MS4 Requirements for Construction Site Storm Water

Runoff Control

Craig T. Maske, P.E., CFM

DODSON | A WALTER P MOORE COMPANY

1

Page 2: Minimum Requirements for Construction Site Compliance

Presentation Topics

• Definitions

• MS4 and Construction Site Operator Requirements

• Tools for Reviewers/Inspectors

• Questions

2

Page 3: Minimum Requirements for Construction Site Compliance

Definitions

• Municipal Separate Storm Sewer System

• Regulated Construction Site

– Small

– Large

• Storm Water Pollution Prevention Plan (SWP3)

3

Page 4: Minimum Requirements for Construction Site Compliance

Pre-Construction Requirements

• Construction Site Operator

– Prepare Storm Water Pollution Prevention Plan (SWP3)

– Notify TCEQ of intent to discharge

– Notify MS4 operator

4

Page 5: Minimum Requirements for Construction Site Compliance

Pre-Construction Requirements

• Large and Small Construction Sites

5

Prepare SWP3 X X

Submit NOI to TCEQ X ---

Submit NOI to MS4 Operator X (7 Days) X (2 Days)

Post Site Notice at Entrance X X

Post NOI at Entrance X ---

Large Sites

(>=5 Ac)

Small Sites

(>1 Ac < 5 Ac)Task Notes

Fee $225/$325 (efile/paper)

(Small Sites Submit Site Notice)

Obtaining CGP Coverage

Page 6: Minimum Requirements for Construction Site Compliance

Pre-Construction Requirements

• MS4 Operator

– Review Site Plans/SWP3

– Receive and File NOI/Site Notice

– Issue Local Permits

6

Page 7: Minimum Requirements for Construction Site Compliance

Pre-Construction Requirements

• Storm Water Pollution Prevention Plan Review

– SWP3 must contain all elements noted in Part III, Section F of TCEQ permit

– Many of these elements are not prepared until after permitting

– Additional elements added by Construction Site Operator prior to construction

7

Page 8: Minimum Requirements for Construction Site Compliance

SWP3 Versus SWP3

8

Page 9: Minimum Requirements for Construction Site Compliance

Construction Requirements

• BMPs must be planned and implemented

– Sediment and erosion controls

– Waste controls

– Other controls

• Inspections, maintenance and recordkeeping

– Construction Site Operator (regular)

– MS4 Operator (periodic)

• And assess penalties as necessary

9

Page 10: Minimum Requirements for Construction Site Compliance

Inspections

10

Photo Courtesy of Jon Jones, P.E., Wright Water Engineers, Inc.

Page 11: Minimum Requirements for Construction Site Compliance

Post-Construction Requirements Construction Site Operator

• Prepare and submit notice of termination (NOT) to TCEQ

• Large operators submit copy to MS4 operator

• Remove site notice and fill out bottom corner • Small operators submit copy of completed SN to MS4

• Keep copies of all paperwork for your records • At least 3 years from date of NOT

11

Page 12: Minimum Requirements for Construction Site Compliance

Post-Construction Requirements MS4 Operator

• Receive NOT/completed Site Notice

• Ensure project meets termination requirements

• Ensure post-construction controls are in place

– Established vegetation, detention, etc.

– Depending on ordinance

12

Page 13: Minimum Requirements for Construction Site Compliance

Tools for MS4s

• Storm Water Ordinance

– Requirements for construction operators

– Citations and fines for violations

• TCEQ Small Business/Local Government Assistance Program

– www.TexasEnviroHelp.org

13

Page 14: Minimum Requirements for Construction Site Compliance

Final Thoughts…

• MS4 operators get to act as the first line of plan review and enforcement for TCEQ

• More construction site runoff requirements coming soon…

• More MS4 permit requirements coming soon…

14

Page 15: Minimum Requirements for Construction Site Compliance

Questions??