mrp and jit

27
MRP and JIT

Upload: reina

Post on 18-Jan-2016

53 views

Category:

Documents


0 download

DESCRIPTION

MRP and JIT. Introduction. Many products are not single entities, they are composed of subassemblies and parts, some purchased and some manufactured. A production plan specifies quantities of each final product (end item), subassemblies, and parts needed at distinct points in time. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: MRP and JIT

MRP and JIT

Page 2: MRP and JIT

Introduction

Many products are not single entities, they are composed of subassemblies and parts, some purchased and some manufactured.

A production plan specifies quantities of each final product (end item), subassemblies, and parts needed at distinct points in time.

To generate a production plan two things are required: estimates for the end-product demand, and a master production schedule (MPS)

Forecast independent demand – plan dependent demand The need for one item is created by the need for another item

The MPS is a delivery plan for the manufacturing organization: includes exact amounts and delivery timings for each end product is derived from the demand estimates, but is not necessarily equal to

them MPS must account for manufacturing constraints (such as capacity) and

on-hand finished-goods inventory

Page 3: MRP and JIT

Introduction

Breaking the MPS into a production schedule for each component of an end-item is achieved by the material requirements planning (MRP) system

The MRP system determines material requirements and timings for

each phase of production. Material shortage is another major manufacturing constraint

The MRP system was introduced by Joseph Orlicky (IBM, 1960’s); by 1989, sales of MRP software and implementation support exceeded $1 billion

MRP II – manufacturing resources planning Includes demand management, forecasting, capacity planning, MPS, rough-

cut capacity planning, capacity requirements planning, dispatching, input/output control

ERP – enterprise resources planning Targets all operations of a company: manufacturing, distribution,

accounting, financial, and personal

Page 4: MRP and JIT

Production planning process End-ItemDemandEstimate

Master ProductionSchedule (MPS)

Material RequirementsPlanning (MRP)

Rough-CutCapacity

Detailed CapacityPlanning

MaterialPlan

PurchasingPlan

ShopOrders

Shop Floor Control

UpdatesClosed-Loop MRP

Page 5: MRP and JIT

MRP Procedure

Purchase orders – outside orders Jobs – orders from within the plant Buckets – time is divided into discrete chunks End items – finished products Lower-level items – constituent parts of the end items Bill of material (BOM) – relationship between end and the lower-level items

The basic MRP procedure is simple: for each level in the bill of material, beginning with end items, MRP does the following:

1. Netting: Determine net requirements by subtracting on-hand inventory and any scheduled receipts from the gross requirements. The gross requirements for level-zero items come from the MPS, while those for lower-level items are the result of previous MRP operations

2. Lot sizing: Divide the netted demand into appropriate lot sizes to form jobs

3. Time phasing: Offset the due dates of the jobs with lead times to determine start times

4. BOM explosion: Use the start times, the lot sizes, and the BOM to generate gross requirements of any required components at the next level(s)

5. Iterate: Repeat these steps until all levels are processed.

Page 6: MRP and JIT

MRP Procedure: Lot SizingDetermining the lot size (order quantity or production quantity) of an item

Static lot sizing rule: A decision rule that orders the same quantity each time an order is

placed Tend to generate higher average on-hand inventory because they

create inventory remnants Can provide extra safety stock

Dynamic lot sizing rule: A decision rule that changes the order quantity with each order,

typically so that each order is just large enough to prevent shortages over a specified time period

Tend to cause instability by tying lot-size to gross requirements Lower-level components may not be able to respond sufficiently fast

to changes in requirements

Page 7: MRP and JIT

MRP Procedure: Static Lot Sizing

1. Fixed order quantity (FOQ)

Order (or produce) a fixed quantity, or a multiple of that fixed quantity by combining the net requirements of P periods

2. Economic Order Quantity (EOQ)

Order (or produce) the economic order quantity, plus any additional items needed to replenish safety stock if it has fallen below its desired level

Yields minimum total setup/ordering costs and the holding costs

Assumes relatively constant demand

Page 8: MRP and JIT

MRP Procedure: Dynamic Lot-Sizing1. Lot-for-Lot (L4L)

Produce exactly the quantity required in each period to satisfy gross requirements, and used if setup cost < carrying cost for 1 period of demand

Simple to use, and agrees with Just-In-Time philosophy of ordering (or producing) only when required

Lot size can be modified easily for purchase discounts or restrictions, scrap allowances, process constraints, etc

Minimizes on-hand inventory, but maximizes number of orders placed (so can be expensive if setup/ordering costs are significant)

2. Periodic Order Quantity (POQ) Order (or produce) a quantity equal to the gross requirements for P periods minus any items in on-hand inventory plus any additional items needed to replenish safety stock if it has fallen below its desired level

Restores safety stock and covers exactly P periods of gross requirements.

