mr. najam saeed, chairman. mr. javaid akhtar, member.. no.15.pdf · present: before lahore...
TRANSCRIPT
PRESENT:
BEFORE LAHORE DEVELOPMENT AUTHORITY COMMISSION,
LAHORE
Mr. Najam Saeed, Chairman.
Mr. Javaid Akhtar, Member.
Reference No. 15/2015
Mst. Farzana Shuja-ur-Rahman Lak, Plot No. 237, Block AlIII,
Gulberg III, Lahore
Applicant
Vs.
Lahore Development Authority through Additional Director General
(Housing) IAuthorized Officer, 467/0-11,Main Boulevard, M.A. Johar
Town, Lahore.Respondent
Order
The applicant vide One Window NO.2218213dated 02-11-2015
submitted an application for filing a reference to the LOA Commission. The
Additional Director General (Housing) IAuthorized Officer, LOA, filed this
reference under sub-section (4) of section 32 of the LOA (Amendment) Act,
2013 read with sub-rule (1) of Rule 7 of the Lahore Development Authority
Commission Rules, 2014 in respect of the illegal construction made on Plot
No. 237, Block AlIII, Gulberg III, Lahore. Reference received on 11.12.2015
was entered in the Institution Register at Serial No.15 of 2015. Notice along
with a copy of the reference filed by the LOA was sent to the applicant forsubmission of their written reply. Mr. Zahid Zafar Khan appeared on behalfof the applicant. Miss Saleha Shahid, Dy. Director and Mr. Sikandar Haroon,
Assistant Director, Town Planning, LOAappeared on behalf of the LOA. The
. • 1 ~~~S~/\b7r~~\\{:, ,
parties heard and the site of the plot was visited by the Commission in the
presence of the representatives of the parties on 05.01.2016, 03.02.2016
and on 04.04.2016.
Facts of the case as contained in the reference are as under:-
• A commercial building plan comprising of one basement (parking),
Ground floor and 10 upper floors was submitted on 28.12.2005. The
plans up to plinth level were released on 20.03.2006.
• On completion of construction upto plinth level owner applied for the
release of upper floor plans on 07-07-2006. As per policy a letter for joint
inspection was forwarded to Town Nazim Gulberg on 18-07-2006 and
accordingly site was jointly inspected by Director Town Planning and Town
Nazim Gulberg and after receiving joint inspection report from Town Nazim
Gulberg on 29-08-2006, plans up to 38 ft height were released on
09.10.2006.
• After completing construction upto 38 feet height, owner again applied
for the release of plans of upper floors on 31-10-2006. And again joint
inspection letter was forwarded to Town Nazim Gulberg on 03-11-
2006. Site was again jointly inspected by Director Town Planning and
Town Nazim Gulberg and after receiving joint inspection report from
Town Nazim Gulberg on 05-12-2006, plans up to 150'-0" were
released on 21.12.2006.
• As per report of field staff owner started doing excess coverage
therefore notices U/S 40 of LOA act 1975were issued on 05-01-2007.
• Owner of the plot got stay order from the Civil Court of (Mr. Amjad AliBajwa) on 21-02-2007 in which LOA was restrained to demolish the
construction.• After that owner submitted revised building plans on 06-06-2007. The
plans were under process when High Rise Building Commission
inspected the site on 19-06-2007 and made certain observations as
under:
,
~
• Width of ramp is 16 feet against required 18 feet.
~~.~\---------- - ------- ----- --- ---';- -- __.,-.------ - -&It~"-\\__\..b --2
• Building has been projected about 3 feet in width from 1st
floor to top floor.
• Width of emergency stair case is less than 3 feet and main
stair case is 3'-6" instead of required 4 feet.
• Owner submitted an application to the High Rise Building Commission
(HRBC) by stating that he may be allowed to continue the construction
as some of the violations were mistakenly noted by the Commission
i.e. Width of ramp is 16 feet against required 18 feet.
• The application of the owner was sent to Mr. Kamil Khan Mumtaz,
Architect Member of the Commission who admitted that width of ramp
for parking shown as 16 feet in the approved plan was in accordance
with the relevant regulations of LOA for the year 2005 and that the
width of ramp to be 18 feet was noted by him under a mistake of fact.
