mildenhall hub heat network opportunities · mildenhall hub heat network opportunities ramboll 40...
TRANSCRIPT
Intended for
West Suffolk Partnership
Document type
Final Report
Date
May 2016
MILDENHALL HUB HEAT NETWORK
OPPORTUNITIES
MILDENHALL HUB
HEAT NETWORK OPPORTUNITIES
Ramboll
40 Queen Square
Bristol BS1 4QP
T +44 (0)117 929 5200(0)117 929 5200
F +44 (0)117 929 523944 (0)845 299
1610
Revision 3
Date 16/05/2016
Made by Sophie Cator and Gemma Giribet
Checked by Robin Glendinning
Approved by Anthony Riddle
Description Report
Ref 1620001100
Document ID 581652-1 / WSHNO-14-001
Version 3
Heat Network Opportunities
CONTENTS
Glossary 1 Executive Summary 3 1. Introduction and Background 1 1.1.1 Objectives 2 1.1.2 Strategic Background and Policy 2 1.1.3 Previous Work Undertaken 3 2. Energy Demand Mapping 5 2.1 The Study Area 6 2.2 Heat Demand 7 2.2.1 Methodology 7 2.2.2 Existing Buildings 9 2.2.2.1 Town Centre 9 2.2.2.2 Industrial Estate 9 2.2.3 New Development 11 2.2.3.1 Mildenhall Hub Site 11 2.2.3.2 Other Planned Developments 12 2.2.4 Heat Demand Summary 14 2.3 Cooling Demand 17 2.3.1 Methodology 17 2.3.2 Cooling Demand Summary 17 2.4 Power Demand 19 2.4.1 Methodology 19 2.4.2 Existing Buildings 19 2.4.3 Mildenhall Hub 20 2.4.4 Electricity Demand Summary 20 3. Energy Supply Opportunities 22 3.1 Existing Supply Assets 22 3.2 Future Supply Assets 23 3.3 Potential Supply Assets 23 3.3.1 Gas CHP 25 3.3.2 Biomass 25 3.3.3 Absorption Chillers 26 3.3.4 Solar Thermal Panels 26 3.3.5 Industrial Heat Recovery Using Heat Pumps 27 3.3.6 Water Source Heat Pumps 27 3.3.7 Energy Centre Options 28 4. Heat Network Opportunity Appraisal 31 4.1 Identification of Opportunity Areas 31 4.1.1 Heat 31 4.2 Heat Network Routing Strategy 33 4.3 List of Identified Opportunities 35 4.4 Opportunity Appraisal 36 4.4.1 Mildenhall Hub 38 4.4.2 Northern Light Industrial Area 39 4.4.3 Mildenhall Hub with Extension to Light Industrial Area 41 4.4.4 Summary 42 5. Energy Masterplanning for Preferred Opportunities 43 5.1 Energy Demand Assumptions 44 5.1.1 Mildenhall Hub Concept Design Alterations 44 5.1.2 Heat Demand Assessment 45
Heat Network Opportunities
5.1.3 Electricity Demand Assessment 47 5.1.4 Project Phasing 47 5.2 Energy Supply Assumptions 48 5.2.1 Overview of General Assumptions for All Scenarios 48 5.2.2 Solar PV 50 5.2.3 Gas CHP 51 5.2.4 Biomass Boiler 53 5.2.5 Water Source Heat Pump 55 5.2.6 Solar Thermal 57 5.2.7 Ground Source Heat Pump 59 5.3 Modelling Results 61 5.3.1 Results without Solar PV 61 5.3.1.1 Economics 61 5.3.1.2 Carbon 62 5.3.2 Results with Solar PV 63 5.3.2.1 Economics 63 5.3.2.2 Carbon 63 5.3.3 Sensitivity Analysis 65 5.3.4 Summary of Modelling Results 69 6. Project Outline RisK assessment 70 6.1 Technical Risks 70 6.2 Commercial Risks 71 6.3 Financial Risks 72 6.4 Planning Risks 73 6.5 Risk Register 74 7. Conclusions, Recommendations and Next Steps 75 7.1 Conclusions 75 7.2 Recommendations 76 7.3 Next Steps 76 7.3.1 Business Model and Business Case 76 7.3.2 Ensuring Correct Design Standards are adopted 76 7.3.3 Safeguarding Wider Network Demand 76 7.4 Summary Implementation Plan 77
TABLES
Table 1: Contents of Report Sections ......................................................... 2 Table 2: Benchmarks Used for Mildenhall Hub and other New Development
Sites ..................................................................................................... 8 Table 3: Expected Floor Areas for Mildenhall Hub (Autumn 2015) ................ 11 Table 4: Planning Applications Considered within the Heat Map ................... 12 Table 5: Summary of Key Figures of Planning Applications .......................... 12 Table 6: Heat Demand for New Developments ........................................... 12 Table 7: Mildenhall Heat Demand summary .............................................. 14 Table 8: Mildenhall Cooling Demand ......................................................... 17 Table 9: Summary of Existing Power Demands .......................................... 19 Table 10: Estimated Annual Power Demand for the Mildenhall Hub .............. 20 Table 11: Extract from Technology Options Appraisal ................................. 24 Table 12: RHI Support for Biomass .......................................................... 25 Table 13: Energy Centre Locations Appraisal ............................................. 29 Table 14: List of Identified Opportunities .................................................. 35 Table 15: Common Assumptions for Opportunity Models ............................. 37
Heat Network Opportunities
Table 16: Key Metrics for Opportunity MH001 to MH005 ............................. 38 Table 17: Key Metrics for Opportunity MH006 to MH007 ............................. 40 Table 18: Key Metrics for Opportunity MH008 to MH009 ............................. 41 Table 19: Options Appraisal Summary ...................................................... 42 Table 20: Floor Areas per Building for Mildenhall Hub ................................. 44 Table 21: Key CHP Parameters ................................................................ 51 Table 22: Capital Costs for CHP Option ..................................................... 51 Table 23: Key Biomass Boiler Parameters ................................................. 53 Table 24: Capital Costs for Biomass Option ............................................... 54 Table 25: Key WSHP Parameters ............................................................. 55 Table 26: Capital Costs for WSHP Option .................................................. 56 Table 27: Solar Thermal Case Key Parameters .......................................... 57 Table 28: Capital Costs for Solar Thermal Option ....................................... 58 Table 29: GSHP Option Key Parameters .................................................... 60 Table 30: Capital Costs for GSHP Option ................................................... 60 Table 31: Summary of Economic Results .................................................. 61 Table 32: NPVs at 6% and 10% Discount Rates ......................................... 61 Table 33: Carbon Savings for Mildenhall Energy Supply Options .................. 62 Table 34: Summary of Economic Results with PV ....................................... 63 Table 35: NPVs at 6% and 10% Discount Rates ......................................... 63 Table 36: Carbon Savings for Mildenhall Energy Supply Options .................. 63 Table 37: Sensitivity of Schemes to RHI Reduction .................................... 65 Table 38: Sensitivity of Economics to Leisure Centre Heat Sale Price ............ 68 Table 39: Risk Register for Mildenhall Hub ................................................ 74
FIGURES
Figure 1: Two Study Areas Considered for Heat Network Opportunities .......... 1 Figure 2 Network Route Diagram from 2013 Feasibility Study ....................... 4 Figure 3: Mildenhall Hub Site and Study Area ............................................. 6 Figure 4: Screenshot of Local Authority Billing Data .................................... 7 Figure 5: Photograph from Mildenhall Industrial Estate (taken during Ramboll
site visit) ............................................................................................... 9 Figure 6: Concept Diagram for Mildenhall Hub ........................................... 11 Figure 7: Estimated Heat Demand for Planned Developments ...................... 13 Figure 8: Estimated Heat Demands for Mildenhall Hub ................................ 15 Figure 9: Estimated Heat Demands within the Study Area ........................... 15 Figure 10: Mildenhall Heat Demand .......................................................... 16 Figure 11: Estimated Cooling Demand of Mildenhall Study Area ................... 18 Figure 12: Mildenhall Hub Estimated Electricity Demand ............................. 20 Figure 13: Mildenhall Hub Power Demand Estimate .................................... 21 Figure 14: Screenshot from DECC Public Database ..................................... 23 Figure 15: Environment Agency Air Pollution Map of Mildenhall .................... 27 Figure 16: River Lark Heat Capacity (courtesy of DECC National Heat Map) ... 28 Figure 17: Council Owned Land in Mildenhall ............................................. 30 Figure 18: Image of Mildenhall High Street (courtesy of Google Maps) ......... 31 Figure 19: Image of the light-industrial area (taken by Ramboll during a site
visit). ................................................................................................... 32 Figure 20: Extracts from Network Route Analysis ....................................... 33 Figure 21: MH001 Opportunity Boundary .................................................. 38 Figure 22: MH007 Industrial Area Opportunity ........................................... 39 Figure 23: MH008 Opportunity Area ......................................................... 41 Figure 24: Indicative Design Option for Mildenhall Hub ............................... 44 Figure 25: Annual Heat Demand by Building Type ...................................... 45
Heat Network Opportunities
Figure 26: EnergyPRO Annual Heat Demand Profile for Mildenhall Hub.......... 46 Figure 27: EnergyPRO Weekly Heat Demand Profile (Jan) ........................... 46 Figure 28: Predicted Daily Electricity Profile for Mildenhall Hub .................... 47 Figure 29: Solar Irradiation Data for Mildenhall .......................................... 50 Figure 30: Example Weekly Profile of Supply Asset Contributions ................. 51 Figure 31: Contribution of Supply Assets to Heat Demand for Biomass Option
........................................................................................................... 53 Figure 32: Photographs of the River Lark (courtesy of Ramboll) ................... 55 Figure 33: Contribution of Supply Assets to Heat Demand for WSHP Option .. 56 Figure 34: Contribution of Solar Thermal Supply Assets to Heat Demand in
Summer ............................................................................................... 57 Figure 35: Contribution of Solar Thermal Supply Assets to Heat Demand in
Winter .................................................................................................. 58 Figure 36: Screenshot from UK Soilscapes Map ......................................... 59 Figure 37: Contribution of Supply Assets to Heat Demand for GSHP Option ... 60 Figure 38: Effect of Removing RHI from Project Cash Flow .......................... 65 Figure 39: Graph of 25 year IRR Varying with Cost of Heat ......................... 66 Figure 40: Graph of 40 year IRR Varying with Cost of Heat ......................... 66 Figure 41: Effect of Varying Capital Costs on Project 25 year IRRs ............... 67 Figure 42: Effect of Varying Capital Costs on Project 40 year IRRs ............... 67
APPENDICES
Appendix 1 Energy Demand Map Data
Appendix 2 Technology Options Appraisal
Heat Network Opportunities
1
GLOSSARY
AQMA Air Quality Management Area
Barg Gauge Pressure Unit (bar)
BaU Business as Usual
BGS British Geological Survey
CAPEX Capital Expenditure
CEVAP Church of England Voluntary Primary School
CHP Combined Heat and Power
CHPA Combined Heat and Power Association
CHPQA Quality Assurance Scheme for Combined Heat and Power
CIBSE Chartered Institution of Building Services Engineers
Coolth Cooling delivered by chilled water loop
CoP Coefficient of Performance
CoP Coefficient of Performance
DECC Department of Energy and Climate Change
DEFRA Department for Environment, Food and Rural Affairs
Delta T The temperature difference between water flowing in the flow and return
sections of the network.
DHN District Heating Network
DNO Distribution Network Operators
EMP Energy Masterplan
ERF Energy Recovery Facility
ESCo Energy Services Company
FHDCLP Forest Heath District Council Local Plan
FiT Feed-In Tariffs
GFA Gross floor area
GIS Geographical Information System
GSHP Ground Source Heat Pump
GWh Gigawatt hour
HIU Heat Interface Unit
HNDU Heat Network Delivery Unit
HRSG Heat Recovery Steam Generator
HTHW High Temperature Hot Water
IES-VE Integrated Environmental Studies - Virtual Environment
IRR Internal Rate of Return
kWth Kilowatts (thermal)
LECs Levy Exemption Certificates
LLPG Local Land and Property Gazetteer
LTHG Low temperature heat generators
LTHS Low Temperature Heating System
LTHW Low Temperature Hot Water
MTHW Medium Temperature Hot Water
MWe Megawatts (electrical)
MWh Megawatt hour
MWth Megawatts (thermal)
NA Not Applicable
NHM National Heat Map
NPV Net Present Value
O&M Operation & Maintenance
OCGT Open Cycle Gas Turbine
OFGEM Office of Gas and Electricity Markets
Heat Network Opportunities
2
OPEX Operational Expenditure
PSV2 Public Service Village 2
PV Photovoltaic
REPEX Reinvestment Expenditure
RHI Renewable Heat Incentive
SAP Standard Assessment Procedure
SBEM Simplified Building Energy Model
WRAP The Waste and Resources Action Programme
WSHP Water Source Heat Pump
Heat Network Opportunities
3
EXECUTIVE SUMMARY
Ramboll was commissioned by St
Edmundsbury Council and Forest Heath
District Council, hereafter known together as
West Suffolk, to complete a study into the
opportunity for heat networks and
decentralised low carbon energy at two
locations.
The two study areas are the Mildenhall Hub
site in Mildenhall and the Public Service
Village 2 (PSV2) site in Bury St Edmunds.
This report was prepared on behalf of Forest
Heath District Council and presents the
results from the study into the Mildenhall
Hub.
RECOMMENDATIONS AND
CONCLUSIONS OF WORK UNDERTAKEN
There is opportunity to supply the various
areas within the proposed Mildenhall Hub
from a lower carbon technology than natural
gas boilers. However, there is not currently
any potential for a district heating network
extending from the Mildenhall Hub. This is
primarily due to low existing heat demand
density in Mildenhall and a lack of plans for
substantial new development.
Analysis was conducted to assess the
potential for a standalone heat network
within the Mildenhall industrial estate. The
project economics were found to be
extremely poor and therefore it was not
considered as an opportunity.
The analysis showed that ground source
heat pump (GSHP), combined heat and
power (CHP) and biomass could be suitable
primary supply technologies for the
Mildenhall Hub.
In order for a scheme to be considered
viable under public sector leadership, the
lowest hurdle IRR was set at 4%.
The GSHP scenario generates attractive
economic results with the IRR over 25 and
40 years estimated to exceed 14%.
However, the scheme’s feasibility would be
heavily affected by any changes to the
current RHI tariffs.
Gas CHP also returned attractive economic
results, with IRRs estimated at 11% for both
25 and 40 year project lifetimes. This
technology benefits from not being
dependent on RHI, but it exhibits a high
sensitivity to heat sale price.
The biomass case is likely to deliver
significant CO2 savings. However the
economic results show that this solution may
only be attractive for a public led project.
It is recommended that these three options
are considered in more detail at feasibility
stage. It is essential that further information
regarding the energy demands of the
Mildenhall Hub is made available before this
takes place.
ENERGY MAPPING AND ASSESSMENT OF
SUPPLY ASSETS
The first phase of the work was to map the
major heat, cooling and electricity demands
of the Mildenhall Hub and surrounding areas.
Three major clusters of energy demand were
identified at the Mildenhall Hub, northern
light industrial area and town centre. These
areas presented the greatest opportunity for
district heating or cooling.
No existing assets were identified that might
be able to supply energy into a network. A
The purpose of this study was to
establish opportunities for district
heating in Mildenhall and to
determine the most appropriate
primary supply technology for the
Mildenhall Hub development.
The work consisted of energy
mapping, opportunity
identification and techno-
economic analysis of the preferred
opportunity.
Heat Network Opportunities
4
technology options appraisal was carried out
in order to present a shortlist of energy
supply technologies that would be suitable
for the scale of demand and environmental
conditions in Mildenhall.
The technologies considered appropriate for
inclusion in the next project phase were gas
CHP, heat-only biomass, water-source heat
pumps (WSHP), GSHPs and solar thermal
panels.
IDENTIFIED OPPORTUNITIES
The process of opportunity identification
involved a combination of qualitative and
quantitative factors including:
energy demand density
proximity to identified supply assets
number of public buildings
potential anchor loads
barriers to construction
Once opportunities were identified, possible
heat network routes were assessed.
Nine heat network opportunities were
identified for high level modelling.
Project
Ref. Project Name
Estimated
25 yr IRR
MH001 Mildenhall Hub Gas
CHP 15%
MH002 Mildenhall Hub
Biomass 9%
MH003 Mildenhall Hub
WSHP 6%
MH004 Mildenhall Hub
Solar Thermal 9%
MH005 Mildenhall Hub
GSHP 7%
MH006 Mildenhall Industrial
Area CHP NA
MH007 Mildenhall Industrial
Area Gas Biomass -9%
MH008 Mildenhall Hub +
Industrial Area NA
MH009 Mildenhall Hub +
Industrial Area -6%
The project key performance indicators
(KPIs) of the opportunities were presented
to West Suffolk for comment and to confirm
Ramboll’s recommendations for preferred
opportunities.
Following the initial opportunities appraisal,
five opportunities were selected for further
analysis. Each opportunity features the
same heat load, but with different supply
technologies. The opportunities are listed as
follows:
1. MH001 Mildenhall Hub supplied by gas
CHP
2. MH002 Mildenhall Hub supplied by
biomass boilers
3. MH003 Hub supplied by a WSHP
4. MH005 Hub supplied by solar thermal
panels
5. MH006 Hub supplied by a GSHP
TECHNO-ECONOMIC ASSESSMENT OF
PREFERRED OPPORTUNITY
The first stage in the techno-economic
modelling process was to re-evaluate the
energy demand assessment based on up to
date information.
Following this, energy profiles were created
using EnergyPRO software which enabled
the sizing of various technology options. An
economic assessment was then undertaken
to determine the performance of each of the
supply options. The results of this
assessment are shown below
Supply
Technology
Estimated
25 yr IRR
Estimated 25
yr NPV
Gas CHP 11% £250,100
Biomass 9% £376,700
WSHP 5% £133,800
Solar
Thermal
NA -£555,400
GSHP 14% £997,500
At the request of Forest Heath District
Council, each of the scenarios was modelled
with the addition of a solar PV array to the
project energy flows and economics.
The results of the study were as follows:
Heat Network Opportunities
5
Supply
Technology
Estimated
25 yr IRR
Estimated 25
yr NPV
Gas CHP 10% £361,900
Biomass 10% £569,800
WSHP 6% £336,800
GSHP 14% £1,171,400
The integration of a Solar PV installation was
found to result in improvements both in
terms of economics and carbon emissions
savings for CHP, biomass, WSHP and GSHP
scenarios.
A sensitivity analysis was carried out to
assess the impact any changes of key
parameters on the economics of each
option.
Without the revenue from the RHI, the
WSHP and biomass projects are no longer
viable. The IRR of the GSHP reduces
significantly and the economics are unlikely
to be attractive except for a public led
scheme. The CHP scheme is not affected by
RHI.
The CHP, biomass and WSHP scenarios were
found to be very sensitive to the heat sale
price when compared to the GSHP option.
In a similar way to the heat sale prices,
changes in project CAPEX reduce the IRRs
for the WSHP scenario to an unattractive
level. However the CHP, biomass and GSHP
scenarios appear to remain feasible even
with a 20% cost increase.
RISK ASSESSMENT
An outline risk assessment was undertaken
for the preferred project opportunities. A
number of key risks were identified;
Accuracy of heat demand data
Hub heating system design
Ground conditions
Properties of the River Lark (WSHP
option only)
Operating costs higher than expected
These risks will require further consideration
during the next phase of the project
NEXT STEPS
Based on the conclusions and
recommendations of the study, a number of
next steps can be identified as follows:
1. West Suffolk to present the results of the
study to council members to ensure
support for the proposed low carbon
solution and to raise awareness of the
project.
