newe weir, river don weir removal technical · pdf filenewe weir, river don weir removal...
TRANSCRIPT
Newe Weir, River Don
Weir Removal Technical Assessment
May ����
Newe Weir, River Don
Weir Removal Technical Assessment
Client: River Don District Salmon Fishery Board
Document number: ����
Project number: �!"�#
Status: Client Issue
Author: David Warren & Stephanie Davidson
Reviewer: Kenneth MacDougall
Date of issue: .� May �#.�
Filename: .�#�.� Newe Weir Technical Assessment Report.docx
Glasgow Aberdeen Inverness Edinburgh
Craighall Business Park
! Eagle Street
Glasgow
G" 6XA
#.". ". �#"#
www.envirocentre.co.uk
Banchory Business
Centre
Burn O’Bennie Road
Banchory
AB . �ZU
#. # !�� �6�
Alder House
Cradlehall Business Park
Inverness
IV� �GH
#."� �6" �.�
Suite .."
Gyleview House
Redheughs Rigg
Edinburgh
EH.� 6DQ
#. . �.� 6� #
This report has been prepared by EnviroCentre Limited with all reasonable skill and care, within the terms of
the Contract with River Don District Salmon Fishery Board (“the Client”). The report is confidential to the Client,
and EnviroCentre Limited accepts no responsibility of whatever nature to third parties to whom this report may
be made known.
No part of this document may be reproduced or altered without the prior written approval of EnviroCentre
Limited.
River Don District Salmon Fishery Board May
Newe Weir, River Don; Weir Removal Technical Assessment
i
Contents Introduction .....................................................................................................................................................
. Project Background .................................................................................................................................
. Scope of Report ....................................................................................................................................... Baseline Conditions .........................................................................................................................................
. Site Location ............................................................................................................................................
. Baseline Surveys ......................................................................................................................................
. Newe Weir ..............................................................................................................................................
. Removal Options Considered .................................................................................................................. Hydrological Assessment and Hydraulic Modelling .........................................................................................
. Hydrological Assessment ........................................................................................................................
. River Don .................................................................................................................................................
. Hydraulic Model Build .............................................................................................................................
. Model Results .......................................................................................................................................... Hydromorphological Assessment ..................................................................................................................
. Site Description and Baseline Conditions ..............................................................................................
. River Don Channel Characteristics in the Vicinity of Newe Weir ..........................................................
. Potential Geomorphological Implications of Newe Weir Removal .......................................................
. Specific Impacts .....................................................................................................................................
. Possible Mitigation Measures ............................................................................................................... Weir Removal Options Appraisal ...................................................................................................................
. Removal Options ...................................................................................................................................
. Partial Removal .....................................................................................................................................
. Full removal ...........................................................................................................................................
. Newe Hydro Scheme ............................................................................................................................. Summary ........................................................................................................................................................
References .............................................................................................................................................................
Appendices A Annual exceedance probability (AEP) and return periods conversion table B Hydrological Analysis C Site Photographs D Hydraulic Modelling Results E Sediment Regime Calculations F Topographical Survey
Figures Figure . ‐ Site location plan and hydrological study extents (red line) ................................................................ Figure . ‐ Features along the study reach ............................................................................................................ Figure . ‐ Location map for the study reach of the River Don ........................................................................... Figure . ‐ Newe Weir ......................................................................................................................................... Figure . ‐ River Don immediately upstream from Newe Weir ........................................................................... Figure . ‐ Wolman pebble counts from representative riffles and bars up‐ and down‐stream of Newe Weir . Figure . ‐ Confluence of Newe hydro scheme lade, Burn of Deochry and River Don at the A bridge ......... Figure . – Bed sediment immediately upstream of weir for removal options .................................................. Figure . ‐ River long section upstream of existing weir (not to scale, and with vertical exaggeration) ............ Figure . ‐ Revised hydro intake locations .......................................................................................................... Figure . ‐ Relocated hydro intake location plan ................................................................................................
River Don District Salmon Fishery Board May
Newe Weir, River Don; Weir Removal Technical Assessment
ii
Tables Table . ‐ Estimated peak flows ............................................................................................................................ Table . ‐ Evaluated scenarios ............................................................................................................................... Table . ‐ Morphological description of the River Don .......................................................................................
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.
1 INTRODUCTION
�.� Project Background
EnviroCentre has been commissioned by the River Don District Salmon Fishery Board to undertake a technical
assessment of the options for the removal of the Newe Weir on the River Don, near Strathdon.
The River Don District Salmon Fishery Board (RDDSFB) want to remove the Newe Weir on the River Don. The
weir presently has a fish pass, but remains an obstacle to migratory fish passage. The weir is presently used by
a third party to abstract river flows that pass through the adjacent Newe Hydro Scheme before being
discharged back to the main channel downstream. The removal of the weir is intended to improve fish passage,
restore river continuity, reinstate natural river processes upstream, reduce maintenance requirements and
improve flood risk.
�.� Scope of Report
This report details the outputs from the below scope of works:
• Baseline surveys: topographic, hydrographic and hydromorphology;
• Hydrological assessment and hydraulic modelling;
• Hydromorphological assessment;
• Weir removal options appraisal, including impact assessment and outline mitigation options.
This assessment does not cover wider ecological aspects of the weir and removal options.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
�
2 BASELINE CONDITIONS
�.� Site Location
The Newe Weir is located on the River Don, approximately �km east of Strathdon, Aberdeenshire, at National
Grid Reference (NGR) NJ �# .�#�. A Location plan is presented as Figure �...
Figure �.� - Site location plan and hydrological study extents (red line)
The land surrounding the weir is predominantly agricultural land, with an area of dense forestry on the
northern banks. A small hydro-electric power station is located to the northeast of the weir, adjacent to Newe
Lodge and the Bridge of Newe. A more detailed description of the River Don at this location is provided in
Section .�. The length of the study reach is approximately km, extending ..�km upstream and ..�km
downstream from the weir.
�.� Baseline Surveys
A number of baseline surveys have been undertaken to assess the current conditions within the river at the
location of the weir, as well as upstream and downstream of the structure.
A topographical survey was undertaken which detailed cross sections of the river channel, structure details and
bank heights along the study reach, providing details for input into the hydraulic model of the river, as well as
crest and bed levels at the weir location itself.
A hydrological survey has been undertaken to determine the flow conditions within the channel, which
involved a walkover survey of the full study reach. This identified any dominant flow regimes, locations of
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
significant structures and features within the river channel, as well as gathering information regarding bank
conditions, floodplain levels and likely overland flow routes. This walkover study was undertaken at the same
time as a hydromorphological survey of the river.
This hydromorphological survey inspected the nature and stability of the river channel along the study reach
along with the general river conditions, natural fluvial processes and potential sediment transport regimes up
and downstream of the weir. This involved Wolman Pebble Counts at riffles and bars both up and downstream
of the weir structure.
The surveys have formed the basis of the weir removal assessment in the following sections.
In this report, where left and right banks are used, these refer to looking downstream.
�.7 Newe Weir
The Newe Weir spans the main channel of the River Don. A weir was initially constructed at Newe sometime
between .!�� and .6## as it does not appear on the first edition Ordnance Survey (OS) map of .!�� (NLS,
n.d.), but is shown in the second edition of .6##. This original weir provided an offtake to supply water via a
lade to a sawmill on the southern (right) bank of the river. The weir was subsequently upgraded to provide an
offtake to the northern bank (left) to power a hydro scheme prior to the national power grid reaching this area.
The original hydro power scheme has long ceased to exist, however a more recent intake has been formed
immediately upstream of the weir to supply water to an Archimedes screw hydro turbine which was installed
approximately .# years ago.
The weir is constructed from stone and concrete, having bankside walls of similar construction immediately
upstream, while a former concrete abstraction lade and large stone boulders are present immediately
downstream of the weir.
A topographic survey of the weir and surrounds has been undertaken (Appendix F), which identifies that the
typical hydraulic head across the weir is ..! m, with upstream water depths of typically #. m – #.� m, although
locally deeper, and downstream water depths of typically ..� m, but deeper than this around the toe of the
weir.
The weir contains a pool and weir type fish pass within the central section of the weir. This has been in place
for many years and has been subject to modifications to improve the flow conditions within the fish pass over
the years. The weir is not considered to be a barrier to fish migration, but will remain an obstacle at certain
flows.
�.8 Removal Options Considered
Two removal options are considered in this assessment:
Partial removal: Assumes that the weir crest is lowered by . m. This will leave a typical drop of
approximately #.! m across the weir footprint.
Full removal: Assumes that the weir crest is lowered by � m.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
"
3 HYDROLOGICAL ASSESSMENT AND HYDRAULIC MODELLING
7.� Hydrological Assessment
The River Don is a major Scottish river which rises in the Cairngorm Mountains and routes east to outfall into
the North Sea at Aberdeen. There are a number of river gauges located along the length of the river, including
at the location of the Newe Weir (..##� Don @ Mill of Newe). This gauge has records from .6!6 through to
.66", however the gauging station was not rated for high flows.
In this report the likelihood of a flood event with a certain magnitude is quantified using the concept of Annual
Exceedance Probability (AEP) expressed as a percentage. The other method that is often used to express flood
risk is the concept of ‘return period’. The relationship between AEP and ‘return period’ is documented in
Appendix A.
The hydrological study undertaken for this assessment focussed upon the peak #.�% AEP flows (equivalent to .
in �## year return period) in order to determine the existing and proposed flood risk in the most extreme
scenarios, and so peak flow estimation was undertaken using two methods for estimating flows in ungauged
catchments, the Revitalised Rainfall-Runoff Method, version � (ReFH�) and the FEH Statistical Method.
Catchment descriptors were derived for the catchment using the FEH Web Service (CEH, �#.�) and are
provided in Appendix B. The catchment area at the location of the weir was estimated to be approximately
.6�. km�. The results of the hydrological analysis are presented in Table .., showing the peak flows for the
�#%, % and #.�% AEP flood conditions. Further details of the calculations are presented in Appendix B.
Table 7.� - Estimated peak flows
AEP% Peak Flow Rate (m7/s)
ReFH� FEH Statistical Method
�# �#. ��.�
.�#.! ."�..
#.� �...� ��#.�
The ReFH� method produces higher flow figures for the lower return period events, however the Statistical
Method produced a higher flow estimate for the #.�% AEP event. In order to be conservative the Statistical
method peak flow of ��#.�m /s was adopted. It is also considered that the Statistical Method is most suited for
estimating flows in catchments of this size.
7.� River Don
The River Don through the study reach meanders through a wide valley floor, with extensive floodplains on
both north and south banks. The site walkover for the hydrological and hydromorphological surveys was
undertaken on ��th
November �#.�, and a photographic record of the walkover is presented in Appendix C. A
detailed description of the river is provided in Table ".., however the below description focuses on key
features along the reach pertinent to the hydraulic modelling and assessment. These locations are presented
on Figure ...
At the upstream end of the reach a small footbridge crosses the river which clearly spans the channel and does
not present a significant restriction to flows. The river appears stable with a width of approximately �#m, and
banks of approximately equal heights. Downstream of the footbridge the river turns to the left (east), and the
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
�
outside of the river channel has been protected with rock armour, approximately �m high, adjacent to the
small road running parallel to the south.
Figure 7.� - Features along the study reach
As the channel routes further south, the banks on the right hand side rise considerably, being approximately -
.�m higher than the left, and so the natural floodplain is located to the north of the river, across the
agricultural fields.
Approximately .#-.�m upstream of the weir crest the intake for the hydro power plant is located on the left
hand bank. This consists of a small lateral weir, covered with a metal trash screen, and flows from this intake
are routed by pipe approximately ��#m to the east to the hydro power plant. This consists of an Archimedes
Screw which is rotated by the flow and head of water passing through the plant. The outfall channel from the
hydro plant routes to the east and converges with the River Don immediately upstream of the Bridge of Newe.
The Newe Weir itself has a width of approximately � m at its crest, and the drop in height through the
structure is approximately �.�- m. The natural channel with through this section of the river is approximately
�#-��m. The Weir is constructed from concrete and a fish ladder is located in the centre of the weir structure.
On the northern side of the weir, the historical intake for the hydro scheme is located, however this is no
longer in use and is sitting redundant. A concrete wall is also located along the right bank at the location of the
weir.
