metedeconk river watershed protection & restoration plan · metedeconk river watershed...
TRANSCRIPT
Metedeconk River WatershedProtection & Restoration Plan
Stakeholder Advisory Committee MeetingJune 21, 2013
Metedeconk River Yacht Club
Project Overview
Funded by the New Jersey Department of Environmental Protection’s Watershed Restoration Program
$666,000 grant from NJDEP
$200,000 for Metedeconk plan development
$466,000 for implementation of highest-priority projects identified in the plan
$91,500 BTMUA in-kind match for planning phase
Main project goals:
Preserve the Metedeconk River as a viable water supply source for the region
Protect the health of the Barnegat Bay estuary
Eliminate water quality impairments, address TMDL’s, and attain compliance with the surface water quality standards throughout the watershed
Project results in formal plan
Strategy for Metedeconk watershed protection & restoration
Prioritized listing of projects/management actions that can be carried out by any of the stakeholders
Project Overview (cont’d)
Plan follows USEPA watershed plan guidance:
“Handbook for Developing Watershed Plans to Restore and Protect Our Waters”
Nine (9) minimum elements of watershed plans
Project Overview (cont’d)
BTMUA and Metedeconk Watershedin Relation to the Barnegat Bay Watershed
BTMUA
Task 1 - Establish Stakeholder Advisory Committee completed/ongoing
Task 2 - Visual Assessment Project Plan (VAPP) completed - July 2011
Task 3 - Watershed Technical Analysis completed - July 2011
Task 4 - Set Plan Objectives completed - September 2011
Task 5 - Identification of Watershed Management Strategies completed
- May 2012
Task 6 - Education and Outreach Program completed - October 2012
Task 7 - Quality Assurance Project Plan (undergoing revision)
Task 8 - Development of the Metedeconk River Watershed Protection
and Restoration Plan completed
Task 9 - Development of Conceptual Design Plans (under review)
Task 10 - Final Report
Task 11 - Implementation (Phase 2) Scope Development
Project Tasks / Status
Stakeholder Meetings
SAC meetings held at key project stages
1. Kickoff “breakfast” meeting; project introduction, preliminary goals & objectives (1/13/10, MRYC, Brick)
2. Review of SVA & Watershed Technical Analysis findings (4/27/11, Ocean County College)
3. Finalize watershed plan goals & objectives (7/13/11, Brick Twp)
4. Watershed management strategies review and prioritization with decision support tool (11/29/11, Howell)
5. Draft Metedeconk watershed plan (4/26/12, Jackson)
Steering Committee
1. Draft SVA & Technical Analysis; SAC meeting planning (3/9/11)
2. Watershed strategies & prioritization; E&O and QAPP (10/25/11)
Education & Outreach Committee (1/31/12)
Task 8 – Development of Watershed Plan
Draft plan open for public
comment – April-May 2012
Plan revisions; discussions
with municipalities to gather
additional, local-priority
implementation projects –
summer/fall 2012
Meetings/presentations to
NJDEP - May & December 2012
NJDEP/USEPA Region II review
and comments addressed –
winter/spring 2013
PLAN FORMALLY APPROVED BY NJDEP MAY 23, 2013
Metedeconk River WatershedProtection & Restoration Plan
Plan is a work product of:
Stakeholder Advisory Committee
Steering Committee
Education & Outreach Committee
Diverse and representative group of watershed interests
Committee input vital to the success of project
Based upon stakeholders’ goals, objectives and priorities
Result is plan built consensus that is broadly supported
Will help secure successful plan implementation
Metedeconk River WatershedProtection & Restoration Plan
Lots of public interest in the Metedeconk watershed plan
Presentations:
New Jersey Environmental Federation (NJEF) Annual