When trying to guarantee any level of service for an assembly, the service for the component parts must be much greater

Page 9: MRP and JIT

MRP Example 1: The Product Structure Diagram

End item - parent

Lower level items - components

Red toy carD70524

(1)

Red bodyT19862

(1)

Axle/wheel assemblyS44381

(2)

AxleS11844

(1)

WheelR21174

(2)

Red truck

Car and truck gift pack Level 0

Level 1

Level 2

Level 3

Part Number Description

External Sales

D70524

S44381

S11844

R21174

T19862

Red truck

Red toy car

A/W assembly

Axle

Wheel

Red body

Page 10: MRP and JIT

Shortcomings of Material Requirement Plan Uncertainty: MRP ignores demand uncertainty, supply

uncertainty, and internal uncertainties that arise in the manufacturing process

Capacity Planning: Basic MRP does not take capacity constraints into account

Lead Times Dependent on Lot Sizes: In MRP lead times are assumed fixed, but they clearly depend on the size of the lot required

Quality Problems: Defective items can destroy the linking of the levels in an MRP system

Data Integrity: Real MRP systems are big (perhaps more than 20 levels deep) and the integrity of the data can be a serious problem

Order Pegging: A single component may be used in multiple end items, and each lot must then be pegged to the appropriate item

Page 11: MRP and JIT

Introduction to Just-In-Time Revolution The successful manufacturing organizations in North

America and throughout the world have common essential characteristics: company that produces high quality products at low cost, and responds quickly to customer’s requests for delivery, changes in design, and changes in volume

The process of improving manufacturing productivity with emphasis on high quality and low cost often uses terms such as: the Just-in-Time (JIT) approach, zero inventory, total quality management, world class manufacturing, and the search for excellence

What stands behind the words ”Just-in-Time”?

Page 12: MRP and JIT

Introduction to Just-In-Time Revolution Just-in-Time system – approach alternative to MRP

Page 13: MRP and JIT

The Philosophy of JIT

The goal of JIT is to (1) remove all waste from the manufacturing environment, and as result: Right quantity of products are produced in the highest quality at

exactly right time (not late or early) Have zero inventory, zero lead time, no queues

Waste = inventory + disruptions of the flow + poor quality + counting + scheduling + moving + sorting + etc.

JIT seeks to (2) eliminate all uncertainty, including machine breakdowns

Kaizen = pursue continuous improvement

Page 14: MRP and JIT

The Philosophy of JIT

Continuous improvement. Attacking fundamental problems - anything that does not add value to the

product. Devising systems to identify problems. Striving for simplicity - simpler systems may be easier to understand, easier to

manage and less likely to go wrong. A product oriented layout - produces less time spent moving of materials and

parts. Quality control at source - each worker is responsible for the quality of their own

output. Poka-yoke - `foolproof' tools, methods, jigs etc. prevent mistakes Preventative maintenance, Total productive maintenance - ensuring machinery

and equipment functions perfectly when it is required, and continually improving it.

Page 15: MRP and JIT

The Philosophy of JIT Eliminating waste. There are seven types of waste:

waste from overproduction. waste of waiting time. transportation waste. processing waste. inventory waste. waste of motion. waste from product defects.

Good housekeeping - workplace cleanliness and organisation. Set-up time reduction - increases flexibility and allows smaller batches. Ideal batch

size is 1item. Multi-process handling - a multi-skilled workforce has greater productivity, flexibility and job satisfaction.