During the site walkover it was noted that there were stockpiles of gravel adjacent to the channel upstream of
the weir. It was later established from the client that gravel and sediment is removed annually from behind the
weir. It was noted that the depth of the channel was greater adjacent to the hydro intake where it appeared
more gravel had been removed.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
�
The bed level for approximately �#-�#m upstream of the weir was shallow with a depth of approximately #.� m
measured from the topographical survey. This is due to the build-up of sediment trapped behind the weir and
prevented from being transported downstream.
Downstream of the weir the channel returns to a less artificially constrained state with bedrock appearing
along the banks. A small pool is located at the toe of the weir which is wider than the downstream channel
width, at approximately ��- #m. The river channel as it continues to route east is approximately .!-�#m wide.
The river turns to the left (northeast) adjacent to the properties located on Waterside Road, and at this
location there is significant bank protection on the right banks in the form of large boulders. This can be seen in
photograph ! in Appendix C.
Approximately .##m further downstream, the outfall from the hydro power plant discharges into the main
river channel on the left bank. This outfall channel is approximately �m wide, and on the day of the walkover
survey the flow within this channel was very similar to the flow in the River Don. Immediately downstream of
this outfall channel a small tributary (Burn of Deochry) discharges into main river channel, also on the left bank.
This location is illustrated in photograph .. in Appendix C.
The River Don continues in a north-easterly direction, passing below the Bridge of Newe, before then routing in
an easterly direction, meandering through agricultural fields. The channel through this downstream section of
the study reach is approximately .�-.�m wide.
7.7 Hydraulic Model Build
7.7.� Model Elements
A .-Dimensional (.D) hydraulic model constructed in Infoworks RS (version ...�) based upon the surveyed river
sections.
The model contained � surveyed sections, � bridges and the weir structure. A number of interpolated sections
were also added to the model to increase model run stability. Bank levels were taken from the topographical
survey, and where river sections were extended across the floodplain, OS Terrain � DTM information was used
to supplement the topographical survey.
7.7.� Manning’s Roughness
The Manning’s ‘n’ roughness vales used within the model were based upon observations of the channel, bank
and floodplain conditions during the site walkover. The values have been based upon the values stated by
Chow (Chow, .6�6), and range from #.# �-#.#"� for the channel bed, and #.#"#-#...# for the banks and
floodplains.
7.7.7 Model Scenarios
In order to determine the baseline conditions for the peak #.�% AEP event the model, and then assess the
impact of any removal works, the hydraulic model was run for a range of scenarios which are listed in Table .�
below.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
�
Table 7.� - Evaluated scenarios
Scenario Description
A. Functional Floodplain* Baseline Scenario.
Flood levels under typical / as surveyed conditions during a 0.5% AEP
river flow.
B. Partial Removal of Weir Weir level reduced by #.6-.m. Bed level in upstream channel lowered
to accommodate lowered weir crest. Lowering extends approximately
�#-!#m upstream. Some infilling of the pool downstream of weir.
C. Full Removal of Weir Bed level at weir lowered by �m. Bed levels upstream lowered to
accommodate change in levels. Downstream pool also filled in with
sediment from upstream. Upstream sediment removal/bed re-grading
extends approximately �#m.
*as defined by Scottish Planning Policy (SPP).
7.8 Model Results
7.8.� Assessment of Baseline Flood Risk – Scenario A
SEPA’s Online Flood Maps indicate that during the #.�% AEP event there would be significant flooding in the
surrounding area, with flows out of bank extending across the majority of the floodplain. Upstream of the weir
flows are shown to be out of the northern banks covering the fields between the river and the A6"". Adjacent
to the weir structure flows are shown out of bank on both the north and south of the river with extensive
flooding surrounding the hydro power plant. Further downstream, the SEPA Flood Maps show that the
properties to the south of the river on Waterside Road would be inundated with flows routing out of the right
banks.
The Baseline Scenario A was run to more accurately determine the flood extents in this area and to verify the
flood risk to any properties in the locality.
From the model runs it was determined that as per the SEPA flood map, there was significant out of bank
flooding in the upper area of the study reach, predominantly from the left bank at the location just
downstream of the small footbridge. This would route flood waters across the large floodplain to the north of
the river, inundating the agricultural fields through this area. Along the central part of the river reach upstream
of the weir, there are additional out of bank flows noted on the left banks which would also inundate the
northern floodplain. Flood flows on the floodplain would route in an easterly direction. A small amount of
flooding is predicted out of the right (southern) banks along the river upstream of the weir.
At the location of the weir, flows are shown to route out of bank on both sides during the peak of the flood
event. On the left banks, the flood flows would route east towards the hydro power plant, and on the right
banks the water would overtop onto agricultural fields. Immediately downstream of the weir, flows would
continue to be out of both banks, with the left inundating the dense forestry area, and the right extending
across the floodplain towards Waterside Road.
At the houses located on Waterside Road downstream of the weir, the ground levels have been taken from the
OS Terrain � DTM and are estimated to be approximately ���.�-��� mAOD. At cross-section DON_.�..
adjacent to this location, the peak water level is estimated to be approximately ���..6 mAOD. As such it is
considered that in the baseline scenario these houses would be at risk of inundation during the #.�% AEP
event.
Downstream of the Bridge of Newe, flows are indicated to spill out of the right bank and route across the
floodplain to the south of the river.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
!
Detailed results of the maximum water levels at each cross section are presented in Appendix D.
Based upon the results of the modelling of the baseline Scenario A, it is considered that the flooding shown on
the SEPA Online Flood Maps would be representative of the #.�% AEP event.
7.8.� Scenario B - Partial Removal
The baseline model was revised to include a partial removal of the weir structure, which included reducing the
height of the crest by #.6-.m across its full width, as well as lowering the bed levels upstream to account for
this lowering. The pool at the downstream toe of the structure was also partially backfilled to allow a smoother
transition through the structure.
The results of the modelling identified that in the upstream of the study reach the peak water levels and
estimated out of bank spills were broadly similar to the baseline scenario, which was as to be expected.
Immediately upstream of the weir structure where the bed levels had been reduced, the peak water level had
dropped in line with the drop in bed level, and this had a backwater affect which extended approximately
�#m upstream.
Immediately downstream of the reduced height weir where the pool was partially backfilled, the peak water
level was estimated to increase which was in line with the increase in bed level. The three river cross sections
downstream of this all showed in increase in peak water levels, but only by a maximum of �mm. Out of bank
flows on the left bank through this section were also shown to marginally increase which would route through
the wooded area and east towards the hydro power plant. Flows out of the right bank were shown to be at
approximately the same level.
The peak water levels and bank overtopping adjacent to the properties on Waterside Road were estimated to
be only !mm lower than the baseline scenario, indicating that the partial removal of the weir structure would
have minimal impact upon the flood risk to these properties.
In the downstream section of the study reach the peak water levels were shown to be between �#-"#mm
different, however the magnitude of these would not be considered to be significant due to the extents of the
wide floodplains through this area.
It is considered that the partial removal of the weir structure and lowering of the crest would have minimal
impact upon the flood risk to properties and land both up and downstream of the weir structure.
7.8.7 Scenario C – Full Removal
The baseline model was revised to include the full removal of the Newe Weir structure, which included the
removal of the concrete structure and the regrading of the channel bed up and downstream. The removal of
sediment and gravel from upstream of weir was assumed to extend for approximately �#m, with the
downstream pool also being backfilled so as to provide a smoother transition through the level change. It is
anticipated that the concrete sides to the weir structure would be retained following the removal of the weir to
provided support to the banks through this location and so these were retained within the model.
The modelling has indicated that as in the partial removal scenario, the upstream section of the study reach
would not be affected by the weir removal. The peak water levels and bank overtopping rates are as per the
baseline scenario, indicating no extensive upstream impact from the weir removal.
Where the bed levels within the channel have been lowered, the peak water level was estimated to also be
lower, with a maximum decrease at the weir of approximately ..!m. Out of bank floodplain flows across the
northern floodplain upstream of the weir structure location were also indicated to increase. This is considered
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
6
to be due to the lowered bed levels at the location of the removed weir allowing greater floodplain flows back
into the river channel, and thus providing a less restricted flow route across the floodplain.
Downstream of the removed weir, the peak water levels were estimated to increase marginally, however the
maximum increase was only indicated to be !mm. At the location of the properties on Waterside Road the
peak water level was estimated to be �mm lower than the baseline scenario, and so it is considered that there
would be negligible impact upon the flood risk to these properties.
In the downstream portion of the study reach the water levels differ from the baseline scenario by a maximum
of approximately �#mm, however as noted above this is not considered to have any detrimental impact upon
any downstream properties.
Following review and comparison of the peak water level results for the #.�% AEP event, it is considered that
the full removal of the weir structure would have a negligible effect on any upstream or downstream
properties in terms of flood risk. Out of bank flows were indicated to increase into the northern floodplain
upstream of the structure, however these would route east across agricultural land and then back into the
main river channel further downstream.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.#
4 HYDROMORPHOLOGICAL ASSESSMENT
8.� Site Description and Baseline Conditions
A reach of River Don between The Colquhonnie House hotel and the A6""/A6� road junction was inspected on
the ��th
of November �#.�; this included the Newe hydro scheme lade. The water level at the gauging station
at Culfork was #.��m, which is slightly higher than the average recorded flow level of #..�m. The weather was
dry and very frosty on the day of survey.
The extent, nature and stability of the channel along a �.!km reach was inspected, along with the general river
conditions in the immediate area of influence, with particular reference to the Newe Weir and hydro scheme.
A location map is provided in Figure "...
A morphological summary of the river conditions at and around the site is provided in Table "...
Figure 8.� - Location map for the study reach of the River Don
Table 8.� - Morphological description of the River Don
Geomorphological feature Description
Valley and terrain
Upland catchment dominated by fluvio-glacial
surficial deposits and metamorphic basement.
Managed agricultural land and temperate forest
are the predominant land uses. The valley is
largely symmetrical with heights greater than
"##m. The valley sides are stable, composed of
glacio-fluvial loose debris and well-vegetated. No
signs of failure are apparent along the river in the
terraces. The valley floor is continuous and
greater than .# channel widths in places. The
riparian buffer strip is wide and continuous.
Study reach
Newe weir and
hydro scheme
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
..
Geomorphological feature Description
Floodplain
The valley is confined within at least one
continuous terrace. The valley floor is continuous
forming a wide floodplain when not confined by
terraces. Fluvio-glacial deposits dominate the
surface geology and managed land use.
Vegetation comprises improved grassland,
deciduous woodland and coniferous forest.
Channel planform
No recent overbank deposits were noted however
trash lines were noted approximately .m above
the bankfull level. The planform is sinuous with
regular meanders and local bank erosion causing
minor lateral activity. Meander scars are apparent
on the floodplain as topographic lows marked by
a change in vegetation.
Channel
The bankfull width and depth on the day of survey
varied from approximately .�m in pool sections
to .#m in riffles, and between .m and #. m
respectively. The average reach slope is
“moderate” (�-!°) with a number of gravel point
bars and lateral bars. The flow type is
uniform/rapid, or plane-riffle, with pool-riffle
features. Artificial levees are noted along the
length of the surveyed section upstream of the
A6"" road bridge. Levee heights vary between .m
and m above the channel bed.
Bed sediment
The bed substrate ranges from cobble to gravel
clasts with occasional boulders. The bed armour is
mobile. Barforms are commonly point bars with
riffle features. Both bed and bar clasts are well
imbricated.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.�
Geomorphological feature Description
Left bank characteristics
The bank is layered, comprising a coarse sand and
gravel matrix capped by thin sandy soils. A layer
of cobbles and gravels is apparent at the bank toe
of variable thickness. Bank top vegetation
comprises healthy grass, sedges, and shrubs with
occasional small deciduous trees. Mature
vegetation cover is sparse and discontinuous over
the upper bank forming a narrow belt adjacent to
the channel. Local bank erosion was noted on the
outside of meander bends or opposite bars. River
flow processes are parallel to the bank.
Geotechnical failures are apparent on the
unstable bank faces in the form of slab failures.
Right bank characteristics
The natural bank materials and processes are
similar to those described for the left bank.
However, the right bank has been heavily
armoured by boulders at a number of locations,
most notably at the outside of meander bends
and adjacent to the residential properties at
Waterside.
Interpretative observations
The River Don river valley generally has
insignificant stability problems with the stable
channel being well-adjusted to the existing
hydrophysiological regimes under the current
climate. The stable bed and banks indicate a
steady state sediment balance with the river
establishing dynamic equilibrium under the
existing conditions.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.