Conference (April 6, 2013, Georgian Court University)
New Jersey Water Environment Association (NJWEA)
Annual Conference (May 15, 2013, Bally’s Atlantic City)
Awards:
2012 Barnegat Bay Partnership Guardian of the Bay Award
2012 Ocean County Freeholders’ Clam Digger Award
2013 NJ Association of Environmental Authorities
Wave Award, Forward Thinking Category
Summary of Major Issues
Stormwater is the primary cause of problems within the watershed
Impervious Cover
%Impervious
ChannelStability
Water Quality
StreamBiodiversity
Pollutantsof Concern
Characteristic
0-10 StableGood to Excellent
Good to Excellent
Sediment,temperature
Stable
11-25 UnstableFair to Good
Fair to Good…&
nutrients,metals
Unstable
26-100Highly
UnstableFair to Poor
Poor …& bacteria Highly unstable
Percent impervious cover within the “unstable” category
from Schueler, 1995
Summary of Major Issues
Stormwater is the primary cause of problems within the watershed
Overall water quality still holding, but degrading
TMDLs & 303(d)
Water Quality: Surface Water
BTMUA Monitoring Program
Extensive, including 68 samplingstations
North and South Branches
Routine samples collected at or immediately upstream of intake
USGS, EPA
List of Identified ImpairmentsSubbasin HUC14 Area (mi
2) Subwatershed Name TMDL 2010 Integrated List (Priority Ranking)
NB 1 02040301020010 8.6Metedeconk R NB
(above I 195)
Phosphorus, Stream
Fecal Coliform
Dissolved Oxygen (M)**, Arsenic (L), DDD(L),
DDT(L), DDE(L), Chlordane in Fish Tissue(L),
Mercury in Fish Tissue(L), PCB in Fish
Tissue(L), Turbidity*, Lead*
NB 2 02040301020020 10.9Metedeconk R NB (Rt 9
to I 195)
Stream Fecal
Coliform
Dissolved Oxygen(M)**, Temperature(M),
Arsenic(L), Turbidity*
NB 3 02040301020030 6.1 Haystack BrookStream Fecal
ColiformCause Unknown(M)
NB 4 02040301020040 4.8 Muddy Ford BrookStream Fecal
Coliform
TP(M), TSS(M), Arsenic(L)**, Mercury in
Water Column(L)
NB 5 02040301020050 7.9Metedeconk R NB
(confluence to Rt 9)
Stream Fecal
ColiformTemperature(M), Arsenic(L)**, Lead*
SB 1 02040301030010 5Metedeconk R SB
(above I 195 exit 21 rd)
Stream Fecal
ColiformDissolved Oxygen (M)**, Arsenic (L), Lead*
SB 2 02040301030020 5.6
Metedeconk R SB
(74d19m15s to I 195
X21)
Stream Fecal
ColiformTurbidity*
SB 3 02040301030030 7.6
Metedeconk R SB
(Bennetts Pd to
74d19m15s)
Stream Fecal
Coliform
Cause Unknown (M), Polychlorinated
biphenyls(L), Mercury in Fish Tissue(L),
Chlordane in Fish Tissue(L)
SB 4 02040301030040 7.8Metedeconk R SB (Rt 9
to Bennetts Pond)
Stream Fecal
Coliform, Lake Fecal
Coliform
Arsenic(L)**
SB 5 02040301030050 4.8Metedeconk R SB
(confluence to Rt 9)
Stream Fecal
ColiformArsenic(L)**, Lead*
CNFL 1 02040301040020 9.2Metedeconk R
(Beaverdam Ck to confl)
Stream Fecal
Coliform, Lake Fecal,
Total Coliform
Arsenic(L)**, Cause Unknown(M)
* = listed on draft 2012 303(d) list
** = listed on 2010 303(d) List, but NOT included on draft 2012 303(d) list
Summary of Major Issues
Stormwater is the primary cause of problems within the watershed
Overall water quality still holding, but degrading
TMDLs & 303(d)
Natural flow regime is degrading
Summary of Major Issues
Stormwater is the primary cause of problems within the watershed
Overall water quality still holding, but degrading
TMDLs & 303(d)
Natural flow regime is degrading
Data gaps
Groundwater data
Antiquated infrastructure
Metedeconk River WatershedProtection & Restoration Plan
Management Strategies Summary
1. Retrofit existing stormwater detention basins
2. Install structural BMP at existing direct outfalls; where
feasible
3. Source control and flow path BMPs (runoff reduction at the
source); treatment train approach
4. Resource conservation and protection
5. Strengthen stormwater management ordinances for more
Low Impact Development (LID), zero runoff goal