2. A full business case should be produced
following a detailed feasibility exercise
once there is more certainty regarding
the design of the Hub.
3. The results of the study must be
provided to the Mildenhall Hub Design
Team to enable them to incorporate it
into the designs and adopt appropriate
heating systems.
Heat Network Opportunities
1
1. INTRODUCTION AND BACKGROUND
Ramboll was commissioned by St Edmundsbury Council and Forest Heath District Council,
hereafter as West Suffolk, to complete a study into the opportunity for heat networks and
decentralised low carbon energy at two locations.
West Suffolk is planning work with other public sector organisations to bring together a number
of public services, such as council offices, education and leisure, within the towns of Mildenhall
and Bury St Edmunds onto single sites. The two study areas are:
Mildenhall Hub site in the town of Mildenhall. This development will be led by Forest Heath
District Council
Public Service Village 2 (PSV2) site in the town of Bury St Edmunds. This development
will be led by St Edmundsbury Borough Council.
Figure 1: Two Study Areas Considered for Heat Network Opportunities
This report presents the results from the study into the Mildenhall Hub.
Heat Network Opportunities
2
1.1.1 Objectives
The aims of the study were set out in the invitation to quote as:
to identify and evaluate the feasibility of options for on-site low carbon heat and
power
to explore preferred options to gain support by key stakeholders
to establish the outline financial cases to take forward preferred options to the next
stage of wider project development
These objectives were maintained throughout the course of the work.
The report comprises the following sections:
No. Section Title Contents
2 Energy Demand Mapping An overview of energy demands within the study
area and mapping outputs. A summary of the
methodology.
3 Energy Supply Mapping An overview of existing, future and potential energy
supply assets within the study area and technology
options appraisal.
4 Heat Network Opportunity
Appraisal
A high level review of potential decentralised energy
opportunities including key metrics for each possible
scheme.
5 Energy Masterplanning for
Preferred Opportunity
A techno-economic assessment of the preferred heat
network opportunity.
6 Project Outline Risk assessment A risk register for the project to date, including
potential mitigation measures.
7 Conclusions, Recommendations
and Next Steps
A series of conclusions and recommended actions
following the results of the study.
Table 1: Contents of Report Sections
1.1.2 Strategic Background and Policy
Heat networks projects can be highly complex to deliver due to many interrelated commercial,
financial, technical and planning factors including:
1. inherent economic value and commercial risk 2. complexity of stakeholder relationships/appetites for involvement 3. councils capacity and appetite for involvement as a delivery partner and in some cases
conflicting commercial and strategic objectives for proposed projects
4. strength of local planning policy
Successful delivery through to procurement will require a scheme that is aligned to the Council’s
drivers, aspirations and capacity, and ability to deliver. It must be financially viable and
deliverable under the preferred delivery model as well as being attractive to a range of
stakeholders including developments, existing key anchor load and potential delivery partners.
The councils of St Edmundsbury and Forest Heath have created the partnership, West Suffolk, to
deliver effective development to a high standard of sustainable design. At the time of writing,
Heat Network Opportunities
3
measures had already been taken in the form of two previous studies, one of which was
conducted by Ramboll in 2013.
The successful bid to the Heat Network Delivery Unit (HNDU) demonstrates the will of the councils to implement successful district heating schemes and meet their objectives for sustainable development. HNDU can support the Councils from heat mapping through to detailed project development.
The West Suffolk Strategic Plan 2014-2016 provides an indication of the main motivators for the Councils. District heating is relevant to two out of three of the priorities set out in the document:
The promotion of energy efficiency measures is one of the actions listed to achieve Priority 1
– Increased Opportunities for Economic Growth.
Alleviation of fuel poverty is encompassed in Priority 3 – Homes for Our Communities, which
can often be achieved through district heating schemes.
In addition to the Strategic Plan priorities, the West Suffolk Sustainability Strategy (Dec 2013) sets out the range of issues which the councils wish to influence at a local level through appropriate use of services.
A mixture of technical and social issues is identified in the Sustainability Strategy. The desire to contribute to the carbon reduction target of a 60% reduction in CO2 against the 2004 baseline can be assisted through use of district heating and cooling. We propose to refer back to this target when reporting the potential CO2 savings of opportunities identified in the
energy masterplanning exercise. Social issues are also identified; primarily the problem around fuel poverty and the need for affordable warmth. It is proposed that reductions in the business as usual heat prices will be incorporated into the study to demonstrate economic viability
whilst taking into account affordable energy prices.
Planning policies are recognised by the councils as a tool to present the case for sustainability. Further ways in which planning policies can be used to help progress the identified district heating opportunities are outlined in section 7.
1.1.3 Previous Work Undertaken
In July 2011, St Edmundsbury Borough Council commissioned a report titled ‘Investigating Decentralised Energy in Bury St Edmunds’. The report provided a technical evidence base to support local authority actions and planning policies for decentralised energy. It also provided a technical and financial options appraisal to help inform policy making and investment decisions in decentralised energy (heating, cooling and electricity) projects in Bury St Edmunds and their potential to be delivered to existing and
planned mixed development in the town over the next 20 years. The study did not constitute a complete technical and financial feasibility study; rather it identified which options were worth taking to the next stage. One of the identified options focused on Bury Leisure Centre in Western Way and proposed further investigation around the potential to develop a district heating scheme around anchor loads in close proximity to the Leisure centre.
On the basis of that study, St Edmundsbury Borough Council and its project partners decided to
commission this feasibility study for a decentralised energy scheme based around Bury Leisure
Centre which Ramboll undertook in 2013.
Heat Network Opportunities
4
The objectives of the feasibility study were to evaluate options for a decentralised energy project
opportunity based around Bury Leisure Centre. The brief was to identify an opportunity that was
financially viable, capable of delivering CO2 reductions in line with Suffolk’s targets under its
Creating the Greenest County programme and affordable to the project stakeholders.
Figure 2 Network Route Diagram from 2013 Feasibility Study
The study found that:
A potential case existed whereby Bury Leisure Centre exports heat to a network that is
separately developed by the project stakeholders, but that the margin on buying and selling
of heat for supply into the network was likely to be low, generating low IRR’s for the project
stakeholders.
The economic case for connecting St Edmundsbury CEVAP School and King Edward IV School
to the identified heat network opportunity was poor.
Options for implementing solar PV, biomass heating and solar thermal were worth further
consideration, given that reasonably attractive IRRs were identified.
However, no further investigation was carried out following the study.
Heat Network Opportunities
5
2. ENERGY DEMAND MAPPING
This section provides an overview of heat, cooling and power demand within the study area. The
aim was to produce energy maps and databases suitable for use in identifying and assessing heat
network opportunities in Mildenhall.
As heat supply strategy was the main objective of the study, developing heat maps was the
primary focus of the energy mapping phase of work. Cooling was assessed at high level in order
to identify any opportunities for combined heating and cooling networks. Finally the map of
electricity demand was developed to establish any opportunities for private wiring of electricity
that could be supplied by supply assets such as combined heat and power (CHP) engines or solar
photovoltaic (PV) panels.
To support this phase of works West Suffolk provided the following information:
In Excel format:
National Heat Map (NHM) Data
Gas and electricity billing records for municipal buildings
Local Land and Property Gazetteer (LLPG).
ArcGIS Layers:
Background Mapping – Ordnance Survey MasterMaps,
Planning Application information
Forest Heath District Council Local Plan
Council owned land.
Links to the planning portal were also provided in addition to a number of general background
documents.
The following sections summarise the identified heat, cooling and power demands identified
within the study area.
Heat Network Opportunities
6
2.1 The Study Area
The study considers a 1 km “buffer area” around the Mildenhall Hub site. This was deemed by the
Forest Heath District Council and Ramboll to be an appropriate area to encompass major
opportunities.
Mildenhall Hub aims to concentrate public facilities in one location that are currently scattered
across the town and that are either reaching the end of their lives or are in need of
refurbishment. Converging public services buildings is intended to improve public access, service
delivery and efficiency.
The Mildenhall Hub project is currently under design with Mildenhall College Academy, Forest
Heath District Council, Anglia Community Leisure, Suffolk County Council, Suffolk Police and
Crime Commissioner/Suffolk Constabulary and West Suffolk Clinical Commissioning Group. Other
public services in town such as the library service, are considering taking part of Mildenhall Hub.
The Hub envisions a range of public services working collectively and collaboratively with
communities and sharing spaces.
Figure 3 shows the location of the Mildenhall Hub site and surrounding buffer area. The boundary
includes the town centre and the industrial estate to the north, in addition to potential areas of
new development to the south and east.
Figure 3: Mildenhall Hub Site and Study Area
Heat Network Opportunities
7
2.2 Heat Demand
A heat demand map was created to include existing and planned buildings within Mildenhall Hub
and the buffer area. The sub-sections below outline the methodology used to map the heat
demands for existing buildings, the Mildenhall Hub development and other planned
developments.
2.2.1 Methodology
Due to the fact that the NHM data is defined within these building type categories, multiple
records are often present for within the same building. For example where a shop and dwelling
are present in the same building two records are located in the same building.
Therefore, the information provided by the NHM was aggregated by location; aggregating the
multiple heat demands into a single point and assigning them the category with the highest heat
demand of the building.
It is important to note that the NHM data is likely to be overestimating the industrial heat loads.
This is due to the fact that the buildings often have large floor areas, but only localised heating
which is not reflected in the benchmarks. This is explored further in section 4.
Any records below 100,000 kWh were then filtered out of the heat map. A load below this
threshold would typically have a heat exchanger of the order of 50 kW, which is relatively small
and from experience on other projects loads smaller than this will not in themselves form the
basis for an energy network. These smaller loads could potentially be connected to a network
already under development and depending on the proximity of the network connection they may
serve to improve the project economics. However, designing networks specifically to serve these
loads may reduce the overall economic returns. These smaller connections should be considered
on a case by case basis in the next phase of works.
The Council also provided gas and electricity billing data from 2014/2015 for Local Authority
buildings in Bury St Edmunds, which was included in the heat map. When there were data points
from both the NHM and billing data, the NHM records were replaced.
The gas data was factored using an estimated boiler efficiency of 80%. The figures were degree
day corrected based on the region’s 20-year average in order to take account of annual weather
variations.
Figure 4: Screenshot of Local Authority Billing Data
Heat Network Opportunities
8
Following the inclusion of the billing data an exercise was carried out to estimate the heat
demand of existing buildings that appeared to be of interest, but were not included in the NHM or
billing data. Buildings which may present significant heat demands such as hotels and nursing
homes were identified through a desktop assessment of the study area maps. The heat demand
was estimated using the floor areas extracted from the OS maps and CIBSE benchmarks1.
Three benchmarking methods were applied to estimate the heat demand for the Mildenhall Hub
development:
CIBSE benchmarks for existing buildings were adjusted to take into account the
potential higher energy efficiency of new buildings.
A combination of energy modelling outputs (SAP, SBEM and IES-VE) from Ramboll’s
experience in energy strategies in addition to CIBSE data was used. This was corrected to
reflect expected improvements under future updates to the building regulations.
Benchmarks were formulated to reflect separately 2010 Building Regulations and the
2013 Building Regulations amendments.
The billing data for existing public buildings which are due to be moved to the new
site was assessed to give an indication of the likely requirements of the new buildings.
Reduction in demand due to the improved thermal efficiency of buildings was taken into
account during this exercise.
In a similar way to the proposed Mildenhall Hub buildings, heat demands for other planned
developments within the buffer area were calculated using benchmarks including a combination
of energy modelling outputs (SAP, SBEM and IES-VE) from Ramboll’s experience in energy
strategies in addition to CIBSE data which was corrected to reflect expected improvements under
future updates to the building regulations.
Building Type Energy Demand
(kWh/unit)
Units
Government Buildings 74 sqm
Police 157 sqm
Leisure Centre 141 sqm
Health 93 sqm
Library 60 sqm
Education - primary 60 sqm
Education - academy 58 sqm
Fire Department 206 sqm
Public access 104 sqm
Residential 5,840 House
Residential 3,760 Flat
Commercial Offices 12.3 Sqm
Table 2: Benchmarks Used for Mildenhall Hub and other New Development Sites
A full table of point heat demands is presented as Appendix 1. The sections below outline a
number of key heat load opportunities in further detail.
1 Energy Efficiency in Buildings. CIBSE Guide F
Heat Network Opportunities
9
2.2.2 Existing Buildings
2.2.2.1 Town Centre
The town centre has a mix of residential building with several small hotels, small shops and some
public buildings. In general terms, the heat loads in Mildenhall, especially in the town centre, are
small and many of them are estimated to be around 100 MWh.
Billing data was available for Mildenhall Swimming Pool, the Forest Heath District Council offices
and Mildenhall Depot. However, these services were intended for relocation to the Hub.
2.2.2.2 Industrial Estate
Based on NHM data, the industrial estate in the north of the town centre appeared to feature high
energy demands per building and a considerable number of buildings exceeding the 100 MWh
threshold.
In order to ascertain the buildings which were likely to have wet heating systems compatible with
DH, Ramboll undertook a visual analysis of the buildings in the area firstly using publicly available
tools such as Google Maps, Google Street View and Bing Maps. Following this a site visit was
undertaken to confirm the conclusions.
The majority of the buildings were observed to be warehouses with small retail frontages, offices
or workshops. It was also noted that the industrial estate was generally low in development
density.
Specific examples of businesses include:
Nestor UK Ltd – Pharmaceutical
Gerda – Manufacturer of fire safety and security products and services.
Electronic Metal Work Services – Manufacture of sheet metal components and assemblies,
powder coat or stove enamelling and silk screen printing,
Mildens Garage – Repairing and maintenance of cars and vans,
English Architectural Glazing – Design and manufacturing cladding packages,
JEB Engineering Design Limited – Provider of individual components through complex
assemblies,
Thoroughbred – Industrial doors,
Complete Office Solutions Ltd. – Office supplies and furniture.
Figure 5: Photograph from Mildenhall Industrial Estate (taken during Ramboll site visit)
Heat Network Opportunities
10
The analysis of the industrial estate also included identification of the buildings with stacks and,
therefore, the buildings that are likely to feature gas boilers. This assessment is associated with a
margin of error due to the fact that stacks may also be related to process or ventilation systems.
However, it was deemed to be an appropriate starting point for the heat demand assessment.
One particular building of interest within the industrial estate was Witton Chemical Company Ltd.
Their manufacturing site features a range of batch reactors, centrifuges, driers and storage
vessels that are used for the production of a range of chemical types. The heat demands for the
site are served by a steam based system due to the temperature requirements of the processes
undertaken.
It is important to note that, as described in the methodology in section 2.2.1, industrial loads
within the NHM are often found to be overestimated. Therefore as part of the Opportunity
Appraisal conducted in section 4, further investigation was required into the exact businesses
present and the likelihood of them presenting an opportunity for decentralised energy networks.
Heat Network Opportunities
11
2.2.3 New Development
2.2.3.1 Mildenhall Hub Site
Figure 6 shows the concept drawing provided by the Forest Heath District Council which gave an
indication of floor areas to enable the benchmarking process. This concept layout was based on
the 2014 business plan.
Figure 6: Concept Diagram for Mildenhall Hub
Category Floor Area
(m2)
Government buildings 3,096
Police 306
Leisure Centre 4,075
Health 409
Library 250
Education – primary school 170
Education - academy 0
Fire Department 234
Public access 360
Table 3: Expected Floor Areas for Mildenhall Hub (Autumn 2015)
The total annual heat demand for the site was estimated to be 1,818 MWh. A breakdown by
building function is presented in Table 7.
Following the heat mapping exercise and opportunity analysis (section 4), the concept
diagram was updated and new floor areas were provided in January 2015. This affected the
predicted heat loads.
The new heat demand estimates were not included in this heat mapping section as the
project had progressed to techno-economic modelling stage. However, a revision of the heat
demand was carried out in advance of the techno-economic modelling for preferred
opportunities. This is presented in section 5.1.2.
Heat Network Opportunities
12
2.2.3.2 Other Planned Developments
Forest Heath District Council Local Plan (FHDCLP) envisions for Mildenhall a town centre with a
broad range of retail and services and plans the allocation of new residential areas to meet the
needs of the local people. Two residential allocations are situated in the north-east limit of the
study area and the Town Centre area close to the Mildenhall Hub.
Figure 7 shows the principal allocations includes in the FHDCLP. The expansion of the industrial
area, recreational space and other community services are also shown.
Four planning applications were found to be of interest within the study area. At the time of
writing three of the applications had been granted whereas the Mildenhall Community Centre was
approved with conditions.
The table below shows the planning applications with significant/major developments that are
located in the Study Area buffer.
Table 4: Planning Applications Considered within the Heat Map
Information was gathered from the planning documents to establish dwelling numbers and floor
areas allocated to each use type within the developments as shown below:
Table 5: Summary of Key Figures of Planning Applications
The benchmarked heat demands are presented in Table 6 and Figure 7.
Table 6: Heat Demand for New Developments
Code Application number
Application Main characteristics
FHDCPA01 F/2012/0531/FUL Approved with conditions
Construction of a new community building (following demolition of existing community building) and erection of 20 dwellings (18 affordable and 2 market rented)
FHDCPA02 DC/14/2320/FUL Granted Erection of 9 No. dwellings and 1 No. B1 office unit
FHDCPA03 DC/13/0927/OUT Granted Residential development of up to 78 dwellings with creation of new vehicular access
FHDCPA04 DC/15/0452/FUL Granted Proposed conversion and alterations to the existing White Hart public House with new build construction to the rear to form 12N o. dwellings for affordable rent
Code Residential
Commercial Offices (m2) Community Centre (m2) No Houses No Flats
FHDCPA01 20 0 0 216
FHDCPA02 8 1 57.8 0
FHDCPA03 78 0 0 0
FHDCPA04 4 8 0 0
Code Residential Heat
(kWh) Commercial Offices
Heat (kWh)
Community Centre Heat
(kWh)
Total Heat (kWh)
FHDCPA01 116,800 0 2,657 119,457
FHDCPA02 50,480 711 0 51,191
FHDCPA03 455,520 0 0 455,520
FHDCPA04 48,404 0 0 48,404
Heat Network Opportunities
13
Figure 7: Estimated Heat Demand for Planned Developments
Heat Network Opportunities
14
In addition to the Local Plan and Planning Application information, the RAF Mildenhall site was
also considered to be of interest. The RAF currently operates a station located outside of the
study area to the north. In January 2016 it was announced that operations at RAF Mildenhall
would cease and the site would become available for other uses. It is expected that all military
personnel will have left the site by 2022.
Suggestions have been made for 4,000 new homes and 100,000 m2 of employment land at the
site, which would present a significant opportunity for decentralised energy networks. Although
the project was at too early a stage to consider as part of this report, it is important to note the
plans in the event that it presents an opportunity in future.
2.2.4 Heat Demand Summary
Figure 10 shows the point load heat map for the Mildenhall Hub and surrounding study area. This
includes both existing buildings and heats loads estimated for Mildenhall Hub and the new
development areas.
The mapped heat demand data is presented below in Table 7, Figure 7 and Figure 8.