8.� River Don Channel Characteristics in the Vicinity of Newe Weir
The Newe Weir presents an obstacle to fish migration (Figure ".� and Figure ". ). Anecdotal evidence suggests
that adult fish are able to migrate to the pool at the base of the weir but find the existing fish pass difficult to
navigate. On the day of survey, high velocity turbulent flows were observed within the fish ladder.
A spoil heap of gravel and cobbles was observed adjacent to the weir at the left bank and a deep scour hole
was noted in the River Don channel at the hydro scheme intake. These observations support the anecdotal
evidence that the River Don main stem is dredged upstream from the weir to keep the hydro scheme intake
clear of sediment.
Figure 8.� - Newe Weir
Figure 8.7 - River Don immediately upstream from Newe Weir
The River Don has aggraded upstream from Newe Weir such that there is currently a signigicant drop-height in
bed levels between upstream and downstream of the weir. Observations indicate that the aggraded clasts are
predominantly gravel-size and finer. Representative Wolman pebble counts from an upstream riffle and bar
show a marginally finer sediment distribution than samples obtained from a downstream bar and riffle (Figure
"."). These results and observations suggest that the weir is currently trapping finer-grained sediment
potentially leading to a depletion in fines downstream between the weir and the tributary at the A6"" road
bridge.
The Burn of Deochry tributary at the downstream road bridge has formed a junction bar of sand- to gravel-size
clasts at the confluence with the River Don (Figure ".�). A large super-elevated point bar adjacent to the
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
."
properties at Waterside appears to represent deposition from higher flow regimes than the normal range of
flows, and is thus, relict. This may be partly induced by the excessive artificial bank armouring on the opposite
right bank and therefore inhibits the natural flow process and sediment dynamics.
High flow velocities were noted in the Newe hydro scheme lade on the day of survey. Similar to the Burn of
Deochry tributary, the hydro scheme lade appears to be supplying the River Don main stem with finer-grained
sediment at the confluence suggesting this size-range is syphoned into the lade at the upstream intake.
Upstream riffle, DB� = D�mm. Upstream bar, DB� = EBmm, Dmax = �B�mm
Downstream riffle, DB� = DBmm Downstream bar, DB� = EBmm, Dmax = ���mm
Figure 8.8 - Wolman pebble counts from representative riffles and bars up- and down-stream of Newe Weir
Figure 8.B - Confluence of Newe hydro scheme lade, Burn of Deochry and River Don at the AF88 bridge
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.�
8.7 Potential Geomorphological Implications of Newe Weir Removal
Transport of sediment through a catchment and along the length of a river is continuous. Increased erosion in
the upper reaches of a system can affect a considerable length of the downstream river environment for many
miles (and for many years or decades) as the increased sediment loads propagate downstream. Along the river
channel transport system itself, channel forms (such as bars) may appear to be stable but their composition is
in fact changed on an annual or biannual basis as their grains are replaced. Similarly the sediments that make
up the river floodplain (valley floor and terraces) are typically mobile on a time scale of decades or centuries.
The floodplain acts as a storage reservoir for sediments transported in the channel, alternately storing
sediment by deposition and releasing sediment to the channel by bank erosion. The integral connection
between floodplain and channel is crucial in maintaining the dynamic nature of a fluvial system.
A number of indicators have been identified as resulting from disruption of the longitudinal continuity of the
river system and interruption of the sediment transport regime (Kondolf, .66�). Instream mining, for instance,
directly alters the channel geometry and bed elevation and produces a local sediment deficit.
Weirs trap some of the incoming bedload sediment, passing “hungry” water downstream which typically
erodes the channel bed and banks to regain part of its sediment load. The direct results of incision include
undermining of structures, such as bridge piers, and exposure of buried pipeline crossings. Incision of the
riverbed typically causes the alluvial aquifer to drain to a lower level resulting in a loss of aquifer storage. Just
as below dams, gravel-bed rivers may become coarsened or armoured. The increase in sediment size can
threaten the success of spawning by salmonids.
Although the River Don does not show adverse signs of sediment starvation downstream from the Newe Weir,
the downstream surveyed reach does not show the same diversity in bed and bar forms as the upstream reach.
It is anticipated that removing the Newe Weir would re-introduce the full range of bedload and suspended load
sediment sizes to the downstream reaches of the River Don; this would encourage the channel to distribute the
additional supplied sediment over a range of flows to re-establish dynamic equilibrium. As a result of the
proposed weir removal a more varied channel morphology would develop to the advantage of in-channel
biota.
The weir removal process should provide mitigation against the adverse effects of the steep height difference
between the channel bed above and below the weir. The weir removal will alter the equilibrium profile of the
bed, creating a locally steeper gradient. If mitigation is not included as part of the weir removal process, there
is the potential for headcutting to occur as an over-steepened knickpoint can erode upstream.
8.8 Specific Impacts
8.8.� Shorter term impacts
In the full weir removal scenario where the bulk of the sediment is removed from the upstream channel behind
the weir, the short term impact may be that there may be a decrease in sediment supply during high flows
when stored sediment will no longer be available to be transported across the weir to downstream. The
downstream bar and bedforms may become “fixed” in that they will no longer evolve or change over the
medium-to long-term.
Alternatively, if not all of the upstream sediment is removed during the removal of the weir, there will be a
quantity of sediment which is likely to be transported downstream immediately following weir removal. It is
likely that high flows will transport this sediment downstream and that it will naturally infill the downstream
pool with the coarser material, whilst the finer material will be transported as suspended load further
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.�
downstream. This will alter the river’s sediment regime locally in the short-term; however, over longer
timescales it is considered that a new sediment transport equilibrium will be established.
8.8.� Longer term impacts
Based upon the width of the river, the length upstream that sediment may be removed from and an estimate
of the average depth of sediment removal, it is estimated that up to approximately ",###m may require to be
excavated from the river channel. If the weir is just removed with no thought to grading the bed levels then it is
suggested this could have significant consequences downstream. All of the sediment could be moved in the
next couple of spates and dumped overbank, block the tributary and lade confluences, and start forming mid-
channel bars.
Permanent removal of the full volume of sediment from behind the weir has the potential to deplete the
sediment supply for the downstream reach, and over the longer term there is potential for lateral and vertical
erosion if the river has too much transport capacity and too little sediment supply, especially if no mitigation is
provided for the steeper channel gradient after the weir is removed. However studies from previous projects
and rivers show that the estimated bed load within the River Don annually is approximately �##-�,�##m /year.
(high level calculations to support this are presented in Appendix E).
It is noted that there is currently an upstream sediment source which readily supplies sediment downstream as
evidenced by the requirement for annual dredging at the hydro intake upstream of the weir, as noted during
the site walkover and from anecdotal evidence.
8.B Possible Mitigation Measures
A number of mitigation measures are presented below to ensure the stability of the river channel following the
removal of the weir:
.. Stockpiles of removed sediment to re-stock river if required;
�. Sediment removed from main river channel, and placed along the banks and sides of the channel for
the river to naturally work through and transport downstream. Natural variation in flows will allow the
various grades of material to be transported downstream over time providing a more naturally graded
river channel. It is considered that due to the natural supply of sediment that is noted above, only a
certain percentage of the excavated material would require to be retained in the river, estimated to
be approximately �#%. The placement of this sediment will need to be considered so as not to disrupt
the natural bar form and bedform distribution. It can be placed on the outside of meander bends, no
greater than bankfull level where it is most likely to be entrained during higher flows. In the lower
sinuosity sections dredged sediment could be placed on the bed in steeper reaches, but not so that it
smothers the whole bed, or on part of the exposed bar features.
. The downstream pool could be immediately backfilled with material during the weir removal to avoid
any significant steep sections within the channel. Larger boulders in-stream would dissipate the
energy within the flows and the sediment would be redistributed more naturally over time. Boulders
placed at the margins could help stabilise the finer sediments after deposition. Depending on their
placement in the scour pool itself, the boulders may help limit vertical scour by protecting the bed or
may help direct the location of scour.
". Where there could potentially be a step in the river bed where the weir structure once stood, there is
the potential for this to become unstable through erosion. In order to prevent this, the base of the
weir structure could potentially be left in place to provide bed armouring and protection. Additional
steps below the weir could also be introduced to create a step-pool bed morphology in order to
reduce the gradient differential and dissipate energy.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.�
�. In addition, the concrete wingwalls along the length of the existing weir could potentially be retained
to provide bank support.
�. Although not directly linked to the removal of the weir structure, there is the potential to remove a
volume of material from the super-elevated point bar from downstream adjacent to the Waterside
properties. This will allow for a slightly greater channel capacity during higher flows and could
potentially mitigate some flood risk to these properties. It will also allow more natural flow processes
to occur.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.!
5 WEIR REMOVAL OPTIONS APPRAISAL
B.� Removal Options
The below appraisal outlines the options for both the partial and full removal of the Newe Weir structure,
identifying the potential impacts in terms of flood risk, morphology, fish passage and other external receptors.
For each option a number of mitigation measures have been identified which would be recommended to
minimise or prevent many of the proposed detrimental impacts, however this report does not include for any
outline design of these measures.
The estimated extent of sediment behind the weir that is more likely to be mobilised as a consequence of the
two removal options is shown in Figure �... For the partial removal, this extends approximately !#m upstream
and equates to approximately 6##m , while for the full removal option, this extends to approximately �#m
and equates to approximately ",###m .
Figure B.� – Bed sediment immediately upstream of weir for removal options
B.� Partial Removal
B.�.� Extents of works
The partial removal of the weir structure will involve the reducing the height of the weir crest by .m to result in
a drop in height across weir of less than .m (approx. #.!m). The volume of material behind the weir is in the
estimated order of between .-� years’ of natural averaged bedload, so this material could be redistributed
locally within the channel to allow it to be mobilised at different flow rates and mitigate the impact of returning
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
.6
this material to the river system. This will include partially infilling the pool below the weir with stone from the
weir and sediment from behind the weir to allow a managed transition in bed levels through the structure.
The existing fish pass which is located on the weir would be part-removed with the remaining structure left in-
situ.
The existing wingwalls which are located along the banks of the river at the weir location are to be retained to
provide stability to the banks as the bed and water levels are reduced, and the disused inlet lade located just
downstream of the weir will be backfilled. There is the potential for using the upstream excavated material to
fill this lade.
B.�.� Assessed impacts
The partial removal of the weir will have the following impacts upon the river:
Flood Risk
The hydraulic modelling detailed in Section highlighted that following the partial removal of the weir, there
would be negligible impact on flood risk to any properties up or downstream of the weir.
A marginal increase in the peak out of bank flows on the left bank downstream of the weir was identified
during the modelling of this scenario, however the total volume that was estimated to route out of bank was
similar and so there is not considered to be a significant increase in flood risk to this area. The flood flows
would route through the wooded area on the northern banks in an easterly direction to then flow back into the
river further downstream.
Morphology
Following a partial removal of the weir there will be less of a restriction for sediment transport within the river,
however a constraint will still remain which would restrict bed load transport downstream. As noted in Section
" the River Don appears to have an abundant sediment supply, and so it is considered that retaining a partial
barrier will mean that material would continue to accumulate behind the weir.
Due to the reduced height of the weir, there would be less trapping of finer suspended load and so it is
considered that there would be a slight improvement to the supply of finer sediment downstream.
Fish Passage
As noted above, the partial removal of the weir would retain the remaining fish pass structure. This may
require some ancillary works to ensure that the concrete structure retains its integrity and continues to
function as a fish pass. As such it is considered that there would continue to be an obstacle to migratory fish,
however it would not be as large as the existing weir structure.
Hydro Scheme
Due to the bed levels upstream of the weir being lowered in this scenario, the normal water level immediately
upstream of the weir would also be reduced. This would result in flows which are abstracted for the hydro
scheme being affected. Abstraction for the hydro scheme only occurs when the water within the River Don is
above a certain level, and due to the lowering of the weir, the waters are unlikely to exceed this level with as
much frequency, thus affecting the productivity and effectiveness of the hydro scheme.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
�#
In order to mitigate this, the intake location would require to be moved upstream by approximately 6#m.
Further details on the impact to the hydro scheme are included in Section �." below.
B.�.7 Mitigation
In terms of morphology, the excavated gravel from upstream of the partially removed weir could be
redistributed within the local reach, including the reach immediately downstream of the weir to promote
varied bedforms within the channel, however there would only be a limited supply of this material. Other
potential mitigation measures are noted in Section ".�.