3. The HRBC directed the owner to remove the irregularities and
directed the LOA to make sure these violations are removed. As per LOA
reference building stands completed upto 9th floor:
Sr.No Non-Compoundable Compoundable ViolationsViolations
1. Building has been projected in sidespace about 3 feet in width from 1stfloor to top floor due to which excesscoverage of 8739 sft done.
2. Guard roomconstructed in setbackspace.
3. Double storey roomsconstructed in rearspace.
4. Generator and steelstairs installed in sidespace
5. Width of emergencystair case is 3 feet andmain stair case is 3'-5"instead of required 4feet.
3
4. The representative of the LOA was asked to prepare a detailed
report regarding the violations. The report prepared by the Dy. Director, TP
is reproduced below:
1. Ramp and toilet for disabled persons are missing.2. Rear mandatory space is 12'-10", instead of 13'. Due to which excess
coverage is 6.33 sft.3. About 3' building is projected in all 4 sides therefore, causing excess
coverage of 9650 sft.4. There is excess coverage of 2949.2 sft & 703.4 sft on 9th and 10th floor
respectively.5. 11th floor is also constructed illegally covering area of 843.55 sft. It is
currently being used for the installation of Cooling Plant.6. Circular fire escape stair case area measuring (6'*6') reserved on 9th & 10th
floor each is used for other purpose. So, violation of total area of 72 sft.7. Area reserved for emergency stair case (6'*7') is used for other purposes
thus, causing total coverage of 420sft.8. Width of emergency stair case is 3' & 3'9" and main stair case is 3'6" & 4'2".9. Width of access stair from 9th to 10th floor is reduced to 2'-8".10.On ground floor, parking space reserved for 12 Cars in approved plan
(dated 07-10-06) is converted into hall and lobby (38'*54') measuring 2052sft.
11.Hence, excess parking requirement generated due to hall (1678.25 sft) is3.36 Cars.
12.Hotel comprised of 73 rooms (on 2nd to 8th floor). So, parking requirementfor hotel area is 12.17 Cars.
13.1st floor and 10th floor is being used as restaurant (1791 sft), cafe (793.32sft) and gym (698.69 sft.). Hence creating parking demand for 6.6 cars.
14.Office area on basement (195 sft) and on 2nd floor (686.85 sft) is requiringparking space for 0.88 Car.
15.Space reserved for 7 Cars measuring 896 sft in basement is used for otherpurposes. Moreover, in the light of above mentioned uses, total parkingrequirement at present is 23 cars but, there is shortage of 12 Cars.(Note: Car parking is not applied on 9th floor as it is not yet completelyconstructed. May be decided by the Commission.)
16.Space reserved for 61 motor cycles in basement measuring 915 sft is usedfor other purposes. At present, parking required for motor cycles is 3.68 no.of motor cycles, which is not provided.
17.According to clause 5.3.6 (C), the basement if used for other purposes thancar parking shall be constructed after leaving all the mandatory openspaces. But at site, mandatory spaces are mainly covered in the basementfor constructing office, laundry, workshop and mosque.
A copy of the above report was handed over to Mr. Zahid Zafar,
representative of the applicant.
4
5. The Commission visited the site again on 04.04.2016 in the
presence of Miss Saleha Shahid, Dy. Directed TP and Mr. Zahid Zafar the
representative of the applicant. Measurements were rechecked. It was
observed that the Guard Room constructed in the set back and the double
storey rooms constructed in the rear space have been demolished. However
the Commission made following observations during the visit:
I. The width of the building is 38'-5" against approved 38 ft.
Similarly length of the building is 102'-7" against approved 102'.
Therefore, an area of 64 sq.ft. from the setbacks has been added
in the building which is a non-compoundable violation.
II. Building is projected on all the four sides by 3ft. from the 1stto
the 10thfloor.Projections from the 1stto the 9thfloor are calculated as
under:
Sides area (102.58x3x2) = 615.48 sft.
Front and Rear area (44.41x3x2) = 266.46 sft.
Total area of projection on one floor = 881.94 sft.
Total area of projection of 9 Floors = 7937 sft.
iii. Projections on the 10thfloor are as under:-
Right side (48.16x 3) =Left side (56x3) =Front side (44.41x3) =
144.48 sft.