Building Type Number of Buildings
Sum of Heat Demand (kWh)
Mildenhall Hub
Government Buildings 1 269,700
Recreational 1 679,100
Health 1 449,200
Education 1 12,100
Fire Station 1 56,900
Central Hub 1 44,000
Education (Sixth Form
College) 1 306,700
Rest of Study Area
Commercial Offices 3 1,362,000
Education 3 254,700
Government Buildings 6 926,500
Health 3 32,100
Hotels 7 209,100
Industrial 54 13,296,900
Recreational 1 13,700
Residential 2 27,900
Retail 5 631,500
Transport 11 3,589,300
Planning Applications 4 540,600
TOTAL 108 22,700,000
Table 7: Mildenhall Heat Demand summary
Heat Network Opportunities
15
Figure 8: Estimated Heat Demands for Mildenhall Hub
Figure 9: Estimated Heat Demands within the Study Area
It is again important to note that the NHM data is likely to be overestimating the industrial heat
loads and therefore they were revised at opportunity identifications stage.
Heat Network Opportunities
16
Figure 10: Mildenhall Heat Demand
Heat Network Opportunities
17
2.3 Cooling Demand
A cooling demand map was created including existing buildings, the Hub site and other planned
developments for the purpose of identifying the potential for combined heat and cooling
networks.
2.3.1 Methodology
The potential cooling demands of existing buildings was estimated by applying CIBSE cooling
benchmarks to floor areas extracted from the OS map data.
It is important to note that at this stage of energy assessment the cooling map shows the
potential demands based on building type. The existing cooling technology within the buildings is
not taken into consideration, but should be investigated as part of the next project stage.
The buildings located in the light-industrial area north of the town centre were also included in
the cooling benchmarking although only those considered offices were gauged. No other cooling
demands were identified in the area where warehouses and workshops are the most predominant
building types. The benchmarks for these offices are probably overestimated since it is unlikely
that the whole building area is potentially cooled.
The cooling demands of the buildings planned in Mildenhall Hub were estimated by applying
cooling benchmarks to the quoted floor areas as established in the business case. The cooling
benchmarks for new buildings include internal modelling (SAP, SBEM, and IES) and corrected
CIBSE data to reflect expected improvements of the updates to the building regulations.
Cooling demand was estimated for the planned developments identified in section 2.2.3.2. The
calculation methodology was similar to that used for the proposed buildings within the Mildenhall
Hub development, using benchmarks based on floor area, internal modelling and adjusted CIBSE
data. Since it is estimated that residential buildings do not have cooling demands, the new
developments, which are mainly residential developments, do not present cooling demand.
2.3.2 Cooling Demand Summary
Figure 11 shows the mapped cooling demands for Mildenhall Hub and the surrounding study
area.
The summary of the estimated cooling demands for the Mildenhall Hub and, other proposed and
existing buildings within the study area are as follows:
Building Type Number of
Buildings
Sum of Cooling Demand
(kWh)
Government buildings 5 211,133.6
Commercial Offices 35 461,138.6
Mildenhall Hub
Government Buildings 1 4,613
Public Access 1 11,160
TOTAL 3,101,115
Table 8: Mildenhall Cooling Demand
Heat Network Opportunities
18
Figure 11: Estimated Cooling Demand of Mildenhall Study Area
Heat Network Opportunities
19
2.4 Power Demand
The power demand was considered due to the fact that the site electricity requirement is relevant
to certain low carbon technologies such as CHP, where there is potential for electricity to be
privately wired to buildings.
Private wiring involves the distribution of decentralised generated power to one or a number of
consumers via a privately owned distribution network. Distribution of power via a private wire
does not utilise infrastructure owned by National Grid or distribution network operators (DNOs).
For low voltage power generated by a CHP the electricity demand must be suitably close or the
network losses become significant. This is due to the fact that the conductor (network) losses
which arise from distribution of power are proportional to current and length of the network; for a
fixed voltage, line resistance and therefore conductor losses increase with distance.
Conductor losses can be reduced by decreasing the current. This can be achieved by increasing
the distribution voltage using a step-up transformer or a high voltage generator. However, the
additional capital cost associated with both of these approaches would normally be inhibiting for
small-scale CHP. As a result of this, throughout the analysis it was noted that private wire supply
would only be viable in the immediate vicinity of supply assets.
2.4.1 Methodology
The electricity demand for each building within the hub was estimated using a combination of
Ramboll’s in-house modelling results and CIBSE benchmarks2.
For new developments, in a similar way to the heat demand estimates, when using CIBSE
benchmarks, the electricity was factored down by 35 % to account for improvements to building
standards. This figure was approximated through energy modelling in previous buildings projects.
2.4.2 Existing Buildings
Only the buildings that were taken into account in the heat demand mapping previously (heat
demands higher than 100 MWh) were benchmarked and had their electricity demand estimated.
The higher electricity demands correspond to retail buildings mostly located in the town centre
and near to the Mildenhall Hub site. A summary of the power demands excluding the new
buildings in the Hub within the study area is presented in Table 9.
Building Number of
Buildings
Annual Power
Demand (kWh)
Commercial Offices 35 2,082,190
Government Buildings 6 572,100
Health 11 269,700
Hotels 20 730,250
Industrial 18 1,236,390
Nursing homes 2 104,590
Retail 115 15,394,200
Table 9: Summary of Existing Power Demands
2 Energy Efficiency in Buildings. CIBSE Guide F
Heat Network Opportunities
20
2.4.3 Mildenhall Hub
The estimated power demand for the new Mildenhall Hub site is presented in Table 10.
Building Annual Power Demand
(kWh)
Government buildings 36,117.63
Police 10,465.00
Recreational3 270,136.60
Health 18,154.50
Education 548,476.50
Central Hub 47,624.13
Commercial Offices 930,974.35
Table 10: Estimated Annual Power Demand for the Mildenhall Hub
It should be noted that the mapped demand points are shown further apart than the buildings in
the massing concept diagram in order to make them clearer.
Figure 12: Mildenhall Hub Estimated Electricity Demand
2.4.4 Electricity Demand Summary
Figure 13 shows a map of the estimated annual electricity demands within the study area.
3 Includes library and leisure
Heat Network Opportunities
21
Figure 13: Mildenhall Hub Power Demand Estimate
Heat Network Opportunities
22
3. ENERGY SUPPLY OPPORTUNITIES
This section presents the assessment of potential energy supply assets in the study area. The
magnitude of heat and/or electricity available in combination with the location of the supply is
taken into account in the assessment of potential DH opportunities.
The supply assets were considered in three categories:
Existing – operational supply assets
Future - planned supply assets
Potential – opportunities for the creation of new supply assets specifically to supply a
decentralised energy network
A heat supply opportunity database was created which contains information about existing and
future heat supply assets which could potentially feed district heating networks within the study
area. Each supply asset was identified through the use of one or more of the following resources
as part of Ramboll’s desktop research:
DECC High Level Water Source Heat Map
National Heat Map
OFGEM accredited Renewable Obligation sites
DECC CHP development map
WRAP database for ERF’s
Biomass energy centre website
DECC Restats website
Environment Agency website
ADE database of District Heating Installations
Visual Inspection of the area on Bing and Google maps
Reports from previous studies undertaken
Local planning applications
BGS Geothermal mapping
Potential energy supplies were considered through a technology options appraisal, which is
outlined in section 3.3.
3.1 Existing Supply Assets
The investigation into existing supply assets was carried out predominantly using the DECC public
energy supply database and CHP Focus database. The data was filtered to show all installations
within West Suffolk.
In particular, the assets that were of interest would be existing CHP or biomass installations with
the potential for exporting heat. Additionally the presence of water treatment works or landfill
sites may provide opportunities.
Heat Network Opportunities
23
Figure 14: Screenshot from DECC Public Database
The assessment showed that no existing supply assets are situated within the Mildenhall Hub
study area. Therefore any decentralised energy networks would have to be supplied by future
installations or purpose-built supply assets.
3.2 Future Supply Assets
Through a review of the available data sources and an assessment of planning applications it
became apparent that there are no planned energy supply assets within the study area.
Correspondence with Forest Heath District Council confirmed that there were no available
opportunities at present. Therefore focus was placed on the potential for creation of new supply
assets.
3.3 Potential Supply Assets
This section presents the results of a review of the potential supply technologies that could feed
heat, coolth and or power into the district energy networks. Appropriate technologies have been
identified on the basis of the presence of a suitable resource or clear suitability of a site to a
particular technology.
A full qualitative technology options appraisal was conducted and is presented as a table in
Appendix 2. The list of criteria included in the appraisal included, but was not limited to:
Fuel source and fuel risk
Security of supply
Site requirements
Technology and planning risks
CO2 reduction potential
Transportation
Environmental impacts
Timeframe for delivery
Capital and operational costs
Revenue potential
Overall financial performance and funding opportunities.
Based on the assessment of each of these criteria for a number of supply technologies, a
conclusion was drawn regarding whether the technology should be considered as part of the
opportunity appraisal. A summary of the findings of this assessment is shown in Table 11 below.
Heat Network Opportunities
24
Technology CO2 Abatement Potential Revenue Potential General
Consider in
Opportunity
Appraisal?
Gas Combined Heat and
Power Plant
Medium as part of technology mix if operating on
Natural Gas.
Heat and power sales Low risk, well proven technology at the scale of
the project. Reasonable financial performance
expected.
Yes
Dual fuel boiler Low Heat sales only Low risk and low cost, but low carbon reduction
potential.
No
Biomass heating High on individual technology basis. Medium as
part of technology mix.
Heat sales and RHI Reasonable financial performance expected.
Low risk technology as long as fuel supply is
secured.
Yes
Biomass CHP Steam
cycle
High Heat and power sales and RHI Not considered commercially viable at this
scale.
No
Organic Rankine Cycle High Heat and power sales and RHI Marginal financial performance at this scale. No
Gasification CHP High Heat and power sales and RHI Technology not established at this scale. No
Anaerobic Digestion
with CHP
High on individual technology basis. Medium as
part of technology mix.
FiT(<5MW), RHI, heat and power
sales
Unlikely to be commercially viable at this scale. No
Waste Incineration CHP High Heat and power sales and RHI Not an appropriate scale for the site. No
Bio liquid CHP High on individual technology basis. Medium as
part of technology mix.
Heat and power sales High fuel prices reduce economic viability. No
Absorption chiller Carbon emissions savings are sensitive depending
on the fuel source of the heat production
Coolth sales Requires low cost heat to be financially viable. Yes
Solar Thermal Panels High Heat sales and RHI Reasonable payback expected. Large area
required.
Yes
Ground Source Heat
Pump/Heat Store
Medium - as part of site wide heat network Heat sales and RHI Reasonable payback expected but can only
deliver low grade heat.
Yes
Water source heat
pumps
Medium - as part of site wide heat network Heat sales and RHI Reasonable paybacks expected. Nearby source
has been identified.
Yes
Air source heat pumps Medium - as part of site wide heat network Heat sales and RHI Poor payback expected. No
Industrial heat recovery Medium to high - as part of site wide heat network Heat sales and RHI Good payback if suitable source identified. Yes
Deep geo borehole Medium Heat and power sales and RHI Not suitable at this scale. No
Table 11: Extract from Technology Options Appraisal
Heat Network Opportunities
25
3.3.1 Gas CHP
Gas engine CHP was considered as a lower carbon heat. CHP engines use natural gas from the
gas network to generate electricity and make use of the remaining thermal energy that would
otherwise be wasted. This technology can potentially reduce a building’s carbon footprint
resulting from energy use when compared to importing electricity from the grid and generating
heat in fossil fuel fired boilers.
The heat output from a CHP could be used to supply the Mildenhall Hub or DHN in addition to the
electricity output could be sold to the grid or retailed through a bilateral contract.
CHP engines are available to suit a wide range of heat and electricity demands and can be
installed on a modular basis to match the phased development of a heat network.
3.3.2 Biomass
Biomass fuel, supplied in the form of wood chip or pellets, may be a suitable fuel to generate
heat and power at the site. Biomass boilers are becoming increasingly popular in the UK due to
their strong green credentials, the simplicity of the technology and the relatively cheap fuel costs.
Renewable biomass fuels are produced from sustainably grown trees that are cut down and
processed into either chip or pellet form.
The size of boiler selected for the scheme is affected by two main factors:
the base load heat demand of the network
the optimisation of revenue through the Renewable Heat Incentive (RHI) scheme
Consideration of thermal store / buffer vessel size should also be included when sizing biomass
boilers.
The current levels of non-domestic RHI for biomass installations with an accreditation date on or
after 1st January 2016 are shown in Table 12. Please note these figures are revised by the
Government regularly and current trends suggest these could be reduced.
Installation Type Applicable Size Tier RHI Support
(p/kWh)
Small commercial
biomass Less than 200 kWth
1 3.76
2 1.00
Medium commercial
biomass
≥200 kWth
<1 MWth
1 5.18
2 2.24
Large commercial
biomass ≥1 MWth NA 2.03
Table 12: RHI Support for Biomass
For commercial biomass systems with a capacity below 1 MWth, the RHI is awarded in two tiers.
Tier one applies to the useful heat output supplied to a qualifying demand up to that which is
equivalent to the biomass boiler running at full load for 1314 hours. Tier two applies for any heat
output that is supplied to a qualifying demand above that equivalent to 1314 full-load running
hours
The logistics of supply and storage of the biomass fuel are an important consideration when
determining viability technology. Biomass fuel is normally delivered by trucks. This will impact on
transport planning issues as well as limit the distance from which biomass fuel can economically
Heat Network Opportunities
26
and sustainably be supplied. Research into available biomass supplies surrounding Mildenhall
should be carried out at feasibility stage.
Sufficient secure storage space is required at sites using biomass boilers. Sizing of fuel stores
needs to take into consideration economies of scale and security of supply, land take and
planning limitations. In addition, the energy density of different biomass fuels will impact the fuel
store size requirement. To put this in context, biomass pellets have a higher energy density and
are easier to handle than wood chips. This means that the fuel store size requirement and
associated capital cost is lower but this can be offset by the significantly high fuel purchase price.
These issues must be considered in greater detail at feasibility stage.
Air quality management areas (AQMAs) can present a barrier to the implementation of biomass if
restrictions to emissions are in place. However, an assessment of the study area using the DEFRA
AQMA database4 has shown the site does not fall into an AQMA. Forest Heath District Council has
confirmed this.
3.3.3 Absorption Chillers
Absorption chillers produce coolth by using high temperature water or steam to raise the
temperature of a cooling circuit for heat rejection and lower the temperature of a chilled water
circuit used for cooling.
Several factors must be taken into account when considering this technology:
Presence of a suitable heat source – coefficient of performance (CoP) for absorption
chillers decreases with lower heat source temperature
Nature of the load –A reasonably stable base load is required as absorption chillers
are not suited to modulation
Availability space – Absorption chillers are large
Safety of refrigerant – Some absorption chillers use ammonia which will have
stringent health and safety requirements
3.3.4 Solar Thermal Panels
Solar thermal panels present the opportunity to significantly reduce carbon emissions. Typically a
solar thermal system would be sized to supply only the hot water demand and therefore must be
implemented as part of a mix of technologies.
Solar thermal panels require a significant amount of space unaffected by shading from nearby
buildings. Consideration must be given to issues relating to visual pollution and planning
restrictions.
Payback times are expected to be reasonable due to the revenues available through government
funding. The technology is currently eligible to receive RHI funding at a rate of 10.16 p/kWh for
collectors with an installed capacity of less than 200 kWth. This translates into a collector size of
up to 282 m2 [5].
4 http://uk-air.defra.gov.uk/aqma/local-authorities?la_id=105 5 International Energy Agency’s Solar Heating and Cooling Programme (IEA SHC)
Heat Network Opportunities
27
3.3.5 Industrial Heat Recovery Using Heat Pumps
The Environment Agency interactive air pollution map6 was used to identify buildings with
particularly high emissions which might indicate the presence of a stack with the potential for
heat recovery. For the Mildenhall area the Witton Chemical Plant was identified as shown by the
red circle in Figure 15.
Figure 15: Environment Agency Air Pollution Map of Mildenhall
Ramboll conducted a site visit to Mildenhall in November 2015 to assess the opportunities for
industrial waste heat recovery in further detail. It was found that the stack at the plant was too
small to present any opportunity. Furthermore, it is know that the site specialises in small batch
production runs. The batch nature of the processes means that there is no opportunity here to
implement a heat recovery asset that can provide a stable heat supplier to any potential DHN. No
further sources of waste heat were identified and therefore this supply opportunity was excluded
from the study.
3.3.6 Water Source Heat Pumps
The River Lark flows to the south of the Mildenhall Hub site. The National Heat Map was used to
assess the heat capacity of the river. The map shows a capacity between 950 kW and 2,400 kW
6 http://maps.environment-agency.gov.uk/wiyby/wiybyController?x=357683.0&y=355134.0&scale=1&layerGroups=default&
ep=map&textonly=off&lang=_e&topic=airpollution
Heat Network Opportunities
28
Figure 16: River Lark Heat Capacity (courtesy of DECC National Heat Map)
In order to fully quantify the heat resource for a project, information on river depths and flow
rates are required. This should be progressed during a subsequent feasibility phase should
WSHPs be deemed a viable opportunity.
The current levels of non-domestic RHI for WSHP installations with an accreditation date on or
after 1st January 2016 are 8.84 p/kWh at Tier 1 (up to 1,314 run hours) and 2.64 p/kWh for Tier
2.
3.3.7 Energy Centre Options
An investigation was carried out into the areas in which to locate potential new energy centres.
Focus was placed primarily on Council owned land and that of major stakeholders. Figure 17
indicates council owned land within Mildenhall and shows two locations considered within the
industrial estate which include:
Mildenhall Depot in Holborn Ave, which features a large parking area which may be
suitable for an Energy Centre for a potential network in the industrial area (1)
The area next to St Johns Close Post Office, which is Council Owned and part of a
redevelopment area (planning application F/2012/0531/FUL) where there is a Community
Centre planned among other buildings (2).
It should be noted that the economic performance of WSHPs and biomass boilers are heavily
dependent on support from the Renewable Heat Incentive (RHI). The level of support
available for these technologies may be subject to change to future government spending
reviews. This is a risk for project development as if there is a cut in support the projects may
no longer achieve the economic results presented here.
Heat Network Opportunities
29
Location Ownership Space Availability
Access for construction and maintenance
Proximity to energy demand
AQMA restrictions
Mildenhall Hub Site
Forest Heath District Council
High Good access from Queensway
Central to new development heat demand
None
Industrial Area Council Owned Land
Forest Heath District Council
Medium Access from industrial estate
Within industrial estate, but low heat demand density.
None
Table 13: Energy Centre Locations Appraisal
Heat Network Opportunities
30
Figure 17: Council Owned Land in Mildenhall
Heat Network Opportunities
31
4. HEAT NETWORK OPPORTUNITY APPRAISAL
This section presents a series of opportunities for heat networks and decentralised energy which
were identified using the energy maps created in section 2.
Potential opportunities were identified taking into account, but not limited to, the following
criteria:
energy demand density
proximity to identified supply assets
number of public buildings
potential anchor loads
barriers to construction
4.1 Identification of Opportunity Areas
Energy demand density is a key criterion in the validity of heat networks and decentralised
energy supply. For this reason it was the first stage in identifying opportunities.
The following sub-sections present the observation of energy demand clusters and assess their
feasibility at a high level in terms of the other criteria listed above.
4.1.1 Heat
Three areas of high heat demand density were identified on the Mildenhall Heat Demand Map
including the Mildenhall Hub site, Mildenhall Industrial Estate and the Town Centre.
All three of these potential opportunity areas of high heat demand density were assessed during
a site visit carried out in November 2015.
The heat loads in the Town Centre were found to be small pubs and shops which were not
deemed to be appropriate for connection to a heat network. This was due to the fact that the cost
of network construction in urban areas is high and it is highly unlikely that the heat loads would
be sufficient to yield high enough heat sale revenues to pay back the cost. In addition the cost of
retrofitting and connecting existing buildings would present a barrier.
