibility.� Participated in preparation of fit out manual� Handover to purchasers

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

Concept Actual

Page 5: Omniyat Experience Presentatio

Projects involved Projects involved Projects involved Projects involved 2) Bayswater - Business Bay - Dubai

Started in 2006 and completed in 2009, Bayswater is a 30-storey skyscraper located at waterfront plot in Business Bay,Dubai. Designed by Local architects Dubarch, the tower have2 basement floors and a four floor podium with more than800 car park.

The tower's exterior is designed to reflect an unpretentious urbansculpture. Its rectilinear design is sliced longitudinally, creating animpression of two parallel towers inclining in opposite directions. Therectilinear sculpture of the building is carried throughout the interiordesign with a combination of elegant horizontal and vertical elements,strikingly contrasting between black and white marble.

The building offers 700,000 sqft BUA of freehold offices, car park andground floor retail, and high-tech infrastructure. The floor layout arevery flexible to provide office units from 760 sqft to a full floor of13,000 sqft

Development's Lifecycle involved:

Main Duties:

� Project financing.� Business planning and financial updates.� Managed the design process including incorporation of high-tech systems.� Managed the Project management and Quantity Surveying firms� Oversight of sales and marketing.� Managed relationship with authorities (Municipal, RERA (Real Estate Regulatory Authority) , DLD

(Dubai Land Department). In regard to:� Permits� Registration of project and the units� Issuance of Title dead

� Implementation of Strata management and association requirements, being one of the firstprojects mandated under the new Dubai Strata Law.

� Preparation of handover to strata and facility management teams� Working with finance team in management of Escrow account, contractors payments and

drawdowns, while maintaining continues monitoring of the feasibility.� Participated in preparation of fit out manual� Handover to purchasers

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

Concept Actual

Page 6: Omniyat Experience Presentatio

Projects involved Projects involved Projects involved Projects involved 3) The Square – Dubai

Mixed use development of 1,271,000 sqft of BUA, consists of9 midrise buildings of 6 stories and one basement, thebuildings are mainly residential condominiums, an officeblock, and serviced apartments operated by Mövenpick, allwrapped around 1.5 acres of gardens and water features

Arabesque designs, domes, wooden trellises, wind-tower shapes,colonnades and latticework roofs. The Square reflects a neoclassicalArabian style. The Arabian theme is further dramatized in the foyersand hallways through arches, vaults, timber ceilings, mosaic reliefs,exotic curves and arabesques, earthy tones and traditional lanterns.

The building 544 residential units of verity of sizes, 43 retail units (oneleased to Spinneys, 126 office units and 180 serviced apartmentsoperated by Mövenpick.

Development's Lifecycle involved:

Main Duties:

� Project financing.� Business planning and financial updates (up to construction stage where the project was handed

over to other manager).� Managed the design process including the serviced apartments.� Assisted in Handover to purchasers (it was a massive task we all had to participate)

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

Concept

Actual

Page 7: Omniyat Experience Presentatio

Projects involved Projects involved Projects involved Projects involved 4) The Gemini – Business Bay Dubai

The Gemini is located at the southern entrance of Businessbay – Dubai in proximity to Dubai mall and Burj Khalifa (theworld tallest building), concept was done by the Germanarchitect MACINA and IF Architecture and developed in J withlocal architect ARC.

The Gemini is designed as a massive and impressive sculpture of strongblack blocks undercut with a meander of white glass and aluminium,design cues which are maintained throughout in interior detail andexternal construction. The two distinctive icon towers of the erectionare created to stand solitary and yet jointly at the same time, in aneternal state of suspension. Each tower is, in itself, a duality of blackand white with the heavy mass of black extending over light areas ofwhite in a peculiar balance.

The building offers flexible office units a tranquility zone and twostories mal. Several studies conducted to assess alternative use such asoffice retail and hospitality, then Omniyat decided to push thedevelopment back in the pipeline despite the enabling works werecompleted.

Development's Lifecycle involved:

Main Duties:

� BBU studies, and fair land price assessment.� Project financing.� Business planning and financial updates.� Design management� Managed the Project management and Quantity Surveying firms� Oversight of sales and marketing.� Managed relationship with authorities (Municipal, RERA (Real Estate Regulatory Authority) , DLD

(Dubai Land Department). In regard to:� Permits� Registration of project and the units� Issuance of Title dead

� Working with finance team in management of Escrow account, contractors payments anddrawdowns, while maintaining continues monitoring of the feasibility

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

Page 8: Omniyat Experience Presentatio

Projects involved Projects involved Projects involved Projects involved 5) The Octavian – Business Bay Dubai

Located in the heart of Business Bay – Dubai , the 19 storytower designed by the German Architect Kling, The Octavianis a unique form of two-transparent towers, connected by ablack center-piece, which is so designed that it sparkles insunlight, emanating lightness and strength.

The interior is designed in a manner so as to deliver easy maintenanceand operation, along with a classic touch. Both towers of the Octavian hasthree podiums and four basement parking levels.

The building has 1,186,000 sqft BUA that offers flexible size office,tranquility zones, and retail units and over 1200 car park.

Development's Lifecycle involved:

Main Duties:

� Highest Best Use and initial idea formation.� Business planning and financial updates.� Design management� Oversight of sales and marketing.

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

Page 9: Omniyat Experience Presentatio

Projects involved Projects involved Projects involved Projects involved 5) The Binary– Business Bay Dubai

The 34 story building is located in the heart of Business Bay –Dubai and designed by local architect Dubarch, the Binarytwo volumes of the building were situated to embrace theviews surrounding the site, from the canal open space, to thewest side and the lake due south.

The fluid shapes of the two volumes enhanced exposure to the views byeliminating the sharp and straight corners, thus creating two natural,organic forms. One tower is longer than the other one, which created alarge desired terrace overlooking the canal and the water lake.

The building offers 950,000 sqft BUA retail units at ground floor, tranquility zone and flexibleoffice units varies from 700 sqft to a full floor of 15,000 sqft, and car park.

Development's Lifecycle involved:

Main Duties:

Managed the development up to design stage where it was assigned to other development manger� Project financing.� Business planning and financial updates.� Design management� Managed the Project management and Quantity Surveying firms during design stage� Oversight of sales and marketing.

Development Idea

Feasibility & Business Planning

Structuring DesignTender and

Contract

Construction &

Commissioning

Ownership and

Operation

Concept Actual