As noted above the intake for the hydro scheme will require to be relocated further upstream and based on
the estimated gradient of the river bed post-completion, it is estimated that the intake would require to be
shifted approximately 6#m upstream. Further details are included in Section �.".
With regards to fish passage, if the head drop across the weir is <.m and spread over .#-.�m, then this should
not present a major obstacle to fish. There may be a requirement for some designed placement of stone (from
the weir) to below the removed weir to create individual drops of < #. m.
B.7 Full removal
B.7.� Extents of works
The full removal of the weir will involve the demolition of the concrete structure across the full width of the
channel, including the fish pass, as well as the regrading of the channel bed up and downstream. The
immediate influence of the weir is expected to extend approximately �#m upstream and this reach would
require local adjustment of the channel bed and redistribution of sediment. This would include partial infilling
of the downstream pool along with heavier material from the weir to provide a smoother transition through
former weir footprint and allow natural sediment redistribution during higher flows. It is anticipated that the
concrete sides to the weir structure would be retained following the removal of the weir to provided support
to the banks through this location. The toe of weir would also be retained within the channel to provide bed
protection where there is anticipated to be local steepening of the channel gradient where the weir once
stood. Steps in the channel bed could also be introduced which would reduce the gradient differential.
Given the expected volume of sediment behind the weir, it is expected that only around �#% may be directly
retained within the channel, which is in the estimated order of between .-.# years’ of natural averaged
bedload. The remained of the material could be stored on the bankside and re-introduced to the river over a
longer time period, or disposed off site.
B.7.� Assessed impact
The full removal of the weir would have the following impacts upon the river:
Flood Risk
The hydraulic modelling detailed in Section highlighted that following the full removal of the weir, there
would be negligible impact on flood risk to any properties up or downstream of the weir.
A marginal increase in the peak out of bank flows on the left (northern) bank upstream of the weir was
identified during the modelling of this scenario, however there was also an increase in the flow from the
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
�.
floodplain back into the river further downstream and so it is considered that demonstrated an increase in the
floodplain flows. These flows would only affect the agricultural land to the north and not any residential
properties.
Morphology
The full removal of the weir structure would allow for a full range of suspended load and bed load sediment to
be transported downstream, promoting a more varied channel morphology. There would be a short term local
adjustment while the bed adjusted and this would depend on the amount of sediment available within the
channel for re-working.
Finer sediment which would have once been trapped behind the weir structure would pass downstream to the
reach between the weir and the Bridge of Newe. This will result in a broader range of sediment grain sizes with
diverse bed and bar forms. As a result of the varied channel morphology there is likely to be an increase in in-
stream channel habitat variability which is beneficial to in-channel biota.
Fish Passage
Removal of the full height of the weir will ensure that any restriction to the passage of fish has been removed.
Hydro Scheme
As with the partial removal of the weir, the upstream bed levels within the river will be reduced following the
full removal of the weir structure, therefore lowering the water levels. The intake for the hydro scheme will
again be affected by this, however the impact would be greater as the full height of the weir would be
removed. In order to mitigate this, the intake location would require to be moved upstream by approximately
��#m. Further details on the impact to the hydro scheme are included in Section �." below.
B.7.7 Mitigation
Section ".� notes a number of mitigation measures which could be implemented in order to ensure that the
morphology of the river is not detrimentally affected by the removal of the weir. This includes placing the
upstream excavated material along the banks of the river to allow the variation in flows to re-mobilise the
material to provide a naturally graded channel, as well as retaining the base of the weir structure to protect
against bed scour and adding steps, pools and boulders to the channel to dissipate energy.
As noted above, the intake location for the hydro scheme will be affected by the removal of the weir, and so
this will require to be re-located further upstream by approximately ��#m. Further details are present in the
following section.
B.8 Newe Hydro Scheme
The intake for the Newe Hydro Scheme is currently located upstream of the weir, on the left bank, and consists
of a lateral overflow with a trash screen, routing flows into a small section of open channel which then flows
through a sluice gate into a large diameter pipe. This pipeline routes east and connects into the tunnel used by
the historic hydro plant on site and feeds the flows into the power plant approximately ���m to the east.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
��
If the weir were to be either partially or fully removed, this would impact upon the intake as water levels in the
river will have been dropped, and so it would require to be re-located further upstream to allow it to be routed
by gravity into the power plant.
Based upon the topographical survey that was undertaken and the subsequent hydraulic model that was
constructed, a long section of the watercourse from the weir structure and upstream was generated and is
presented as Figure �.�.
Figure B.� - River long section upstream of existing weir (not to scale, and with vertical exaggeration)
From study of these it was determined that the minimum intake level is approximately ���.� mAOD, and so
based upon the estimated upstream gradient of the post-full removal river channel, the new intake would
require to be located approximately ��#m upstream of the existing one. In the scenario where the weir would
only be partially removed, the intake would require to be located approximately 6#m further upstream. Figure
�. illustrates the existing and proposed channel bed profile, with the estimated locations of the relocated
hydro intakes and Figure �." shows these locations on plan.
The new intake could be extended using a pipeline as per the existing situation, however this is likely to be an
expensive option as the diameter of the existing pipe is understood to be .,�##mm.
Alternatively the intake could potentially take the form of an open channel routing flows to the hydro plant so
as to reduce the costs of the extended intake, however it would need to be designed to ensure that sediment
from within the river would not route into the hydro scheme.
A more detailed feasibility study would be required in order to determine the optimal location and solution for
the relocated intake, and a technical variation would be required for the Controlled Activities (Scotland)
Regulations (CAR) licence for the abstraction of flows from the river.
Figure B.7 - Revised hydro intake locations
River Don District Salmon Fishery Board May
Newe Weir, River Don; Weir Removal Technical Assessment
Figure . ‐ Relocated hydro intake location plan
River Don District Salmon Fishery Board May
Newe Weir, River Don; Weir Removal Technical Assessment
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
��
6 SUMMARY
This report was undertaken to assess the impact of the removal of the Newe Weir, River Don, on the hydrology
and hydromorphology of the river system, and identify the potential removal options.
Baseline hydrological and hydromorphological assessments were undertaken, in conjunction with a
topographical survey of the weir and surrounding area.
The hydrological assessment included the creation of a .-dimensional hydraulic model which outlined the
existing flood risk to the land and properties in the vicinity of the weir, and this determined that peak flows in
the #.�% AEP event would route out of bank along the majority of the study reach. The results from this
baseline scenario concurred with the extents of flooding shown on the SEPA Online Flood Maps.
The hydromorphological assessment outlined the baseline conditions within the river, noting that the River
Don river valley generally has insignificant stability problems with the stable channel being well-adjusted to the
existing hydrophysiological regimes under the current climate. The stable bed and banks indicate a steady state
sediment balance with the river establishing dynamic equilibrium under the existing conditions.
Two removal options have been highlighted – partial and full removal – and an assessment was undertaken of
the impact of both of these scenarios.
With regards to hydrology and flood risk, the hydraulic model of the river was updated to include the partial or
full removal of the weir and re-run for the peak flow events. This modelling indicated that in both scenarios the
weir removal had little impact upon the extents and severity of any out of bank flooding, with the risk to
properties not being increased. The maximum flood levels adjacent to the properties downstream at Waterside
reduced by a maximum of !mm in both scenarios and so the impact on flood risk is considered to be negligible.
The weir removal will have a greater impact upon the hydromorphology of the river and this assessment
identified the upstream and downstream impacts of both scenarios.
In the partial removal scenario, it was identified that although the lowered weir would remain a constraint
within the river which would restrict bed load transport downstream, there would be a slight improvement to
the supply of finer sediment downstream. It is recommended that material excavated from upstream of the
weir be redistributed within the local reach, including the reach immediately downstream of the weir to
promote varied bedforms within the channel. The lowered weir would also remain a partial obstacle for
migratory fish.
Fully removing the weir was identified to have a positive impact upon the river as it would allow for a full range
of suspended load and bed load sediment to be transported downstream, promoting more varied channel
morphology. As a result of the varied channel morphology there is likely to be an increase in in-stream channel
habitat variability which is beneficial to in-channel biota. The removal of the weir and upstream sediment
would require to be carefully managed however, as removal of all of this material has the potential to deplete
the sediment supply for the downstream reach, and over the longer term there is potential for lateral and
vertical erosion if the river has too much transport capacity and too little sediment supply.
Mitigation measures have been outlined to prevent this occurring including: retaining the base of the weir
structure to protect against bed scour; the placement of boulders to reduce the gradient differential and
dissipate energy; potentially the creation of a step-pool bed morphology; and the re-distribution of the
excavated bed material to the banks and sides of the channel for the river to naturally work through and
transport downstream, promoting a more naturally graded river channel.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
��
The potential impact upon the intake for the Newe Hydro has identified that the intake would require to be re-
located upstream by approximately 6# and ��#m in the partial and full removal scenarios respectively.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
��
REFERENCES
Kjeldsen, T., Jones, D. & Bayliss, A. (�##!). Improving the FEH statistical procedures for flood frequency
estimation (No. SC#�##�#). Bristol: Environment Agency.
Kondolf, G. M. (.66�). Hungry water: Effects of dams and gravel mining on river channels. Environmental
Management, ��(").
NLS (n.d.). Map images. Edinburgh: National Library of Scotland. Retrieved from http://maps.nls.uk/
WHS (�##6). WINFAP-FEH (Software). Wallingford: Wallingford HydroSolutions Limited.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
APPENDICES
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
A ANNUAL EXCEEDANCE PROBABILITY (AEP) AND RETURN PERIODS
CONVERSION TABLE
Table �: Relationship between annual exceedance probability and return periods
Annual exceedance
probability, AEP (%)
Return period, T (year) Comment
�# � Median annual flood, in the long-term this occurs
every other year, on average.
�# �
.# .#
� �#
. # Typical design standard for urban drainage systems.
� �#
. .##
#.� �## Typical design conditions standard for river or
coastal flooding for most developments. Defines
“functional floodplain” under Scottish Planning
Policy.
#.� �##
#.. .,### Typical design conditions standard for sensitive or
vulnerable developments/contexts.
The annual exceedance probability of particular flood conditions is the chance these conditions (or more
severe) occur in any given year.
The return period of a flood is the long-term average period between flood conditions of such magnitude (or
greater).
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
B HYDROLOGICAL ANALYSIS
Catchment Descriptors
CATCHMENT NJ 7D8B� �����
AREA .6�.�!��
ALTBAR �..
ASPBAR �6
ASPVAR #..
BFIHOST #."��
DPLBAR .!. �
DPSBAR .!6..
FARL #.66�
FPEXT #.#�6�
FPDBAR #."#
FPLOC #.� !
LDP �.!.
PROPWET #.�
RMED-.H !.!
RMED-.D �.�
RMED-�D �...
SAAR .#��
SAAR".�# ..��
SPRHOST "..�"
URBCONC.66# -666666
URBEXT.66# #.###.
URBLOC.66# -666666
URBCONC�### -666666
URBEXT�### #
URBLOC�### -666666
C -#.#.!�6
D. #.""6�
D� #.�#."!
D #. .�!�
E #.�"!.!
F �.��#6�
C(. km) -#.#.!
D.(. km) #."�
D�(. km) #.�#.
D (. km) #. #�
E(. km) #.��.
F(. km) �..�6
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
Statistical Analysis
The FEH statistical method has been applied using WINFAP-FEH software (WHS, �##6) and the WINFAP-FEH
v".. data files.
A pooled analysis was undertaken using the catchment descriptors extracted from the FEH web service to NJ
!"�# .��## (catchment area .6�. km�). The results of this analysis are described below.
The QMED (median annual maximum flood) for the catchment to NJ !"�# .��## was calculated from
catchment descriptors as � .�� m /s. A donor transfer was applied using data from the gauging station with
the closed catchment centroid (..## Don @ Bridge of Alford) (Kjeldsen, Jones & Bayliss, �##!), providing a
QMED estimate of ��.�"�m /s.
The details of the pooling group used are shown in Table F. and Table F�. The General Logistic (GL) was found
to be most suitable and was used to develop the growth curve fittings (Table F ). The peak flow estimates are
shown in Table F".
Table F�: Pooling group details – FEH catchment to NJ 7D8B� �����
Site River Don
Changes made to default pooling group None
No of sites in pooling group ."
