Murrieta Creek Flood Control, Environmental Restoration and Recreation Project. RIVERSIDE COUNTY FLOOD CONTROL & WATER CONSERVATION DISTRICT. DUSTY WILLIAMS General Manager-Chief Engineer. Murrieta Creek Flood Control, Environmental Restoration and Recreation Project. Project Overview - PowerPoint PPT Presentation

TRANSCRIPT

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

  • RIVERSIDE COUNTY FLOOD CONTROL & WATER CONSERVATION DISTRICT

    DUSTY WILLIAMSGeneral Manager-Chief Engineer

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation ProjectProject Overview

    Flooding History

    Project Description

    Project Cost

  • Project OverviewPublic Safety- 100-year flood protection for over 600 homes and commercial structures

    Environmental Restoration- Includes a 163 acre restoration site within the detention basin. Establishment of a 7-mile permanent habitat corridor

    Recreation- Regional Sports Park & trail system

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation ProjectProject Overview

    Location

  • Murrieta Creek Phase 1 at First St.

  • Murrieta Creek Phase 1 at First St.

  • Murrieta Creek Phase 2

  • Murrieta Creek Phase 2

  • Phase 3: Detention Basin Site

  • Phase 3: Detention Basin Site

  • Murrieta Creek: Elm to Tenaja- Phase 4

  • Murrieta Creek near Ivy St. (Phase 4)

  • Overall map

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation ProjectProject OverviewFlooding HistoryMajor Events in 1938 and 1969Presidential Disaster Declarations in 1980, 1993, 1995 and 19981993: $12 million damages in Temecula & Murrieta $88 million in damages to Camp Pendleton

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation ProjectProject DescriptionProject Overview

    Flooding History

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    Flood ControlEnvironmental RestorationRecreationElements

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    ElementsFlood Control

  • Flood Control Element

    Public Safety- 100-year flood protection for over 600 homes and commercial structuresPublic Health - Protection of regional waste water treatment plant.National Security - Reduction to potential flood damages to Camp Pendleton.

  • Channel cross sections

  • Existing Condition and Proposed Design at B Street

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    Environmental Restoration

    ElementsFlood Control

  • Environmental Restoration Element Environmental Restoration- Includes a 163 acre restoration site within the detention basin. Establishment of a 7-mile permanent habitat corridor.

  • Phase 3: Detention Basin Site

  • Detention Basin SiteRestoration Area Highlighted.RestorationAreaElm StreetCherry StreetJefferson AvenueSantaGertrudisCreekWarm Springs Creek

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    RecreationSports ParkElementsFlood ControlEnvironmental Restoration

  • Vertical Picture of Basin Site w/ Recreation Area Highlighted.Public ParkCherry StreetJefferson AvenueSantaGertrudisCreekWarm Springs Creek

  • Basin Site w/ Restoration and Recreation Areas Depicted.Public ParkRestoration AreaSedimentation BasinMeanderingStreamsPondEquestrian TrailBicycleTrailPedestrian -BicycleBridgesParkingLot

  • Recreation Element - Sports Park50-Acre Regional Sports Park within 240-acre detention basin site at Jefferson & Cherry.Four official soccer fieldsA minimum of four baseball / softball fields.A large tot lot.Group picnic facilities.Restroom / snack bar facility.Parking for approximately 360 vehicles.Ample trees and landscaping.

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    Flood ControlEnvironmental RestorationRecreationSports ParkElementsTrailsBicycleEquestrian/Hiking

  • Recreation Element - Trails7+ mile long trail system for equestrians, bicycling and hiking will be built along the entire length of the project.

    Pocket parks / staging areas for trail users

    Dip crossings for trails at all bridges for user safety.

    Parks and trails will be operated with the cooperation of local citizen sponsors.

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    Project CostProject Overview

    Flooding History

    Project Description

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation Project

    Total Cost - $90 million

    Cost Sharing Authorized by Congress 65% Federal Share ($60 million)35% Local Share ($30 million)

    Project Cost

  • Local CostsReal EstateDisposal of materialGuava Street BridgeIvy Street BridgeUtilitiesRecreation Main Street Bridge5% Cash TOTAL$12,298,000 $9,102,428$5,431,034 $3,606,364 $2,916,958 $2,250,000$2,566,648 $3,001,971$41,173,403

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation ProjectProject OverviewBuilt from Shell Station to TenajaFour PhasesFlooding History1980 and 1993Project DescriptionFlood ControlEnvironmental RestorationRecreationProject CostTotal Cost = $90 millionLocal Share = $41 millionSUMMARY

  • Murrieta Creek Flood Control, Environmental Restoration and Recreation ProjectWHEN? Phase 1 Construction Start - September 2003 Phase 2 - Fall 2004 Phase 3 - 2005 Phase 4 - 2006