Figure 18: Image of Mildenhall High Street (courtesy of Google Maps)
As stated in section 2.2.2.2, NHM data typically overestimates light industrial heat demands and
observations made during Ramboll’s site visit to the light industrial area confirmed that this
was likely to be the case. However, a number of buildings were seen to have flues indicating the
Heat Network Opportunities
32
presence of boilers and thus wet heating systems. These buildings were deemed appropriate to
include within a heat network opportunity, but a re-assessment of the estimated heat demand
was conducted. The heat loads were reduced by 20%-70% depending on the number of buildings
connected to the network. This exercise was based on Ramboll’s experience of actual data from
previous projects.
The light industrial area is entirely privately owned and therefore consumer uptake and the
choice of delivery vehicle would present an additional challenge to the project. Furthermore,
since the buildings are privately owned by a wide range of organisations it is likely to be difficult
to establish a commercial arrangement. Potential consumers would have to be strongly
incentivised to connect through the use of low heat prices against the business as usual case.
Figure 19: Image of the light-industrial area (taken by Ramboll during a site visit).
The Mildenhall Hub is comprised of exclusively public building uses and therefore Forest Heath
District Council is likely to be able to drive a low carbon project forward successfully.
Within the Mildenhall Hub, the proposed leisure facility would act as an anchor load due to the
relatively constant heat demand required to heat the pool and changing areas.
It was concluded that heat networks should be considered separately in the two locations
(Mildenhall Hub and the industrial area) with a view to connecting them either from the outset or
at a later phase.
As no existing supply assets were identified in either of these areas, purpose-built energy supply
facilities would be considered. The most appropriate location would sit within the Mildenhall Hub
as it is understood that the project is at a sufficiently early stage of development to incorporate
an energy centre into the design.
Heat Network Opportunities
33
4.2 Heat Network Routing Strategy
Once opportunities were identified, possible heat network routes were assessed. Networks were
routed through council owned green spaces, car parks and other available open areas wherever
possible. Where this was not possible the network was routed along public roadways.
Forest Heath District Council provided GIS layers containing information regarding the constraints
that needed to be taken into account and where possible avoided while developing potential
network routes. This GIS data included information on:
Conservation Areas,
Protected Areas (including Local Nature Reserves, Archaeological Sites, and Sites of Special
Scientific Interest amongst others)
Councils owned land
Planning applications.
Other constraints and opportunities such as railway networks and the existence of underpasses
on the routes were also considered in order to minimise cost and inconvenience. These barriers
and opportunities were assessed as part of a desktop study using resources such as Google Maps
and Bing Maps.
The diagram in Figure 20 presents a selection of locations observed during the site walkover.
Brief descriptions are included below.
Figure 20: Extracts from Network Route Analysis
Heat Network Opportunities
34
1. Queensway – This is the main route for traffic across the Town. Traffic management would be
a consideration should heat network infrastructure be constructed here.
2. Riverbank – Only one barrier appeared to be present on the route from the River to the
Mildenhall Hub, which was a public footpath. The route would be largely soft dig which results
in lower capital expenditure.
3. South of Hub – As above, to the south of the Hub site the only major consideration is the
public footpath.
4. Church Walk – This is the main pedestrian route from the Mildenhall Hub site to the town
centre.
5. A1101 – This is the main road running through Mildenhall and provides the primary link
between the town centre and industrial estate. Traffic management would be a consideration
should heat network infrastructure be constructed here.
6. Mildenhall Industrial Estate – This primarily privately owned and therefore agreements with
landowners would be necessary in order to deploy heat networks. In addition, traffic
management would be necessary should heat network infrastructure be constructed here.
Heat Network Opportunities
35
4.3 List of Identified Opportunities
Table 14 lists the eight opportunities identified and considered for initial assessment.
MH001 to MH005 consider the Mildenhall Hub development only, with a series of supply options.
MH006 to MH007 consider the industrial area opportunity and MH008 to MH009 assesses a
connection between the two areas.
Project Ref. Project Name Description
MH001 Mildenhall Hub Gas CHP Mildenhall Hub heat loads only supplied by
natural gas CHP. Potential for private wiring
of electricity.
MH002 Mildenhall Hub Biomass As MH001 with a heat-only biomass boiler.
MH003 Mildenhall Hub WSHP As MH001 with a water source heat pump.
MH004 Mildenhall Hub Solar Thermal As MH001 with solar thermal panels.
MH005 Mildenhall Hub GSHP As MH001 with a ground source heat pump.
MH006 Mildenhall Industrial Area CHP The light industrial area heat loads supplied
by a CHP engine.
MH007 Mildenhall Industrial Area Gas
Biomass
The light industrial area heat loads supplied
by a heat-only biomass boiler.
MH008 Mildenhall Hub + Industrial
Area
The Mildenhall Hub and light industrial area
connected and supplied by a single CHP
energy centre.
MH009 Mildenhall Hub + Industrial
Area
The Mildenhall Hub and light industrial area
connected and supplied by biomass boilers
in a single energy centre.
Table 14: List of Identified Opportunities
Heat Network Opportunities
36
4.4 Opportunity Appraisal
The following sub-sections present each of the nine opportunities in further detail and show
estimated key metrics for each proposed scheme. Comparison of these metrics enables the
prioritisation of opportunities for progression to masterplanning stage and more detailed analysis.
The opportunity appraisal was intended to narrow down the list of opportunities to the
most viable options to take forward to techno-economic feasibility through a high level
assessment of likely energy flows and costs. It is not intended to comprise a techno-
economic analysis in itself.
Table 15 presents assumptions made as part of the modelling process that were common to each
opportunity.
Variable Assumption
Heat Sale Prices In each case the heat sale price for public buildings was based on
WSC’s current gas costs7 and an assumed boiler efficiency of 80%. The
value used was 5.26p/kWh which encompasses both the unit rate and
standing charge.
Electricity Sale Prices Were calculated depending on the assumed availability of private wire
vs. grid sales. Private wire price was set at Forest Heath District
Council’s avoided electricity cost of 12 p/kWh. Grid sale was set at 4.5
p/kWh.
RHI Revenue The RHI does not account for degression over the project lifetime at
opportunity modelling stage and is therefore considered to be a best
case scenario. RHI is in accordance with 2016 tariffs8.
CAPEX Capital expenditure was based on Ramboll’s supplier database which
encompasses values from previous project experience.
Cost of Gas The cost of gas figures for the CHP cases and for the top up boilers
were taken from DECC’s most recently published energy price figures9.
At this stage energy price inflation was not taken into account.
7 Applying an assumed gas boiler efficiency of 80%. 8 Ofgem, “Tariffs that apply for Non-Domestic RHI for Great Britain”, https://www.ofgem.gov.uk/environmental-programmes/non-
domestic-renewable-heat-incentive-rhi/tariffs-apply-non-domestic-rhi-great-britain
It is important to note that the high level opportunity appraisal does not take project
phasing into account.
All heat loads connections and capital expenditures are assumed to take place in project
year 1. This is due to the fact that the opportunity appraisal is intended as an initial
screening process.
The preferred option(s) taken forward to full techno-economic analysis in section 5 will
include detailed phasing assumptions where relevant.
Heat Network Opportunities
37
OPEX Operational costs were based on Ramboll’s supplier database which
encompasses values from previous project experience.
REPEX A value of 25 % every 20 years was assumed for gas boilers and a
value of 20 % every 25 years for thermal storage. Reinvestment costs
for primary supply technologies are stated within the sections below.
Carbon Factors The carbon savings were calculated using DECC’s most recent
emissions factors10. At opportunity mapping level the predicted changes
to electricity emissions over time was not taken into account and 2016
values were used. At masterplanning level in section 5 the emissions
are modelled in further detail.
Thermal Storage Thermal store sizes are based on an equivalent of 2.5 hours of the full
output of the primary supply technology.
Table 15: Common Assumptions for Opportunity Models
The cost of carbon abatement is calculated as the total capital expenditure (CAPEX) divided by
the estimated tonnes of CO2 saved over the project lifetime.
In each case a single energy centre location is assumed. A multi-energy centre option was not
explored primarily because the scheme is not big enough to justify it. There would be minimal
operational benefit and the capital and O&M costs to the project would be higher.
The following sub-sections present the results of the opportunity appraisal. Again it is
emphasised that this exercise was not intended to comprise a techno-economic analysis in itself;
it was a high level assessment to narrow down the number of scenarios to be taken forward to
full masterplanning and techno-economic analysis.
9 DECC, “Gas and electricity prices in the non-domestic sector”, https://www.gov.uk/government/statistical-data-sets/gas-and-
electricity-prices-in-the-non-domestic-sector 10 Table 1 and Table 2a. https://www.gov.uk/government/publications/valuation-of-energy-use-and-greenhouse-gas-emissions-for-
appraisal
Heat Network Opportunities
38
4.4.1 Mildenhall Hub
This opportunity includes the energy loads
within the Mildenhall Hub development only.
This includes the Mildenhall Academy 6th form
that exists on the site.
As each “building” proposed is connected by a
central hub, it is assumed that there will be a
centrally located energy centre and the heat
distribution system will form part of the
building design. Therefore no heat network
pipe costs were considered. However, it should
be noted that the type of primary supply
technology will affect the required energy
centre size. The implications of this are
considered in section 5.
Figure 21: MH001 Opportunity Boundary
Thermal storage is proposed to optimise the outputs of the primary supply technologies. Storage
was initially sized to equate to 2.5 hours of output equivalent to the capacity of the primary
supply asset. For example the thermal store associated with a 300 kW biomass boiler would be
750 kWh.
In the CHP case, it was assumed that 75% of the electricity generated by the CHP could be
private wired to the Mildenhall Hub. This assumption was based on the expectation that the heat
and electricity demands are likely to be of similar orders of magnitude and also due to the fact
that the student accommodation should provide a suitably diverse demand profile. The
assumption was explored in further detail at detailed techno-economic modelling stage.
Table 16 shows the key metrics for this opportunity.
Network Reference MH001 MH002 MH003 MH004 MH005
Primary heat supply
technology Gas CHP Biomass WSHP Solar GSHP
Supply Asset Capacity 200 kWe 350 kWth 300 kWth 200 kWth 175 kWth
Total Network length 0 m 0 m 442 m 296 m 100 m
Total project CAPEX £0.6 M £0.5 M £1.0 M £792k £0.7 M
Annual Operating
Costs (incl. Fuel) £105 k £55 k £37 k £48.5k £55 K
Annual revenue from
heat sales £111 K £100 K £100 k £92 k £92 K
Annual revenue from
electricity sales £121 K NA NA NA NA
Annual revenue from
RHI NA £39 K £61 k £49 K £23 K
Annual CO2 Savings 125 tonnes 400 tonnes 240 tonnes 130 tonnes 120 tonnes
Estimated Non-
Discounted IRR 15% 9% 6% 9% 7%
Table 16: Key Metrics for Opportunity MH001 to MH005
Heat Network Opportunities
39
4.4.2 Northern Light Industrial Area
This scenario encompasses the industrial area in the north, connecting mainly industrial buildings
but also the Great Heath Primary School, the Mildenhall Lodge Care Home and some Commercial
Offices and Retail buildings, providing some variability to the heat demand in the area.
Only the most potentially likely industrial buildings to have a potentially sufficient heat demand
are connected to this network. In order to establish which buildings were most likely to connect,
an assessment of the existing stacks was conducted as described in section 2.2.2.2. Once
connections were identified, a review of the heat loads was conducted to refine the NHM data.
This resulted in a reduction of the total heat demand when compared to the figures presented in
section 2.2.
The opportunity for combined heat and cooling was considered in this case as the energy
mapping exercise showed this area to present a possible cluster of cooling load. However, upon
further investigation no building use types were identified that are deemed to have sufficient
cooling load to justify a establishing a district cooling network.
A number of industrial buildings were selected to connect to the DHN along with other relevant
assets. These other assets comprise a potential new development that includes a new community
centre and 20 new dwellings with a total annual heat demand around 7,570 MWh.
It is unlikely that any private wire opportunities would be possible to private organisations due to
the complexity of the commercial arrangements and high capital cost in comparison to the
available revenue. Therefore all electricity is assumed to be sold to the grid.
Figure 22: MH007 Industrial Area Opportunity
Heat Network Opportunities
40
The opportunity modelling results are shown in Table 17.
Network Reference MH006 MH007
Primary heat supply technology Gas CHP Biomass
Supply Asset Capacity 400 kWe 750 kWth
Total Network length 3,255 m 3,255 m
Total project CAPEX £4.3 M £4.1 M
Annual Operating Costs (incl. Fuel) £227 K £104 K
Annual revenue from heat sales £160 K £160 K
Annual revenue from electricity sales £99 K NA
Annual revenue from RHI NA £83 K
Annual CO2 Savings 100 tonnes 600 tonnes
Estimated Non-Discounted IRR NA -9%
Table 17: Key Metrics for Opportunity MH006 to MH007
Heat Network Opportunities
41
4.4.3 Mildenhall Hub with Extension to Light Industrial Area
This scenario considers a heat network connecting the Northern Industrial Area and Mildenhall
Hub. The total annual heat demand is estimated to be 8,570 MWh.
The chosen technology to assess this opportunity was a biomass fired boiler due to the fact that
for the Hub-only scheme it showed a combination of reasonable rates of return and a relatively
low cost of carbon abatement. If this opportunity was found to be viable, alternative supply
opportunities would be investigated at the Masterplanning stage.
It was assumed that the CHP could supply 80% of the Mildenhall Hub’s electricity, but that the
remainder would be sold to the grid.
This option uses a 1.5MW biomass boiler with a thermal store. Peaking and backup heat supply
would be provided by natural gas boilers.
Figure 23: MH008 Opportunity Area
Network Reference MH008 MH009
Primary heat supply technology Gas CHP Biomass
Supply Asset Capacity 750 kWe 999 kWth
Total Network length 4,700 m 4,700 m
Total project CAPEX £5.9 M £5.4 M
Annual Operating Costs (incl. Fuel) £389 K £165 K
Annual revenue from heat sales £256 K £256 K
Annual revenue from electricity sales £263 K NA
Annual revenue from RHI NA £110 K
Annual CO2 Savings 80 tonnes 800 tonnes
Estimated Non-Discounted IRR NA -6%
Table 18: Key Metrics for Opportunity MH008 to MH009
Heat Network Opportunities
42
4.4.4 Summary
Table 19 below shows a summary of the key indicators of the eight opportunities for the
Mildenhall study area that have been assessed during the options appraisal. The simple payback
field is highlighted to indicate the opportunities expected to generate positive rates of return.
As stated previously, it should be emphasised that this summary of opportunities is intended to
narrow down a high number of opportunities and is therefore presented at high level only.
Section 5 presents a full techno-economic analysis.
Opportunity CAPEX Annual O&M
Costs
Annual
Revenue
Estimated
IRR
Net Impact
on Carbon
Emissions
MH001 £0.6 M £105 K 232 K 15% 125 tCO2e/yr
MH002 £0.5 M £55 K 139 K 9% 400 tCO2e/yr
MH003 £1.0 M £37 K 161 K 6% 240 tCO2e/yr
MH004 £0.8 M £49 K 141 K 9% 130 tCO2e/yr
MH005 £0.7 M £55 K 115 K 7% 120 tCO2e/yr
MH006 £4.3 M £227 K £259 K NA 100 tCO2e/yr
MH007 £4.1 M £104 K £243 K -9% 600 tCO2e/yr
MH008 £5.9 M £389 K £519 K NA 80 tCO2e/yr
MH009 £5.4 M £165 K £366 K -6% 800 tCO2e/yr
Table 19: Options Appraisal Summary
Five options were found to be likely to generate a positive return on investment and these were
taken forward for a more detailed energy economic assessment the next project phase. The
supply technologies in these cases were:
biomass
gas CHP
WSHP
GSHP
solar thermal
The standalone network in the light industrial area to the North was not found to be viable. This
was predominantly due to the low heat demand density.
The connection of the Mildenhall Hub to the Northern light industrial area via a DH network was
deemed to be unfeasible. This was attributed to the low heat demand density in combination with
the high heat network infrastructure cost associated with connecting the two areas.
Heat Network Opportunities
43
5. ENERGY MASTERPLANNING FOR PREFERRED
OPPORTUNITIES
The project key performance indicators (KPIs) resulting from the opportunity modelling were
presented to the Council for comment and to confirm Ramboll’s recommendations for preferred
opportunities. This section explores the preferred opportunities in further technical and economic
detail.
Five opportunities were selected for further analysis. Each opportunity features the same heat
load, but with different supply technologies. The opportunities are listed as follows:
1. MH001 Mildenhall Hub supplied by gas CHP
2. MH002 Mildenhall Hub supplied by biomass boilers
3. MH003 Hub supplied by a WSHP
4. MH005 Hub supplied by solar thermal panels
5. MH006 Hub supplied by a GSHP
At the request of Forest Heath District Council, all scenarios were modelled with and without the
addition of solar photovoltaic (PV) panels, with the exception of the solar thermal case.
The first stage in the analysis was to enter the energy demand data for the Mildenhall Hub and
establish the ‘business as usual’ (BaU) or ‘do nothing’ scenario, which enabled the calculation of
relative carbon and cost savings of the four low carbon options against the scenario where only
natural gas fired boilers are installed.
Following this, heat supply information for the five low carbon energy supply options was entered
into an EnergyPRO model to generate results which indicate the economic and carbon potential.
EnergyPRO creates hourly annual demand and supply profiles to enable accurate calculation of
economic and carbon results.
Heat Network Opportunities
44
5.1 Energy Demand Assumptions
Due to the fact that the plans for the Mildenhall Hub were evolving during the time of writing,
changes were being made to the concept design as the opportunity modelling was conducted.
Therefore, before conducting the techno-economic analysis for preferred opportunities,
the energy demand estimates from section 2 were revised to ensure the most up to
date information was being used and thus the results would be presented to the
highest possible degree of accuracy.
5.1.1 Mildenhall Hub Concept Design Alterations
A revised business case with more detail on the design was issued in January 2016 by the
Developer with alterations to the previous concept design. The new design maintained the
existing Sixth Form College building and concentrated the other services into two adjacent
buildings. Figure 24 shows the revised layout. The corresponding floor areas are presented in
Table 20.
The main building has Public Access that functions as a hall and hub for the building. This public
access area includes a reception, offices, health centre, library, café, and pre-school. This
building also incorporates spaces for meeting and conference rooms, an academy (with changing
rooms), a wet and dry leisure centre, a kitchen and plant rooms.
The fire and police stations would share another building within the site with common facilities.
Figure 24: Indicative Design Option for Mildenhall Hub
Building Function Floor Area (m2)
Public Access 2,029
Shared meeting space and hall 646
Education Provision 8,420
Education Changing Room Provision 222
Kitchen and Plant Rooms 350
Leisure Centre 4,155
Fire & Police Station 250
Table 20: Floor Areas per Building for Mildenhall Hub
Heat Network Opportunities
45
5.1.2 Heat Demand Assessment
Due to the fact that further information was made available by the Forest Heath District Council
regarding the possible area schedule of the Mildenhall Hub, the benchmarking exercise outlined
in section 2.2.3 was repeated using the new values.
It is important to note that the updates to the area schedule were not retrospectively included in
the opportunity modelling stage as the work had already been completed. The opportunity results
in section 4.4 are based on the previous schedule.
Figure 25 shows the updated breakdown of the heat demand with respect to the building use
class and the end use of the heat energy. Education and Leisure (leisure classed as
“Recreational”) building types are expected to be the largest energy consumers in the Hub.
