03_Oil & Gas www.multiconsult.no Mobin (Iran)_ SW & Cooling Water System PROJECT Mobin (Iran) SW & Cooling Water System PROJECT TYPE Detail Engineering LOCATION Asaluyeh, Iran CLIENT Sadra/Aker Marine Contractors PERIOD 2002-2004 KEY NUMBERS Pump basin: 13000 m 2 , Intake/outlet culverts: 1400 m, Pumping capacity: 106 m 3 /s The project comprises a cooling water project with intake and outlet culverts, pumping basin and some infrastructure (buildings etc). The main parts of the project are a pumping station basin covering an area of 13,000 m 2 , an intake culvert structure, approx. 1000 m long, and an outlet culvert approx. 400 m long. The cross section of the culverts is 13 x 5 m. Two 120 m long culvert elements will be constructed in a dry dock in Busher, towed to Asaluyeh and installed on the seabed at 20 - 40 m depth. The remaining part of the culvert was prefabricated in 25 meter long sections, transported by barge to site and lifted into position by a crane barge. 411-HM-002: 03_038, rev. 10.09.2010 Mobin SW & Cooling Water System - Photo: Multiconsult

Upload: others

Post on 02-Jun-2020

6 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Mobin (Iran) - Multiconsult...03_Oil & Gas Mobin (Iran)_ SW & Cooling Water System Engineering services Multiconsult has a contract for the detailed design of civil structures with

03_Oil & Gas

www.multiconsult.no

Mobin (Iran)_SW & Cooling Water System

PROJECT

Mobin (Iran) SW & Cooling Water System

PROJECT TyPE

Detail Engineering

LOCATION

Asaluyeh, Iran

CLIENT

Sadra/Aker Marine Contractors

PERIOD

2002-2004

KEy NUMBERS

Pump basin: 13000 m2, Intake/outlet culverts:

1400 m, Pumping capacity: 106 m3/s

The project comprises a cooling water project with intake and outlet culverts, pumping basin and some infrastructure (buildings etc).

The main parts of the project are a pumping station basin covering an area of 13,000 m2, an intake culvert structure, approx. 1000 m long, and an outlet culvert approx. 400 m long. The cross section of the culverts is 13 x 5 m.

Two 120 m long culvert elements will be constructed in a dry dock in Busher, towed to Asaluyeh and installed on the seabed at 20 - 40 m depth. The remaining part of the culvert was prefabricated in 25 meter long sections, transported by barge to site and lifted into position by a crane barge.

411-

HM

-002

: 03_

038,

rev.

10.

09.2

010

Mobin SW & Cooling Water System - Photo: Multiconsult

Page 2: Mobin (Iran) - Multiconsult...03_Oil & Gas Mobin (Iran)_ SW & Cooling Water System Engineering services Multiconsult has a contract for the detailed design of civil structures with

03_Oil & Gas

www.multiconsult.no

Mobin (Iran)_SW & Cooling Water System

Engineering services

Multiconsult has a contract for the detailed

design of civil structures with Aker Marine

Contractors. Aker has a contract with Iran

Marine Industrial Company (SADRA), which

is a turnkey contractor for the cooling water

project versus Mobin.

The Aker contract is including detailed design

of civil structures and marine operations.

For parts of the work Multiconsult has

engaged the local consulting company Sazeh

Pardazi Iran (SPI).

Diciplines

• Geology

• Geotechnics

• Landscaping

• Roads

• Water & sewage

• Civil

Scope of work

Construction of site was performed according

to plan.

PROJECT

Mobin

PROJECT TyPE

Detail Engineering

LOCATION

Asaluyeh, Iran

CONTRACT

NOK 9 mill.

Mobin SW & Cooling Water System - Photo: Multiconsult

Mobin SW & Cooling Water System - Photo: Multiconsult

Mobin SW & Cooling Water System - Photo: Multiconsult