6. Aggressive watershed education and outreach
Metedeconk River WatershedProtection & Restoration Plan
Two-Fold Prioritization Approach
1. HUC14 sub-watershed basis
- Water quality (stream impairments)
- Runoff reduction
2. Individual projects
- Identified by stakeholders
- Identified by project team:
- Stream visual assessments
- Rutgers stormwater planning tool
- NJEIT proposals not awarded
- Etc.*
Implementation Projects
Watershed # ProjectsNB2 13
NB5 13
SB5 8
CFL1 11
NB4 5
NB1 2
NB3 10
SB4 14
SB2 3
SB3 14
SB1 0
More than 90 projects identified to date
Watershed Plan Implementation
Stakeholder committee involvement
“Planning” Committee “Implementation” Committee
Convene on regular schedule to discuss plan implementation
Initial funding for implementation projects:
$466,000 from current NJDEP grant
$700,500 319(h) grant just awarded from NJDEP
~$1.2 million total
New Metedeconk Watershed website forthcoming
http://brickmua.com/metedeconk/watershed.asp
Watershed Plan Implementation
Metedeconk watershed education and outreach
General and target audiences identified (e.g. municipalities,
businesses, civic groups, etc.)
Specific educational materials for implementation projects
Presentations to municipal planning boards, zoning boards and
environmental commissions
Water quality monitoring (QAPP)
Evaluate progress towards water quality objectives
Assess long-term trends in
watershed health
Implementation Projects
Project Rank
Model Stormwater Management/Low Impact Development (LID) Ordinance Designed for the Metedeconk Watershed
1
Brick Park & Ride Site (Visual Assessment Site TR1-2) 2
Stormwater Outfall at Route 9 (former Jamesway Site - Visual Assessment Site NF14)
3
Park along South Lake Drive (Visual Assessment Site SG) 4
Brick Plaza (Visual Assessment Site CBB-3) 5
Howell Township Fire Substation (Visual Assessment Site GH-1 - Maxim Southard Road)
6
Stormwater Basin off of Moses Milch Drive (Visual Assessment Site GR4) 7
Stormwater Discharge Pipe Near Arkansas Drive (Visual Assessment Site TR23-1) 8
Downtown Lakewood (Clifton Avenue) 9
Culvert beneath Pine Street (Visual Assessment Site SE-P) 10
Outfall at Maypink Lane & Juniper Place (Visual Assessment Site GR2) 11
Stormwater Discharge Pipe at Newbury School (Visual Assessment Site SPC-1) 12
Project Rank
Model Stormwater Management/Low Impact Development (LID) Ordinance Designed for the Metedeconk Watershed
1
Brick Park & Ride Site (Visual Assessment Site TR1-2) 2
Stormwater Outfall at Route 9 (former Jamesway Site - Visual Assessment Site NF14)
3
Park along South Lake Drive (Visual Assessment Site SG) 4
Brick Plaza (Visual Assessment Site CBB-3) 5
Howell Township Fire Substation (Visual Assessment Site GH-1 - Maxim Southard Road)
6
Stormwater Basin off of Moses Milch Drive (Visual Assessment Site GR4) 7
Stormwater Discharge Pipe Near Arkansas Drive (Visual Assessment Site TR23-1) 8
Downtown Lakewood (Clifton Avenue) 9
Culvert beneath Pine Street (Visual Assessment Site SE-P) 10
Outfall at Maypink Lane & Juniper Place (Visual Assessment Site GR2) 11
Stormwater Discharge Pipe at Newbury School (Visual Assessment Site SPC-1) 12
Develop an LID Ordinance
Not included in conceptual designs but recommended for Phase 2
Conceptual Designs
Five projects:
Moses Milch basin in Howell
Rain garden in Lakewood (South Lake Drive)
Rain garden, soil decompaction, pervious asphalt in Jackson
Brick Plaza in Brick
84” stormwater outfall in Lakewood
Conceptual
Additional investigations necessary
– Need to resolve unknown items
Modification to occur during design
All include education & outreach
Costs
Conservative
Contingencies
– Assumptions
Private contractors
Fixed percentages for engineering, general conditions, etc.