Figure 25: Annual Heat Demand by Building Type
The peak diversified demand for the Mildenhall Hub was calculated to be just less than 1.1 MW.
The annual demand from this building was calculated as 1,940 MWh.
The heat demand profile for the Hub was assessed in combination with degree day profiling to
develop a detailed picture of heat demand across the year. Diversification of demand profiles was
also accounted for at this stage.
Hourly energy demand profiles were constructed for the Mildenhall Hub using EnergyPRO based
on the various use types. It was assumed that the public offices would close at the weekend, but
that the leisure centre and library as well as the central Hub would remain open.
Figure 26 shows the modelled annual heat consumption for the Mildenhall Hub.
Heat Network Opportunities
46
Figure 26: EnergyPRO Annual Heat Demand Profile for Mildenhall Hub
An example heat demand profile for a typical week in January is shown in Figure 27. As the
profile is taken from the winter months the graph represents some of the peak annual heat load
values.
Figure 27: EnergyPRO Weekly Heat Demand Profile (Jan)
Heat Network Opportunities
47
5.1.3 Electricity Demand Assessment
As part of the detailed energy assessment for techno-economic modelling, predicted electricity
profiles were analysed to enable a more accurate estimation of the proportion of electricity that
could be private wired rather than sold to the grid.
As no predicted half hourly data was available from the Developer at the time of writing, a likely
daily electricity profile was constructed based on actual half hourly data profiles obtained from
Ramboll’s other Local Authority masterplanning projects. Given that the largest proportion of the
Hub is made up of public offices and educational facilities, the profile was taken from a similar
large public facility.
The profile was then scaled in accordance with the difference in total electricity demand of the
Mildenhall Hub and the sample building. The weekday profile is shown in Figure 28.
Figure 28: Predicted Daily Electricity Profile for Mildenhall Hub
The profile clearly shows a steady daytime load of over 400 kW and overnight base load of 70
kW.
During the weekend the profile would be expected to reduce due to the lack of occupancy in the
offices and schools. However the leisure facility and library would remain open which represent a
total of about 15% of the annual electricity load. Therefore a daytime increase would still be
expected over the weekend of at least 100 kW.
5.1.4 Project Phasing
Limited information regarding project timescales was available at the time of writing. From the
Developer’s initial project plan it was apparent that construction was sue to start in September
2017, with completion in December 2018. As there was no indication that the construction of
various areas of the Hub would be phased, it was assumed that the entire heat demand for the
project would therefore be available at the start of 2019.
Heat Network Opportunities
48
5.2 Energy Supply Assumptions
Five different primary supply technologies were considered. The sub-sections below present an
overview of the modelling assumptions including the required sizing of each supply asset, capital
and operational costs, carbon emissions and also key practical considerations.
5.2.1 Overview of General Assumptions for All Scenarios
There are a number of overarching assumptions for each modelled scenario:
The BaU case was assumed to be a communal plant room solution with gas fired boilers. The
BaU cost of gas in all cases was assumed to be the average value observed in the Forest Heath
District Council billing data which was calculated to be 4.2 p/kWh.
Due to the fact that the BaU scenario also involves a single plant room solution, the costs of
construction for the plant room/energy centre at the Mildenhall Hub would be absorbed into the
development costs (as it would be required in any case) and they are therefore not included in
the capital costs for any scenario. The stated “energy centre and plant” costs for each option
include major plant items, other equipment (pumps, heat exchangers, etc.) and balance of plant.
Specific cost quotations were not obtained for this analysis at masterplanning level. The assumed
plant and network capital costs were based on Ramboll’s database of historic supplier data
and benchmarking and it is recommended that a cost consultant be commissioned at feasibility
stage to conduct a detailed evaluation of project costs. Specific annual costs are presented for
each scenario in the sub-sections below.
Reinvestment costs for each system were also included in the model. They are based on
Ramboll’s previous experience on existing projects in the UK and Denmark. Plant reinvestment
costs have been calculated based on:
10% reinvestment over a 25 year reinvestment cycle for the thermal store
50% reinvestment over a 20 year reinvestment cycle for the gas boilers
50% reinvestment over a 15 year reinvestment cycle for the CHP engines
50% reinvestment over a 15 year reinvestment cycle for the biomass boilers
50% reinvestment over a 15 year investment cycle for heat pumps.
Reinvestment for the balance of plant is assumed to be covered under the on-going operation
and maintenance costs.
In a similar way to the capital cost estimates, O&M costs were taken from Ramboll’s database of
historic supplier data and benchmarking. Specific annual costs are presented for each scenario in
the sub-sections below.
The electricity costs for the heat pumps were taken from DECC’s most recently published
energy price figures11.
The cost of gas figures for the CHP cases and for the top up boilers were taken from DECC’s
most recently published energy price figures12. It was assumed that if the Council runs plant to
supply the whole Hub site, they would be able to obtain a more favourable rate which has been
11 DECC, “Gas and electricity prices in the non-domestic sector”, https://www.gov.uk/government/statistical-data-sets/gas-and-
electricity-prices-in-the-non-domestic-sector 12 DECC, “Gas and electricity prices in the non-domestic sector”, https://www.gov.uk/government/statistical-data-sets/gas-and-
electricity-prices-in-the-non-domestic-sector
Heat Network Opportunities
49
factored into the scheme economics. Gas supplied to the CHP engine was assumed to be exempt
from CCL.
The sale price of heat from each supply asset is based on the BaU gas value with an applied
boiler efficiency of 80%. 5% of the cost was deducted to represent an incentive against the BaU.
Avoided boiler maintenance and replacement costs were accounted for at a rate of 0.15 p/kWh.
The resulting heat sale price was calculated to be 5.26 p/kWh.
RHI revenue is set in accordance with 2016 tariffs13. In the first instance the 2016 tariff values
are applied to the first 20 years of each of the relevant modelling scenarios. As part of the
sensitivity analysis degression of the RHI over time is assessed.
Carbon emissions factors were taken from DECC’s most recently published figures14. Gas was
assumed to have a constant emissions factor of 0.184 tonnes CO2/kWh. Electricity was assumed
to change over time in accordance with DECC’s estimates, starting with a generation-based grid
average value of 0.273 tonnes CO2/kWh in the first operational year of 2019.
13 Ofgem, “Tariffs that apply for Non-Domestic RHI for Great Britain”, https://www.ofgem.gov.uk/environmental-programmes/non-
domestic-renewable-heat-incentive-rhi/tariffs-apply-non-domestic-rhi-great-britain 14 Table 1 and Table 2a. https://www.gov.uk/government/publications/valuation-of-energy-use-and-greenhouse-gas-emissions-for-
appraisal
Heat Network Opportunities
50
5.2.2 Solar PV
As previously stated, each model was tested with and without the addition of a roof-mounted
solar PV array, in order to test the effects on the economics if a solar PV scheme was included as
part of the low carbon decentralised energy project.
The scheme was sized taking two main factors into consideration; the available roof space and
the FIT tariff bands.
In order to remain just within the 150 kW to 250 kW band with a total panel area of 1,690 m2
was required, which corresponds to approximately 248 kW.
The total floor area of the Mildenhall Hub was expected to be over 16,000 m2. Assuming the
entire building is three storeys15 the roof space is therefore expected to be approximately 5,300
m2. Even allocating 50% of this to buildings services (e.g. ventilation systems) and allowing for
panel spacing would leave sufficient space for the 1,690 m2 of panel area calculated above.
In the biomass, WSHP and GSHP cases it is assumed that the Mildenhall Hub consumes the entire
electricity output from the solar PV installation. For the CHP case it is assumed that 75% would
be consumed by the Mildenhall Hub with the remaining 25% exported to grid.
Based on the typical levels of solar irradiation in Mildenhall throughout the year, the annual
electricity output of the panels was estimated to be 229 MWh.
Figure 29: Solar Irradiation Data for Mildenhall
PV pricing forecasts were obtained from the 2012 DECC Solar PV cost update16, which presents
the likely reduction in panel costs over a 20 year period.
OPEX assumptions were taken from the most recent Government cost statistics17
15 This is a general assumption as no information was available. 16 Solar PV Cost Update, Parsons Brinkerhoff for the Department of Energy and Climate Change, May 2012 17 “PV Cost Update”, https://www.gov.uk/government/statistics/pv-cost-update
Heat Network Opportunities
51
5.2.3 Gas CHP
The Gas CHP scenario would involve the use of a 358 kWth CHP engine fuelled by natural gas. The
sizing was optimised to ensure annual full load equivalent running hours of at least 4,500 hours
and a contribution to total annual heat demand in the region of 60%.
The CHP engine would operate in combination with natural gas boilers supplying a total back up
and peaking capacity of approximately 1.1 MW.
Accumulator thermal storage can provide significant operational benefits to gas engine CHP
schemes. The optimal size of thermal store will depend on a trade-off between capital cost and
operational cost savings. The modelling carried out at this stage has assumed a capacity based
on 2.5 full load output of the CHP engine. In this case the thermal storage capacity was
calculated to be 900 kWh which corresponds to a water volume of 31 m3.
Table 21 shows the key parameters of this scenario:
Parameter Value
CHP Capacity 358 kWth
Gas Boiler Capacity 2 No. 550 kWth
Thermal Store Capacity 0.9 MWh
Annual CHP Electricity Output 1,008 MWh/yr
Annual CHP Heat Output 1,520 MWh/yr
Annual Boilers Heat Output 420 MWh/yr
Table 21: Key CHP Parameters
The contribution of the CHP engine and boilers to the heat demand for a sample week in January
is shown in the figure below. The thermal store is not shown on the graph due to the fact that it
acts to store and release energy, but it is not a supply asset.
Figure 30: Example Weekly Profile of Supply Asset Contributions
The capital cost estimates are shown in Table 22 below.
Item Cost
Energy Centres and Plant £228 K
Thermal Store £43 K
External pipework and trenching NA
Contractor and Design £40 K
Total £311 K
Table 22: Capital Costs for CHP Option
The operational cost considerations for this scenario consist of the gas cost and on-going O&M.
Annual O&M for the energy centre and plant was included at just under £10 K per annum.
Heat Network Opportunities
52
Revenues are obtained through the sale of heat and electricity. Based on the constructed profiles
in section 5.1.2, it was assumed that electricity could be private wired to the Mildenhall Hub at a
rate of 12 p/kWh for approximately 75% of the time. The remaining 25% of the electricity would
be sold to the grid at 4.5 p/kWh.
Heat Network Opportunities
53
5.2.4 Biomass Boiler
The biomass heating option would involve the installation of a biomass boiler in the energy
centre. For this option, a single 550 kW biomass fired boiler was selected along with a 1,100 kW
of gas fired boilers for provision of back up and peaking capacity.
During any subsequent feasibility and design phases, it may be decided to remove the
requirement to provide gas fired back up and peaking boilers. This would remove the need for a
gas connection and the cost savings would contribute to offsetting the additional cost associated
with biomass heating. The impact of this has not been assessed in this report.
A thermal store was included as part of the biomass option to:
act as a buffer vessel
improve response of the biomass boilers
reduce inefficient short cycling of biomass boiler
provide peak heat supply capacity
The thermal store capacity was sized based on 2.5 full load output of the biomass boiler. This is
equivalent to of 1.38 MWh which corresponds to an approximate volume of 47 m3.
The key figures for the biomass operation are shown in Table 23 below.
Parameter Value
Biomass Fired Boiler Capacity 550 kWth
Gas Fired Boiler Capacity 1,100 kWth
Thermal Store Capacity 1.38 MWh
Annual Biomass Heat Production 1,920 MWh/yr
Annual Natural Gas Heat Production 20 MWh/yr
Table 23: Key Biomass Boiler Parameters
Figure 31 below shows how the biomass boiler, thermal store and gas fired boilers could operate
and contribute to annual heat demand for the Mildenhall Hub. As the graph presents only heat
generation assets, the thermal store is not directly represented. However, the operation of the
thermal store can be seen where the area under the heat demand curve appears to be unfilled.
Figure 31: Contribution of Supply Assets to Heat Demand for Biomass Option
Heat Network Opportunities
54
A breakdown of the estimated project costs is shown in Table 24.
Item Cost
Energy Centres and Plant £617 K
Thermal Store £50 K
External pipework and trenching N/A
Contractor and Design £100 K
Total £767 K
Table 24: Capital Costs for Biomass Option
The operational costs in this scenario include the biomass fuel, natural gas and on-going O&M. It
is assumed that the biomass fuel will take the form of wood chip. In this case it was decided that
chip would be favourable to wood chip due to the fact that it is considerably cheaper than pellets.
A disadvantage of wood chip is that it requires a relatively large storage area; however it was
assumed that sufficient space could be incorporated into the Mildenhall Hub design due to the
large land area covered by the site.
The cost of wood pellets included in the model was £110 per tonne. This figure was based on
quotations obtained for similar past projects.
In addition to revenue from heat sales, it was assumed that all heat produced by the biomass
boilers was eligible for RHI payments according to 2016 tariff rates for biomass under 999 kW.
This corresponds to figures of 5.24 p/kWh and 2.27 p/kWh for Tier 1 and Tier 2 respectively.
As projects such as this often rely heavily on RHI revenues, the sensitivity of the project
economics to this factor is analysed in section 5.3.3.
Heat Network Opportunities
55
5.2.5 Water Source Heat Pump
Since the internal heating system of the Mildenhall Hub is yet to be designed, there is an
opportunity to include a low temperature space heating system that is suited to low temperature
heat sources such as heat pumps (water source and ground source) and solar thermal collectors.
Low temperature space heating includes technologies such as under floor heating or oversized
radiators. These have much higher heat transfer surface areas than traditional systems which
mean the circulating fluid within the system can be cooled further thereby releasing more of the
heat content. This means lower heating system operating temperatures can be used (35 °C – 60
°C on the flow depending on floor construction). Lower heating system operating temperatures
may also allow a greater range of pipework materials to be used.
The proposed energy supply technology for this option is a 550 kW WSHP. This option would
involve installing a heat loop within a deep section of the River Lark approximately 450 m to the
south of the proposed Mildenhall Hub site.
The river was observed during Ramboll’s visit to the site in autumn 2015 and photos are shown
below. If this project is selected for progression to feasibility stage, depth and temperature
measurements must be taken to assess the heat availability in further detail. At masterplanning
stage the limited information represents a risk to the project.
Figure 32: Photographs of the River Lark (courtesy of Ramboll)
The heat pump unit would be located within the Hub’s boiler house and connected to the river
loop via insulated pipework buried in the ground. Also located within the boiler house would be
two 550 kW gas fired boilers to provide back up and peaking capacity.
A thermal store is included to assist in balancing of heat demand, increase utilisation of the
WSHP installation and reduce heat required from the gas fired boiler plant. The thermal store was
sized at 47 m3 which corresponds to a capacity of approximately 1.38 MWh.
The key energy production figures for this scenario are shown in Table 25 below.
Parameter Value
WSHP Capacity 550 kW
Gas Fired Boiler Capacity 1,100 kW
Thermal Store Capacity 1.38 MWh
Annual WSHP Heat Production 2,000 MWh
Annual Natural Gas Heat Production 55 MWh
Table 25: Key WSHP Parameters
Heat Network Opportunities
56
Figure 33 shows how the WSHP and gas fired boilers are expected to operate and contribute to
the heat demand for the Mildenhall Hub.
Figure 33: Contribution of Supply Assets to Heat Demand for WSHP Option
The capital costs for this scenario are shown in Table 26. The WSHP option requires pipework to
connect the heat pump units with the heat recovery loops. This cost is included under external
pipework and trenching.
Item Cost
Energy Centres and Plant £932 K
Thermal Store £50 K
External pipework and trenching £316 K
Contractor and Design £195 K
Total £1,493 K
Table 26: Capital Costs for WSHP Option
The operational costs consist of electricity to run the heat pump, gas for the peaking boilers and
on-going O&M. Annual maintenance costs were approximated to be £3,300 per annum.
In addition to revenue from heat sales, it was assumed that all heat produced by the WSHP was
eligible for RHI payments at the 2016 tariff rates. At the time of writing the values were currently
set at 8.95 p/kWh at Tier 1 and 2.67 p/kWh at Tier 2 for all capacities.
As projects such as this often rely heavily on RHI revenues, the sensitivity of the project
economics to this factor is analysed in section 5.3.3.
Heat Network Opportunities
57
5.2.6 Solar Thermal
This scenario involves the installation of solar thermal collectors on south easterly sections of the
roof of the Mildenhall Hub buildings.
The solar thermal collector installation was sized with a total area of 282 m2, equivalent to
around 200 kWth of peak heat supply capacity. This is the maximum installation size that is
currently supported under the RHI.
This option includes a 17 m3 thermal store to assist in supply and demand balancing.
In the UK, the performance of solar thermal collectors is highly seasonal. Two 550 kWth gas
boilers were included within this option to ensure adequate heat is provided when the solar
thermal system is unable to meet the peak demand. These boilers shall also provide back-up
capacity and would be located in the boiler house with the thermal store.
The key energy production figures for this scenario are shown in Table 27 below.
Parameter Value
Solar Thermal Capacity 200 kW
Gas Fired Boiler Capacity 1,100 kW
Thermal Store Capacity 0.50 MWh
Annual Solar Thermal Heat Production 167 MWh
Annual Natural Gas Heat Production 1,773 MWh
Table 27: Solar Thermal Case Key Parameters
Figure 34 and Figure 35 below show how the solar thermal collector and gas fired boilers are
expected to operate and contribute to the weekly heat demand for the Mildenhall Hub in summer
and winter respectively. Due to the heavily seasonal nature of the technology, the gas boilers can
be seen to produce almost all of the required heat in the winter months.
Figure 34: Contribution of Solar Thermal Supply Assets to Heat Demand in Summer
Heat Network Opportunities
58
Figure 35: Contribution of Solar Thermal Supply Assets to Heat Demand in Winter
The estimated capital costs for this scenario are presented in Table 28.
Item Cost
Energy Centres and Plant £563 K
Thermal Store £30 K
External pipework and trenching N/A
Contractor and Design £89 K
Total £682 K
Table 28: Capital Costs for Solar Thermal Option
The operating costs include the cost of gas and the on-going O&M.
In addition to revenue from heat sales, it was assumed that all heat produced by the solar
thermal collectors was eligible for RHI payments at 2016 rates of 10.28 p/kWh.
As projects such as this often rely heavily on RHI revenues, the sensitivity of the project
economics to this factor is analysed in section 5.3.3.
Heat Network Opportunities
59
5.2.7 Ground Source Heat Pump
The final option is the installation of a GSHP. Similarly to the WSHP option, this technology is
suited to low temperature space heating systems such as under floor heating, which should be
considered during the design phase of the Mildenhall Hub.
For this option a 550 kWth GSHP is proposed. The ground loop would be installed in trenches
within the grounds of the Hub and Sixth Form College. Once installed, the ground above the
ground loop can be utilised for a variety of recreational purposes. The ground loop would be
connected to the heat pump unit that would be located in the boiler house.
The thermal conductivity of the soil into which the ground loop is installed will influence the
required length and therefore cost of the collector. Dry, loose soil such as loams, sand and gravel
are freely draining and will trap air. This means the thermal conductivity for these soil types will
be low which will increase the collector length requirement for a given heat pump output.
Clay, silty and saturated soils have much higher thermal conductivities which will reduce the
required collector length for the same heat pump output. Furthermore, sandy or loamy soils that
are saturated will have a significantly higher thermal conductivity that when dry. Thermal
conductivity also varies by bedrock type which will influence the length and number of boreholes
required for vertical ground loop installations.