168 sft.
133.23 sft.
Total projections on 10thfloor = 446 sft.
Total area of projections (ii) + (iii) = 8383sft.
iv. An area of 600 sft. has been covered on the 11thfloor without
approval of plan. But since this area is being used for cooling
plant, it has not been included for calculation for extra car parking
requirement.6. The main non-compoundable violation in this case is conversion
of basement meant for parking and the usage of area approved for parking
on the ground floor for other usages which has resulted in shortage of
parking. In the basement, office, laundry, workshop and mosque have been. ~>\. ~\~ 5 ~§~~~~--;,l~~\l6-
constructed. On the ground floor the parking area has been converted into a
Seminar hall. The owner and her representative have committed that they
will remove the constructions in violation of approved plan in the basement.
If the owner and management fulfill its commitment, the car parking will be
available for 16 cars and 61 motorcycles in the basement and for two cars in
the front setback. Even then shortage of parking for five cars will remain in
which the car parking requirement for the 9th floor is not calculated.
7. Provisions of inadequate parking or conversion of car parking
area into other usages is a serious non-compoundable violation under the
regulation No. 10.11.1 of LOA Building and Zoning Regulations 2007. This
is not an issue only related to urban development regulations but it is public
importance matter concerning general public welfare. Shortage of car
parking resulting from the inadequate parking provided by the owners of high
rise building ultimately affects the public services. If the owners of high rise
buildings will not provide car parking as stated in the plan or use the area
reserved for car parking for other usages, it will augment the traffic hazard
and traffic congestion on roads and public places. Such a violation will be at
the cost of public interest and will aggravate the ever increasing parking
problem in the City particularly in commercial areas.
8. Since the shortage or non-provision of car parking is non
compoundable violation, therefore, the Commission has to determine the
rate of penalty. Clause (c) of sub-section (5) of Section 32 of the LOA
(Amendment) Act, 2013 provides as follows:-
"(5) The Commission shall consider and make appropriate
recommendations on matters relating to-
(c) illegally constructed structures, give recommendations in
order to regularize such structures, if deemed appropriate,
requiring the owner to adhere to the appropriate law, rules and
regulations, recommending such conditions, modifications,
amendments, fines, penalties, demolitio~nt~ctu. res.ac.c.ordin~.to the nature of each case." ~ .....i". \, ._ . 0~Q-,
\ ,".J -. -_. \
- 6 -----.--- ...--' ....- .-" .. .. --'-----D7t~L{\. b
Clause (c) of sub-rule (3) of Rule 8 of the Lahore Development Authority
Commission Rules, 2014 further elaborates the provisions of the Act ibid as
under:
(3) The Commission may, by majority, make appropriate
recommendations which may include;
(c) Illegal construction:
(i) demolition by the applicant;
(ii) demolition by the Authority and recovery of dues and fines by
it",
(iii) rectification of the illegal construction and apportionment
of the responsibility or cost to each party;
(iv) partial demolition and recovery of cost thereof;
(v) determination of rights and obligations of the parties in the
event of demolition; and
(vi) approval of plan and construction, subject to payment of
fees and penalties to the Authority.
This being so, the Commission can make appropriate recommendations
including imposition of penalty for non-compoundable violations, according
to the nature of each case in the light of the above quoted provisions.
9. Chief Engineer, Traffic Engineering Planning Agency (TEPA)
was asked to work out car parking per Kanal and cost of construction of
parking at public places per sq. ft. According to TEPA maximum 4 cars can
be parked in one Kanal and estimated construction cost of parking is Rs.
3500/- per sft. The rate of Rs. 3500/- per sft. calculated by TEPA is not
disputed but the Commission cannot agree with the working of 4 cars per
Kanal which seems unreasonable. The Commission, therefore, has worked
out area required for each car on the basis of prescribed criteria in the
Regulation No. 5.3.3 of the above mentioned Regulations as under:
• Stall area for one car
• Minimum area for drive way (9 ft. length x 8 ft. width) 72 sft.• Minimum area required for ramp (30 ft. length x 18 ft.
width) 540 sft.• Area per car worked out on the basis of 24 cars in a two
Kanal plot 22 sft.• Additional area for the pillars of 2ft. x 2ft. size taking
average pillar to pillar distance18 ft. (2ft. x 25 ft.) 50 sft.