Total no. of years �"�
Pooling group L-CV #.�
Pooling group L-SKEW #.�.!
Heterogeneity measure (H�) �. !"6(review of pooling group is desirable)
Suitable distributions and goodness of fit General Logistic (#.�"#�)
Table F�: Pooling group details - FEH catchment to NJ 7D8B� �����
Station Distance Years of
data
QMED
AM
L-CV L-SKEW Discordancy
9004 (Bogie @ Redcraig) 0.22 26 31.622 0.312 0.274 0.95
66006 (Elwy @ Pont-y-gwyddel) 0.244 38 73.024 0.187 0.133 0.285
21013 (Gala Water @ Galashiels) 0.26 43 51.535 0.273 0.305 0.634
45005 (Otter @ Dotton) 0.284 50 69.81 0.284 0.413 1.538
12008 (Feugh @ Heugh Head) 0.287 21 141.628 0.201 0.11 0.278
47006 (Lyd @ Lifton Park) 0.334 43 80.468 0.275 0.293 0.47
52005 (Tone @ Bishops Hull) 0.347 51 43.861 0.199 0.076 0.732
9003 (Isla @ Grange) 0.35 47 49.309 0.218 0.148 0.904
21032 (Glen @ Kirknewton) 0.379 44 44.45 0.267 0.236 0.253
203024 (Cusher @ Gamble's Bridge) 0.392 41 49.515 0.134 0.013 1.775
67008 (Alyn @ Pont-y-capel) 0.394 47 22.981 0.184 0.353 2.384
11004 (Urie @ Pitcaple) 0.413 18 21.42 0.306 0.268 0.833
12006 (Gairn @ Invergairn) 0.415 28 59.871 0.202 0.085 0.486
28023 (Wye @ Ashford) 0.425 48 16.528 0.21 0.3 2.479
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
Table F7: Pooled growth curve - FEH catchment to NJ 7D8B� �����
AEP (%) Growth Factor
�# .
�# .. �6
.# ..��6
" �.#�
� �." "
. �.!�
#.� . .
#.� ".#!�
Table F8: Peak Flow Estimates (m7/s)
AEP (%) FEH catchment to NJ 7D8B� �����
(catchment area �FE.7km�)
�# ��.�"�
."�.#6
#.� ��#.��
Summary of estimate using the Flood Estimation Handbook revitalised flood hydrograph method (ReFH)
Site details
Site description:
Catchment Area (km²): 196.28
None
Site name: Don @ Newe Weir
Easting: 338450
Northing: 812200
Model run: 2 yearSummary of results
Rainfall - FEH 2013 (mm): 23.16
Total Rainfall (mm): 15.47
Peak Rainfall (mm): 4.21 70.33
2150.61
1006.57Total runoff (ML):
Total flow (ML):
Peak flow (m³/s):
Loss model parametersName Value User-defined?
Cini (mm) 124.56 No
Cmax (mm) 399.2 No
Use alpha correction factor No No
Alpha correction factor n/a No
Rainfall parameters (Rainfall - FEH 2013 model)Name Value User-defined?
Duration (hh:mm:ss) 04:30:00 No
Timestep (hh:mm:ss) 00:30:00 No
SCF (Seasonal correction factor) 0.77 No
ARF (Areal reduction factor) 0.87 No
Seasonality Winter n/a
Routing model parameters
ParametersWhere the user has overriden a system-generated value, this original value is shown in square brackets after the value used.* Indicates that the user locked the duration/timestep
UK Design Flood Estimation
Generated on Monday, February 20, 2017 12:21:08 PM by dwarrenPrinted from the ReFH Flood Modelling software package, version 2.2.6029.28099
Checksum: 3A08-A285
Country: Scotland
Using plot scale calculations: No
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 1 of 5
Name Value User-defined?Tp (hr) 2.39 No
Up 0.65 No
Uk 0.8 No
Name Value User-defined?
BF0 (m³/s) 8.51 No
BL (hr) 35.37 No
BR 1.14 No
Baseflow model parameters
Name Value User-defined?Urban area (km²) 0 No
Urbext 2000 0 No
Impervious runoff factor 0.7 No
Imperviousness factor 0.3 No
Tp scaling factor 0.5 No
Sewered area (km²) 0.00 Yes
Sewer capacity (m³/s) 0.00 Yes
Urbanisation parameters
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 2 of 5
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
00:00:00 0.442 0.000 0.138 0.000 8.506 8.506
00:30:00 0.830 0.000 0.261 0.215 8.388 8.604
01:00:00 1.543 0.000 0.489 1.051 8.281 9.332
01:30:00 2.818 0.000 0.909 3.054 8.197 11.251
02:00:00 4.208 0.000 1.395 7.233 8.165 15.398
02:30:00 2.818 0.000 0.959 14.980 8.228 23.208
03:00:00 1.543 0.000 0.533 25.895 8.440 34.335
03:30:00 0.830 0.000 0.289 37.997 8.833 46.829
04:00:00 0.442 0.000 0.155 49.247 9.407 58.654
04:30:00 0.000 0.000 0.000 57.258 10.127 67.385
05:00:00 0.000 0.000 0.000 59.413 10.918 70.331
05:30:00 0.000 0.000 0.000 56.383 11.692 68.074
06:00:00 0.000 0.000 0.000 50.397 12.382 62.779
06:30:00 0.000 0.000 0.000 43.148 12.956 56.104
07:00:00 0.000 0.000 0.000 35.866 13.406 49.272
07:30:00 0.000 0.000 0.000 29.649 13.742 43.391
08:00:00 0.000 0.000 0.000 24.424 13.982 38.406
08:30:00 0.000 0.000 0.000 19.776 14.139 33.916
09:00:00 0.000 0.000 0.000 15.484 14.223 29.706
09:30:00 0.000 0.000 0.000 11.497 14.239 25.736
10:00:00 0.000 0.000 0.000 7.808 14.193 22.001
10:30:00 0.000 0.000 0.000 4.632 14.094 18.726
11:00:00 0.000 0.000 0.000 2.325 13.951 16.277
11:30:00 0.000 0.000 0.000 1.017 13.782 14.800
12:00:00 0.000 0.000 0.000 0.368 13.600 13.968
12:30:00 0.000 0.000 0.000 0.086 13.413 13.498
13:00:00 0.000 0.000 0.000 0.002 13.225 13.227
13:30:00 0.000 0.000 0.000 0.000 13.039 13.039
14:00:00 0.000 0.000 0.000 0.000 12.856 12.856
14:30:00 0.000 0.000 0.000 0.000 12.676 12.676
15:00:00 0.000 0.000 0.000 0.000 12.498 12.498
15:30:00 0.000 0.000 0.000 0.000 12.322 12.322
16:00:00 0.000 0.000 0.000 0.000 12.150 12.150
16:30:00 0.000 0.000 0.000 0.000 11.979 11.979
17:00:00 0.000 0.000 0.000 0.000 11.811 11.811
Time series data
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 3 of 5
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
17:30:00 0.000 0.000 0.000 0.000 11.645 11.645
18:00:00 0.000 0.000 0.000 0.000 11.482 11.482
18:30:00 0.000 0.000 0.000 0.000 11.320 11.320
19:00:00 0.000 0.000 0.000 0.000 11.161 11.161
19:30:00 0.000 0.000 0.000 0.000 11.005 11.005
20:00:00 0.000 0.000 0.000 0.000 10.850 10.850
20:30:00 0.000 0.000 0.000 0.000 10.698 10.698
21:00:00 0.000 0.000 0.000 0.000 10.548 10.548
21:30:00 0.000 0.000 0.000 0.000 10.400 10.400
22:00:00 0.000 0.000 0.000 0.000 10.254 10.254
22:30:00 0.000 0.000 0.000 0.000 10.110 10.110
23:00:00 0.000 0.000 0.000 0.000 9.968 9.968
23:30:00 0.000 0.000 0.000 0.000 9.828 9.828
24:00:00 0.000 0.000 0.000 0.000 9.690 9.690
24:30:00 0.000 0.000 0.000 0.000 9.554 9.554
25:00:00 0.000 0.000 0.000 0.000 9.420 9.420
25:30:00 0.000 0.000 0.000 0.000 9.288 9.288
26:00:00 0.000 0.000 0.000 0.000 9.157 9.157
26:30:00 0.000 0.000 0.000 0.000 9.029 9.029
27:00:00 0.000 0.000 0.000 0.000 8.902 8.902
27:30:00 0.000 0.000 0.000 0.000 8.777 8.777
28:00:00 0.000 0.000 0.000 0.000 8.654 8.654
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 4 of 5
AppendixCatchment descriptors
Name Value User-defined value used?
Area (km²) 196.28 No
ALTBAR 511 No
ASPBAR 79 No
ASPVAR 0.1 No
BFIHOST 0.47 No
DPLBAR (km) 18.36 No
DPSBAR (mkm-¹) 189.1 No
FARL 1 No
LDP 36.81 No
PROPWET (mm) 0.63 No
RMED1H 8.8 No
RMED1D 36.7 No
RMED2D 51.1 No
SAAR (mm) 1057 No
SAAR4170 (mm) 1162 No
SPRHOST 41.24 No
Urbext2000 0 No
Urbext1990 0 No
URBCONC 0 No
URBLOC 0 No
Urban Area (km²) 0 No
DDF parameter C -0.02 No
DDF parameter D1 0.45 No
DDF parameter D2 0.5 No
DDF parameter D3 0.32 No
DDF parameter E 0.25 No
DDF parameter F 2.27 No
DDF parameter C (1km grid value) -0.02 No
DDF parameter D1 (1km grid value) 0.46 No
DDF parameter D2 (1km grid value) 0.5 No
DDF parameter D3 (1km grid value) 0.31 No
DDF parameter E (1km grid value) 0.25 No
DDF parameter F (1km grid value) 2.17 No
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 5 of 5
Summary of estimate using the Flood Estimation Handbook revitalised flood hydrograph method (ReFH)
Site details
Site description:
Catchment Area (km²): 196.28
None
Site name: Don @ Newe Weir
Easting: 338450
Northing: 812200
Model run: 30 yearSummary of results
Rainfall - FEH 2013 (mm): 49.47
Total Rainfall (mm): 33.05
Peak Rainfall (mm): 8.99 150.77
4903.70
2292.64Total runoff (ML):
Total flow (ML):
Peak flow (m³/s):
Loss model parametersName Value User-defined?
Cini (mm) 124.56 No
Cmax (mm) 399.2 No
Use alpha correction factor No No
Alpha correction factor n/a No
Rainfall parameters (Rainfall - FEH 2013 model)Name Value User-defined?
Duration (hh:mm:ss) 04:30:00 No
Timestep (hh:mm:ss) 00:30:00 No
SCF (Seasonal correction factor) 0.77 No
ARF (Areal reduction factor) 0.87 No
Seasonality Winter n/a
Routing model parameters
ParametersWhere the user has overriden a system-generated value, this original value is shown in square brackets after the value used.* Indicates that the user locked the duration/timestep
UK Design Flood Estimation
Generated on Monday, February 20, 2017 12:21:23 PM by dwarrenPrinted from the ReFH Flood Modelling software package, version 2.2.6029.28099
Checksum: 3A08-A285
Country: Scotland
Using plot scale calculations: No
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 1 of 6
Name Value User-defined?Tp (hr) 2.39 No
Up 0.65 No
Uk 0.8 No
Name Value User-defined?