Some or all need to be implementable in Phase 2
Refined during design
Moses Milch Drive Detention Basin
Moses Milch Drive: Howell
Retrofit existing detention basin
Major assumptions
Liner and underdrains do not exist
Soil infiltration is sufficient
Seasonal high water table is more than 4 feet from the surface
Recommends design follow Ocean County Retrofit Project’s Project Recommendations and Guidelines
Retrofit Existing Stormwater Basins
Moses Milch Drive Detention Basin
Conceptual cost estimate: $400,000
Within range from Ocean County basins
Opportunities to reduce cost
Design can be modified
Low flow channel
Planting plan, etc
Clifton Avenue Outfall: Lakewood
Outfall at Clifton Avenue: Lakewood
Two components:
Source control
End of pipe – constructed wetland
– End of pipe component cannot be implemented in Phase 2
Major assumptions
Slope/alignment of 84” pipe
Water table
Land acquisition / construction permitted
Outfall at Clifton Avenue
Constructed wetland
Conceptual cost: $1.3M (without land acquisition)
Relies on land acquisition
Significant project
Look for opportunities to reduce cost
– Length of pipe / connection to 84” pipe
Captures/treats a portion of the water quality design storm
Couple wetland with extensive source control
Can modulate source control / urban GSI
htt
p:/
/sto
rm-t
ree.
com
/pro
ject
s/
Brick Plaza: Brick
Brick Plaza
Represents a “blank slate” with multiple options
Conceptual design represents a sample
Good opportunity for partnership with owner of plaza
Detailed survey needed for evaluation of other alternatives
Brick PlazaConceptual cost estimate: $300,000
Major assumptions:
Soil will readily infiltrate (urban land)
Owner will approve
Local drainage needs to be better defined
Other alternatives
Re-grade and install trench
Include channel improvements
Retro-fit parking lot islands
Infiltration tree boxes
Green roofs, other htt
p:/
/sto
rm-t
ree.
com
/pro
ject
s/
Arkansas Dr. / Woodlane Rd: Jackson
Arkansas Dr / Woodlane Rd
Source control & drainage improvements
Water table in neighborhood – problematic
Sumps to storm sewer
Infiltration BMPs…..?
Improve drainage along Woodlane Rd
Soil decompaction at athletic field
Modular
Arkansas Dr / Woodlane RdConceptual cost estimate:
>$500,000 (asphalt)
– Can reduce with refined design (not entire lot)
$200,000 (source control)
$80,000 (rain garden)
– Likely require some type of pre-treatment (forebay / reduce sediment load)
Major assumptions:
Soil will readily infiltrate at rain garden and lot
Water table
South Lake Drive: Lakewood
South Lake Drive
Rain garden
Major assumptions
Water table
Pipe condition
South Lake Drive
Conceptual Cost Estimate: $100,000
Water table could be problematic
Additional sites could provide excellent opportunity
Conceptual Designs
Costs and designs will likely be refined with additional investigations
Common elements are need for detailed survey and seasonal high water table elevation
Some or all of all 5 can be implemented during Phase 2
Watershed Plan ImplementationConclusion
Implementation will be a long process
Important to maintain active Stakeholder Advisory Committee through implementation
BTMUA to continue to serve leadership role
Maintain strong working relationship with NJDEP, BBP and stakeholders towards common watershed goals
Metedeconk Plan is “Everyone’s Plan” – projects can/should be completed by all as opportunities arise
Leverage funding and partnership opportunities
Plan will be “living document” with updates (Table 5-3) as projects are completed and new ones are identified
Metedeconk website will be portal for status and updates
Robert KarlSource Water SupervisorBrick Township Municipal Utilities Authority1551 Highway 88 WestBrick, NJ 08724Tel: (732) 458-7000Fax: (732) [email protected]
Dan O’RourkeProject ManagerCDM Smith110 Fieldcrest AvenueEdison, NJ 08837Tel: (732) 225-7000Fax: (732) [email protected]
Project Contacts