The UK Soilscapes map18 (extract shown in Figure 36 below) identifies the soils around the
Mildenhall Hub as being freely draining lime-rich loamy soils. Consequently, it is likely the length
requirement for the ground loop will be significant on a meter per heat pump kW output basis.
Figure 36: Screenshot from UK Soilscapes Map
Also located in the boiler house would be two 550 kW gas fired boilers to provide back up and
peaking capacity. A thermal store is included to assist in balancing of heat demand, increase
utilisation of the GSHP installation and reduce heat required from the gas fired boiler plant.
The key energy production figures for this scenario are shown in Table 29.
18 http://www.landis.org.uk/soilscapes/ NOTE: Soilscapes was used for high-level observations only. Soilscapes is not intended as a
means for supporting detailed assessments, such as land planning applications or site investigations; nor should it be used to support
commercial activities.
Heat Network Opportunities
60
Parameter Value
GSHP Capacity 550 kW
Gas Fired Boiler Capacity 1,100 kW
Thermal Store Capacity 1.38 MWh
Annual GSHP Heat Production 1,900 kWh
Annual Natural Gas Heat Production 14 MWh
Table 29: GSHP Option Key Parameters
Figure 37 below shows how the GSHP, thermal store and gas fired boilers could operate and
contribute to the heat demand for a week in January when the load is at its highest.
Figure 37: Contribution of Supply Assets to Heat Demand for GSHP Option
The GSHP scenario involves pipework to connect the heat pump units with the heat recovery
loops. This cost is included under external pipework and trenching.
Item Cost
Energy Centres and Plant £529 K
Thermal Store £50 K
External pipework and trenching £220 K
Contractor and Design £120 K
Total £919 K
Table 30: Capital Costs for GSHP Option
The operational expenditure in this case consists of the electricity required to run the heat pump,
natural gas for the boilers and on-going O&M costs. Maintenance costs were included at a rate of
£3,300 per annum.
In addition to revenue from heat sales, it was assumed that all heat produced by the GSHP was
eligible for RHI payments at the 2016 tariff rates. These are the same as the RHI levels for
WSHPs at 8.95 p/kWh and 2.67 p/kWh for Tier 1 and Tier 2 respectively.
As projects such as this often rely heavily on RHI revenues, the sensitivity of the project
economics to this factor is analysed in section 5.3.3.
Heat Network Opportunities
61
5.3 Modelling Results
As previously stated, the techno-economic analysis was conducted using EnergyPRO software. A
model was built for each of the five energy supply options for the Mildenhall Hub.
The results were compared according to the following key performance indicators:
Internal rate of return (IRR)
Net present value (NPV) at a 3.5% discount rate19
CO2 savings against BaU.
The models have been assessed over a 25-year and 40-year project lifetime.
The lowest IRR hurdle rate considered for project viability is 3.5 % to 4.0 % which is in line with
the lowest acceptable values for public borrowing. However, should the Council wish to work in
partnership with a private ESCo IRRs in excess of 10 % would have to be achieved. These rates
were taken into account when evaluating the economic results.
The first operational year of the project was taken to be 2019, as this was the date presented in
the Developer’s indicative project plan.
5.3.1 Results without Solar PV
5.3.1.1 Economics
The table below presents a summary of the key economic results for each of the five
opportunities without the addition of solar PV. It is colour coded whereby the IRRs are green
in excess of 10% and yellow in excess of 4 %.
Opportunity CAPEX IRR 25 yrs 25 yr NPV @
3.5% DR IRR 40 yrs
40 yr NPV @
3.5% DR
CHP £310,500 11% £250,100 11% £387,300
Biomass £766,500 9% £376,700 9% £493,100
WSHP £1,492,400 5% £133,800 6% £368,100
Solar Thermal £682,300 NA -£555,400 -7% -£519,000
GSHP £918,300 14% £997,500 15% £1,249,400
Table 31: Summary of Economic Results
Table 32 presents the NPVs at 6% and 10% discount rates.
Opportunity 25 yr NPV @
6% DR
25 yr NPV @
10% DR
40 yr NPV @
6% DR
40 yr NPV @
10% DR
CHP £131,600 £12,500 £193,900 £31,300
Biomass £172,700 £1,077,900 £226,700 -£36,900
WSHP -£117,500 -£536,800 -£8,700 -£380,800
Solar Thermal -£537,500 -£536,800 -£520,800 -£531,800
GSHP £650,600 £268,700 £767,600 £305,000
Table 32: NPVs at 6% and 10% Discount Rates
19 DR set at the lowest project hurdle rate
Heat Network Opportunities
62
Two of the scenarios stand out as the most viable; the CHP and GSHP options. The IRR of 14% in
the GSHP case is highly likely to be attractive to private energy services companies, should
Forest Heath District Council not wish to take on the costs and operation of the project
themselves.
The IRRs of 11% in the CHP case are attractive enough for a public sector led project and are
also likely to attract private investment should the Council seek it.
The biomass scenario is also found to generate positive returns, with IRRs at 9% for 25 and 40
year lifecycles. This is sufficient to be considered viable for a publicly led project.
The WSHP scenario returns positive IRRs of 5% and 6% over 25 and 40 years respectively. This
shows that the project is likely to be viable if led by Forest Heath District Council. The high
capital costs are the reason for the relatively low returns when compared to the GSHP case, and
if these could be brought down the economics would look significantly more attractive.
Contrary to the findings of the opportunity assessment in section 4, the solar thermal scheme
was not found to be viable. This is most notably due to the fact that the detailed seasonal energy
profiling carried out in EnergyPRO provided a more comprehensive overall figure for the
contribution of heat to the system from the collectors.
5.3.1.2 Carbon
The CO2 savings for each of the four options against the BaU case have been calculated using the
EnergyPro model and are shown in Table 33 below. The CO2 savings calculated here are based on
heat use only and do not account for electricity consumption of the customers. Please note the
carbon figures quoted do not account for grid decarbonisation.
Opportunity
Annual CO2
savings
(tonnes)
CO2 savings over
25 yr lifetime
(tonnes)
Carbon intensity
(kg.CO2/MWh)
Cost of CO2
abatement20
(£/tonne CO2)
CHP 115 2,883 198 £108
Biomass 376 9,396 50 £82
WSHP 391 9,779 40 £153
Solar Thermal 40 1,009 223 £676
GSHP 402 10,046 37 £91
Table 33: Carbon Savings for Mildenhall Energy Supply Options
The results show that the GSHP, WSHP and biomass scenarios are likely to result in significant
CO2 savings when compared to the BaU. The cost of carbon abatement in the biomass, GSHP and
CHP cases is relatively low at £82, £91 and £108 per tonne respectively over a 25 year project
lifetime.
20 Over 25 year lifetime
Heat Network Opportunities
63
5.3.2 Results with Solar PV
5.3.2.1 Economics
The table below presents a summary of the key economic results for each of the four
opportunities with solar PV. Please note that the solar PV scenario is excluded from the solar
thermal case since it is assumed that there will be insufficient roof space for both installations.
Opportunity CAPEX IRR 25 yrs 25 yr NPV @
3.5% DR IRR 40 yrs
40 yr NPV @
3.5% DR
CHP £477,100 10% £361,900 11% £592,500
Biomass £933,100 10% £569,800 10% £778,800
WSHP £1,658,900 6% £336,800 7% £653,800
GSHP £1,084,900 14% £1,171,400 14% £1,535,100
Table 34: Summary of Economic Results with PV
Table 35 presents the NPVs at 6% and 10% discount rates.
Opportunity 25 yr NPV @
6% DR
25 yr NPV @
10% DR
40 yr NPV @
6% DR
40 yr NPV @
10% DR
CHP £498,200 £319,800 £603,900 £352,000
Biomass £1,053,800 £747,800 £1,149,400 £776,700
WSHP £1,494,800 £1,114,900 £1,639,900 £1,097,100
GSHP £1,673,200 £1,218,100 £1,842,100 £1,270,500
Table 35: NPVs at 6% and 10% Discount Rates
The inclusion of a solar PV installation has a positive effect on the performance of the four
scenarios modelled. Both 25 year and 40 year NPV are improved by between £100k-200k and
200k-£285k respectively. For the CHP scenario, solar PV has the least effect since this option
includes two forms of competing on-site power generation. Solar PV has the most benefit for the
biomass and WSHP scenarios where IRRs are improved by one percentage point.
5.3.2.2 Carbon
The CO2 savings for the modelling scenarios which include PV are shown below. Conversely to the
assessment of the scenarios without PV, the carbon savings analysis presented in below also
account for electricity consumption of the customers in the Hub.
Opportunity
Annual CO2
savings
(tonnes)
CO2 savings over
25 yr lifetime
(tonnes)
Carbon intensity
(kg.CO2/MWh)
Cost of CO2
abatement21
(£/tonne CO2)
CHP 143 3,578 183 £133
Biomass 404 10,103 148 £92
WSHP 419 10,486 134 £158
GSHP 430 10,753 138 £101
Table 36: Carbon Savings for Mildenhall Energy Supply Options
21 Over 25 year lifetime
Heat Network Opportunities
64
In all cases the inclusion of solar PV increases the annual CO2 savings by 28 tonnes per year.
Similarly, the carbon intensity increases for all cases, except CHP, when compared to the without
PV assessment since electricity consumption related CO2 emissions are now accounted for.
However, biomass, WSHP and GSHP continue to achieve significant CO2 emissions savings when
compared to the CHP case.
Heat Network Opportunities
65
5.3.3 Sensitivity Analysis
The results of the Mildenhall Hub energy model are sensitive to a number of key assumptions.
Consequently, the EnergyPRO model was re-run to assess the impact any changes of these key
parameters on the economics of each option. The parameters assessed in the sensitivity analysis
are discussed below.
The sensitivity analysis was conducted on the models excluding the effects of solar PV in order to
put focus on the heat supply asset.
Renewable Heat Incentive
There is currently a great deal of uncertainty regarding the future of support for renewable heat
technologies under the Renewable Heat Incentive. During the Governments Autumn Statement
released on 25th November 2015 it was announced that the RHI scheme would be extended to
2020/21. However, the security of the current tariffs is still uncertain.
The implication of the above on four of the proposed energy supply options for the Mildenhall Hub
is that value of payments from the RHI could be reduced or removed completely.
Firstly the best and worst cases were compared. These were considered to be the 2016 tariffs
compared to no RHI whatsoever. The results are shown in Figure 38.
Figure 38: Effect of Removing RHI from Project Cash Flow
It is clear that without support from the RHI the biomass and WSHP are no longer viable. The IRR
of the GSHP option is significantly reduced from 20% to 4%.
Given the dramatic difference in IRRs with and without RHI, the results were tested again with
reductions in RHI revenue of 10% and 50%. The results for a 25 year project lifetime are
presented in Table 37.
Scenario Base Case IRR -10 % RHI -50 % RHI
Biomass 9% 8% 2%
WSHP 5% 4% -4%
Solar Thermal NA NA NA
GSHP 14% 13% 8%
Table 37: Sensitivity of Schemes to RHI Reduction
-15%
-10%
-5%
0%
5%
10%
15%
20%
Biomass WSHP Solar Thermal GSHP
IRR
ove
r 4
0 Y
ears
RHI
No RHI
Heat Network Opportunities
66
Heat Sale Price
The assumed total heat sale price was varied by +/- 10% and 20% in order to observe the
change in IRR. The variation was applied to the entire price including standing charges.
Figure 39 shows the results of the analysis.
Figure 39: Graph of 25 year IRR Varying with Cost of Heat
Figure 40: Graph of 40 year IRR Varying with Cost of Heat
It can be seen that the CHP scenario is most heavily dependent on the heat sale price. An
increase of 10% or 20% makes the scheme significantly more attractive, but an equivalent
reduction results in the scheme IRRs appear to be borderline. The high dependence on heat sale
price can be attributed to the fact that the heat revenue in this case makes up a greater
proportion of the total cash flow than in the other scenarios.
The GSHP option maintains attractive rates of return even with a 20% reduction in heat sale
price.
Heat Network Opportunities
67
The results show that for the WSHP and biomass options a 10% or 20% reduction in heat sale
price reduces the IRR to a point where the viability of the project would be questioned. In the
case of the biomass scenario a 20% reduction results in a low rate of return.
Over a 25 year project lifetime the solar thermal does not return a positive IRR even with an
increase of heat sale price of 20%. Over 40 years an increase of 20% results in a positive IRR,
but the value is still not significant enough to be considered attractive.
Project Capital Costs
Sensitivity was also carried out on the project capital costs. This was deemed necessary due to
the fact that capital costing of the project opportunities was carried out based on Ramboll’s
experience in the low and zero carbon energy market in the UK, which were not confirmed with
the market specifically for this project.
The impact of altering the costs by +/- 10% and 20% for each opportunity is shown in Figure 41.
Figure 41: Effect of Varying Capital Costs on Project 25 year IRRs
Figure 42: Effect of Varying Capital Costs on Project 40 year IRRs
Even with a 20% increase in capital costs the GSHP scenario remains viable with IRRs exceeding
11%.
Heat Network Opportunities
68
The CHP option maintains IRRs of approximately 7-9% when presented with an increase in
capital cost. This is still considered to be sufficient for a publicly led scheme.
The capital cost increases bring the biomass scenario’s rates of return down to 6% which is could
be attractive for a public led project. However, a 20% reduction in the estimated costs results in
the IRR exceeding 10% for both 25 and 40 year lifetimes, which significantly increases the
appeal of the scheme.
In a similar way to biomass, the sensitivity of the WSHP scheme to capital cost is significant due
to the borderline nature of the modelling results. A reduction in cost results in the rates of return
reaching values which are more likely to be considered for implementation, but any increase in
costs reduces the project IRRs down to unattractive levels.
In the case of the proposed solar thermal scheme, even a 20% reduction in the estimated capital
expenditure is not sufficient for a positive rate of return.
Leisure Centre Heat Sale Prices
Following completion of the techno-economic analysis phase, the Council stated that an
additional risk had arisen in the form of the heat sale price to the leisure centre portion of
Mildenhall Hub.
Due to amendments to the size and staffing of the proposed leisure facility, it was deemed likely
that they would receive a significant discount to the heat sale price or even free heat. Therefore
analysis was conducted to establish the effect of this on the project economics.
Firstly it should be noted that the total estimated revenue from heat sales to the leisure facility in
the base scenarios was over £30 K per annum. This represents approximately 30% of the total
heat sale revenue and is therefore a significant factor in the economic results.
The two scenarios with the most attractive economic results were assessed: CHP and GSHP. The
leisure centre heat sale revenue was removed from the project cash flow to demonstrate the
worst case scenario. The results of the sensitivity analysis are presented in Table 38.
Scenario
Base IRR 25 Yrs
25 Yr IRR
without LC
Revenue
Base IRR 40 Yrs
40 Yr IRR
without LC
Revenue
CHP 11% -9.1% 11% -6.9%
GSHP 14% 9.8% 15% 10.1%
Table 38: Sensitivity of Economics to Leisure Centre Heat Sale Price
The results show that in the CHP case, the results are heavily affected by the loss of revenue and
the project is no longer viable. This is due to the fact that the annual operating margin in this
case is only marginally more than the amount of heat sale revenue from the leisure centre under
the base case.
In the case of the GSHP the scheme was still found to be viable without the leisure centre heat
sale revenue, despite the reduction in IRR of over 4%. This is due to two key factors: firstly, the
GSHP IRRs were well above the hurdle rate to begin with and so a reduction would have to be
significant to reduce viability. Secondly the annual operating margin in the base was well in
excess of the value of the leisure centre base case heat sale revenue and therefore the scheme is
still paying back at a reasonable rate.
Heat Network Opportunities
69
5.3.4 Summary of Modelling Results
The results from the technical modelling, economic assessment, carbon assessment and
sensitivity analysis can be summarised as follows:
The results show that GSHP and gas CHP technology are the most promising options for
energy supply at the Mildenhall Hub development in terms of economics alone.
WSHP and biomass options also return reasonable IRRs and are considered to be viable
for a publically led project.
The GSHP, WSHP and biomass options result in the greatest CO2 savings and were found
to have the lowest cost of carbon abatement.
Solar thermal technology was found to be inappropriate for the site. Even with increases
in heat sale price and reductions in the estimated capital expenditure, the scheme does
not appear to generate attractive rates of return.
The integration of a Solar PV installation was found to result in improvements both in
terms of economics and carbon emissions savings for CHP, biomass, WSHP and GSHP
scenarios.
Without the revenue from the RHI the WSHP and biomass projects are no longer viable.
The IRR of the GSHP reduces significantly and the economics are unlikely to be attractive
except for a public led scheme. The CHP scheme is not affected by RHI.
The CHP, biomass and WSHP scenarios were found to be very sensitive to the heat sale
price when compared to the GSHP option.
In a similar way to the heat sale prices, changes in project CAPEX reduce the IRRs for the
WSHP scenario to an unattractive level. However the CHP, biomass and GSHP scenarios
appear to remain feasible even with a 20% cost increase.
The implications of these results on the next steps for Forest Heath District Council are presented
in section 7.
Heat Network Opportunities
70
6. PROJECT OUTLINE RISK ASSESSMENT
This section presents an outline risk assessment for the preferred project opportunity outlined in
section 5. A number of key risks were identified relating to four main aspects of project
implementation: technical, commercial, financial and planning.
A risk register was created and is presented in Table 39. Each of the identified risks is
summarised below.
6.1 Technical Risks
Accuracy of Heat Demand Estimates
The Mildenhall Hub project is within the early phases of the development process and the design,
size and layout is potentially subject to significant change. The energy demand assessment has
been undertaken using the concept layout and floor areas current at the time of the analysis.
Consequently, there is a significant risk that the energy demands of the Hub will change which
will jeopardise the validity of the assumptions, analysis and conclusions presented in this report.
In order to mitigate against this risk, the energy demand and supply assessment should be
revisited in detail once the outline and detailed design for the Mildenhall Hub has been fixed.
Hub heating system design – i.e. traditional opposed to low temp system
The heat supply options assessed during the energy master plan for Mildenhall include low
temperature heat generators (LTHG) such as WSHP and GSHP. These produce heat at a
temperature of up to 45 °C and are best suited to low temperature heating systems (LTHS), such
as underfloor heating or modern, high surface area heat emitters (radiators). In order to protect
against legionella, DHWs systems supplied by LTHGs require supplementary heating. This is
normally provided by electrical heating elements located within DHW storage tanks or traditional
fossil fuel fired or electric low temperature hot water (LTHW) boilers.
Traditional LTHW heating systems are operated at much higher temperatures than LTHS,
typically between 70 °C and 80 °C. In order to be compatible with LTHW heating systems, the
temperature of the heat output from LTHS would need to be increased by an auxiliary heat
source such as gas fired or electric boilers. This will increase heating energy usage and
associated costs of the Hub as well as decreasing potential carbon savings, thereby significantly
reduces the benefit of utilising LTHGs
Heat sources that produce LTHW, such as natural gas fired CHPS and biomass fired boilers, are
compatible with both LTHS and LTHW heating systems.
There is a risk that the final Mildenhall Hub design includes a LTHW heating system that is not
compatible with, and will therefore exclude, LTHGs as potential heat supply assets. Since the
Mildenhall Hub project is currently in the concept design phase there is an opportunity to ensure
a LTHS is implemented into the final design. This will mitigate against this risk and ensure the
Hub’s heating system is flexible and compatible with both LTHG and LTHW heat sources.