BF0 (m³/s) 8.51 No
BL (hr) 35.37 No
BR 1.14 No
Baseflow model parameters
Name Value User-defined?Urban area (km²) 0 No
Urbext 2000 0 No
Impervious runoff factor 0.7 No
Imperviousness factor 0.3 No
Tp scaling factor 0.5 No
Sewered area (km²) 0.00 Yes
Sewer capacity (m³/s) 0.00 Yes
Urbanisation parameters
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 2 of 6
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
00:00:00 0.944 0.000 0.296 0.000 8.506 8.506
00:30:00 1.772 0.000 0.561 0.460 8.390 8.851
01:00:00 3.295 0.000 1.064 2.254 8.294 10.549
01:30:00 6.019 0.000 2.014 6.577 8.249 14.826
02:00:00 8.988 0.000 3.177 15.691 8.311 24.002
02:30:00 6.019 0.000 2.240 32.845 8.583 41.428
03:00:00 3.295 0.000 1.265 57.370 9.185 66.555
03:30:00 1.772 0.000 0.692 84.908 10.195 95.103
04:00:00 0.944 0.000 0.372 110.858 11.619 122.477
04:30:00 0.000 0.000 0.000 129.774 13.381 143.155
05:00:00 0.000 0.000 0.000 135.455 15.315 150.771
05:30:00 0.000 0.000 0.000 129.115 17.217 146.332
06:00:00 0.000 0.000 0.000 115.753 18.934 134.687
06:30:00 0.000 0.000 0.000 99.280 20.389 119.668
07:00:00 0.000 0.000 0.000 82.569 21.557 104.126
07:30:00 0.000 0.000 0.000 68.255 22.461 90.715
08:00:00 0.000 0.000 0.000 56.247 23.141 79.388
08:30:00 0.000 0.000 0.000 45.605 23.631 69.236
09:00:00 0.000 0.000 0.000 35.800 23.951 59.751
09:30:00 0.000 0.000 0.000 26.692 24.114 50.807
10:00:00 0.000 0.000 0.000 18.234 24.135 42.369
10:30:00 0.000 0.000 0.000 10.902 24.029 34.932
11:00:00 0.000 0.000 0.000 5.520 23.823 29.344
11:30:00 0.000 0.000 0.000 2.429 23.552 25.982
12:00:00 0.000 0.000 0.000 0.883 23.248 24.131
12:30:00 0.000 0.000 0.000 0.206 22.931 23.137
13:00:00 0.000 0.000 0.000 0.004 22.610 22.614
13:30:00 0.000 0.000 0.000 0.000 22.293 22.293
14:00:00 0.000 0.000 0.000 0.000 21.980 21.980
14:30:00 0.000 0.000 0.000 0.000 21.672 21.672
15:00:00 0.000 0.000 0.000 0.000 21.367 21.367
15:30:00 0.000 0.000 0.000 0.000 21.067 21.067
16:00:00 0.000 0.000 0.000 0.000 20.772 20.772
16:30:00 0.000 0.000 0.000 0.000 20.480 20.480
17:00:00 0.000 0.000 0.000 0.000 20.193 20.193
Time series data
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 3 of 6
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
17:30:00 0.000 0.000 0.000 0.000 19.909 19.909
18:00:00 0.000 0.000 0.000 0.000 19.630 19.630
18:30:00 0.000 0.000 0.000 0.000 19.354 19.354
19:00:00 0.000 0.000 0.000 0.000 19.082 19.082
19:30:00 0.000 0.000 0.000 0.000 18.815 18.815
20:00:00 0.000 0.000 0.000 0.000 18.550 18.550
20:30:00 0.000 0.000 0.000 0.000 18.290 18.290
21:00:00 0.000 0.000 0.000 0.000 18.033 18.033
21:30:00 0.000 0.000 0.000 0.000 17.780 17.780
22:00:00 0.000 0.000 0.000 0.000 17.531 17.531
22:30:00 0.000 0.000 0.000 0.000 17.285 17.285
23:00:00 0.000 0.000 0.000 0.000 17.042 17.042
23:30:00 0.000 0.000 0.000 0.000 16.803 16.803
24:00:00 0.000 0.000 0.000 0.000 16.567 16.567
24:30:00 0.000 0.000 0.000 0.000 16.334 16.334
25:00:00 0.000 0.000 0.000 0.000 16.105 16.105
25:30:00 0.000 0.000 0.000 0.000 15.879 15.879
26:00:00 0.000 0.000 0.000 0.000 15.656 15.656
26:30:00 0.000 0.000 0.000 0.000 15.436 15.436
27:00:00 0.000 0.000 0.000 0.000 15.220 15.220
27:30:00 0.000 0.000 0.000 0.000 15.006 15.006
28:00:00 0.000 0.000 0.000 0.000 14.795 14.795
28:30:00 0.000 0.000 0.000 0.000 14.588 14.588
29:00:00 0.000 0.000 0.000 0.000 14.383 14.383
29:30:00 0.000 0.000 0.000 0.000 14.181 14.181
30:00:00 0.000 0.000 0.000 0.000 13.982 13.982
30:30:00 0.000 0.000 0.000 0.000 13.786 13.786
31:00:00 0.000 0.000 0.000 0.000 13.592 13.592
31:30:00 0.000 0.000 0.000 0.000 13.401 13.401
32:00:00 0.000 0.000 0.000 0.000 13.213 13.213
32:30:00 0.000 0.000 0.000 0.000 13.028 13.028
33:00:00 0.000 0.000 0.000 0.000 12.845 12.845
33:30:00 0.000 0.000 0.000 0.000 12.665 12.665
34:00:00 0.000 0.000 0.000 0.000 12.487 12.487
34:30:00 0.000 0.000 0.000 0.000 12.312 12.312
35:00:00 0.000 0.000 0.000 0.000 12.139 12.139
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 4 of 6
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
35:30:00 0.000 0.000 0.000 0.000 11.968 11.968
36:00:00 0.000 0.000 0.000 0.000 11.800 11.800
36:30:00 0.000 0.000 0.000 0.000 11.635 11.635
37:00:00 0.000 0.000 0.000 0.000 11.471 11.471
37:30:00 0.000 0.000 0.000 0.000 11.310 11.310
38:00:00 0.000 0.000 0.000 0.000 11.152 11.152
38:30:00 0.000 0.000 0.000 0.000 10.995 10.995
39:00:00 0.000 0.000 0.000 0.000 10.841 10.841
39:30:00 0.000 0.000 0.000 0.000 10.688 10.688
40:00:00 0.000 0.000 0.000 0.000 10.538 10.538
40:30:00 0.000 0.000 0.000 0.000 10.391 10.391
41:00:00 0.000 0.000 0.000 0.000 10.245 10.245
41:30:00 0.000 0.000 0.000 0.000 10.101 10.101
42:00:00 0.000 0.000 0.000 0.000 9.959 9.959
42:30:00 0.000 0.000 0.000 0.000 9.819 9.819
43:00:00 0.000 0.000 0.000 0.000 9.681 9.681
43:30:00 0.000 0.000 0.000 0.000 9.546 9.546
44:00:00 0.000 0.000 0.000 0.000 9.412 9.412
44:30:00 0.000 0.000 0.000 0.000 9.279 9.279
45:00:00 0.000 0.000 0.000 0.000 9.149 9.149
45:30:00 0.000 0.000 0.000 0.000 9.021 9.021
46:00:00 0.000 0.000 0.000 0.000 8.894 8.894
46:30:00 0.000 0.000 0.000 0.000 8.769 8.769
47:00:00 0.000 0.000 0.000 0.000 8.646 8.646
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 5 of 6
AppendixCatchment descriptors
Name Value User-defined value used?
Area (km²) 196.28 No
ALTBAR 511 No
ASPBAR 79 No
ASPVAR 0.1 No
BFIHOST 0.47 No
DPLBAR (km) 18.36 No
DPSBAR (mkm-¹) 189.1 No
FARL 1 No
LDP 36.81 No
PROPWET (mm) 0.63 No
RMED1H 8.8 No
RMED1D 36.7 No
RMED2D 51.1 No
SAAR (mm) 1057 No
SAAR4170 (mm) 1162 No
SPRHOST 41.24 No
Urbext2000 0 No
Urbext1990 0 No
URBCONC 0 No
URBLOC 0 No
Urban Area (km²) 0 No
DDF parameter C -0.02 No
DDF parameter D1 0.45 No
DDF parameter D2 0.5 No
DDF parameter D3 0.32 No
DDF parameter E 0.25 No
DDF parameter F 2.27 No
DDF parameter C (1km grid value) -0.02 No
DDF parameter D1 (1km grid value) 0.46 No
DDF parameter D2 (1km grid value) 0.5 No
DDF parameter D3 (1km grid value) 0.31 No
DDF parameter E (1km grid value) 0.25 No
DDF parameter F (1km grid value) 2.17 No
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 6 of 6
Summary of estimate using the Flood Estimation Handbook revitalised flood hydrograph method (ReFH)
Site details
Site description:
Catchment Area (km²): 196.28
None
Site name: Don @ Newe Weir
Easting: 338450
Northing: 812200
Model run: 200 yearSummary of results
Rainfall - FEH 2013 (mm): 67.58
Total Rainfall (mm): 45.15
Peak Rainfall (mm): 12.28 211.70
6998.01
3266.68Total runoff (ML):
Total flow (ML):
Peak flow (m³/s):
Loss model parametersName Value User-defined?
Cini (mm) 124.56 No
Cmax (mm) 399.2 No
Use alpha correction factor No No
Alpha correction factor n/a No
Rainfall parameters (Rainfall - FEH 2013 model)Name Value User-defined?
Duration (hh:mm:ss) 04:30:00 No
Timestep (hh:mm:ss) 00:30:00 No
SCF (Seasonal correction factor) 0.77 No
ARF (Areal reduction factor) 0.87 No
Seasonality Winter n/a
Routing model parameters
ParametersWhere the user has overriden a system-generated value, this original value is shown in square brackets after the value used.* Indicates that the user locked the duration/timestep
UK Design Flood Estimation
Generated on Monday, February 20, 2017 12:20:25 PM by dwarrenPrinted from the ReFH Flood Modelling software package, version 2.2.6029.28099
Checksum: 3A08-A285
Country: Scotland
Using plot scale calculations: No
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 1 of 7
Name Value User-defined?Tp (hr) 2.39 No
Up 0.65 No
Uk 0.8 No
Name Value User-defined?