Minimum parking area required for one Car 272 sft.
On the basis of requirement of area of 272 sft. for one car, the penalty
calculated at the rate of Rs. 3500/- for provision of parking at the public
expenses comes to Rs. 9, 52, 000/-. In the present case there is a short fall
of area for 5 cars as discussed above provided hotel management makes
available space for parking of 16 cars and 61 motorcycles in the basement.
The penalty for shortage of 5 cars comes to Rs. 47, 60, 000/-. The above
requirement of car parking and the penalty has been worked out tentatively
without considering the usage of the 9th floor which still requires finishing.
Exact car parking requirements, actual shortage of car parking and amount
of penalty on the above fixed rate shall be calculated on the basis of the
revised plan which will be submitted by the applicant. In case the above
recommended penalty rate is not acceptable to the applicants, they may opt
to rectify the violation by removing structure by creating additional space for
car parking on the ground floor, which can be done without any damage to
the main building structure.
10. Shortage of car parking and conversion of parking area are two
violations under above mentioned Regulation No.1 0.11.1. The applicant has
converted an area of 2052 sft. as per measurement at site. Thus an excess
area 2052 sft. has been created for use as Seminar Hall. For compoundable
violation penalty for excess area has been prescribed @ Rs. 904 sft. The
violation committed by the applicant is non-compoundable. Hence a penalty
twice the rate of compoundable rate is recommended to be imposed. The
penalty on this account comes to Rs. 37, 10, 016. If the applicant converts
the Seminar Hall again into car parking she will be not I,~,~O this penalty. t\_ ~QO-/\
8 -~~:-- 6;=7\~t-ll\ -~ ''-- 't l.. ".....
11. Building is projected on all four sides by 3ft. from the 1st to the
10th floor. Total area of projections comes to 8383 sft. which though forms
integral part of the authorized building but violates space regulations. It is a
compoundable violation and penalty thereof has been provided in the
Building Regulations, 2005 under which the building plans were processed
and approved. Penalty for the compoundable violation, therefore, is imposed
at the rates provided at serial No. 1 of the Appendix-O of the Regulations
ibid, which is Rs.226 per sft. for the 1st and the subsequent floors. Total
amount of penalty on this account is calculated as Rs. 18, 94, 558/-
12. So far as the Generator placed in the side space is concerned, it
is not a permanent structure and at the same time, it is an essential
requirement due to electricity load shedding problem. As no regulations
existed in respect of the placement of the generators at the time of approval
of building plans, it is recommended that the generators should be
temporarily allowed to be placed in the rear set back at the opposite end of
the emergency exit stairs by demolishing the decorative arches illegally
constructed in the side and rear setbacks. LOA should consider that in future
site for placement of generators should be specifically indicated in the
building plan within the building line or in some additional space in the
setbacks.
13. Width of the main stair case is 3'-5" instead of required 4 feet and
at floor No.9 & 10 the width of the stairs is 2'-8" only. Width of the stairs at
floor No.9 & 10 should be increased if it is possible without much damage
to the structure of the building in consultation with the Architect and the
Structure Engineer. However, shortage of the width on the 1st to the 8th floors
is recommended to be condoned and regularized on payment of a penalty of
Rs. 10,000/- per floor. Total penalty would be Rs. 80, 000/-. In case the
Architect and the Structure Engineer advice that width of the stairs at the 9th
and 10th floor cannot be rectified without damage to the structure, then it
14. The Honourable Lahore High Court vide its order dated
01.03.2013 in Writ Petition No. 1619/2003 constituted a Fire Safety
Commission. According to the order dated 11.07.2013 in the above
mentioned petition, the Commission constituted by the High Court, inter alia,
recommended;
"External steel staircases must be installed at all high-rise building
above 38 feet for safe evacuation, where exits are not already
available."
During hearing on 27.09.2013 Additional Director General, LDA submitted
before the Honourable High Court that the recommendations of the Court
were being seriously considered by the LDA for incorporation in the new
regulations. Although this Commission could not find any regulation to
implement the above mentioned recommendations yet considering the
commitment of LDA before the Honourable High Court, the steel stairs in the
side set back are held to be in line with the recommendations of the Fire
Safety Commission and has to be allowed for the time being. As far as, the
width of emergency stairs is concerned it cannot be condoned since it is
essential to ensure safe passage during an emergency. Therefore it is
recommended that applicant should rectify the width of stairs according to
Regulations.
