McCord Road Underpass Project

McCord Road Underpass

Thursday, August 14, 2014

John

Page 2: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Welcome

ODOT Construction

• Theresa Pollick, Public Information Officer

• Douglas Raby, P.E. Area Engineer

• Daniel Kelsey, P.E. Project Engineer

ODOT – Administrative

Lucas County Engineers Office

• Keith Early, P.E. Lucas County Engineer

• Jeff Lohse, P.E. Chief Deputy Engineer

Page 3: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Project History

1994: TMACOG & the Lucas County Engineers

Office identified the rail crossing at McCord

Road as a safety and congestion concern.

Estimated 100 trains per day

Both Train and vehicle traffic are projected to

increase.

State Railroad Grade Separation Funding

became available: Lucas County Engineers

office and TMACOG applied.

Page 4: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Project Basics

A project to construct an underpass at McCord

Road and the Norfolk-Southern railroad track

Build a roundabout at North Mall Drive/Hall

Street.

Prime Contractor: Beaver Excavating

Company

Project Cost: $24.3 Million

Start: August 4, 2014

Complete: November 2016

Page 5: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

McCord Road Today

Page 6: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

McCord Rd Winter 2016

Page 7: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Construction Timeline

2014

Now through December

• Intermittent lane restrictions on McCord Road

from Airport Highway to Angola Road

• Lane restrictions possible on N. Mall Drive

• Crews build temporary railroad track foundation

& temporary roadway (S. Holland Park

Boulevard)

• Restrictions will be for moving equipment

Page 8: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

ODOT Project McCord Rd

Stage 1

Page 9: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Construction Timeline

2015 McCord

• Spring 2015 – McCord Road/Hall/Mall Drive

75 DAY CLOSURE

McCord Road at North Mall Drive & Hall

Street will be closed to construct

roundabout

• Accommodate Springfield Local Schools

• Detour: Airport Highway; Holland-Sylvania

Road; Angola Road

Page 10: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Construction Timeline

2015

• 75 Day Closure

North Mall Drive at the west entrance to

Wal*mart

Summer 2015

Page 11: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Construction Timeline

2015 – Early Spring-Fall 2015

• Stage 2: Preliminary construction of stage 2

will start in March 2015

• Stage 2 has 4 phases including:

The closures of McCord Road -North Mall

Drive – Hall Street from May through August.

• The pump station construction will begin

early 2015 as well.

Page 12: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

ODOT Project McCord Rd

Stage 2

Page 13: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

ODOT Project McCord Rd

Stage 2: Pedestrian Plan

Page 14: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Construction Timeline

• Stage 3: Fall 2015-Spring 2016

• Roundabout at McCord Road and Mall

Drive/Hall opens

• Temporary road (Holland Park Roadway) will

be open

• McCord will remain closed through August

2016

Page 15: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

ODOT Project 140236 McCord Rd

Stage 3

Page 16: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Construction Timeline

Stage 4

Remaining portion of McCord Road, north of

the roundabout, will be completed by end of

September 2016

Remove temporary road, temporary railroad

tracks and resurface the project.

Page 17: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

ODOT Project 140236 McCord Rd

Stage 4

Page 18: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from
Page 20: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Nearby ODOT Projects

• I-475 Bridge Widening Projects

• TWO CLOSURES OF ANGOLA ROAD

SEPTEMBER 2014 - 90 day Closure of Angola at

I-475.

• SPRING 2015 - 90 day Closure of Angola at

I-475.

Detour: McCord; Airport Hwy; Holland-Sylvania

Page 21: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Nearby ODOT Projects

• I-475 Bridge Widening Projects

• Possibility of Angola Road and McCord Road

begin closed at the same time

• GOAL is to minimize this possibility

Page 22: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

Public Information

Page 23: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from

OHGO

Page 24: McCord Road Underpass Project - dot.state.oh.us · PDF fileMcCord Road Underpass Project McCord Road Underpass Thursday, August 14, 2014 John . Welcome ... Drive – Hall Street from