BF0 (m³/s) 8.51 No
BL (hr) 35.37 No
BR 1.14 No
Baseflow model parameters
Name Value User-defined?Urban area (km²) 0 No
Urbext 2000 0 No
Impervious runoff factor 0.7 No
Imperviousness factor 0.3 No
Tp scaling factor 0.5 No
Sewered area (km²) 0.00 Yes
Sewer capacity (m³/s) 0.00 Yes
Urbanisation parameters
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 2 of 7
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
00:00:00 1.290 0.000 0.405 0.000 8.506 8.506
00:30:00 2.421 0.000 0.771 0.630 8.392 9.022
01:00:00 4.502 0.000 1.472 3.089 8.304 11.393
01:30:00 8.223 0.000 2.820 9.038 8.284 17.322
02:00:00 12.280 0.000 4.526 21.665 8.414 30.079
02:30:00 8.223 0.000 3.242 45.674 8.835 54.509
03:00:00 4.502 0.000 1.847 80.323 9.720 90.043
03:30:00 2.421 0.000 1.014 119.538 11.183 130.721
04:00:00 1.290 0.000 0.547 156.801 13.238 170.039
04:30:00 0.000 0.000 0.000 184.344 15.782 200.126
05:00:00 0.000 0.000 0.000 193.122 18.580 211.702
05:30:00 0.000 0.000 0.000 184.581 21.341 205.922
06:00:00 0.000 0.000 0.000 165.783 23.845 189.628
06:30:00 0.000 0.000 0.000 142.344 25.975 168.319
07:00:00 0.000 0.000 0.000 118.424 27.696 146.120
07:30:00 0.000 0.000 0.000 97.892 29.038 126.929
08:00:00 0.000 0.000 0.000 80.688 30.058 110.746
08:30:00 0.000 0.000 0.000 65.476 30.806 96.281
09:00:00 0.000 0.000 0.000 51.481 31.309 82.789
09:30:00 0.000 0.000 0.000 38.479 31.589 70.068
10:00:00 0.000 0.000 0.000 26.379 31.664 58.043
10:30:00 0.000 0.000 0.000 15.845 31.557 47.402
11:00:00 0.000 0.000 0.000 8.064 31.305 39.369
11:30:00 0.000 0.000 0.000 3.561 30.959 34.519
12:00:00 0.000 0.000 0.000 1.296 30.563 31.859
12:30:00 0.000 0.000 0.000 0.303 30.147 30.450
13:00:00 0.000 0.000 0.000 0.006 29.726 29.732
13:30:00 0.000 0.000 0.000 0.000 29.309 29.309
14:00:00 0.000 0.000 0.000 0.000 28.897 28.897
14:30:00 0.000 0.000 0.000 0.000 28.492 28.492
15:00:00 0.000 0.000 0.000 0.000 28.092 28.092
15:30:00 0.000 0.000 0.000 0.000 27.697 27.697
16:00:00 0.000 0.000 0.000 0.000 27.309 27.309
16:30:00 0.000 0.000 0.000 0.000 26.925 26.925
17:00:00 0.000 0.000 0.000 0.000 26.547 26.547
Time series data
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 3 of 7
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
17:30:00 0.000 0.000 0.000 0.000 26.175 26.175
18:00:00 0.000 0.000 0.000 0.000 25.807 25.807
18:30:00 0.000 0.000 0.000 0.000 25.445 25.445
19:00:00 0.000 0.000 0.000 0.000 25.088 25.088
19:30:00 0.000 0.000 0.000 0.000 24.736 24.736
20:00:00 0.000 0.000 0.000 0.000 24.388 24.388
20:30:00 0.000 0.000 0.000 0.000 24.046 24.046
21:00:00 0.000 0.000 0.000 0.000 23.709 23.709
21:30:00 0.000 0.000 0.000 0.000 23.376 23.376
22:00:00 0.000 0.000 0.000 0.000 23.048 23.048
22:30:00 0.000 0.000 0.000 0.000 22.724 22.724
23:00:00 0.000 0.000 0.000 0.000 22.405 22.405
23:30:00 0.000 0.000 0.000 0.000 22.091 22.091
24:00:00 0.000 0.000 0.000 0.000 21.781 21.781
24:30:00 0.000 0.000 0.000 0.000 21.475 21.475
25:00:00 0.000 0.000 0.000 0.000 21.173 21.173
25:30:00 0.000 0.000 0.000 0.000 20.876 20.876
26:00:00 0.000 0.000 0.000 0.000 20.583 20.583
26:30:00 0.000 0.000 0.000 0.000 20.294 20.294
27:00:00 0.000 0.000 0.000 0.000 20.009 20.009
27:30:00 0.000 0.000 0.000 0.000 19.728 19.728
28:00:00 0.000 0.000 0.000 0.000 19.452 19.452
28:30:00 0.000 0.000 0.000 0.000 19.178 19.178
29:00:00 0.000 0.000 0.000 0.000 18.909 18.909
29:30:00 0.000 0.000 0.000 0.000 18.644 18.644
30:00:00 0.000 0.000 0.000 0.000 18.382 18.382
30:30:00 0.000 0.000 0.000 0.000 18.124 18.124
31:00:00 0.000 0.000 0.000 0.000 17.870 17.870
31:30:00 0.000 0.000 0.000 0.000 17.619 17.619
32:00:00 0.000 0.000 0.000 0.000 17.372 17.372
32:30:00 0.000 0.000 0.000 0.000 17.128 17.128
33:00:00 0.000 0.000 0.000 0.000 16.887 16.887
33:30:00 0.000 0.000 0.000 0.000 16.650 16.650
34:00:00 0.000 0.000 0.000 0.000 16.416 16.416
34:30:00 0.000 0.000 0.000 0.000 16.186 16.186
35:00:00 0.000 0.000 0.000 0.000 15.959 15.959
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 4 of 7
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
35:30:00 0.000 0.000 0.000 0.000 15.735 15.735
36:00:00 0.000 0.000 0.000 0.000 15.514 15.514
36:30:00 0.000 0.000 0.000 0.000 15.296 15.296
37:00:00 0.000 0.000 0.000 0.000 15.081 15.081
37:30:00 0.000 0.000 0.000 0.000 14.870 14.870
38:00:00 0.000 0.000 0.000 0.000 14.661 14.661
38:30:00 0.000 0.000 0.000 0.000 14.455 14.455
39:00:00 0.000 0.000 0.000 0.000 14.252 14.252
39:30:00 0.000 0.000 0.000 0.000 14.052 14.052
40:00:00 0.000 0.000 0.000 0.000 13.855 13.855
40:30:00 0.000 0.000 0.000 0.000 13.661 13.661
41:00:00 0.000 0.000 0.000 0.000 13.469 13.469
41:30:00 0.000 0.000 0.000 0.000 13.280 13.280
42:00:00 0.000 0.000 0.000 0.000 13.093 13.093
42:30:00 0.000 0.000 0.000 0.000 12.909 12.909
43:00:00 0.000 0.000 0.000 0.000 12.728 12.728
43:30:00 0.000 0.000 0.000 0.000 12.550 12.550
44:00:00 0.000 0.000 0.000 0.000 12.373 12.373
44:30:00 0.000 0.000 0.000 0.000 12.200 12.200
45:00:00 0.000 0.000 0.000 0.000 12.029 12.029
45:30:00 0.000 0.000 0.000 0.000 11.860 11.860
46:00:00 0.000 0.000 0.000 0.000 11.693 11.693
46:30:00 0.000 0.000 0.000 0.000 11.529 11.529
47:00:00 0.000 0.000 0.000 0.000 11.367 11.367
47:30:00 0.000 0.000 0.000 0.000 11.208 11.208
48:00:00 0.000 0.000 0.000 0.000 11.050 11.050
48:30:00 0.000 0.000 0.000 0.000 10.895 10.895
49:00:00 0.000 0.000 0.000 0.000 10.742 10.742
49:30:00 0.000 0.000 0.000 0.000 10.591 10.591
50:00:00 0.000 0.000 0.000 0.000 10.443 10.443
50:30:00 0.000 0.000 0.000 0.000 10.296 10.296
51:00:00 0.000 0.000 0.000 0.000 10.152 10.152
51:30:00 0.000 0.000 0.000 0.000 10.009 10.009
52:00:00 0.000 0.000 0.000 0.000 9.869 9.869
52:30:00 0.000 0.000 0.000 0.000 9.730 9.730
53:00:00 0.000 0.000 0.000 0.000 9.594 9.594
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 5 of 7
Time (hh:mm:ss)
Rain (mm)
Sewer Loss (mm)
Net Rain (mm)
Runoff (m³/s)
Baseflow (m³/s)
Total Flow (m³/s)
53:30:00 0.000 0.000 0.000 0.000 9.459 9.459
54:00:00 0.000 0.000 0.000 0.000 9.326 9.326
54:30:00 0.000 0.000 0.000 0.000 9.195 9.195
55:00:00 0.000 0.000 0.000 0.000 9.066 9.066
55:30:00 0.000 0.000 0.000 0.000 8.939 8.939
56:00:00 0.000 0.000 0.000 0.000 8.813 8.813
56:30:00 0.000 0.000 0.000 0.000 8.690 8.690
57:00:00 0.000 0.000 0.000 0.000 8.568 8.568
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 6 of 7
AppendixCatchment descriptors
Name Value User-defined value used?
Area (km²) 196.28 No
ALTBAR 511 No
ASPBAR 79 No
ASPVAR 0.1 No
BFIHOST 0.47 No
DPLBAR (km) 18.36 No
DPSBAR (mkm-¹) 189.1 No
FARL 1 No
LDP 36.81 No
PROPWET (mm) 0.63 No
RMED1H 8.8 No
RMED1D 36.7 No
RMED2D 51.1 No
SAAR (mm) 1057 No
SAAR4170 (mm) 1162 No
SPRHOST 41.24 No
Urbext2000 0 No
Urbext1990 0 No
URBCONC 0 No
URBLOC 0 No
Urban Area (km²) 0 No
DDF parameter C -0.02 No
DDF parameter D1 0.45 No
DDF parameter D2 0.5 No
DDF parameter D3 0.32 No
DDF parameter E 0.25 No
DDF parameter F 2.27 No
DDF parameter C (1km grid value) -0.02 No
DDF parameter D1 (1km grid value) 0.46 No
DDF parameter D2 (1km grid value) 0.5 No
DDF parameter D3 (1km grid value) 0.31 No
DDF parameter E (1km grid value) 0.25 No
DDF parameter F (1km grid value) 2.17 No
Printed from the ReFH Flood Modelling software package, version 2.2.6029.28099
Page 7 of 7
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
C SITE PHOTOGRAPHS
Number Photo Description
.
Looking
upstream from
the upstream
extent of the
study reach.
�
Looking
downstream in
the upstream
part of the
study reach,
showing point
bar feature.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
Number Photo Description
River meander,
looking
upstream.
"
Looking
downstream on
river channel,
approaching the
weir location.
�
Hydro intake on
LHB
immediately
upstream of the
weir. (looking
upstream)
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
Number Photo Description
�
Newe Weir with
existing fish
ladder and
downstream
section of
channel.
�
Looking
downstream
from the weir.
Dense forestry
are on the LHB
and the houses
of Waterside
are visible in the
distance on the
RHB.
!
Significant bank
protection at
meander
adjacent to the
houses on
Waterside Road.
Looking
downstream,
protection on
RHB.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
Number Photo Description
6
Looking
downstream
towards Bridge
of Newe. Large
elevated point
bar on LHB.
.#
Looking
upstream from
Bridge of Newe
at hydro
outflow
confluence.
River Don
channel to the
left of image,
outflow channel
from the hydro
plant to the
right.
..
Burn of Deochry
flowing into
River Dee (far
right on image)
immediately
downstream of
outfall channel
from Hydro
plant. Finer
sediment can be
seen in the bed
from this
channel as
opposed to the
coarser bed
material in the
River Dee on
the left.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
Number Photo Description
.�
Bed of River
Don
immediately
downstream of
Bridge of Newe,
showing fine
sandy sediment,
and also dead
fish.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
D HYDRAULIC MODELLING RESULTS
Don_0000
Don_0249
Don_0249!
Don_0249!!
Don_0562
Don_0562!
Don_0562!!
Don_0938
Don_0938!Don_0938!!
Don_1097
Don_1207
Don_1256
Don_1380
Don_1650
Don_1716Don_1856
Don_1946
Don_2195Don_2195!
Don_2354
Don_2653
Don_2653!