15. In the present case the area where emergency stairs were to be
provided as per approved plan, has been used by the owner for other
purposes.The owner by shifting the emergency stairs outside the building in
the open space against the approved building plan have committed a non
compoundable violation and also has created additional useable space
within the building. Being a non-compoundableviolation no penalty has been
prescribed in the Regulations underwhich the building planswere approved.
Therefore, the penalty for non-compoundable violation is to be decided by
the Commission. In cases of non-compoundable violations the contentionthat the penalty should be calculated on the basis of the rates prevalent at
10
the time of construction, cannot be accepted because
shown in the cases of non-compoundable violations. The present rate of
excess covered area in respect of the compoundable violation is Rs. 904/
per sft. for the ground floor and Rs. 6001- per sft. for the upper floors. In this
case the alternate arrangement has been made therefore the penalty twice
the rate of similar compoundable violation is recommended to be imposed.
The amount of penalty is worked out as under:
Excess area on the ground floor. 6ft.x7ft=42 sft. @
Rs.1808/- sft. Rs. 75, 963/-
Excess area on the upper floors 42sftx9=378 sft. @
Rs.12001- sft. Rs. 4,53,6001-
However if the applicant decides to avoid penalty and provide the emergency
stairs at its original place as approved in the plan, without much damage to
the structure of the building and re-construct in consultation with the Architect
and the Structure Engineer, the penalty will not be imposed.
16. The excess coverage on the 9th, 10th and 11th floors if exceeds
the prescribed coverage under the Regulation has to be dealt in accordance
with the Regulations under which the building plans were approved keeping
in view the height restrictions and floor area ratio. In case the covered area
as per revised plan does not violate building height restrictions or floor area
ratio, no penalty is to be imposed.
17. At the time of inspection, the Commission observed that an area
of 64 sqf. has been added in the building out of the mandatory setbacks.
Although the reduction of the setbacks is a marginal one, yet it is a non
compoundable violation under the Regulations which were applicable in this
case at the time of approval of the plans as well as under the presently
prevailing Regulations. The Honorable Supreme Court in the case of MIs
Tricon Developers condoned the similar setback violation by imposing a
penalty of Rs. 3,000,0001- for the area of 432 sq. ft (length of Tricon building
216 ft. x 2 ft. included in the building line out of 13 ft. side setback). The said
penalty was paid by MIs Tricon on 08-10-2008. The rate~sq. ft. comes to \/" \
.. , \, - ~1Cj ~Q_/~ 11 -()~t~~(C6--~
Rs. 6,944/. At that time the price of commercial land on the Jail Road falling
in Gulberg as per DC's valuation table, was Rs. 15,00, 000/- per Marla i.e.
Rs. 6666/- per sft. Thus the penalty imposed was slightly above the then
prevailing price of the commercial land as per DC's valuation table. In order
to evolve uniform criteria for imposition of penalty for the non-compoundable
violation of setback area, the Commission feels that such violations should
not be ignored and a heavy but a uniform penalty keeping in view the
location, should be imposed. In fact it should have been at the rates actually
prevailing in the market since the owner is covering the area for his or her
own benefit. But determination of actual residential and commercial prices
prevailing in the market is almost impossible due to concealment of the
actual transaction prices. Therefore, it would be fair if the commercial price
as per DC's valuation table be taken as basis for determination of penalty for
all kinds of high rise buildings on the main roads as the land on such roads
is considered commercial whether the high rise building are constructed for
commercial activity or residential apartments or for any other use. Adoption
of DC' valuation table is also well justified as the rate will vary according to
the location of the building wherein such violation has been committed. The
rate of penalty as per DC's valuation table will not be too harsh or too lenient.
