ObjectivesObjectivesParticipants will be able to:
Distinguish between DMNC and PMPCUnderstand the purpose of the DMNC dataIdentify the requirements for DMNC testsDescribe the DMNC data submittal processIdentify noncompliance associated with DMNC submittalIdentify NYISO reference documents
3For Training Use Only
DMNC and PMPCDMNC and PMPC
Dependable Maximum Net Capability (DMNC)
Market Administration and Control Area Service Tariff (MST) Defined Term 2.40
The sustained maximum net output of a Generator, as demonstrated by the performance of a test or through actual operation, averaged over a continuous time period as defined in the ISO Procedures.
4For Training Use Only
DMNC and PMPCDMNC and PMPC
Proven Maximum Production Capability (PMPC)
Not a defined term • referenced in ICAP Manual Attachment D and ICAP
User’s Guide
Maximum production capability of a generator
Used in energy market
DMNC is default PMPC if PMPC not submitted
5For Training Use Only
NYISO Use of DMNCNYISO Use of DMNC’’ss
DMNC RatingIs the ICAP (Installed Capacity) value of a ResourceUsed to determine UCAP (Unforced Capacity) value
• UCAP = DMNC X (1 – EFORD)
Used in Interconnection and Long Term Resource StudiesUsed by Market Monitoring Used by Transmission OwnersUsed for Outage Scheduling
6For Training Use Only
NYISO Use of DMNCNYISO Use of DMNC’’ss
PMPC Rating
Limits Generator energy offers
• Market Information System (MIS)
7For Training Use Only
CheckupCheckup
Select the letter that has a correct statement:
a. DMNC is the Digital Maximum Net Capacity for a generator
b. DMNC is the Dependable Maximum Net Capability for a load serving entity.
c. DMNC is used to determine the amount of generator capacity for the ICAP market
d. DMNC values are NOT used to determine the amount of generator capacity for the ICAP market
8For Training Use Only
CheckupCheckup
Select the letter that has a correct statement:
a. PMPC is used to determine capacity to offer in the ICAP Market
b. DMNC is used to determine capacity to offer in the ICAP Market
c. PMPC and DMNC are used to determine capacity to offer in the ICAP Market
d. None of the above is correct
9For Training Use Only
DMNC Data RequirementsDMNC Data Requirements
Perform DMNC Tests or submit data from actual operation or Resources
Applied to next like capability period
10For Training Use Only
DMNC Test RequirementsDMNC Test Requirements
Operating configuration
Same operating configuration and fuel mix that would be used during peak load conditions for summer and winter
11For Training Use Only
DMNC Test RequirementsDMNC Test Requirements
Data submittals
Submit data in accordance with Installed Capacity Manual Section 4.2
• Attachment D (E-mail preferred. Fax, mail, and courier makes extra work for all, but is allowed.)
• Electronically: ICAP Automated Market SystemICAP Automated Market User’s Guide Sect. 11
No more than 60 days after DMNC Test Period
12For Training Use Only
CheckupCheckup
Select the correct statement from the list below. May a generator use data from a February 20, 2007 DMNC test in
lieu of performing a DMNC test to sell UCAP in the 2008 Summer Capability Period?
a. No, previous test data may never be used in lieu of a testb. No, the February 20, 2007 test was a winter capability test that can
not be used for the summer period c. Yes, the test data is good for one year in either capability period.d. Yes, the test data is from a like period and is less than one year
old.
OctSepAugJulyJuneMayAprMarFebJanDecNov
Winter Capability Period Summer Capability Period
13For Training Use Only
CheckupCheckupSelect the letter that has the correct answer to the question.A generator is being converted from a coal to a biomass unit. Is the
DMNC test performed while on coal valid for the unit after the conversion to biomass?
a. Yes, the plant heat rate while on coal or biomass would be the same, therefore, the unit output will not change for the conversion.
b. Yes, the plant configuration and fuel mix will remain the same except during the peak for the season.
c. No, another test is required because of the change in fuel from the previous test.