Ground conditions As discussed in section 5.2.7, the ground conditions around the Mildenhall Hub will dictate the length requirement and associated cost of the ground loop as well as the quantity of heat than can be safely extracted on an annual basis. The heat extraction potential, and ground loop requirements and costs presented in this report are based on high level assumptions. There is a
Heat Network Opportunities
71
risk that these assumptions do not reflect the actual requirements for the Mildenhall Hub GSHP option. Consequently, there is a risk that the ground loop needs to be significantly larger than estimated in this report in order to achieve the same stated heat pump output. This would increase the capital costs and therefore affect the economic performance of the GSHP option. In addition, local soil conditions may restrict the quantity of heat that can be extracted locally, meaning the heat pump size is over estimated and a greater reliance on fossil fuel back up plant will be necessary.
In order to mitigate against this risk during future feasibility phases, it is recommended that a
ground condition survey is undertaken to accurately determine heat loop requirements and costs,
as well as determine the quantity of heat that can be sensibly extracted annually. Properties of River Lark
The heat that can be extracted from a body of water by a WSHP is a function of the flow rate and
volume of the pool in which the coil is situated. The Environment Agency place strict limitations
on allowable temperature changes to a water body that result from water and heat extraction /
discharge in order to protect the ecology. This will place a limit on the allowable heat extraction
from the River Lark by the potential Mildenhall Hub WSHP and will be particularly relevant in
periods of low flow such as during the summer months.
There is a risk that the annual heat output estimated during the EnergyPro modelling analysis for
the Mildenhall Hub has been overestimated. This will increase the heat output required from the
fossil fuel fired back up plant.
In order to mitigate against this risk, it will be necessary to undertake a detailed river survey and
formal discussions with the Environment Agency during any subsequent feasibility phase to
determine maximum permissible annual heat extraction from the River Lark.
6.2 Commercial Risks
Commercial Arrangement and Delivery Vehicle
If the project developed into a wholly private sector based scheme, the Local Authority would not
have any control over how scheme developed and there is a risk that the private sector may not
grow the scheme to its full potential. If the project remains wholly Local Authority led, they
remain in full control, but also take on full developmental and operational risk.
Whichever delivery route is taken forward Forest Heath District Council will need to procure the
scheme through the private sector since it won’t have the necessary expertise to develop or
operate the scheme alone. The Local Authority will need technical, commercial and legal support
through this process so that it can secure the best partnering arrangement in its interests and
those of the local community.
Policy Assumptions made in the analysis were based on policy at the time of writing. The Government’s policies and incentives are subject to change and this presents an on-going risk to the project. A specific example of this is the uncertainty around RHI. There is a risk that the tariff may reduce or be removed completely over time thus providing the system operator with lower revenue. The impact of this is explored in more detail in section 5.3.3.
Heat Network Opportunities
72
Development Risk
Programme delay presents a further development risk, in addition to difficulties encountered by
Forest Heath District Council in planning.
Operational Risk
The operating cost may be higher than expected due to the following issues occurring:
high heat losses
high return temps
high heat purchase / generation costs
high maintenance costs
lower than expected operating margins
lower volume of heat sales
poor take up
Consideration could also be given to adopting a tariff structure that incentivises retrofitting
measures that address heating system return temperatures.
6.3 Financial Risks
Development and operational costs
The development and operational costs presented in this report are derived from similar projects
using Ramboll’s database. These costs are highly project specific and will be dependent on how
the energy system is designed, procured and operated.
There is a risk that these costs have been underestimated or overestimated which will affect the
economic performance of the five options assessed. In order mitigate against this risk, a detailed
assessment of the development and operational costs should be undertaken for the options taken
forward to the detailed feasibility stage.
Capital Costs
The capital costs used within this study are based on Ramboll’s database of historic supplier data
and benchmarking. Specific quotations were not obtained and there is a risk that the stated
capital costs are underestimated or overestimated. This will affect the validity of the analysis
undertaken and the arrived conclusions.
In order to mitigate against this risk it is recommended that a cost consultant is commissioned to
conduct a detailed evaluation of project costs as part of any future development phases.
Unknown Future Project Expansion
The extent and nature of the future developments surrounding the Mildenhall Hub is unknown. It
is therefore difficult to future proof the Hub’s energy plant to supply a future district heating
network of unknown size. Oversizing the energy centre for potentially future will add significant
risk to the economic performance of the Mildenhall Hub energy scheme.
This risk would be considered especially high since it is likely that the land surrounding the Hub
will be developed into low density housing. The options for future proofing the Mildenhall Hub
Energy Scheme for potential future expansion are discussed in more detail in section 7.3.3.
Heat Network Opportunities
73
6.4 Planning Risks
Restrictions on River Lark
In order to protect the ecology of water bodies, the Environment Agency place strict limitations
on temperature changes that arise from water and heat extraction / discharge. This could
potentially limit the quantity of heat that can be extracted by a WSHP located at the Mildenhall
Hub. This is discussed in more detail in section 6.1. In addition, the Environment Agency may be
unwilling to grant a licence to extract heat from the River Lark. Should this option be taken
forward to detailed feasibility it is recommended that early discussions are held with the
Environment Agency to determine the licence requirements and any restrictions that could apply.
Heat Network Opportunities
74
6.5 Risk Register
Table 39: Risk Register for Mildenhall Hub
Risk No. Risk description Potential impact (including on cost and
schedule)
Impact (low
1- high 4)
Likelihood
(low 1-
high 4)
Current Risk
Rating
Mitigation to date Mitigation
Achieved Date
Further Action Action Owner
1 Accuracy of estimated heat demand Business case affected by variation in
heat sales.
2 3 6 All available information used and
comparisons made to similar buildings.
Jan-2016 At the next project stage the heat demand
calculations should be revised as new design
information becomes available.
Local Authority
/ Consultant
2 Hub heating system design Business case and technical viability. 3 1 3 Assumptions regarding heating system
expectations clearly stated in EMP report.
Jan-2016 Importance of appropriate heating system must be
emphasised throughout ongoing design stages.
Local Authority
/ Consultant
3 Ground conditions Presence of low conductivity soil will
increase collector loop length and
therefore cost
3 3 9 UK soil map consulted Jan-2016 Detailled soil investigations to be undertaken during
the design phase if GSHP selected
Local Authority
/ Consultant
4 Properties of River Lark (WSHP only) unsuitable for WSHP Technical and economic viability. 3 3 9 River observed during site visit. Nov-2015 Gather data from Environment Agency on
temperature, flow rate and depth and feasibility
stage.
Local Authority
/ Consultant
5 Uncertainty around commercial arrangement There may be additional costs to the
project or extensions to timescale
depending on chosen arrangement.
1 2 2 NA NA Conduct detailed business case and soft market
testing to deduce preferred commercial arrangement
and its effects on project,
Local Authority
/ Consultant
6 Assumptions around incentives are subject to uncertainty
and government policy
Business case, reduction removal of
incentives will impact business case and
project viability
2 2 4 Cost of heat has been modelled with and
without RHI, a conservative value has been
assumed in the modelling
Jan-2016 Status of Incentives to be kept under review
throughout feasibilty stage and on a continuous basis
as the project develops
Local Authority
/ Consultant
7 Development risk (change to master plan) Changes to heat load affect business case
and technical viability.
3 1 3 Sensitivity analysis carried out to show
effects of reduced load.
Jan-2016 Review project economics whenever significant
changes are made to development plans.
Local Authority
8 Operating costs higher than expected Business case 2 3 6 O&M costs based on previous projects. Jan-2016 Gather further data from suppliers at fasibility stage. Local Authority
/ Consultant
9 Development, investment and operational costs are
subject to uncertainty and will change as the project
develops
Business case, impact on NPVs, IRRs 2 2 4 Costs based on data from previous projects Jan-2016 Continued refinement of design assumptions and
improved cost estimates at feasibility stage. Engage a
cost consultant at delivery stage.
Local Authority
/ Consultant
10 Capital cost are higher than BaU case. Project fails to get funding, not
developed, opportunity lost
1 3 3 Sensitivity analysis carried out to quantify
risk.
Jan-2016 Feasibility work should include detailed cost
research.
Local Authority
/ Consultant
11 Current assumptions don't allow for future expansion of
network i.e. to new developments which are not
currently known and planned. This may reduce the long-
term business case for investment beyond what has been
proposed here.
Business case. Project is limited in its
ability to expand beyond the Hub, new
developments cannot connect.
2 2 4 There are currently no planned
developments of scale in Mildenhall. Design
for low temperatures in new development
could liberate network capacity.
Jan-2016 Consider potential for decentralised supplies feeding
into a larger network. Blanked connections sized for
Hubs full load should be included on the heating
system header to allow connection to any future DHN
or Energy Centre.
Local Authority
/ Consultant
12 Air quality management (CHP and Biomass only) If further measures are required to
address emissions the business case ,ay
be affected.
3 1 3 No AQMA regulations currently in place in
Mildenhall.
Jan-2016 Review status at design stage. Local Authority
/ Consultant
13 Environment agency and use of River Lark (WSHP only) Potential restrictions to use of river may
limit viability.
4 2 8 NA NA Conduct full investigation at feasibility stage. Local Authority
/ Consultant
Planning
Mitigation & ActionRisk Identification Risk Assessment
Commercial
Financial
Technical
Heat Network Opportunities
75
7. CONCLUSIONS, RECOMMENDATIONS AND NEXT STEPS
This section outlines the conclusions, recommendations and next steps for West Suffolk, resulting
from the techno-economic analysis and risk appraisal.
7.1 Conclusions
The results of the study suggest that that under the assumptions of the techno-economic model,
the GSHP options is the most economically attractive. However, it is important to note that the
project is heavily reliant in the availability of RHI revenue at its current rates and sudden removal
of the RHI scheme may render the project unfeasible. Therefore moving forward with this
technology should only be done following further research into the Government’s plans for the
continuation of current incentives. Increasing the assumed capital expenditure by 20% or
reducing the assumed heat sale price by 20% does not drive down the project IRRs to an
unattractive level.
The gas CHP case was found to be the second most attractive technology option in terms of
economics, achieving an IRR of approximately 11%. However, the project economics are very
sensitive to the heat sale price and therefore the business case should be reassessed upon
further investigation into the commercial arrangements. A positive aspect of CHP is that it is not
affected by changes to RHI revenue.
Biomass has the potential for significant carbon savings when compared to the CHP and solar
thermal options. However, the economic results show that this solution may only be attractive for
a public led project. For this reason any variation in the heat sale and CAPEX assumptions was
found to be a deciding factor in the validity of the scheme.
The results of the WSHP show that the economic performance of this solution is marginal and
only likely to be attractive for a public led project. The capital expenditure was found to be higher
than all other scenarios mostly due to the requirement for pipe infrastructure between the river
and the plant room. This may present an additional barrier to implementation.
The solar thermal option was not found to be feasible in any case. The sensitivity analysis
showed that even improvements to the heat sale prices and capital costs could not bring the
project economics up to an acceptable level.
The integration of a Solar PV installation will increase the capital outlay for the project. However,
solar PV was found to result in small improvements both in terms of economics and carbon
emissions savings for CHP, biomass, WSHP and GSHP scenarios.
Overall, three out of the five scenarios stood out as being valid energy solutions for
the Mildenhall Hub: GSHP, gas CHP and heat-only biomass.
Each of the options was found to be sensitive to changes in key project variables
and therefore further investigation is required to establish the single preferred
scheme for Forest Heath District Council to implement.
Heat Network Opportunities
76
7.2 Recommendations
It is recommended that Forest Heath District Council progresses all three of the preferred options
of GSHP, CHP and biomass to feasibility stage.
A presentation of the energy masterplanning results should be given to all relevant stakeholders
to gauge interest in the proposed schemes and obtain feedback on how each technology might or
might not be appropriate for their requirements. Stakeholder engagement is crucial at the
earliest project stages to ensure opportunities or barriers are not overlooked.
Further techno-economic modelling must be conducted when more accurate information is
available regarding the final masterplan for the Mildenhall Hub. At present the energy demand
information is not deemed to be accurate enough to clearly state feasibility.
7.3 Next Steps
7.3.1 Business Model and Business Case
There is a great deal more work to be done around technical, financial and commercial analysis
and de risking of the project before it can progress to business case.
To progress the project further, will require a detailed business case that should include financial
modelling as stated above, and also consideration of appropriate procurement, delivery and
governance options for the project. This should include the relative advantages and
disadvantages of each option, together with identification of the preferred course of action.
7.3.2 Ensuring Correct Design Standards are adopted
The design of the internal heating systems at the Mildenhall Hub will have a significant impact on
the operational capacity and efficiency of the primary supply technology.
The final Hub design should incorporate appropriate internal heating system designs to ensure
flow and return temperatures are compatible with the primary supply technology. Forest Heath
District Council, through their Planning and Building Control departments, should ensure that
systems are being designed, installed and commissioned appropriately.
Although no new developments were identified as part of this EMP, new developments may
emerge in future within the vicinity of the network. If this is the case then appropriate design
standards should be considered so that opportunities for connection are not missed.
7.3.3 Safeguarding Wider Network Demand
Since the extent and nature of the future developments around the Mildenhall Hub is unknown, it
is difficult to future proof the Hub’s energy plant to supply a future district heating network.
Furthermore, oversizing the energy plant would add cost to the project and therefore will put the
economic performance of the Hub’s energy strategy at risk. This risk is considered high as it is
likely that the land surrounding the Hub will be developed into low density housing which rarely
has an economic case for the establishment of a district heating network. However, the following
measures will provide some flexibility and facilitate development of a district heating network.
Heat Network Opportunities
77
1. Provide sufficient space within the Energy Centre to locate an additional future boiler. The
headers within the energy centre should include blank connections for an additional heat
supply asset. This will also facilitate the connection of temporary boilers for use during any
major outage (major boiler or CHP service) or reworking of the energy centre.
2. The headers within the energy centre should include a set of connections through which the
full heat demand of the Mildenhall Hub can be provided. This would allow the Hub to be
connected to a future district heating network should any opportunity arise.
3. The energy centre should be located and designed such that heat supply assets can be
removed and relocated to a future energy centre. This would enable the boilers to be utilised
as part of a future district heating network should any opportunity arise.