Network - River DonNewe Weir
Powered by
Map Centre Coords x: 337224, y: 812126Date Printed: 05/05/2017Scale 1:3000
100m
Scenario A Results
Node Max Flow (m3/s) Max Stage (m AD) Max Velocity (m/s)
Don_0000 207.709 259.589 3.023
Don_0249 207.683 261.27 3.543
Don_0249! 207.713 260.025 3.824
Don_0249!! 207.677 260.69 3.85
Don_0562 209.991 262.972 3.409
Don_0562! 207.664 261.811 3.693
Don_0562!! 210.021 262.57 3.51
Don_0938 31.578 263.649 1.897
Don_0938! 33.587 264.098 1.552
Don_0938!! 31.689 263.973 2.478
Don_1097 146.199 265.136 2.552
Don_1097! 146.203 263.495 6.502
Don_1207 217.234 264.745 7.313
Don_1207! 217.234 264.967 5.641
Don_1224 217.237 265.349 7.559
Don_1256 217.236 266.022 4.87
Don_1380 219.016 266.772 3.58
Don_1511 217.272 267.218 3.112
Don_1650 139.83 268.248 2.417
Don_1716 141.689 268.454 2.162
Don_1745 141.976 268.509 2.047
Don_1778 218.642 269.755 2.42
Don_1778! 218.642 267.712 3.837
Don_1856 218.629 269.93 2.252
Don_1946 32.246 270.657 1.328
Don_2195 32.728 270.608 1.684
Don_2195! 32.269 270.644 1.61
Don_2354 61.611 270.662 2.551
Don_2653 71.871 272.378 2.194
Don_2653! 61.516 271.029 2.254
Don_2899 45.722 273.849 1.841
Don_2994 152.823 273.492 6.992
Don_3129 220.67 276.055 3.556
Don_3129! 152.823 273.492 7.236
Scenario B Results
Node Max Flow (m3/s) Max Stage (m AD) Max Velocity (m/s)
Don_0000 211.712 259.611 3.03
Don_0249 211.721 261.297 3.569
Don_0249! 211.713 260.049 3.855
Don_0249!! 211.698 260.716 3.88
Don_0562 212.456 263.004 3.418
Don_0562! 211.742 261.838 3.726
Don_0562!! 212.424 262.604 3.493
Don_0938 31.503 263.692 1.908
Don_0938! 33.311 264.136 1.558
Don_0938!! 31.453 264.006 2.471
Don_1097 147.624 265.127 2.586
Don_1097! 147.815 263.52 6.201
Don_1207 219.446 264.702 7.165
Don_1207! 219.446 264.934 5.549
Don_1224 219.485 265.271 7.474
Don_1256 219.361 266.011 4.63
Don_1380 219.79 266.757 3.456
Don_1511 219.482 267.21 3.028
Don_1650 137.575 268.28 2.401
Don_1716 137.812 268.465 2.194
Don_1745 138.327 268.509 2.482
Don_1778 219.845 268.487 4.223
Don_1778! 219.845 267.843 4.699
Don_1856 219.809 269.093 3.671
Don_1946 30.81 270.58 1.34
Don_2195 31.004 270.538 1.654
Don_2195! 30.485 270.568 1.578
Don_2354 63.254 270.592 2.57
Don_2653 72.606 272.381 2.241
Don_2653! 61.174 271.026 2.346
Don_2899 50.374 273.847 1.834
Don_2994 152.294 273.497 6.981
Don_3129 220.67 276.052 3.551
Don_3129! 152.294 273.497 7.226
Scenario C Results
Node Max Flow (m3/s) Max Stage (m AD) Max Velocity (m/s)
Don_0000 212.566 259.616 3.031
Don_0249 212.547 261.303 3.574
Don_0249! 212.565 260.054 3.861
Don_0249!! 212.556 260.721 3.886
Don_0562 213.423 263.011 3.424
Don_0562! 212.537 261.844 3.732
Don_0562!! 213.394 262.61 3.488
Don_0938 33.539 263.7 2.026
Don_0938! 33.336 264.144 1.552
Don_0938!! 34.573 264.015 2.598
Don_1097 148.179 265.112 2.591
Don_1097! 148.179 263.521 6.163
Don_1207 220.313 264.706 7.158
Don_1207! 220.313 264.93 5.545
Don_1224 220.302 265.273 7.434
Don_1256 220.278 266.009 4.632
Don_1380 220.298 266.761 3.444
Don_1511 220.334 267.212 3.031
Don_1650 138.677 268.286 2.52
Don_1716 138.714 268.472 2.219
Don_1745 138.96 268.508 2.789
Don_1778 220.748 267.933 3.864
Don_1778! 220.802 267.844 4.246
Don_1856 220.562 268.706 4.53
Don_1946 31.696 270.508 1.114
Don_2195 27.697 270.267 2.025
Don_2195! 28.801 270.464 2.099
Don_2354 61.81 270.494 2.931
Don_2653 73.053 272.38 2.252
Don_2653! 62.347 271.034 2.322
Don_2899 49.343 273.848 1.939
Don_2994 153.614 273.502 7.005
Don_3129 220.67 276.061 3.567
Don_3129! 153.614 273.502 7.25
Scenario A Scenario B Scenario C
Node Max Stage (m AD) Max Stage (m AD) Max Stage (m AD)
Don_0000 259.589 259.611 0.022 259.616 0.027
Don_0249! 260.025 260.049 0.024 260.054 0.029
Don_0249!! 260.69 260.716 0.026 260.721 0.031
Don_0249 261.27 261.297 0.027 261.303 0.033
Don_0562! 261.811 261.838 0.027 261.844 0.033
Don_0562!! 262.57 262.604 0.034 262.61 0.04
Don_0562 262.972 263.004 0.032 263.011 0.039
Don_0938! 264.098 264.136 0.038 264.144 0.046
Don_0938!! 263.973 264.006 0.033 264.015 0.042
Don_0938 263.649 263.692 0.043 263.7 0.051
Don_1097! 263.495 263.52 0.025 263.521 0.026
Don_1097 265.136 265.127 -0.009 265.112 -0.024
Don_1207! 264.967 264.934 -0.033 264.93 -0.037
Don_1207 264.745 264.702 -0.043 264.706 -0.039
Don_1224 265.349 265.271 -0.078 265.273 -0.076
Don_1256 266.022 266.011 -0.011 266.009 -0.013
Don_1380 266.772 266.757 -0.015 266.761 -0.011
Don_1511 267.218 267.21 -0.008 267.212 -0.006
Don_1650 268.248 268.28 0.032 268.286 0.038
Don_1716 268.454 268.465 0.011 268.472 0.018
Don_1745 268.509 268.509 0 268.508 -0.001
Don_1778! 267.712 267.843 0.131 267.844 0.132
Don_1778 (W) 269.755 268.487 -1.268 267.933 -1.822
Don_1856 269.93 269.093 -0.837 268.706 -1.224
Don_1946 270.657 270.58 -0.077 270.508 -0.149
Don_2195! 270.644 270.568 -0.076 270.464 -0.18
Don_2195 270.608 270.538 -0.07 270.267 -0.341
Don_2354 270.662 270.592 -0.07 270.494 -0.168
Don_2653! 271.029 271.026 -0.003 271.034 0.005
Don_2653 272.378 272.381 0.003 272.38 0.002
Don_2899 273.849 273.847 -0.002 273.848 -0.001
Don_2994 273.492 273.497 0.005 273.502 0.01
Don_3129! 273.492 273.497 0.005 273.502 0.01
Don_3129 276.055 276.052 -0.003 276.061 0.006
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
E SEDIMENT REGIME CALCULATIONS
River Don catchment area to the Newe Weir = .6� km�
Applying calculations based upon equations from NRA .66. – Provided in the Guidebook of Applied
Geomorphology which state that for catchments greater than .##km� the following equation can be applied:
�.�CA...�
= �.�*.6�...�
= .,."# t/yr = E77m7/yr
Regional variations of fluvial sediment yield in eastern Scotland (McManus & Duck) notes that there is a
general trend of "-�## tonnes/km�/year. This would result in a total sediment yield of approximately " �-
�.,��� m /yr. However, based upon Table . from the above publication, the River Don has an approximate
sediment yield of .!." t/km�/yr. For the catchment to the Newe Weir this would result in approximately ,�#�
t/year, or �,## m /yr. This figure is the total load and includes both suspended and bed load. The bed load is
then estimated to be approximately .#% of total load. => ���m7/yr
EnviroCentre have undertaken analysis into the infilling of a former in-stream sand and gravel quarry on the
River Clyde. The former quarry extent has been compared to the present development of the alluvial fan at the
inflow to the former quarry pool. This volume of sediment has been calculated and an annual sediment load
estimated from the period since quarrying ceased. The findings indicate an annualised bedload sediment
accumulation of �,!�. m /yr from a contributing catchment area of "��km
�. Scaling this to the catchment of
the Don @ Newe Weir (.6�km�) this would result in a yield of �,8D�m
7/yr.
The above methods of prediction would indicate an annualised bedload transport in the range of ��� – �,B��
m7/yr.
River Don District Salmon Fishery Board May �#.�
Newe Weir, River Don; Weir Removal Technical Assessment
F TOPOGRAPHICAL SURVEY
2
6
6
.
7
7
2
6
6
.
8
6
2
6
6
.
9
3
2
6
6
.
6
7
2
6
6
.
2
4
2
6
5
.
8
7
2
6
5
.
0
02
6
4
.
7
6
2
6
4
.
6
4
264.96
2
6
4
.
5
3
2
6
4
.
4
4
2
6
4
.
5
9
2
6
4
.
8
3
2
6
5
.
0
0
2
6
5
.
2
1
2
6
6
.
0
2
2
6
6
.
5
0
2
6
6
.
4
2
2
6
6
.
6
5
2
6
7
.
0
1
2
6
6
.
7
2
2
6
6
.
6
5
2
6
6
.
7
9
2
6
6
.
9
1
2
6
6
.
0
8
2
6
5
.
9
5
2
6
6
.
9
1
2
6
7
.
4
1
2
6
7
.
5
3
2
6
7
.
4
2
2
6
6
.
4
5
2
6
6
.
6
2
2
6
7
.
0
7
2
6
7
.
2
4
2
6
7
.
0
6
2
6
6
.
6
1
2
6
5
.5
9
265.70
2
6
5
.4
8
2
6
5
.3
0
2
6
5
.3
9
2
6
5
.4
6
2
6
5
.4
6
2
6
5
.2
8
2
6
5
.2
2
2
6
5
.0
7
2
6
5
.1
1
2
6
5
.2
2
2
6
5
.8
2
2
6
5
.9
1
267.1
4
266.95
267.90
267.69
266.94
266.97
267.02
267.01
267.63
267.58
267.34
268.09
267.97
267.65
267.19
2
6
6
.
1
9
2
6
6
.
1
9
266.1
0
265.39
265.18
264.5
9
264.4
9
267.27
267.46
267.56
267.65
268.00
267.95
267.9
3
2
6
8
.
4
2
268.43
267.54
267.58
267.99
268.18
268.75
2
6
8
.
8
7
2
6
6
.
4
3
2
6
7
.0
2
267.56
2
6
8
.
5
3
2
6
8
.
4
4
2
6
8
.
4
6
2
6
8
.
4
6
267.8
3
2
6
8
.4
0
2
6
8
.0
9
268.2
2
268.4
5
268.4
4
268.46
268.45
268.4
6
2
6
8
.9
1
2
6
8
.9
3
268.87
2
6
8
.8
8268.89
268.9
3
268.9
2
2
6
8
.
9
1
269.17
269.27
269.30
269.23
269.03
268.84
2
6
8
.7
1
2
6
8
.6
0
2
6
9
.0
1
2
6
8
.5
5
2
6
8
.7
3
2
6
8
.5
9
2
6
8
.7
5
2
6
8
.3
6
2
6
7
.7
1
2
6
7
.7
5
2
6
7
.5
4
2
6
7
.5
8
2
6
7
.4
4
2
6
7
.4
6
2
6
7
.4
6
2
6
7
.4
2
267.90
2
6
7
.4
0
267.4
6
267.4
7
268.7
0
268.8
3
268.6
0
268.7
4
268.7
1
2
6
8
.
2
5
2
6
8
.
2
4
2
6
8
.
4
4
2
6
8
.
1
0
2
6
7
.
7
7
2
6
7
.
6
3
2
6
7
.
5
3
2
6
7
.
3
9
267.67
2
6
7
.
2
3
2
6
7
.
1
0
2
6
6
.
9
1
2
6
6
.
7
2
267.22
267.10
266.98
266.81
266.84
266.95
267.10 267.31
267.34
267.34
267.46
267.43
267.44
267.43
267.39
267.35
267.33
267.22
2
6
6
.
4
6
267.27
2
6
6
.
9
8
267.47
267.65
267.7
4
267.7
3
2
6
7
.
9
5
266.0
4
2
6
5
.9
9
268.2
9
2
6
8
.
3
42
6
6
.
5
8
267.44
2
6
8
.
3
4
2
6
8
.
3
2
2
6
8
.
3
1
2
6
8
.
3
4
2
6
8
.
3
3
2
6
8
.
3
3
2
6
8
.
3
2
2
6
7
.9
6
2
6
7
.8
5
267.88
2
6
7
.
8
7
267.96
2
6
7
.9
2
2
6
7
.
4
7
2
6
7
.
4
4
267.71
267.56
2
6
7
.7
7
265.36
2
6
5
.3
8
2
6
5
.
5
4
2
6
6
.
6
8
2
6
6
.
7
6
2
6
5
.
9
2
2
6
5
.
9
2
265.97
266.05
267.7
3
267.4
2
266.8
2
266.8
6
266.5
0
266.2
7
265.4
7
265.2
2
265.0
3
264.6
5
265.84
265.15
265.28
265.25
265.43
265.27
265.38
265.25
264.99
265.18
265.00
264.98
264.91
266.19
266.65
266.49
266.89
266.56
266.65
267.01
267.05
2
6
9
.2
9
2
6
9
.3
5
269.4
0
2
6
9
.
4
0
268.68
268.25
268.36
268.25
268.55
268.98
269.05269.03
2
6
8
.
2
4
2
6
8
.
3
5
2
6
8
.
1
9
2
6
8
.
5
4
2
6
9
.
0
1
2
6
9
.
2
7
2
6
8
.
6
2
2
6
8
.
2
3
2
6
7
.
1
5
2
6
6
.
9
0
267.80
267.57
268.02
267.80
267.13
267.05
XS7
XS8
XS9
XS10a
XS10b
XS11
XS12
XS13
Unable to survey
centre of weir
and downstream pool
Do not scale this drawing
Status
Client
Project
Title
Drawing No. Revision
File path:
Scale Date
ApprovedCheckedDrawn
Rev Date InitialsAmendment
Craighall BusinessPark, Eagle Street,
Glasgow, G4 9XATel: 0141 341 5040Fax: 0141 341 5045
A1
Notes
k:\368420\drgs\cad\working
Don District Salmon Fishery Board
Newe Weir Removal
Topographical survey of weir location
DRAFT368420-SK-001 A
1:500 15/05/2017
DW KMD KMD