d. No, another test is required because a drought has impacted the biomass futures market
14For Training Use Only
Submittal FrequencySubmittal FrequencySubmit DMNC data during each DMNC Test Period
• Summer 6/1 to 9/15• Winter 11/1 to 4/15
A generator may perform additional tests during the DMNC Test Period
Validated and Approved DMNC Rating is Valid for • Balance of current period (If requested and validated by NYISO)• Subsequent like Capability Period
15For Training Use Only
DMNC Time LineDMNC Time Line
OctSepAugJulyJuneMayAprMarFebJanDecNov
Winter Capability Period Summer Capability Period
Winter DMNC Test Period Summer DMNCTest Period
11/14Summer Test Submittal
Deadline(60 days after end of
test period)
6/14 Winter test submittal deadline
(60 days after end of test period)
16For Training Use Only
Out-of-Period DMNC’s
OctSepAugJulyJuneMayAprMarFebJanDecNov
Winter Capability Period Summer Capability Period
Winter DMNC Test Period Summer Test Period
Out-of-Period DMNC for Summer
Capability Period
Out-of-Period DMNC for
Winter Capability
Period
Out-of-Period DMNC data
•To begin next Capability Period
•Summer—DMNC data from after 3/1 and prior to 6/1 •Winter--- DMNC data from after 9/1 and prior to 11/1
•Must be verified by a DMNC test within the next DMNC Test Period or penalties will apply
17For Training Use Only
ExampleExample
11/2/07Winter618.59/17/074
5/1/06Summer632.007/22/053
5/1/08Summer621.56/2/20072
5/1/07Summer615.506/1/061
Effective DateSeasonDMNCResults
TestDate
Test
Identify the letter that lists the DMNC test that would be valid for the 2008 Summer Capability Period.A. Test #1 C. Test #3B. Test #2 D. Test #4
OctSepAugJulyJuneMayAprMarFebJanDecNovWinter Capability Period
Winter DMNC Test Period
Summer Capability Period
Summer Test Period
18For Training Use Only
TestsTestsNet of any station service load – for all facilities (ICAP Manual Section 4.2.3)
Resource Specific Requirements (ICAP Manual Section 4.2.2)
Fossil, Nuclear, Hydro
Sustained maximum net output for 4 consecutive hours (top-of-hour to top-of-hour)
• Integrated hourly average
19For Training Use Only
TestsTestsCombustion Turbine
Sustained maximum net output for 1 hour (top-of-hour to top-of-hour) integrated hourly average
Corrected for temperature• Average ambient temperature at time of
Transmission district’s peak load during previous 4 like capability periods
• Posted in NYISO Web Site• Temperature Data
• From approved weather station or recorded auditable device at the generator site
20For Training Use Only
Transmission District PeaksTransmission District Peaks
Transmission District’s seasonal peak during the previous four like-Capability Seasons
21For Training Use Only
TestsTestsCombined Cycle
Sustained maximum net output for 4 consecutive hours• Integrated hourly average at top of each hour
Corrected for temperature• Average ambient temperature at time of Transmission
district’s peak during previous 4 like capability periods• Posted in NYISO WEB Site
• Temperature Data• From approved weather station or recorded auditable
device at the generator site
22For Training Use Only
TestsTests
Intermittent Power (Wind Farms and Solar Arrays)
Nameplate capacity----aggregated in groups
23For Training Use Only
TestsTestsSpecial Case Resources
If distributed generator• Demonstration test of generator output for 1 hour
• Net of auxiliary and station service loads
If not, confirmation of UCAP value sent to Responsible Interface Party (RIP) with registration
• See ICAP Automated Market User’s Guide Section 11.1.2.1 for entering DMNC data
24For Training Use Only
CheckupCheckup
Which of the following facilities requires DMNC data of four sustained consecutive hours:
a. Fossil, Combustion Turbine, Hydrob. Fossil, Hydro, Nuclearc. Combustion Turbine, Hydro, Nucleard. Hydro, Fossil, Gas Turbine
25For Training Use Only
CheckupCheckup
Which of the following facilities requires temperature correction to DMNC data:
a. Combustion Turbine, Combined Cycleb. Fossil, Hydro, Nuclearc. Combustion Turbine, Combined Cycle, Hydrod. Hydro, Fossil
26For Training Use Only
Test Scheduling (TB 029)Test Scheduling (TB 029)
• If >100 MW• Required to notify NYISO Scheduling and
Transmission Owner (TO)• At least 5 days in advance
• Must bid hours for test in DAM• If cancelling—notify NYISO and TO by 1400
hours day before
• If > 25 MW and <99 MW• Required to notify NYISO Scheduling and TO
• At least 2 days in advance
• If < 25 MW• No advanced notification requirement
27For Training Use Only
Test SchedulingTest Scheduling
Generator may request Out of Merit to perform tests
Reference NYISO Tech Bulletins 45 and 29
Energy provided by Generator during testIf scheduled in DAM
• Covered by Bid Production Cost Guarantee
If NOT scheduled in DAM• Paid at Real Time LBMP
28For Training Use Only
Day of TestDay of Test
Day of test—all generators
• Ensure RT hours are scheduled
• Adjust RT bid to allow RT Dispatch (RTD) to schedule Generator to DMNC rating
• Request permission to start test from NYISO through Transmission Owner (TO)
• 3 hours before test starts
• Notify NYISO, through TO, test has • Started and completed
29For Training Use Only
Reporting DMNC DataReporting DMNC Data
Submit DMNC data into the ICAP Market System on the NYISO Web Site
Can enter, maintain or view data onlineICAP Manual Section 4.2 for requirementsICAP User Guide Section 11
Submit ICAP Manual Attachment D formsBy email (preferred), courier, mail or fax
30For Training Use Only
To enter data select “Maintain DMNC/PMPC Results”
Test MP Org
Select season based on the “Date of Test”,not the “Effective Date”
Submitting Test Data
Note: ICAP System was updated to Add a Mitigation Tab
31For Training Use Only
PTID Type:AllInternalExternalSCR
Test Type:AllDMNCPMPC
Generation Types:AllCombined CycleCombustionEnergy LimitedFossil FuelHydroIntermittentNuclear SteamOther
AllYesNo
Submitting Test Data
Use the filter above to access a list of relevant units.
32For Training Use Only
PTID Name:Drop down list of all PTIDs associated with Supplier
Effective Date – select first day of month the test is to be effective using calendar icon.•Can not be same day as test date•Cannot be for month spot market has already run•Must be >the system date
Test Type:DMNCPMPC Date of Test
Begin Hour
4 yr. Avg Amb temp for peak day & hr of like season for TO where Gen resides (Combustion & Combined cycle only)
Previous post test rating•Auto defaulted value
Test Temp at top of hr at start of test at gen site (Combustion & Combined Cycle only)
MW output to grid•Integrated hourly average starting at top of each required hour
Rating determined using manufacturer’s temp adjust (Combustion & Combined cycle only)•Temp adjust hourly readings then average them
Remarks
Actual DMNC rating•If> pre-test----red•If out of period----blue
Submitting Test Data
“Add DMNC/PMPC” allows input of DMNC data.
33For Training Use Only
Submitting Attachment DSubmitting Attachment D
Enter into ICAP System same data as entered/shown in Attachment D
Additionally enter:Test A, B, C---only Fossil and Nuclear Generators
A—Over pressureB—Top Feed Water Heater O/SC---Exceptions to Procedures Explained in Remarks section
Submit by email (preferred), fax, mail, courier or fax to NYISO Auxiliary Market Operations. See Attachment D Instructions page in the file.