It will still be much less than the market value of the excess area even at the
sale rate of the residential apartments. Therefore, the Commission has
decided to recommend that in the cases of above discussed non
compoundable violation, it will not be unfair to charge penalty determined on
the basis of commercial rates of the DC's Valuation Table as on the date of
filing of reference in the Commission. Those who have committed an illegality
cannot be leniently dealt with and they must also suffer for the delay. As per
DC's valuation table applicable on the date of filing of the present reference,
the rate in respect of commercial properties falling on the Gulberg Roads is
Rs.18,00,000/- per Marla i.e. Rs.8000/- per sft. Therefore, penalty @ Rs.
8000/- per sft. for the 64 sft. area (included by the respondents in the building
line out of the setbacks), is recommended to be imposed. The total amount
of such penalty comes to Rs. 5,12, 000/-. \'\ ~() )- ------'"-::-~ \
12
18. The summary of penalties discussed above is given below:
Tentative penalty for shortage of car parking Rs.47,60,000
Penalty for conversion of car parking Rs. 37,10,016
Penalty for excess coverage i.e. projections Rs. 18,94558
Penalty for conversion of emergency stairs for other use Rs. 5,29,563
Penalty for setback violation. Rs. 5,12,000\
Penalty for shortage of width of main stairs Rs. 1,80,000
Total amount of Penalties Rs. 1, 15,86, 137
19. The above amount of Rs. 1, 15, 86, 137 is subject to variation in
accordance with final car parking requirement to be determined in the light
of the revised plan to be submitted by the applicant and removal of violations
in the basement. In case any of the above recommended penalties is not
acceptable to the respondents, they may opt to rectify the violation to avoid
the penalty.
20. In case of any patent error or omission apparent from the face of
the record, is subsequently discovered in any or all the above measurements
or computations, the Commission may rectify the same on an application by
either party after affording an opportunity of being heard to the other party.
21. In view of the above discussed facts, the record perused, the
evidence examined and discussions made with the representatives of the
LOAand the applicant, recommendations of the Commission are as under:-
1) The applicants shall provide ramp and toilet for disabled persons
which cannot be condoned even by imposition of penalty.
2) The respondents will revise the building plans accordingly, either
by rectification of the violation or payment of penalty asdiscussed above. The revised plans submitted by the
respondents will be processed expeditiously by the concerned
Director Town Planning and if they line with these
~~ ..~..c0__________ -- ------i-----.,6lt~l1\l6
13
recommendations and have no other non-compoundable
violation, those will be accepted within four months from the date
of submission of the revised building plans at One Window by
the respondents.3) Unless the respondents file an appeal, they can opt at any time
after receipt of this order but not later than 15 days after the
expiry of the period of appeal, to rectify the above discussed non
compoundable violation. In case they opt to rectify the non
compoundable violation, they shall ensure that the violation is
rectified before they file the revised building plans.
4) Within 30 days after clearance of the building plans or after the
expiry of the above mentioned period of four months, whichever
is earlier, Challan for payment of the above determined amount
of Rs. 1, 15, 86, 137 simultaneously along with the Challan( s) for
the amount of any other penalties @ rates of 2005 Regulations
for the for compoundable violations already committed, if any,
not discussed above or not mentioned in the present reference
by the LOA as well as any other charges recoverable from the
respondents as per law, will be issued by the LOA to the
respondents, which shall be paid by the respondents within 60
days of the receipt of the Challans by them. In case of any
difference of opinion as regards the final amount of penalty
determined on the basis of the revised plan duly approved, the
matter may be referred to the Commission on applicant's request
to determine the final amount of penalties in the light of these
recommendations.5) In case the respondents, instead of payment of penalty for the
non-compoundable violation, opt to rectify it, the amount of
Challan will be reduced accordingly. Rectification of violations, at
the option of the respondents, will be ensured by the LOA before
the approval of the revised plans.6) It is further recommended to resolve the issue that on payment
of the above amount, the issuance of Com
-14
be ensured by the LOA within 60 days of the payment of theabove amount or on completion of incomplete work, if any,
whichever is later.7) In case the applicants do not opt for payment of penalty and do
not demolish the illegal construction or rectify the non
compoundable violation, the illegal construction shall be
demolished or violation shall be rectified by the LOA at the cost
and risk of the applicants and car parking at in the basement and
on the ground floor shall be restored by providing approach ramp
for ground floor parking. Till the time of the rectification the
building may also be sealed.
...
Member, LOAC Chairman, LOAC
Announced
07.04.2016
15