Levelled / mixed production - to smooth the flow of products through the factory. Kanbans - simple tools to `pull' products and components through the process. Jidoka (Autonomation) - providing machines with the autonomous capability to use

judgement, so workers can do more useful things than standing watching them work. Andon (trouble lights) - to signal problems to initiate corrective action

Page 16: MRP and JIT

JIT Systems

Four requirements for the success of a JIT system

1. Elimination of waste

Uncovering problems by eliminating cost-adding processes (rock-river picture)

Reduce (or eliminate) setup times, lot sizes, lead times

Low setup times small batch sizes reduction of capacity loss If large batch is run before the problem is found

many parts have to be repaired/discarded

Preventive maintenance

Multi-skilled work force provides flexibility in scheduling

Foolproof operations – ensure that simple errors are not made

Page 17: MRP and JIT

JIT Systems

Four requirements for the success of a JIT system

2. Employee involvement in decision making Improving process by implementing employees’

suggestions Develop employee motivation and mutual trust between

workers and management

3. Supplier participation The good relationships make joint improvement efforts

possible Reduce the number of suppliers and establish long-term

associations with them

Page 18: MRP and JIT

JIT SystemsFour requirements for the success of a JIT system

4. Total quality control Each employee is given more responsibility for the

production process.

Every employee can stop the whole production line if quality is not satisfactory

Highly reliable equipments are needed to escape high level of frustration

Repetitive manufacturing and a stable master production schedule are needed

Having some excess capacity allows variability to be met without constantly injecting more inventory into the system and permits time for the workers to experiment with ways to eliminate wastes

Page 19: MRP and JIT

Kaizen

Kaizen = pursue continuous improvement

Page 20: MRP and JIT

Why Push and Pull?

MRP is the classic push system. The MRP system computes production schedules for all levels based on forecasts of sales of end items. Once produced, subassemblies are pushed to next level whether needed or not.

Page 21: MRP and JIT

Why Push and Pull? JIT is the classic pull system. The basic mechanism is that production

at one level only happens when initiated by a request at the higher level. That is, units are pulled through the system by request. The ideal cell is self-contained with all necessary equipment and resources.

Page 22: MRP and JIT

Kanban Systems“Kanban” = cards or visible

record

A communication signal from a consumer (downstream process) to a producer (upstream process)

A manual information system to control production, material transportation, and inventory

Page 23: MRP and JIT

Kanban kanban is the means through which JIT is managed refers to a signal of some kind. kanbans are signals used to

replenish the inventory of items used repetitively within a facility kanban signal is an empty container designed to hold a standard

quantity of material or parts When the container is empty, the customer sends it back to the

supplier. The container has attached to it instructions for refilling the container such as the part number, description, quantity, customer, supplier, and purchase or work order number

Some other common forms of kanban signals are supplier replaceable cards for cardboard boxed designed to hold a standard quantity, standard container enclosed by a painting of the outline of the container on the floor, and color coded striped golf balls sent via pneumatic tubes from station to station

Page 24: MRP and JIT

Dual Card System

Each workcenter has 5 components:• Production cell• Input store (A)• Output store (B)• P-kanban post (C)• T-kanban post (D)

All parts stored in containersEach container has fixed capacity = authorization to produce or to moveEach container has T- or P-kanban attached

Page 25: MRP and JIT

Characteristics of Kanban System

A kanban system is not for everyone

Works best when flow is uniform and the product mix is highly stable (similar to bucket brigade)

Set-up operations are short at every workcenter

Variability disrupts a kanban system

Extra cards must be introduced to avoid backorders

Kanban does not work well in systems with many active stock numbers – difficult to control large number of kanbans

Page 26: MRP and JIT

Comparison of MRP and JIT Systems

These methods offer two completely different approaches to basic production planning in a manufacturing environment. Each has advantages over the other, but neither seems to be sufficient on its own. Both have advantages and disadvantages, suggesting that both methods could be useful in the same organization.

Main Advantage of MRP over JIT: MRP takes forecasts for end product demand into account. In an environment in which substantial variation of sales are anticipated (and can be forecasted accurately), MRP has a substantial advantage.

Main Advantage of JIT over MRP: JIT reduces inventories to a

minimum. In addition to saving direct inventory carrying costs, there are substantial side benefits, such as improvement in quality and plant efficiency.

Page 27: MRP and JIT

JIT works best in “favorable” manufacturing environments: little demand variability, reliable vendors, and small set up times

MRP worked well in favorable environments (comparable to JIT) and better in unfavorable environments

Comparison of MRP and JIT Systems