7.4 Summary Implementation Plan
Heat Network Opportunities
78
APPENDIX 1
ENERGY DEMAND MAP DATA
Heat Network Opportunities
79
HEAT
Address Postcode Building Type Heat Demand
(kWh) Source
1 Breck Gardens IP28 7AU Residential 138,754 National Heat Map filtered and aggregated
Plot 6 Land At Queensway Farm Queensway
Residential 136,595 National Heat Map filtered and aggregated
Mildenhall College - Sheldrick Way IP287JX Education 306,739 National Heat Map filtered and aggregated
Mildenhall Hub - Sheldrick Way
Central Hub 44,087 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way
Government
Buildings 269,706 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way IP287JX Police 56,891 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way IP287JX Recreational 679,113 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way IP287JX Health 44,912 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way IP287JX Education 12,127 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way IP287JX Library 17,833 Mildenhall Hub benchmarked
Mildenhall Hub - Sheldrick Way IP287JX Education 606,497 Mildenhall Hub benchmarked
Wamil Court Wamil Way IP28 7JU Health 447,978
National Heat Map filtered and
aggregated
17 Mill Street IP287DP Hotels 188,430 Estimated using CIBSE TM46
Mildenhall Swimming Pool Recreation Way IP287HG Government Buildings 815,767 Billing data from the Council
32 St Andrews Street IP287HB Retail 234,980 National Heat Map filtered and aggregated
25 The Bell Hotel High Street IP287EA Hotels 201,630 Estimated using CIBSE TM46
Flat 2 14 Mill Street IP28 7DP Retail 102,899 National Heat Map filtered and aggregated
Second Floor 8 Breckland House Churchyard IP287EE Health 104,190
National Heat Map filtered and
aggregated
2 A Mill Street IP28 7DP Hotels 207,484 National Heat Map filtered and aggregated
Flat 14 A High Street IP28 7EQ Hotels 249,494 National Heat Map filtered and aggregated
14 Market Place IP287EF Hotels 183,760 National Heat Map filtered and aggregated
15 Market Place IP287EF Retail 158,951 National Heat Map filtered and
Heat Network Opportunities
80
Address Postcode Building Type Heat Demand
(kWh) Source
aggregated
Spar Stores Market Place IP28 7EF Hotels 121,391
National Heat Map filtered and
aggregated
5 King Street IP287EZ Commercial Offices 159,193 National Heat Map filtered and aggregated
Flat 4 5 Police Station Square IP28 7ER Hotels 115,456 National Heat Map filtered and aggregated
Fire Station North Terrace IP287AA Government Buildings 146,806
National Heat Map filtered and aggregated
Mildenhall Police Station Kingsway IP287HS Government Buildings 146,806
National Heat Map filtered and aggregated
97 Kingsway IP287HS Transport 216,352 National Heat Map filtered and aggregated
Top Flat 6 Kingdom Hall Of Jehovahs Witnesses North Terrace IP28 7AA Industrial 266,915
National Heat Map filtered and aggregated
Forest Heath District Council College Heath Road IP287EY Government Buildings 104,999 Billing data from the Council
Flat Mildenhall Social Club Recreation Way IP28 7HG Recreational 131,682
National Heat Map filtered and
aggregated
48 50 Kingsway IP287HR Government Buildings 146,806
National Heat Map filtered and aggregated
Land Adjacent Great Heath Cp School St Johns Close
Education 136,468 National Heat Map filtered and aggregated
143 St Johns Close IP287NX Health 541,200 Estimated using CIBSE TM46
77 Merlin House Fred Dannatt Road IP287RD Transport 548,011
National Heat Map filtered and
aggregated
Unit 3 30 Hampstead Avenue IP287AS Transport 155,311 National Heat Map filtered and aggregated
Cedar Lodge Chiswick Avenue IP287BD
Government
Buildings 22,971 Billing data from the Council
Unit B 83 James Carter Road IP287DE Industrial 236,260 National Heat Map filtered and aggregated
Plot 74 Fred Dannatt Road
Industrial 241,922 National Heat Map filtered and aggregated
Plot 69 Fred Dannatt Road
Industrial 241,922 National Heat Map filtered and aggregated
Plot 70 Fred Dannatt Road
Retail 187,266 National Heat Map filtered and
Heat Network Opportunities
81
Address Postcode Building Type Heat Demand
(kWh) Source
aggregated
Unit 23 James Carter Road IP287DE Industrial 241,922
National Heat Map filtered and
aggregated
Unit 27 James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Unit 25 James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Plot 60 James Carter Road
Industrial 241,922 National Heat Map filtered and aggregated
Unit 30 James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Unit 31 James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Unit 32 James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Unit 35 James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Unit 17 Hampstead Avenue IP287AS Industrial 241,922
National Heat Map filtered and
aggregated
Unit 12 Plot 24 Hampstead Avenue IP28 7AS Industrial 745,398 National Heat Map filtered and aggregated
Rd Castings Leyton Avenue IP287BL Industrial 1,590,040 National Heat Map filtered and aggregated
Unit A 53 Leyton Avenue IP287BB Transport 182,561 National Heat Map filtered and aggregated
Plot 58 Finchley Avenue
Transport 194,484 National Heat Map filtered and aggregated
Plot 59 Finchley Avenue
Industrial 241,922
National Heat Map filtered and
aggregated
Unit 10 Leyton Avenue IP287BL Industrial 249,330 National Heat Map filtered and aggregated
Unit 8 Leyton Avenue IP287BL Industrial 241,922
National Heat Map filtered and
aggregated
Unit 2 Leyton Avenue IP287BL Industrial 241,922 National Heat Map filtered and aggregated
Unit 1 Leyton Avenue IP287BL Industrial 241,922 National Heat Map filtered and aggregated
Heat Network Opportunities
82
Address Postcode Building Type Heat Demand
(kWh) Source
Plot 44-45 Leyton Avenue
Industrial 241,922
National Heat Map filtered and
aggregated
Plot 14 Finchley Avenue IP287BG Industrial 148,558 National Heat Map filtered and aggregated
Plot 7 Holborn Avenue
Industrial 241,922
National Heat Map filtered and
aggregated
Plot 8 Holborn Avenue IP287AN Transport 408,668
National Heat Map filtered and
aggregated
Plot 10 Finchley Avenue
Industrial 241,922 National Heat Map filtered and aggregated
95 Hampstead Avenue IP287AS Industrial 241,922 National Heat Map filtered and aggregated
11 B Finchley Avenue IP287BG Industrial 241,922 National Heat Map filtered and aggregated
11 B Finchley Avenue IP287BG Transport 149,522 National Heat Map filtered and aggregated
96 Hampstead Avenue IP287AS Industrial 241,922 National Heat Map filtered and aggregated
Plot 88 James Carter Road
Commercial Offices 114,881 National Heat Map filtered and aggregated
38 Southgate Avenue IP287AT Industrial 241,922 National Heat Map filtered and aggregated
Mildenhall Monumentals 37 Southgate Avenue IP287AT Industrial 241,922 National Heat Map filtered and aggregated
36 Southgate Avenue IP287AS Industrial 241,922 National Heat Map filtered and aggregated
39 Hampstead Avenue IP287AS Industrial 241,922 National Heat Map filtered and aggregated
40 Hampstead Avenue IP287AS Industrial 241,922
National Heat Map filtered and
aggregated
41 Hampstead Avenue IP287AS Industrial 241,922
National Heat Map filtered and
aggregated
94 C Hampstead Avenue IP287AS Industrial 241,922 National Heat Map filtered and aggregated
93 Hampstead Avenue IP287AS Industrial 241,922
National Heat Map filtered and
aggregated
Plot 52 Chiswick Avenue
Industrial 241,922 National Heat Map filtered and
Heat Network Opportunities
83
Address Postcode Building Type Heat Demand
(kWh) Source
aggregated
F W Cocksedge & Sons Ltd 25 Hampstead Avenue IP287AS Retail 179,199
National Heat Map filtered and
aggregated
Safepac House Field Road IP287AP Transport 421,243 National Heat Map filtered and aggregated
Plot 21 Chiswick Avenue
Industrial 241,922 National Heat Map filtered and aggregated
Plot 23 Chiswick Avenue
Industrial 241,922 National Heat Map filtered and aggregated
Unit B 18 Delmore House Chiswick Avenue IP287AY Industrial 241,922 National Heat Map filtered and aggregated
Delmore House Chiswick Avenue
Industrial 241,922 National Heat Map filtered and aggregated
Plot 17 Chiswick Avenue
Industrial 241,922 National Heat Map filtered and aggregated
Plot 53 Chiswick Avenue IP287AY Transport 191,822 National Heat Map filtered and aggregated
Plot 54 Chiswick Avenue
Industrial 259,244
National Heat Map filtered and
aggregated
Plot 55 Chiswick Avenue
Industrial 241,922 National Heat Map filtered and aggregated
56 Chiswick Avenue IP287AY Industrial 241,922 National Heat Map filtered and aggregated
Plot 15 Chiswick Avenue
Industrial 241,922 National Heat Map filtered and aggregated
St Marys Primary School North Terrace IP287AB Education 150,245 National Heat Map filtered and aggregated
College Heath Middle School Girton Close IP287PT Education 274,752
National Heat Map filtered and
aggregated
Plot 52a Chiswick Avenue IP287AY Industrial 241,922 National Heat Map filtered and aggregated
Logika House 2 Holborn Avenue IP287AN Industrial 241,922
National Heat Map filtered and
aggregated
Unit 10 Chiswick Avenue IP287AY Industrial 241,922 National Heat Map filtered and aggregated
Unit 9 Chiswick Avenue IP287AY Industrial 241,922 National Heat Map filtered and aggregated
Heat Network Opportunities
84
Address Postcode Building Type Heat Demand
(kWh) Source
31 Southgate Avenue
Industrial 241,922
National Heat Map filtered and
aggregated
30 A Hampstead Avenue IP287AS Transport 193,307 National Heat Map filtered and aggregated
32 Southgate Avenue IP287AT Industrial 241,922
National Heat Map filtered and
aggregated
27 28 Hampstead Avenue IP287AR Industrial 206,087
National Heat Map filtered and
aggregated
Silverline Office Equipment Ltd James Carter Road IP287DE Industrial 241,922 National Heat Map filtered and aggregated
Plot 57 Finchley Avenue IP287BG Industrial 241,922 National Heat Map filtered and aggregated
Nestor Uk Ltd Chiswick Avenue IP287AX Commercial Offices 52,294 Benchmarked
Nestor Uk Ltd Chiswick Avenue IP287AX Transport 621,570 National Heat Map filtered and aggregated
Heat Network Opportunities
85
COOLING
Address Building Type Postcode Cooling Demand
(kWh)
British Red Cross Recreation Way Commercial Offices IP287HG 11,787
24 Swallow Mead Farm Worlington Road Commercial Offices IP287DY 12,370
31 Wamil Way Commercial Offices IP287JU 5,556
Beeches Moat The Street Commercial Offices IP286AW 4,967
13 Mill Street Commercial Offices IP287DW 13,295
47 Lloyds Tsb Bank High Street Commercial Offices IP287DZ 15,698
46 St Andrews Street Commercial Offices IP287HB 13,526
27 29 Barclays Bank High Street Commercial Offices IP287EA 7,287
30 St Andrews Street Commercial Offices IP287HB 1,814
Second Floor 8 Breckland House Churchyard Commercial Offices IP287EE 7,364
34 High Street Commercial Offices IP287EA 11,486
27 High Street Commercial Offices IP287EA 5,092
11 Market Place Commercial Offices IP287EF 5,839
20 B Market Place Commercial Offices IP287EF 8,290
5 King Street Commercial Offices IP287EZ 26,008
1 Police Station Square Commercial Offices IP287ER 1,743
2 The Forge Cottage High Street Commercial Offices IP287EJ 1,553
Springvale Police Station Square Commercial Offices IP287ER 3,120
The Court House Queensway Government Buildings IP287EW 18,780
Fire Station North Terrace Government Buildings IP287AA 13,044
Mildenhall Police Station Kingsway Government Buildings IP287HS 23,140
Mildenhall District Office Government Buildings IP287EY 148,775
16 Mill Street Commercial Offices IP287DP 1,275
48 50 Kingsway Government Buildings IP287HR 7,394
Radio Base Station 18 A Chiswick Avenue Commercial Offices IP287AY 5,025
Heat Network Opportunities
86
Address Building Type Postcode Cooling Demand
(kWh)
Cedar Lodge Chiswick Avenue Commercial Offices IP287BD 32,809
Unit 1g Plot 84 Gregory Road Commercial Offices IP287DF 2,740
Merlin Park Fred Dannatt Road Commercial Offices IP287RD 7,947
Unit 21 James Carter Road Commercial Offices IP287DE 7,447
Unit 4 Wallis Court James Carter Road Commercial Offices IP287DD 21,037
Plot 88 James Carter Road Commercial Offices
48,505
First Floor Front 26 Hampstead Avenue Commercial Offices IP287AS 22,414
Unit 15 Chiswick Avenue Commercial Offices IP287AY 8,579
Nestor Uk Ltd Chiswick Avenue Commercial Offices IP287AX 17,050
M And M Leisure Field Road Commercial Offices IP287AL 24,453
Beatrice Carter Place Field Road Commercial Offices IP287AL 24,068
Plot 1 Holborn Avenue Commercial Offices
29,531
Mildenhall Hub Government Buildings
4,613
Mildenhall Hub Central Hub - Public Access
11,160
Heat Network Opportunities
87
ELECTRICITY
Address Building Type Postcode Power Demand (kWh)
Worlington Hall Hotel Mildenhall Road Hotels IP288RX 97,853
The Walnut Tree Newmarket Road Hotels IP288RU 35,266
Milden Court Hereward Avenue Health IP287LP 28,407
34 Market Place Retail IP287EQ 60,864
British Red Cross Recreation Way Commercial Offices IP287HG 48,671
26 C Worlington Road Retail IP287DY 47,928
24 Swallow Mead Farm Worlington Road Commercial Offices IP287DY 51,077
20 Cameron Mews Mill Street Hotels IP287DP 32,614
31 Wamil Way Commercial Offices IP287JU 22,941
Wamil Court Wamil Way Nursing home IP287JU 84,548
42 Queens Arms Queensway Hotels IP287JY 20,277
Barton Hall The Street Nursing home IP286AW 20,041
Bell Cottage Bell Lane Hotels IP286AJ 3,629
The Bell Bell Lane Hotels IP286AJ 11,319
Beeches Moat The Street Commercial Offices IP286AW 20,508
17 Mill Street Hotels IP287DP 137,232
Riverside Clinic Vets 15 Silver Lodge Mill Street Health IP287DP 11,347
13 Mill Street Commercial Offices IP287DW 54,897
11 Mill Street Retail IP287DP 66,344
5 A Mill Street Retail IP287DP 205,976
3 Mill Street Retail IP287DP 180,808
47 Lloyds Tsb Bank High Street Commercial Offices IP287DZ 86,426
The Pavilion Recreation Way Health IP287HG 50,127
32 St Andrews Street Retail IP287HB 699,204
46 St Andrews Street Commercial Offices IP287HB 55,848
25 The Bell Hotel High Street Hotels IP287EA 100,270
27 29 Barclays Bank High Street Commercial Offices IP287EA 40,118
13 St Andrews Street Hotels IP287HB 21,534
30 St Andrews Street Commercial Offices IP287HB 7,489
22 St Andrews Street Retail IP287HB 24,968
37 B High Street Retail IP287EA 125,904
37 A High Street Retail IP287EA 68,184
37 High Street Retail IP287EA 143,976
35 High Street Retail IP287EA 146,496
Heat Network Opportunities
88
Address Building Type Postcode Power Demand (kWh)
14 Mill Street Retail IP287DP 270,392
Second Floor 8 Breckland House Churchyard Commercial Offices IP287EE 40,543
30 High Street Retail IP287EQ 78,240
34 High Street Commercial Offices IP287EA 63,232
4 Mill Street Retail IP287DP 148,032
6 Mill Street Retail IP287DP 133,596
27 High Street Commercial Offices IP287EA 28,035
23 A High Street Retail IP287EA 51,464
23 High Street Retail IP287EA 49,816
22 26 High Street Retail IP287EQ 108,224
20 Tigers Head High Street Hotels IP287EQ 24,917
18 High Street Retail IP287EQ 171,368
16 High Street Retail IP287EQ 346,408
14 High Street Hotels IP287EQ 39,941
13 High Street Retail IP287EQ 140,856
1 2 Market Place Retail IP287EF 185,320
4 Market Place Retail IP287EF 113,472
5 Market Place Retail IP287EF 77,616
7 Market Place Health IP287EG 44,894
9 Market Place Hotels IP287EF 7,022
9 A Market Place Retail IP287EF 37,752
33 A Market Place Retail IP287EF 122,184
29 B Market Place Retail IP287EF 129,480
30 Market Place Retail IP287EF 24,224
31 Market Place Retail IP287EF 35,592
32 Market Place Retail IP287EF 73,064
21 The White Hart Hotel High Street Hotels IP287EA 32,434
10 Market Place Health IP287EF 20,007
12 Market Place Retail IP287EF 277,424
11 Market Place Commercial Offices IP287EF 32,146
13 Market Place Retail IP287EF 82,632
14 Market Place Hotels IP287EF 23,576
15 Market Place Retail IP287EF 121,736
27 Market Place Retail IP287EF 338,512
28 Market Place Hotels IP287EF 18,594
21 Market Place Retail IP287EF 51,528
23 Market Place Retail IP287EF 75,272
Heat Network Opportunities
89
Address Building Type Postcode Power Demand (kWh)
24 Market Place Retail IP287EF 76,904
26 Market Place Retail IP287EF 75,912
20 Market Place Retail IP287EF 65,192
19 Market Place Retail IP287EF 59,776
18 Market Place Retail IP287EF 59,752
17 Market Place Retail IP287EF 58,616
20 B Market Place Commercial Offices IP287EF 45,637
7 King Street Retail IP287EZ 201,432
39 King Street Retail IP287EZ 35,848
54 Kingsway Retail IP287HR 131,480
5 King Street Commercial Offices IP287EZ 143,186
1 King Street Health IP287ES 15,788
9 Maids Head Kingsway Hotels IP287HN 39,637
7 Police Station Square Retail IP287ER 39,216
6 Police Station Square Retail IP287ER 67,960
4 5 Police Station Square Hotels IP287ER 21,034
1 Police Station Square Commercial Offices IP287ER 9,597
12 C High Street Hotels IP287EQ 11,778
12 B High Street Retail IP287EQ 74,480
12 A High Street Retail IP287EQ 80,928
10 High Street Retail IP287EQ 86,472
8 High Street Retail IP287EQ 33,120
1 New Street Retail IP287EN 46,024
2 New Street Retail IP287EN 69,264
4 New Street Retail IP287EN 114,968
2 The Forge Cottage High Street Commercial Offices IP287EJ 8,548
Springvale Police Station Square Commercial Offices IP287ER 17,178
3 High Street Retail IP287EJ 189,240
1 Manor Court High Street Retail IP287EH 57,192
2 Manor Court High Street Retail IP287EH 46,504
3 Manor Court High Street Retail IP287EH 60,680
4 Manor Court High Street Retail IP287EH 45,000
5 Manor Court High Street Retail IP287EH 49,152
6 Manor Court High Street Retail IP287EH 31,408
7 High Street Retail IP287EQ 11,512
9 High Street Retail IP287EQ 14,688
11 High Street Retail IP287EQ 179,720
Heat Network Opportunities
90
Address Building Type Postcode Power Demand (kWh)
North Terrace Garage North Terrace Retail
317,208
The Court House Queensway Government Buildings IP287EW 50,889
Fire Station North Terrace Government Buildings IP287AA 35,346
Mildenhall Police Station Kingsway Government Buildings IP287HS 62,701
Ambulance Station Chestnut Close Health IP287NL 24,885
103 Half Moon Inn Kingsway Hotels IP287HS 27,023
9 Brandon Road Retail IP287HZ 42,996
Mildenhall Health Clinic Chestnut Close Health IP287NL 56,696
Holiday Accomodation 23 North Terrace Hotels
24,302
1 Market Street Retail IP287ES 80,400
Mildenhall District Office Government Buildings IP287EY 320,937
16 Mill Street Commercial Offices IP287DP 7,020
48 50 Kingsway Government Buildings IP287HR 20,036
Mildenhall Tyre 3 Field Road Retail IP287AF 55,308
143 St Johns Close Retail IP287NX 106,284
Unit C 81 Fred Dannatt Road Retail IP287RD 176,496
Ro 25a Hampstead Avenue Retail IP287AS 254,504
Radio Base Station 18 A Chiswick Avenue Commercial Offices IP287AY 20,748
Cedar Lodge Chiswick Avenue Commercial Offices IP287BD 31,976
85 Gregory Road Retail IP287DF 540,504
Unit 1g Plot 84 Gregory Road Commercial Offices IP287DF 11,314
Unit 1h Plot 84 Gregory Road Retail IP287DF 27,808
Unit 1i Plot 84 Gregory Road Retail IP287DF 27,984
Unit 1e Plot 84 Gregory Road Retail IP287DF 23,344
Unit 1c Plot 84 Gregory Road Retail IP287DF 19,116
Unit 1a Plot 84 Gregory Road Retail IP287DF 28,104
Unit A 83 James Carter Road Commercial Offices IP287DE 94,881
82 A James Carter Road Retail IP287DE 62,280
82 D James Carter Road Retail IP287DE 110,416
5 Merlin Park Fred Dannatt Road Retail IP287RD 94,112
13 Merlin Park Fred Dannatt Road Retail IP287RD 57,752
14 Merlin Park Fred Dannatt Road Retail IP287RD 61,712
15 Merlin Park Fred Dannatt Road Retail IP287RD 57,776
16 Merlin Park Fred Dannatt Road Retail IP287RD 59,128
12 Merlin Park Fred Dannatt Road Retail IP287RD 96,256
Merlin Park Fred Dannatt Road Commercial Offices IP287RD 32,812
Plot 70 Fred Dannatt Road Retail
777,400
Heat Network Opportunities
91
Address Building Type Postcode Power Demand (kWh)
Unit 1-5 65 James Carter Road Retail IP287DE 57,408
Unit 3 65 James Carter Road Retail IP287DE 57,832
Unit 4 James Carter Road Retail IP287DE 54,696
Unit 21 James Carter Road Commercial Offices IP287DE 30,749
Unit 26 James Carter Road Retail IP287DE 99,048
Unit 34 James Carter Road Retail IP287DE 125,032
Unit 33 James Carter Road Retail IP287DE 129,104
Unit 19 Hampstead Avenue Retail IP287AS 187,264
Unit 20b Leyton Avenue Retail IP287BL 184,860
Unit B 53 Leyton Avenue Retail IP287BL 342,212
47 Leyton Avenue Retail IP287BL 241,144
Unit 11 Leyton Avenue Retail IP287BL 59,452
Unit 10 Leyton Avenue Retail IP287BL 41,692
Unit 9 Leyton Avenue Retail IP287BL 42,808
Unit 7 Leyton Avenue Retail IP287BL 44,280
Unit 4 Leyton Avenue Retail IP287BL 45,168
Plot 43a Leyton Avenue Retail IP287BL 183,764
L G Aves And Son Finchley Avenue Retail IP287BG 132,504
Unit 4 Wallis Court James Carter Road Commercial Offices IP287DD 86,862
Plot 88 James Carter Road Commercial Offices
200,279
Unit 7 Chiswick Avenue Retail IP287AY 290,248
F W Cocksedge & Sons Ltd 25 Hampstead Avenue Retail IP287AS 1,003,816
First Floor Front 26 Hampstead Avenue Commercial Offices IP287AS 92,547
Field Road Service Station Field Road Retail IP287AL 42,440
Unit 15 Chiswick Avenue Commercial Offices IP287AY 35,424
14 Chiswick Avenue Retail IP287AY 87,112
Plot 18a Chiswick Avenue Retail
125,432
Nestor Uk Ltd Chiswick Avenue Commercial Offices IP287AX 70,400
M And M Leisure Field Road Commercial Offices IP287AL 100,966
Unit 1 Holborn Avenue Retail IP287AN 292,752
Unit 2 Holborn Avenue Retail IP287AN 190,144
Crossways North Terrace Health IP287AE 7,718
1 St Johns Close Retail IP287NT 17,724
Beatrice Carter Place Field Road Commercial Offices IP287AL 99,379
84 Field Road Health IP287AL 9,834
Unit 8 Chiswick Avenue Retail IP287BD 183,480
Plot 1 Holborn Avenue Commercial Offices
121,933
Heat Network Opportunities
92
Address Building Type Postcode Power Demand (kWh)
6 Merlin Park Fred Dannatt Road Retail IP287RD 87,992
Swimming Pool Recreational
234,619
Mildenhall Hub Government Buildings
36,118
Mildenhall Hub Police
10,465
Mildenhall Hub Health
18,155
Mildenhall Hub Education
548,477
Mildenhall Hub Central Hub
47,624
Mildenhall Hub Leisure Centre
270,137
Mildenhall Hub Commercial Offices
930,974
Heat Network Opportunities
93
APPENDIX 2
TECHNOLOGY OPTIONS APPRAISAL
Heat Network Opportunities
94
Heat Network Opportunities
95
Heat Network Opportunities
96