36For Training Use Only
NYISO Verifies Data NYISO Verifies Data
NYISO Market Monitoring and Performance (MMP) reviews submitted DMNC data for completeness
• Determined within 10 days
NYISO MMP “validates” data30 day validation period
• If submitted >45 days prior to deadline• If< 45 days of deadline-----45 day review period
NYISO Auxiliary Market Operations “approves”submitted DMNC data in ICAP System
after MMP provides validation documentation
37For Training Use Only
CheckupCheckup
For an ICAP System submittal, the date entered in the effective date field is the:
a. The start date of the testb. The completion date of the testc. The current test period end date d. None of the above
38For Training Use Only
CheckupCheckup
For the Combined Cycle and Combustion Units, the 4 year average temperature for the peak day and hour of the like season for the TO where the generator resides would be entered into which field?
a. Avg Amb Temp (°F)b. Pre Test Rating (MW)c. Test temp (degF) d. None of the above
39For Training Use Only
ICAP System Calculations
The “Days to Expiration” field is color coded (green > 30 days; yellow between 30 and 1; red = DMNC Rating expired)
ICAP System sets the Expiration Date when the DMNC Rating is Approved.
Status•Approved by NYISO•Rejected by NYISO•Undecided—yet to be acted on
Expiration Date - Date the rating will expire, at 11:59:59 PM
Select View Monthly DMNC/PMPC Days to Expiration –Days remaining before the test will expire
40For Training Use Only
DeficienciesDeficiencies
Implications of not reporting on time Penalty may apply – Market Administration and Control Area Services Tariff (MST) Article 5.12.12 and ICAP Manual Section 6.1
If in-period DMNC data does not meet or exceed out-of-period DMNC rating used to start period
Penalty may apply – MST Article 5.12.8 and 5.14.2
Exemptions from performance and regulation penalties
Reference Special Settlement Rules Tech Bulletin 155
41For Training Use Only
Planned UpdatePlanned Update
Planned for Winter 09-10 Capability Period
Deliverability Limits
• Capacity Resource Interconnection Service (CRIS)
42For Training Use Only
Planned UpdatePlanned Update
CRIS Adjusted DMNC Calculations:
Summer
MIN (Summer CRIS CAP X Summer DMNC)
Winter
TRUNC (Winter CRIS % X Winter DMNC)
43For Training Use Only
ReferencesReferencesMST Tariff Article 5.12 - Requirements Applicable to Installed Capacity SuppliersNYISO Installed Capacity Manual
Section 4 Installed Capacity Requirements Applicable to Installed Capacity SuppliersAttachment D: DMNC Audit Forms, the Procedure to Adjust a PMPC and Weather Adjust DMNC data
ICAP User’s GuideSection 11 Maintain and View DMNC/PMPC dataSection 14.6 Data dictionary, Uploads/Downloads
NYISO ICAP Web site---ICAP market softwareTech Bulletin 029 Scheduling and Reporting Generator Dependable Maximum Net Capacity (DMNC) Tests
Describes DMNC test scheduling requirements
44For Training Use Only
ReferencesReferences
NYISO Market Participants Users GuideSections 6 and 7 describe Updating Generator Physical Parameters and bidding above DMNC
TB 155 Special Settlement Rules for Generators Conducting Certain Scheduled Steady state
Describes test that exempt Generators from performance penalties
TB 045 Out of Merit GenerationRequesting Out of Merit generation for DMNC testing
TB 126 NYISO Distribution of Resource Capacity and Reactive Power Capacity data to NYCA Transmission Owners
Describes NYISO providing DMNC data to Transmission Owners
45For Training Use Only
ReferencesReferences
Tech Bulletin 047 Updating Generator Physical Parameters in the Market Information System (MIS)
Describes process for updating Generator parameters
46For Training Use Only
SummarySummary
DMNCPMPCPurpose of dataRequirements for submittalsData submittal processNoncompliance
47For Training Use Only
The New York Independent System Operator (NYISO) is a notThe New York Independent System Operator (NYISO) is a not--forfor--profit profit corporation that began operations in 1999. The NYISO operates Necorporation that began operations in 1999. The NYISO operates New Yorkw York’’s bulk s bulk electricity grid, administers the stateelectricity grid, administers the state’’s wholesale electricity markets, and provides s wholesale electricity markets, and provides
comprehensive reliability planning for the statecomprehensive reliability planning for the state’’s bulk electricity system.s bulk electricity system.____________________________________________________________________________________________________________________
www.nyiso.comwww.nyiso.com